Sie sind auf Seite 1von 4

www.revay.com VOL. 16 No.

2, April 1997

method of contracting, it is and will remain these problems.


a disaster. On the other hand, design/build
could be the solution to all that ails the Additionally, this issue records a watershed
construction industry today. It is definitely in the operation of the Toronto office. Mark
a more natural way of buying construction, Doyle, who started and built up the office
but only if the industry adapts to the turned the reins over to Bill Gillan on the
shifting of responsibilities and authority. " twenty-eighth of April I would like to take
this opportunity to recognize Mark's
The primary thrust of this shifting of contribution to the growth of our company
responsibilities and authority must be in and am pleased to report that Mark
by Stephen G. Revay respect of the manner changes in the design continues with us, but in a more exalted
(including those necessitated by changed capacity, as a senior statesman. Bill Gillan
Last June, at the annual meeting of soil conditions) are handled. During the brings to us over twenty years of
Construction Specifications Canada, I last ten years, we were involved in nearly experience in project management, an area
presented a paper entitled Design1Build: as many disputes arising out of design/build where we plan to be more active in the
Panacea or Disaster where I concluded that contracts as all other types combined, with future.
"as long as clients insist on maintaining all the changes in design taking the centre
of the authority and freedom for ordering stage in almost all of them.
changes they have under the conventional The lead article of this issue deals with

CHANGES IN DESIGN/BUILD CONTRACTS


DEFINITION different parts of the world than others. than any of the other names. Courts are
The owner's involvement in the much more interested in the owner's
First came the master builder then, in the design/build process, for instance, may actual involvement in the design process
late nineteenth century, in the early days be much less so than in the EPC type of than in the moniker of the parties'
of railway construction in England, the proceeding. relationship.
design-bid-construct type of project
delivery system was introduced. This Even the method of compensation may The usual phases of a design/build
system is still predominant all over the vary, nevertheless, all of these have a project delivery system are as follows:
world. The master builder has not common characteristic that sets them
completely disappeared, although over apart from the conventional or design 1. The owner decides on a project and
the years he has changed his name to bid-construct process which is that, in develops (either using in-house
turnkey contractor. A variation of the these methods of contracting, the design resources or outside consultants)
turnkey method of buying construction and construction are performed by a the conceptual design and the
services is the design-and-build (or single entity, at least as far as the client budget, as well as selects the site
design/build). The turnkey method is also (i.e. owner) is concerned. This is in where the project may be realized.
known as the package deal. A further contrast to the conventional process 2. The owner (and/or its consultant)
variation of basically the same concept is where the design responsibility rests with prepares the Request for Proposals
the engineer-procure-construct (EPC) the owner. (RFP) including detailed
project delivery system, and more performance requirements and
recently one has been hearing about The name given to the specific project quality specifications.
performance-based contracting. delivery system may be important to the 3. The owner preselects qualified
participant but not necessarily to the contractors with proven capability to
These systems have their own courts where the design-and-build undertake the project.
peculiarities. Some are better known in definition is more readily understood

