Sie sind auf Seite 1von 38

ASSOCIATION FRANAISE DES TUNNELS

ET DE LESPACE SOUTERRAIN

Organization member of the AFTES


www.aftes.asso.fr

AFTES
Recommendations

The design, sizing and


construction of precast
concrete segments
installed at the rear of a
tunnel boring machine (TBM)
GT18R1A1
AFTES
RECOMMENDATIONS FOR

THE DESIGN, SIZING AND CONSTRUCTION


OF PRECAST CONCRETE SEGMENTS
INSTALLED AT THE REAR OF A
TUNNEL BORING MACHINE (TBM)
A.F.T.E.S. will be pleased to receive any suggestions concerning these recommendations

Version 1 - 1997 - approved by the Technical Committee on 13/11/1997 Translated in 1999


Text presented by
M. Pascal GUEDON, SIMECSOL
Working Group leader,
with the collaboration of :
Messrs. AUTUORI Philippe, BOUYGUES - BACHTANIK Bruno, MINISTERE DE L'EQUIPEMENT,
BARTHES Henri, A.F.T.E.S. - BERNARD Simon - BONNA - BILLANGEON Rmi, SPIE BATIGNOLLES
BOCHON Alain, SNCF - CHANTRON Laurent, CETu - CHARDIN Daniel, SOGEA - DARDARD Bruno, SNCF
HUEBER Jean, SETEC - LABONNE Hubert, INDUSTRIELLE DU BETON - LEOGANE Jean Paul, RATP
PETIT Franois, CAMPENON BERNARD SGE - SAMAMA Laurent, SCETAUROUTE - TAQUET Bernard, EDF - CNEH
VAN DUC Tri, CAMPENON BERNARD SGE
A.F.T.E.S. reading panel :
Messrs. GUILLAUME Jean, RAZEL - LAUNAY Jean, DUMEZ - GTM - LECA Eric, SCETAUROUTE
MAUROY Fabien, SYSTRA - NIQUET Jean-Jacques, SOCIETE DU CANAL DE PROVENCE
SCHWENZFEIER Andr, CETu

CONTENTS
Pages Pages
1 - GENERAL 210 3.5.4 - Waterproofing gaskets 219
1.1 - Purpose of recommendations 210 3.5.5 - Segment assembly systems 220
1.2 - Scope of application of recommendations 210 3.5.6 - Connector inserts, pockets 222
2 - HISTORICAL REMINDER 211 3.5.7 - Gaskets for distributing loads at segment
contact joints 222
3 - TUNNEL LINING DESIGN 3.5.8 - Back grouting behind ring extrados 222
3.1 - Introduction 211 3.6 - Lining installed outside the area occupied by
3.2 - Basic data required to design a tunnel lining 211 the TBM 223
3.3 - Lining functions 211 3.6.1 - Ring design principle 223
3.3.1 - Functions associated with operating constraints 211 3.6.2 - Advantages and drawbacks 223
3.3.2 - Functions associated with construction 3.7 - Specific aspects of water conveyance pressure
constraints 212 tunnels 224
3.4 - Description of the concept 212 3.7.1 - Hydrogeological reminders 224
3.4.1 - General 212 3.7.2 - Tunnel lining structural behaviour 224
3.4.2 - General aspects of tunnel lining design 212 3.7.3 - Roughness of segment-lined tunnels 224
3.4.3 - Tapering of rings 212 3.8 - Construction tolerances 224
3.4.4 - Length of rings 213 3.8.1 - Specification 224
3.4.5 - Composition of a lining ring 213 3.8.2 - Identification of main criteria contributing to
3.4.6 - Segment geometry 213 tolerance specification 224
3.4.7 - Nature of lining materials 213 3.8.3 - Accuracy 225
3.5 - Lining installed within the area enclosing 3.9 - Durability 225
the TBM 214 3.9.1 - Segment concrete 225
3.5.1 - Ring design principle 214 3.9.2 - Steel reinforcing bars 225
3.5.2 - Composition of rings 214 3.9.3 - Waterproofing gaskets 226
3.5.3 - Contact surfaces 216 3.9.4 - Connector inserts 226

