Beruflich Dokumente
Kultur Dokumente
CTS RTU
Figure 3 - hardware circuit Design
2.3 SYSTEM FEATURES Figure 8-Process flow during start and monitoring
The features of the designed prototype include the With the hardware initialized fully, the software would be
following; started up after which transmission of data would be
a) Transformer loading measurement; mainly storing initialized. Process would then proceed with transmission
information concerning transformer loading as it varies and retransmission of data until the end of the monitoring
over time. The software application classifies transformer period where data would be analysed.
load in terms of days on which the loading was measured
and percentage of load relative to the transformer ratings. 2.5 TESTING AND CONDITION MONITORING
Loading variation also displayed graphically.
b) Transformer deviation/imbalance measurement; the The software and the hardware were set based on the
software application computes the imbalance on the system process flow while carrying out the first system test.
transformer as a percentage ratio of the maximum deviation The application was configured through the computer serial
port to receive the loading data from the transformer via a 3.1.1 Loading and Deviation
GSM modem connected to the computer. The data was
displayed in real time as it was received from the hardware
setup. The condition monitoring was carried out for seven
hours with accurate transmissions throughout the testing.
The system approximate peak and time was constantly
computed by the software application through comparing
the stored values with the incoming values.
Display curves included; loading current for each phase as
shown in figure 9, percentage load on the transformer,
percentage deviation on the phases. Tables were added to
show the loading history on the transformer and the
percentage load deviation. The application was embedded Figure 11- loading and deviation curve
with Google maps to indicate the location of the
transformers as in figure 10. a) Deviation Summary
The deviation summary was as follows:
Maximum deviation: 71%
Time of Max deviation: 5:12PM
Minimum deviation: 13%
Time of Min deviation: 4:22PM
b) Loading summary
All expressed as percentage of the transformer rated current
Peak load: 9%
Time of Peak: 4:23PM
Base Load: 3%
Time of base: 6:52PM
The Loading summary was as follows:
Figure 9 - real time monitoring interface 3.1.2 Loading Trend
The loading variations in terms of phase currents indicated
that the blue phase was relatively less loaded as compared
to the other phases of the transformer throughout the
condition monitoring, this led to an average deviation of
40% for the time of monitoring.