-1-
4. Firm bids are received from the It is impossible to talk about standard Owner to review in orderly
prequalified contractors and the forms of design/build contracts in the sequence and sufficiently in
contract is awarded subsequent to same way as those that are available for advance so as to cause no delay
the required clarification of the conventional contracting, but there are a in the Work. Upon request of the
proposal. few recognized publications, such as the Owner or the Contractor they
5. The contractor (and/or its so-called Orange Book by FIDIC jointly shall prepare a schedule of
consultant) prepares the design, (Federation Internationale des the dates for submission and
construction specifications and Ingenieurs-Conseils). return of Construction
approved for construction drawings Documents.
and constructs the facility. Paragraph 4.1 of this Contract reads, in
6. The owner carries out the type of part, as follows: 3.2.3 The Owner shall review the
inspection and testing it deems Construction Documents in
desirable and eventually takes the "The Works as completed by the accordance with the schedule
facility over. Contractor shall be wholly in accordance agreed upon, or in the absence of
with the Contract and fit for the purposes an agreed schedule with
What is not defined above is the owner's for which they are intended, as defined reasonable promptness. The
involvement with the actual design in the Contract" Owner's review is for conformity
process (i.e. Phase 5), even though the to the intent of the Contract
extent of this involvement may be the Paragraph 5.2 reads, in part, as follows: Documents. The Owner's review
factor which could determine the shall not relieve the Contractor of
success of the project. "Each of the Construction Documents responsibility for errors or
shall, when considered ready for use, be omissions in the Construction
WHO IS RESPONSIBLE FOR THE submitted to the Employer's Documents or for meeting all
DESIGN? Representative for preconstruction requirements of the Contract
review. In this Sub Clause, "review Documents unless the Owner
The most frequently heard argument period" means the period required by expressly notes the acceptance of
against the design/build method of the Employer's Representative, which a deviation on the Construction
project delivery is that it precludes shall not exceed 21 days ... If the Documents. Any agreed
proper control by the owner with respect Employer's Representative, within such amendment to the Owner's
to long term life, quality and simplicity of review period, notifies the Contractor Statement of Requirements shall
maintenance. Additionally, there is a real that such Construction Document fails be recorded in a Change Order
risk, according to some, that the (to the extent stated) to comply with the signed by the Owner and the
competition among the tenderers will Employer's Requirements, it shall be Contractor."
result in "under-design" which may not rectified, resubmitted and reviewed in
be detectable by the owner or the accordance with this Sub-Clause, at the In a private contract, the corresponding
owner's professional advisors, unless, of Contractor's cost.. clauses read, in part, as follows:
course, a really detailed check of the
design and the specifications is (a) construction shall not commence 1.1 The Contractor shall provide
attempted, in which case the promised prior to the expiry of the review engineering, procurement,
savings by way of reduced design fees periods for the Construction construction, project management
are likely to prove illusory. Documents which are relevant to and construction management.
the design and construction of such
The owner could, of course, prepare part;.. 2.2 The Contractor shall, in
very detailed design and specifications accordance with this Contract,
for the UP, but then the real advantage If the Employer's Representative furnish and pay for all material,
of the design/build method resulting from instructs that further Construction labour tools, equipment and
the specific expertise of the prequalified Documents are necessary for carrying transportation required to perform
bidders may be lost. More importantly, out the Works, the Contractor shall upon the Work and shall perform the
under the above scenario the owner receiving the Employer's Work in a good and workmanlike
could conceivably retain the ultimate Representative's instructions prepare manner so that the Facility will
(e.g. legal) responsibility for the fitness of such Construction Documents." start up and operate as designed.
the facility for its intended purpose.
The Canadian Construction Association 4. 1(b) The Contractor shall perform the
The practical answer to this predicament has prepared (although not yet Work so that it meets the
was thought to have been found in the published) a similar contract (Standard requirements of all applicable
owner's insistence on retaining a close Construction Document CCA14). Article design, construction and other
control of the design development by the GC30 of this document reads, in part, as standards in accordance with the
contractor, however, that insistence follows: Project Design Specifications and
turned out to be the hotbed of all with the requirements of
disputes. "3.2.2 The Contractor shall submit the professional engineering
Construction Documents to the standards,....