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


209
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)
Pages Pages
3.10 - Economic considerations 226 5 - DESIGN OF ASSEMBLY SYSTEMS 236
4 - TUNNEL LINING DESIGN 226 5.1 - Design assumptions for bolts and anchor bolts 236
4.1 - Main parameters influencing sizing 226 5.1.1 - Regulations 236
4.1.1 - Implementation conditions 226 5.1.2 - Nature of actions and loadings 236
4.1.2 - Parameters for analysing ring stresses 227 5.1.3 - Combined actions - Design stresses 236
4.2 - Design assumptions 227
5.2 - Proof of assembly and pick-up components
4.2.1 - Regulations and references 227
using materials other than steel 236
4.2.2 - Material properties 229
4.2.3 - Nature of actions and loadings 229 5.2.1 - Introduction 236
4.2.4 - Combined actions 230 5.2.2 - Actions to be considered 236
4.2.5 - Sizing criteria 231 5.2.3 - Combined actions - Stresses 237
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

4.3 - Determination of stresses in the tunnel lining 232 5.2.4 - Behaviour of materials and assemblies - Tests 237
4.3.1 - Introduction 232 5.2.5 - Conclusions 237
4.3.2 - Hyperstatic reaction method 232 6 - TRANSITION AND ANCILLARY WORKS 237
4.3.3 - Composite solid method 232 6.1 - Design of ancillary works 237
4.3.4 - Adaptation of analysis methods to a segments 6.2 - Construction of transition and ancillary works 237
lining and to TBM-based excavation 233 7 - INSTRUMENTATION 238
4.3.5 - Parameters which can be integrated in the
7.1 - Aims 238
different methods of analysis 233
4.4 - Proof of concrete and reinforcement 235 7.2 - Monitoring methods 238
4.4.1 - Choice of segment wall thickness 235 REFERENCES 239
4.4.2 - Circumferential reinforcement (hoops) 235 ANNEX : 239
4.4.3 - Longitudinal reinforcing bars (arranged parallel TUNNEL LINING CONSTRUCTION -
to the tunnel axis) 235 PRECASTING AND INSTALLATION 239

FOREWORD

T he present text is aimed first and foremost at the different active parties (Owners, Owner's Representatives and Engineers, Consulting
Engineers, Contractors) working in the field of TBM-based mechanized tunnel driving.
The prime aim of the present document is not only to avoid certain past mistakes in the design, sizing and construction of precast concrete
segmental linings installed at the rear of a TBM, but also to contribute to extending know-how in these areas based on the experience gained
over the last decades by the various parties practising of this technique.
It is hoped that this text will stimulate the wish of all those concerned to make progress in relation to the technical aspect of this type of lining
and technology involved.

I - GENERAL 1.2 - Scope of application concrete tunnel linings, these recommenda-


of recommendations tions recall in a section covering design:
the functions which linings must fulfil,
1.1 - Purpose of recommenda-
The present recommendations deal exclusi- the different elements forming tunnel
tions
vely with the case of precast concrete seg- linings and their roles,
ments linings.
The aim of the present recommendations is stressing, in particular, the important points
to provide guidelines for the design, sizing Thus, tunnel lining designs based on using to be complied with to ensure satisfactory
and construction of precast concrete seg- other materials, such as cast iron or steel, or behaviour of the structure during construc-
ments linings installed at the rear of a TBM. having recourse to a mix of these materials tion and throughout its life.
do not fall within the scope of these recom-
In par ticular, they are intended to update The document subsequently reports on the
mendations and call for a specific recom-
and complement past recommendations sizing aspect of linings in relation to which it
mendation drafting project.
presented by A.F.T.E.S. Working Group 7 is impor tant to recall immediately the
(Tunnel Suppor t and Lining) entitled On the other hand, the expression "installed essential osmosis, in the general sense
"rcommandations sur les revtements pr- at the rear of a TBM" does not limit the (design, analysis, construction) of the word,
fabriqus des tunnels circulaires creuss au scope of application of this text to only which must prevail between TBM and lining
tunnelier" (recommendations for prefabri- linings installed within the TBM shield tail; it designers. This process will result in the
cated linings of TBM-driven circular tunnels) also includes linings installed outside the avoidance of many sources of malfunction
(Tunnels et Ouvrages Souterrains (T.O.S.) area occupied by the shield tail, such as liable to lead, in some cases, to cer tain
Special Issue 05-88). linings formed from expanded segments. design inconsistencies at times detrimental
They are also based on other past recom- Thus, following a brief historical reminder to the long-term performance of the struc-
mendations published by A.F.T.E.S. describing the emergence of precast ture.

