Prelim: Laboratory Activity No 4

Research on Inputs to Feasibility Study (Systems Development Cost)

1. Objective(s):
The activity aims:
1. To identify the resources needed to complete project.
2. To research on the cost of each resource requirements.
3. To come-up with high level estimates for the development cost.
2. Intended Learning Outcomes (ILOs):
The students shall be able to:
1. Identify the needed resources to complete a systems development project.
2. Compute the systems development cost.

3. Discussion :
Development costs - one time costs that will not recur after the project has been completed.

These could be the following:

Personnel/Development team members. those who will develop the system. Should be able
to get the no. of hours they will work for the project and the prevailing rate per hour of the
personnel.

Trainings these are trainings needed by the development team related to the project. For the
end-users, this is the end-users training before their actual use of the system in their workplace.

Hardware these could be computers, servers, laptop, mobile, tablet, printers that are needed
during the development of the system. E.g. servers used during testing, computers/laptop by the
developers, etc.

Software these are the tools needed by the development team or the system itself. E.g. the
system will be developed using vb .net and SQL Server database. In this case, you need a
license of visual studio and MS SQL Server. If the Business analyst needs a MS Office or
specific drawing tool like MS Visio, then these are the softwares needed to procure for BA work.

4. Resources:

Roth, R.; Desnnin, A.; Wixom, B. (2013). System Analysis and Design. Fifth Edition: John Wiley & Sons
Singapore Pte. Ltd.

5. Procedure:
Procedure:
1. List down the resource requirements for your systems development project.
2. Research on the prevailing rate or standard rate for each resource.
3. Estimate the total development cost, following the template attached.
Course: Experiment No.:
Group No.: Section:
Group Members: Date Performed:
Date Submitted:
Instructor:

6. Data and Results:

7. Conclusion:

8. Assessment (Rubric SO J ( USER NEEDS):


See attached rubric SO J ( USER NEEDS)
TECHNOLOGICAL INSTITUTE OF THE PHILIPPINES
QUEZON CITY
COLLEGE OF INFORMATION TECHNOLOGY EDUCATION
SYSTEM ANALYSIS AND DESIGN 1

Development Cost Estimates


Project Title:

Project Leader: Laboratory Exercise No. :


Member 1: Section:
Member 2: Date Performed:
Member 3: Date Submitted:
Member 4: Instructor:
Assumptions Approximately of 5 months

Development Team Role, No. of months in the project, Monthly rate, Total

1. HR Project Manager, 5 months, PHP 40,747, Php 203,735.41

http://www.payscale.com/research/PH/Job=Human_Resources_(HR)_
Manager/Salary

2. HR Project Assistant Manager, 5 months, PHP 20,000, Php 100,000

https://myjobstreet.jobstreet.com/career-enhancer/basic-salary-report.php?
param=HR%20Assistant%7C%7C170%7C%7Cph

3. Software Developer, 5 months, PHP 30,998, Php 154,990

http://www.payscale.com/research/PH/Job=Software_Developer/Salary

4. Computer Technician, 2 months, Php 12,000, Php 24,000

http://www.payscale.com/research/PH/Job=Computer_Technician/Salary

Hardware Requirements
Example:

1. 2 ThinkPad X230 Model (laptops) @ Php 40,000 = Php 80,000


Reference: hyperlink
Software Requirement
Example:

1. Visual Studio 2013 Professional with Team Foundation Server (3


licenses) = Php 50,000
Reference: hyperlink

Trainings Needed 1. VB .net trainings = Php 60,000


2. Mobile development = Php 30,000
Reference: hyperlink

Estimated TOTAL
Development Cost:
References: Place here the references for your costing.
Note: attached Screenshots basis for all costing.

Evaluated by: ____Ms. Roxanne A. Ancheta____________ ____________________


Course Advisers Name and Signature Date Signed
System RequestDigital Music Download