-2-
(I) Cooperate with Independent The problem, unfortunately, is much which remains the unresolved mystery
Engineer in reviewing design, more severe; namely the argument for many legal authorities. More
materials and conducting usually centres on the unwritten importantly, however, Paragraph 4.9
inspections, performance tests and preferences of the owner and seldom on places the burden of soil investigation on
handling other matters relating to the precisely written requirements. This the shoulders of the contractor. The
Work." brings us back to the initial question: is it owner is required simply to turn over to
more beneficial to the owner if the the contractor all available information
As can be seen in these three examples, Statement of Requirements is vague without specifying the extent of the
which are typical of all design/build enough to allow the bidders to cash in on investigation the owner should
contracts in their stipulations, the their expertise and ingenuity or would the undertake.
contractor must submit its design and owner's interest be better served if the
specifications (i.e. Construction requirements were set out in great detail For the contractor to be able to cross the
Documents) for review by the owner's and with precision so as to preclude threshold of what an experienced
representative, and no construction may eventual misunderstandings? contractor should or should not foresee,
start prior to such review (unless the time it must satisfy the prerequisite laid down
provided for the review has expired). Of The market reality is that contractors, by Paragraph 4.9 according to which it
course, this review process can, and when preparing a response to an RFP has to obtain all necessary information
frequently will, turn into disagreement seldom spend (or could spend) the time pertaining to risks, contingencies and all
with respect to the contractor's and money to prepare a complete other circumstances which might
compliance with the owner's intentions design and usually base their estimate influence or affect the tender.
(e.g. Project Design Specifications). on experience gained on similar projects.
These disagreements can be and often Unfortunately, those prior projects might As the result of these requirements, is
are acrimonious, time consuming and have been built for different owners with there really any use for Paragraph 4.11?
usually expensive as far as the different requirements, where as on the
contractor is concerned. In reality, this project in question they must meet the Although the CCA document deals with
review is simply a disguised design unwritten preferences of the instant the problem differently by adopting the
approval process, pursuant to which the owner. No wonder that losses on two-pronged approach of US Federal
owners usually get their wish without design/build contracts can, at times, be Government contracts, the CCA fails to
relieving the contractors of their ultimate very significant. answer the fundamental question: what
responsibility for the fitness of the facility, happens if the owner carried out only
and often without paying for the After all, the contractor may be required little or absolutely no sub-surface
enhanced scope. to build to the owner's (albeit unwritten) investigation? To be able to say that the
specifications and is being compensated actually encountered sub-surface or
WHY NOT REQUEST A CHANGE pursuant to a tender price based on its otherwise concealed physical conditions
ORDER? own expertise and perhaps unrelated differ materially from something, that
experience. something had to have been known. And
All of the above referenced contracts, if that something did not exist, then there
and in fact most design/build contracts CHANGES IN SUB-SURFACE can be no change.
contain a changes clause, according to CONDITIONS
which the contract price may be The contract from which this clause was
adjusted if the parties agree to an Perhaps an even greater risk which a taken, is for a design-bid-construct
amendment to the owner's Statement of contractor could be facing on a arrangement which assumes suitable
Requirements (e.g. Project Design design/build project is the potential sub-surface investigations on the part of
Specifications). These clauses also uncertainty of the sub-surface conditions. the owner if for no other reason than to
stipulate that the contractor may not Although both the FIDIC contract be able to complete the design. This
perform such a change in the work (i.e. (Paragraph 4.11) and the CCA reason does not exist in the case of a
in the owner's Statement of Document #14 (Paragraph GC 6.4) design/build arrangement.
Requirements) without a written change contain provisions for the adjustment in
order signed by both parties. the price and the duration of the The second prong is even more
contract, both of these clauses are open nebulous. For it to have proper meaning
However, it is clear from these excerpts to widely differing interpretations. the design first would have had to be
that there is a fundamental difference completed because the character of the
between a genuine variation in the In the FIDIC version (Paragraph 4.11) construction activity, which is the
Statement of Requirements, which is to the prerequisite for the adjustment is that deciding factor in the applicability of this
be paid for by the owner, and a change the actually encountered sub-surface provision, may not be determinable prior
in the design solution proposed by the conditions are of a nature which could to finalizing the design. What is the
contractor, which is at the expense and not have been foreseen by an solution?
time of the contractor, even when the experienced contractor. The problem is,
change resulted from the owner's of course, that the definition of an
request. experienced contractor is just as
nebulous as that of a reasonable man,