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


210
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

Thus, the following aspects will be addres- Since that period, several hundred kilo- 3.2 - Basic data required to
sed in this section of the recommendations: metres of generally small diameter tunnels design a tunnel lining
the main parameters influencing sizing; driven in the London area have been lined
with concrete segments of various shapes Prior to designing any tunnel lining, it is
design assumptions (regulations and and types; they are often ribbed, in other
recommendations, types of materials, essential that Owner s, Owner's
words their shape stems from that of cast Representatives and Engineers specify the
actions and combined actions, sizing crite- iron segments. It should be noted that, most aims and constraints which the planned tun-
ria); of the time, these underground structures nel structure must satisfy:
methods available to the design engineer were built in very low permeability ground
its function(s): rail or road transpor t,
for analysing soil-str ucture interacting in which the excavated periphery offered
water or air conveyance, power or data
stresses and where the refinement of the short-term stability (London clay).
conveyance, storage, etc.;
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

calculations should be adapted to: In time, British manufacturers offered a its operating life;
- the design levels implemented (prelimi- whole range of standard off-the-shelf tunnel
nar y studies, design studies, construction lining segments covering a wide range of the operating constraints:
studies), diameters (1.5 to 6 m internal diameters). - geometrical criteria (clearance, route,
- the nature of the problems encountered One of the significant features of these seg- construction tolerances, etc.),
(sensitivity of the site to ground deforma- ments was their small size and reduced - type and location of all permanent facili-
tions, closeness of other structures, etc.); weight (100 to 400 kg per segment), which ties (benches, inver t slab, wall recesses,
resulted in a large number of ring elements branches, hangers, connector inser ts, wall
cation of the different structural elements for the largest diameter tunnels (12 seg- pockets, suppor t systems for intermediate
forming the lining. ments per ring for a diameter of the order floors and ventilation ducts, etc.),
Moreover, the recommendations draw of 6 m). - roughness criteria for the permanent
attention to the essential control of certain Since 1965, major development in the use works compatible with projected water or
unusual design aspects, such as transition of concrete segments linings in Europe air flows (precast lining possibly combined
between the lining and different types of (Germany, Belgium, Austria, France) and with and internal cast-in-place lining),
underground structures (stations, terminals, Japan is notewor thy, in parallel with the - water tightness criteria (acceptable see-
addits, shafts, pipes, etc.), often causing pro- development of TBMs for excavating large page flows both from outside to inside and
blems which are awkward to deal with. diameter tunnels (approximately 5 to 10 m) conversely for water conveyance tunnels),
Finally, consideration is given to the particu- in soft and water-bearing ground. - fire resistance criteria,
lar aspects of monitoring and instrumenta- Specifically, mechanized erectors, larger size - possible requirements in relation to steel
tion of this type of structure. segments with ver y low precasting tole- reinforcement equipotential;
An annex specific to tunnel lining construc- rances and elastomeric gaskets capable of
environmental constraints:
tion provides a review of the recommenda- guaranteeing lining water tightness even in
heavily water-bearing ground, have appea- - geology, hydrogeology,
tions advocated to ensure total conformity
between the structure engineered at design red. - aggressivity of surrounding ground,
stage and the implemented finished product - site urbanization (limitation of ground
from segment casting stage to segment settlements, etc.),
erection within the tunnel. 3 - TUNNEL LINING DESIGN - presence of nearby underground struc-
This summary of the content of the recom- tures (existing or future, if known),
mendations reveals the full range of the 3.1 - Introduction - seismicity;
areas affecting the design and construction structural sizing criteria resulting espe-
of precast concrete segments linings instal- It is essential to state that there is no unique cially from the above-mentioned
led at the rear of a TBM. It also highlights the design for a segmental lining. constraints:
special care which must be applied to every
stage of the project when working towards Very often, its design is based on the expe- - regulations, standards and recommenda-
completion of a quality finished structure rience and skill acquired by Consulting tions to be applied,
whilst complying with production- and Engineers and Contractors on past projects. - actions and combined actions to be consi-
automation/robotization-related demands Consequently, the purpose of this section is dered.
imposed by a concept of this type. to review the main factors entering into the
design of this type of lining and to draw
attention to cer tain vital engineering 3.3 - Lining functions
aspects, of which a perfect command is
2 - HISTORICAL REMINDER required. It cannot recommend a single type 3.3.1 - Functions associated with
of lining design to reader because too many operating constraints
Up to 1930, TBM-driven tunnels were
mainly lined using cast iron segments. interdependent factors come into play.
During tunnel operation, the segmental
Thereafter, precast concrete segments tun- On the contrary, over-precise recommen- lining may be required to fulfil the following
nel linings started to appear, mainly in Great dations, which do not integrate all the para- functions, which depend entirely on the
Britain, for small diameter tunnels (1.5 to 3 meters, could prejudice construction of a pre-established aims of the Owner, the
m) driven in London clay for use as sewers. quality structure. Owner's Representative and the Engineer :

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


211
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

To act as permanent tunnel lining/support 3.4 - Description of the Segment


compatible with the various environmental concept
constraints;
To act as an envelope intended to ensure 3.4.1 - General
permanent compliance with tunnel opera-
ting clearance(s); An impor tant criterion for tunnel lining
To ensure imperviousness with respect to: design lies in the requirement or not to
interface driving and lining installation func-
- water inflows from the enclosing ground, tions for the purpose of ensuring throu-
- possible fluids flowing freely or under ghout the tunnelling period:
Ri
pressure within the structure. ng
total continuity of tunnel support;
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

It should be recalled that structural imper- total control of water inflows.


