Target Date For Completion

Sr.No Work Front Mechanical Balance Work C&I Balance work


Of Mechanical Balance Work
Commg Activity and Pending Work
completion will be schedule on
1 TOC 15.02.13 1. In Sprinkler alarm line Y-Strrainer is not erected. Not Given .

2 MOT 16.02.2013 1. Four NO's of Nozzle erection is pending. Not Given


2. In Sprinkler 1. LHS Cable laying on MOT is pending.
alarm line Y-Strrainer is not erected.

3 DOT/COT 16.02.2013 Not Given 1.Pressure Switch erection on DV is pending.


1. Handles of BFVs are not placed except at DV 2. Solenoid valve connection with
discharge. 2. In panel is pending
Sprinkler alarm line Y-Strrainer is not erected.

4 BBF(Boiler Burner Front ) 17.02.2013 24.02.2013 1. Wheel of DV inlet drain is not placed. Not given
2. Bucket below
DV venting line is missing.

5 GSOU (Generator Seal oil Unit) 17.02.2013 1. In Sprinkler alarm line Y-Strrainer is not erected. Not Given 1.Pressure Switch connection with panel is pending.
2. 2. Solenoid valve
Flap of Emergency Relief box is broken. connection with panel is pending
3. LHS Cable laying of GSOS is pending.
6 Switch yard 18.02.2013 1. Painting of all MCP is required at switchyard. Not Given 1.Pressure Switch erection is pending on DV for Bus Reactor
2. BFV Pit Transformer is pending.
covers is not erected in switch yard. 2. solenoid valve erection is pending.
3. Numbering of
SHH Valve and MCP is pending in switchyard.
4. Handles of DV suction &
discharge BFVs are not placed as concerned with
Bus Reactor Transformer.

7 APH 18.02.2013 Line is completed.

8 Cable gallery at -1.5 mtr 1. BFV's handles are not placed. Not Given 1.Pressure Switch erection on DV is pending.
2. Solenoid valve connection with
panel is pending

9 Cable gallery at 7.5 mtr 19.02.2013 1. BFV's handles are not placed. Not Given 1.Pressure Switch erection on DV is pending.
2. In Sprinkler alarm line Y-Strrainer is not erected. 2. Solenoid valve connection with
panel is pending

10 Cable gallery at 11 mtr 21.02.2013 1. BFV's handles are not placed. 2. Not Given 1.Pressure Switch erection on DV is pending.
In Sprinkler alarm line Y-Strrainer is not erected. 2. Solenoid valve connection with
panel is pending

11 FOHP (FFPH/Unloading PH/Tank 20.02.2013 1. Handles of BFVs For DV System are not placed. Not Given 1.Pressure Switch erection on DVs are pending.
Area) 2. Solenoid
valve connection with panel is pending.

12 BFP 23.02.2013 Not Given

13 HP & LP Bypass System 1. Pipeline erection is pending. Not Given Erection is pending
2.DV erection is pending.
Not Given
14 GT

1.Pressure Switch connection with panel is pending on


1. Handles of BFVs are not placed except at DV 28.02.13
15 ST Not Given
suction. 2. Solenoid valve connection with
panel is pending on 28.02.13
Target Date For Completion Of C&I
Commissioning Status Remarks
Balance Work

1.Pressure Switch commissioning is pending 2. 24.02.2013


DV is commissioned

1.Pressure Switch commissioning is pending 2. 24.02.2013


DV is commissioned

1.Pressure Switch commissioning is pending 2. 24.02.2013


DV is commissioned

1.Pressure Switch commissioning is pending 2. 25.02.2013


DV commissioning is pending.

1.Pressure Switch commissioning is pending 2. 24.02.2013


DV is commissioned
As per marked drawing of switchyard. 25.02.2013 1. Flushing of FF line for Bus Reactor Transformer
is done on 20-02-2013, during flushing it is
observed that water was coming from protection line
ring header at EL +0.322 mtr only and all other ring
headers were choked including all detection line ring
headers.
2. During DV commg on 21.02.2013 some
nozzle, It is observed that water pressure was very
low after interval of aprox. 1 min. water spraying
has been stop completly.

completed

Only flushing is completed Not Given

Commissioning is pending Not Given

Commissioning is pending Not Given

1. Pressure Switch commissioning is pending. 2. 25.02.2013 DV for LDO unloading pump house is operated on
Commissioning of DVs for FFPH & LDO unloading PH area are 21-02-2013 and observation are as follows:-
completed. 1. Two no. nozzles in LDO
U/L area were found to be choked.
2. One no. nozzle was not developing
proper pressure.
3.Pressure Gauge in 15NB pressure line is not
indicating pressure value.

DV for Fuel Forwarding pump house is operated on


22-02-2013 and observation are as follows:-
1. 5 no. Nozzles are
observed those are not developing proper pressure.
2. BFV at discharge of
DV is having leakage.
3. Tapping of Sprinkler alarm from
pressure gauge at DV suction is having leakage at
the connecting point.

1.Pressure Switch commissioning is pending 2. 25.02.2013


DV is commissioned

Commissioning is pending
1.Pressure Switch commissioning is pending 2.
DV is commissioned
1.Pressure Switch commissioning is pending 2.
DV is commissioned
Sr. No. Work Front DV Status Line Status
1 TOC (Turbine Oil Canal) Charged Charged
2 MOT (Main Oil Tank) Charged Charged
3 DOT/COT charged Charged

BBF(Boiler Burner Front ) Not charged Charged


4
5 GSOU (Generator Seal oil Unit) Charged Charged
6 Switch yard No DV Charged
7 APH No DV Charged
8 Cable gallery at -1.5 mtr Not charged Charged
9 Cable gallery at 7.5 mtr Not charged Charged
10 Cable gallery at 11 mtr Not charged Charged
11 FOHP (FFPH/Unloading PH/Tank Area) Not charged Charged
12 BFP Charged Charged
13 HP & LP Bypass System Not erected Not erected
14 GT Charged Charged
15 ST Charged Charged
Remarks

Four NO'S of Nozzle erection work will be planned after oil synchronisation.

One no. QBD is in burst condition & DV Commissioning job will be planned after
oil synchronisation.

There is no DV for Switchyard Boundary area FF line.

DV Commissioning job will be planned after oil synchronisation.


DV Commissioning job will be planned after oil synchronisation.
DV Commissioning job will be planned after oil synchronisation.

As per project system is not in FF scope.