-3-
CONCLUSION and not an award by an arbitration BILL GILLAN, P ENG. JOINS RAL
board, is nevertheless final and binding
First of all, design/build contracts are not on the parties, unless a party notifies the
for novices. Second, contractors ought other party of its dissatisfaction with such
to ensure that they understand the a decision within twenty-eight days after
owner's requirements (whether written or the receipt of the decision.
simply intended) and clearly qualify the Notwithstanding such a disagreement,
basis of their estimate in their proposal. the parties shall give effect forthwith to
This would go a long way towards every decision of the Board,
clarifying the contractors' position with understanding that such a disputed
regard to design responsibilities. It would decision may eventually be altered either
also make changes, particularly those through an amicable settlement or
caused by sub-surface conditions, easier arbitration.
to monitor. That is, if the contractor's
initial expectations are clear, then any The experience with adjudication boards
changes to those expectations will be in the United Kingdom, where this
obvious. method of dispute resolution has been
Bill Gillan joined RAL, Toronto on April
used for some time now, is that parties
28, 1997 as General Manager for the
It is contended that even those to contracts with such provisions tend to
Ontario Region. He brings with him 27
contracts, such as the ones discussed act fairly and expeditiously with a view to
years of experience in the Canadian
above, which are prepared specifically avoiding the need to go before the
engineering and construction industry,
for design/build arrangements, may not Board.
including over 20 years in the planning,
distribute responsibilities and authorities
design, construction and operation of
in such a manner as to give the Finally, it may not be a bad idea if the
airport facilities. Bill is a civil engineering
relationship proper business efficacy. construction industry investigates the
graduate from the University of Waterloo
More importantly, even the most way the aviation world successfully
and over the years gained extensive
equitable language may not always be operates, wherein airlines buy airplanes,
experience in managing major projects,
sufficient, because there will always be fairly complex and expensive ones,
capital programs, and multi-discriplined
issues left to the fairness and pursuant to the design/build method of
professional and technical staff. With a
reasonableness of the parties. This contracting. Or should it be called a
combination of public and private sector
applies to both parties and not only to package deal?
experience, he has been responsible for
the owner.
the provision of engineering services to
By S.G. Revay
various government departments,
The answer to these issues probably lies
business operations, and the negotiation
in Clause 20 of the FIDIC Orange Book,
of contracts and claims. His extensive
and more particularly in Paragraph 20.3
managerial experience and his
which provides for a Dispute
knowledge of the industry in general will
Adjudication Board, and Paragraph 20.4
add greatly to RALs capacity to serve
which sets out the procedure for
clients in the Ontario Region.
obtaining the decision of the Board. This
decision, which is the decision of experts

The Revay Report is published by Revay and Associates Ltd., a national firm of Construction Managers and Claims
Consultants. The above article has been electronically modified from its original publication. Contents may be reproduced; with
a credit as to source appreciated. Your comments and suggestions for future articles are most welcome. If you have any
questions or would like to obtain other Revay Reports, please feel free to contact any one of the following Revay offices:

MONTREAL:
CONTACT INFORMATION TORONTO: VANCOUVER:
4333 Rue Ste. Catherine 0uest Suite 306, 505 Consumers Road Suite 201; 1985 West Broadway
Montreal,
Please visitQuebec H3Z 1P9 for current office locations.
www.revay.com Toronto, Ontario M2J 4V8 Vancouver, BC V6J 4Y3
IfTel:
you(514)
would 932-2188 Tel: (416)
like to subscribe for The Revay Report, click498-1303
here. Tel: (604) 737-2005
Fax: (514) 939-0776 Fax: (416) 491-0578 Fax: (604) 737-2008
E-mail: revay@dsuper.net E-mail: revay@ican.net E-mail: revayvan@smartt.com

OTTAWA: CALGARY:
th
Suite 301, 39 Robertson Road Suite D262, 1600 - 90 Avenue S.W.
Nepean, Ontario K2H 8R2 Calgary, Alberta T2V 5A8
Tel: (613) 721-6801 Tel: (403) 777-4900
Fax: (613) 596-8172 Fax: (403) 777-4903
E-mail: ralott@istar.ca E-mail: revays@telusplanet.com

-4-

Das könnte Ihnen auch gefallen