Figure 1 : Lining comprising precast segment rings
viousness depends on the ability of the
Continuity is thus initially provided by the
lining elements to oppose the passage of a
TBM shell itself (the shield tail with its rear either parallel plane surfaces, as in the
fluid (water, etc.), both from outside to
seal) and thereafter by the lining, incorpora- case of so-called straight rings;
inside and conversely, within the leakage
ting its water tight gaskets, installed inside
flow limits specified for its operation; or out-of-parallel plane surfaces, as in the
the shield tail.
To ensure air or water conveyance depen- case of so-called tapered rings.
It goes without saying that these design
ding on whether the structure is likely to Depending on the arrangement retained,
options depend entirely on the geological
have to ensure the flow of air (piston relief) the latter ring geometry allows the lining to
and hydrogeological conditions of the sur-
or water respectively; rounding hydrogeological environment best adapt itself to curvature in the hori-
To provide support for permanent service through which the tunnel passes. zontal and vertical alignments of the tunnel
mobile and fixed equipment. or to correct accidental deviations caused
3.4.2 - General aspects of tunnel by the TBM.
3.3.2 - Functions associated with lining design
construction constraints 3.4.3 - Tapering of rings
A precast concrete lining for a TBM-driven
During the construction phase of the tun- tunnel generally comprises a sequence of Ring taper "p" is defined as the difference
nel, the segmental lining may be required to rings placed side-by-side.These rings are divi- between the maximum and the minimum
fulfil some of the following functions resul- ded into sectors and each of these elemen- lengths of the ring and must be dimensio-
tary units is called a segment (see figure 1). ned to ensure that design curves are com-
ting from both construction and environ-
plied with and to allow TBM deviations to
mental requirements: The transverse faces of the rings (see figure be taken up. It can attain several centi-
To provide to the tunnel: 2) can be formed by: metres (see figure 2).
- either immediate suppor t, mainly when
drawing in the TBM shield tail in soft ground,
- or deferred support, when the lining is ins- Straight Curved
talled outside the TBM shield tail; the per-
ipher y of the excavation is stable in the
shor t-term within an enclosing soil-rock
mass of sufficiently low permeability to
allow work to be carried out in satisfactory
conditions, without having recour se to
immediate continuous support;
To provide protection against water
inflows, when tunnel driving is undertaken Straight ring Plan view
Left or right tapered
in water-bearing ground; trapezoidal ring
To provide longitudinal support allowing Straight Curved
the TBM to:
- penetrate the ground,
- if necessary, exert confinement pressure at
the excavation face to ensure its stability
and that the hydrostatic pressure applied to
the TBM cutterhead is taken up;
To support the back-up equipment and
construction plant required for carrying out Universal tapered ring Plan view
the work;
To ensure evacuation of drainage water. Figure 2 : Sequence of rings

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


212
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

Development of techniques (control of Segment Although often used in the past, today their


supply to the workface) tends to favour the use is almost exclusively confined to struc-
use of the universal tapered ring. tures such as shafts. They require an larger
excavation diameter than solid segments for
3.4.4 - Length of rings the same sectional area and inertia.The size
of the hollows allows implementation of an
The ring length may depend on: assembly system based on straight bolts,
operation-linked criteria: which requires greater rearward clearance
during erection than other assembly sys-
- tunnel diameter tems.
- alignment design (horizontal and vertical
3.4.7 - Nature of lining materials
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

radii of curvature),
- limitation of the length of gasket sealing The main constituent materials of a tunnel
material and thus of the risk of a defect in lining are:
tunnel watertightness; concrete, containing:
construction-based criteria: - cement,
- optimization of driving (mucking) and Figure 3 : Typical cross-section of a ring - aggregates,
lining installation cycles,
- admixtures
- size of rings (impact on design of TBM
reinforcing steel.
thrust mechanisms: stroke of thrust cylin-
ders, etc.), 3.4.7.1 - Cement
3.4.6 - Segment geometry
- weight of ring segments (impact on yard- Preference should be given to using addi-
and tunnel-based segment handling equip- The geometr y of a segment is essentially tive-free rapid-hardening cements, whose
ment). linked to the type of ring assembly system durability is unaffected or little affected by
retained. steam curing.
Ring length is generally between 0.60 m and
2.00 m. The following shapes can be distinguished: For this type of application, use of standard
"Solid" segments: CPA-CEM I-type cement is therefore pre-
3.4.5 - Composition of a lining ring These are the most frequently used today;
ferred to the following cement types:

The number of segments comprising a ring almost their full wall thickness contributes - CPJ - CEM II
varies widely from one tunnel project to to the strength of the ring.They incorporate - CLC - CEM V
small size pockets allowing assembly of the
another and is subject to the following - CLK - CEM III
different parts of the ring (by anchor bolts,
constraints:
cur ved bolts, plugs, etc.; see 3.5.5 - - CHF - CEM III.
operating constraints: Segment assembly systems);
However, the latter types can be considered
- limitation of the number of segment "Hollow" or "ribbed" segments: for tunnel linings in aggressive ground
contact joints, therefore of the risk of a
defect in tunnel watertightness,
- limitation of head losses due to seepage of Figure 5 : "Hollow" and "ribbed" segments (Caracas
Underground - Lines 1 and 2)
internal fluids;
construction constraints:
- weight of segments (impact on formwork
stripping operations, handling, yard storage,
ring erection using erector arm),
- size of ring elements (transport from pre-
cast yard, supply to the workface),
- impacts on concreting conditions (curva-
ture),
- segment behaviour under TBM thr ust
(limitation of risk that cracks will appear
under temporar y stresses resulting from
bearing defects between rings),
- positioning of TBM thrust mechanisms.
- ring-to-ring assembly constraints (layout Figure 4 : "Solid" segments
of ring assembly devices). (Lille Underground - lines 1 bis - section B)

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


213
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

3.5 - Lining installed within


the area enclosing the TBM

The various operating and environmental


Lining wall thickness (cm)

constraints referred to above ver y often


impose erection of the lining rings under
cover of the TBM in the rear par t of its
shield tail.
Different points entering into the design of
this type of lining are enlarged upon in the
following sections.
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

3.5.1 - Ring design principle


As already referred to above in Section 3.4,
this lining design can require the adoption
Lining internal diameter (m) of:
either straight rings to be used for the
final lining - open face TBM temporary lining - open face TBM straight sections and tapered rings (or tape-
final lining - compressed air TBM temporary lining - compressed air TBM red wedges) to be used specially for curved
final lining - slurry pressure TBM temporary lining - slurry pressure TBM sections of the tunnel route and/or for cor-
final lining - earth pressure TBM temporary lining - earth pressure TBM recting TBM deviations.
or universal tapered rings to be used on a
Figure 6 gives an idea of the increase in segmental lining wall thickness with respect to the tunnel internal diameter.
systematic basis, including for straight sec-
tions of the tunnel route; the tapers of one
ring compensate for those of another ring,
thereby cancelling out the overall tapering
conditions based on special mix design and The use of standardized water-reducing
effect.
production if necessary. superplasticizers is recommended to obtain
increased workability to achieve higher It should be noted that this second type of
Use of CPA - PMES-type cement may be
strength. design, besides being the most frequently
recommended for certain applications.
used, implies fabricating specific moulds for
N.B. In France, studies are being conducted each segment (the amount of taper being
3.4.7.2 - Aggregates on the fire resistance of silica fumes within different from one segment to the another).
In general, the nature of fine and coarse the framework of the BHP 2000 national
aggregates used depends on the available project. 3.5.2 - Composition of rings
quarries in the area where the tunnel is to
be built. 3.4.7.4 - Reinforcement In general, division of a lining ring into seg-
Aggregate sizes must suit perfectly the geo- Grades of steel used for segment reinfor- ments depends on the ring erection tech-
metrical accuracy of the segments, form- cing cages must comply with applicable nology retained.
work recesses, reinforcement arrangements standards.
and possible connector inserts. 3.5.2.1 - Rectangular and trapezoidal
The most commonly used steels are wel- segments
The proper ties of these materials will be dable hot-rolled or cold-worked Fe E 500
specified on the basis of physical and chemi- This design does not generally allow the
and Fe E 235 grades. excavation cycle to be restar ted until the
cal analyses and examinations. In particular,
aggregates will be sought which are frost- Should hot-rolled steel, generally featuring a ring has been completely erected.
resistant, unreactive, sound, free of fines, large quantity of mill scale, be used, care The gap available between the extrados of
non-absorbent, non-brittle and hard. Sands must be taken to remove this scale before the ring being erected and the intrados of
should preferably contain (mineral) filler. welding (during straightening of coiled steel the shield tail is usually small and ring clo-
Continuous aggregate grading should be or by shot blasting steel bars). sure is very often ensured by a longitudinal
specified to ensure good workability when key, which requires additional forward space
placing the fresh concrete in the moulds. 3.4.7.5 - Reinforcing fibres to allow insertion of this final segment.
Use of metal fibres, exclusively or in addi- To partially satisfy this constraint, use of a
3.4.7.3 - Admixtures tion to conventional reinforcement, has key segment of "trapezoidal shape" in plan
In cases in which aggregates lack fines, use of been experimented in cer tain works. In (see figure 7) is very often resorted to.
additional fly-ash or fillers (e.g. limestone- France, studies are in progress for the pur- Consequently, the geometr y of the seg-
based materials) are recommended. The pose drawing up relevant design r ules, ments adjacent to this ring part will have to
origin of such products should of course be within the framework of the national metal be special to suit that of the key: these adja-
checked. fibre reinforced concrete project (BEFIM). cent elements are called counter segments.

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


214
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

Key

SECTION AA

Direction
Key
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

of advance

Figure 7 : Longitudinally inserted key segment

Figure 8 : Rectangular and trapezoidal segments - perspective view


Thus, in this type of design, a lining ring
generally comprises:
rectangular virtually identical (apart from
possible taper) standard segments, whose DIRECTION OF TBM ADVANCE
number can vary from one project to ano-
ther (see figure 8);
Key segment
two counter segments;
Standard segment Counter segment
one key segment.
Assembly of these ring elements is often
under taken by means of bolts or anchor
bolts (see 3.5.5 - Segment assembly sys-
tems).
In general, contact faces between segments Segments are numbered in accordance with their order of placement
are offset longitudinally both to prevent
defects in watertightness at the corners and Figure 9 : Rectangular and trapezoidal segments -
to maintain a certain pressure on the seg- longitudinal offsetting of contact faces between segments
ments previously placed to prevent them
from loosening completely when the TBM
thrust cylinders are retracted (see figure 9).
In some cases, these contact faces can be DIRECTION OF TBM ADVANCE
aligned (see figure 10); this configuration
can be adopted in particular : Key segment
at future openings (entrances to cross- Standard segment Counter segment
tunnels, etc.) to be provided in the lining;
in areas in which alignment corrections
are made essential (special care must then
be taken in relation to measures to be
adopted to guarantee water tightness at
segment corners);
Segments are numbered in accordance with their order of placement
if defects in water tightness at segment
corners are not a concern (systematic align- Figure 10 : Rectangular and trapezoidal segments -
ment of contact faces). longitudinal alignment of contact faces between segments

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


215
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

Two different ring designs can be conside- front of the existing pockets in the pre- carried out simultaneously (stroke of thrust
red with this type of rectangular or trape- viously erected ring in order that they can cylinders adapted to two ring lengths).
zoidal segment: then be driven in hard. In general, a ring is broken down into an
Universal segment The segment being erected is pushed longi- even number of trapezoidal segments. Half
As its name suggests, this design requires tudinally on the projecting section without the segments are "counter" type, i.e. wider
only one set of rings. any real oppor tunity for crosswise move- on the side of the previously placed ring.
ment. For this reason and for the purpose of The other half are "key" type, i.e. narrower
The key segment can then be erected in any maintaining gradual transverse compression on the side of the previously placed ring
angular position. of the radial gasket section (between seg- (see figure 16).
ments) whilst sliding the segment longitudi-
nally, standard segment geometr y is desi- Once in place, the counter segments pro-
gned in the shape of a parallelogram. vide suppor t for the thrust cylinders, the-
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

reby allowing the TBM to advance again.


Thus, this type of lining ring usually com- During this time, ring erection can continue
prises (see figure 13): with the key segments, as long as the shield
parallelogrammic standard segments , tail seal is not crossed. Subsequently, rear
Key segment at Key segment at
whose number varies from one project to support for the thrust cylinders is transfer-
bottom of ring top of ring another ; red to the key segments without halting
one reversed key segment; TBM penetration.
Figure 11 : Sequence of universal rings
one key segment. This continuous penetration method
requires the following problems to be over-
"Left" and "right" rings Configuration 1, shown in figure 14, requires come:
segments to be erected in the same order
This type of design necessitates resorting to of placement from one ring to another. placement of "key" segments between the
two sets of rings, to which the following Under the pressure exerted by the longitu- "counter" segments;
constraints apply: dinally oriented waterproofing gaskets (bet- total thrust can be mobilized using only
- ring taper, ween segments of the same ring), the rings some of the thrust cylinders or continuous
- key and counter segments with specific can be gradually subjected to disruptive penetration is limited to certain favourable
geometry, rotation in the absence of transverse bolts.
ground conditions requiring reduced thrust;
In time, this rotation can lead to a discre-
- key positions limited to the upper semi- pancy of several centimetres between the more difficult guidance.
circumference of the ring. position of the rings and that of the TBM
If necessary, "left" and "right" rings can be thrust cylinder ram pads. 3.5.3 - Contact surfaces
transformed into universal rings (correction To overcome this gradual rotation, a solu-
of tunnel alignment deviations, etc.). 3.5.3.1 - Circumferential or trans-
tion based on alternate segment erection verse contact joints
with respect to the first ring part placed is
recommended (see figure 15). Contact joints between adjacent rings can
be required to bear :
3.5.2.3 - Trapezoidal segments compressive (possibly eccentric) loads
This ring design may allow tunnel excava- resulting from the longitudinal thrust of the
tion and lining erection operations to be TBM;

Figure 12 : Sequence of "left" and "right" rings - key sys-


tematically positioned above the horizontal diameter

Contractors' final choice of one or the


other type of rings is very often based on
practices tested at length on different pro-
jects.

3.5.2.2 - Parallelogrammic and trape-


zoidal segments
This ring design is associated with the use of
plugs incorporated in the lining wall at the
contact face between successive rings
(transverse contact face) (see 3.5.5 -
Segment assembly systems).
When erected, segments are fitted with
these projecting plugs, which are lined up in
Figure 13 : Parallelogrammic and trapezoidal segments - Perspective view

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


216
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

shear forces due to differential deforma-


tions between adjacent rings associated DIRECTION OF TBM ADVANCE
with:
- offsetting of contact faces between rings Reverse key type segment Key type segment
(see figure 9), shear being transmitted by
permanent ring assembly systems (bolts,
anchor bolts, plugs, tenons, etc.),
- non-uniform load distributions resulting
from the ground or from neighbouring
structures. Segments are numbered in accordance with their order of placement
Obviously, assembly systems offer different
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

capacities for opposing potential displace- Figure 14 : Parallelogrammic and trapezoidal segments - Configuration 1
ment of the ring parts with respect to each
other (out-of-flushness). DIRECTION OF TBM ADVANCE
The final geometry of these contact joints
and their possible additional equipment
must be selected in relation to the purpose Key type segment Reverse key type segment
of the tunnel (wastewater collector, water
conveyance, rail or road tunnel, etc.) and
must be compatible with the out-of-flush-
ness tolerance.
forces resulting from segments overhan-
ging (accidentally or otherwise) during ring Segments are numbered in accordance with their order of placement
assembly.
These contact joints usually fall under one Figure 15 : Parallelogrammic and trapezoidal segments - Configuration 2
of the following types:
a) plane contact joints DIRECTION OF TBM ADVANCE
This contact principle is shown diagramma-
tically in figure 17.
Key type segment Reverse key type segment
Depending on the relative intensity of the
forces described above, radial slippage can
occur leading to out-of-flushness of one
segment with respect to an adjacent one.
Addition of mechanical systems (see
3.5.5.) can help to limit the extent of this
Segments are numbered in accordance with their order of placement
phenomenon.
Out-of-flushness can be acceptable or
Figure 16 : Trapezoidal segments
unacceptable depending on the purpose of
the tunnel (temporary or permanent, air or
water conveyance function to be fulfilled). b) combined geometry contact
When it is unacceptable, it may be possible excavation
joints
to turn to combined geometr y contact
joints of a form allowing transfer of shear This type of contact joint, shown back grouting

forces. in figure 18, is less common than


extrados
waterproofing
excavation gasket

back grouting

extrados boss
waterproofing gasket intrados

plane contact joint

intrados
boss

Figure 17 : Plane contact joint Figure 18 : Example of combined geometry contact joint

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


217
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

excavation excavation

back grouting back grouting

extrados waterproofing gasket extrados waterproofing gasket

convex face concave face

plane contact joint

intrados intrados
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

Figure 19 : Example of plane contact joint Figure 20 : Example of concave-convex cylindrical contact joint

the one above because it is difficult to The final geometry of these contact joints concave-convex cylindrical contact joints
reconcile erection tolerances with the load must therefore be guided by the following (see figure 20):
transfer efficiency which could be assumed aims:
The radius of curvature of the concave sur-
from such a system. to allow correct centring of stresses; face may be greater than that of the convex
Moreover, there is a danger that very high to limit the danger of segment out-of-flu- surface in cases when rotation of ring parts
local stresses will develop in the load trans- shness, which both generates disruptive in contact is expected or, conversely, these
fer zones (boss, tenon and mor tise, etc.) loads and can be detrimental to the pur- radii of cur vature can be essentially the
and reinforcement of these zones, by means pose of the tunnel (e.g. air or water same (the system is then intended to pro-
of reinforcing bars, is often delicate simply conveyance). vide shear strength only);
because of the contact joint geometry. In These contact joints are usually one of the
this type of design, it is thus essential to convex-convex cylindrical contact sur-
following types: faces (see figure 21).
study carefully the geometr y of such
contact joints. a) Plane contact joints c) Other contact joints (see figure 22).
Finally, normal loads are necessarily concen- This type of contact joint, shown in figure
Incorporation of a guide rod can be adop-
trated on reduced surfaces which must be 19, is the most commonly used because, in
general, it is sufficient for transferring the ted in some cases.
capable of sustaining such loads.
forces applied to the rings.
3.5.3.3 - Flanks
3.5.3.2 - Radial or longitudinal contact A mechanical assembly system is generally
joints incorporated; it contributes to maintaining Given the intensity of compressive stresses
erection accuracy by preventing, in particu- often applied to the contact surfaces, whe-
The effects of both the surrounding ground ther they be transverse or longitudinal,
conditions and back grouting cause these lar, gradual drift in both segment alignment
and intersegment contact. experience gained from past projects leads
contact joints between segments of the
to the recommendation that ver y special
same ring to be subjected to: b) Cylindrical contact joints care should be taken in designing segment
compressive loads; When ring stresses are too high to consider flanks in order to limit breakage at their
bending forces: plane contact surfaces, joints are often desi- edges to a minimum.
It should be noted that bending forces are gned with cylindrical surfaces.
It should be borne in mind that these frac-
reduced in the immediate vicinity of the Through plasticizing the concrete, the tures, which are often observed in the seg-
radial contact joint. The inertia of this zone contact surface widens gradually in relation ment intrados and repaired by simply resto-
is effectively lowered with respect to that of to the load and centres it. ring, can also affect the extrados of lining
the standard section; These contact joints can be of different ring par ts and can lead to local damage
transverse shear forces. types: which is difficult to repair and is prejudicial

excavation excavation

back grouting
back grouting

extrados extrados waterproofing gasket

convex face convex face guide rod

intrados intrados

Figure 21 : Example of convex-convex cylindrical contact joint Figure 22 : Example of contact joint incorporating a guide rod

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


218
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

- risk of accident to personnel in charge of 3.5.4.1 - Compressible gasket sections


segment mould-based operations (sharp a) Properties
projecting edges for forming chamfers).
It should be recalled that these are elasto-
To avoid these risks, it is preferable to pro- meric gaskets, which have been designed
vide either sharp edges or, if this chamfer is and manufactured for fitting to precast
retained, to incorporate a foam rubber (or concrete lining segments (see figure 24).
similar) seal over its full length; this Watertigntness is ensured by compressing
construction-based provision will thereby
them during erection and maintaining this
solve the first problem but not the second.
compression throughout the life of the
structure.
3.5.4 - Waterproofing gaskets
During construction, the compressive load
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

It should be recalled that, when an water- is applied by the TBM thrust cylinders or
Figure 23 : Spalling and cracking of concrete cover proofing function is sought from a segmen- segment erector and is temporarily maintai-
tal lining, this can be fulfilled by: ned by the ring building system.
the segments themselves, for which it is Watertigntness of gasket sections is guaran-
to the durability of the wor ks (water important to limit in particular : teed for a permanent hydrostatic pressure
ingress, corrosion of reinforcement, etc.). laid down in the project specifications.
- the mass porosity,
Whilst it is advantageous to provide relative - cracking associated with temporar y or b) Construction configurations
large flanks in the contact zones in order to permanent stresses, In general, the gasket is fitted into a groove
overcome the above problems, it should be
- defects involving formation of the groove formed in the segment faces; it is positioned
ensured that the stresses acting on the
receiving the waterproofing gasket; several centimetres from the segment
contact surfaces remain acceptable, inclu- extrados and fitted around the full perime-
ding under unfavourable construction confi- waterproofing gasket positioned between
ter of the segment.
gurations (eccentricity of load from thrust the segments.
cylinders especially in cur ved alignments, Gasket section dimensions must be compa-
Properties of the latter are described in the
erection tolerances, etc.). tible with erection tolerances and take into
"recommandations pour les profils d'tan-
account ring out-of-roundness.
Detailed geometrical design of these flanks chit entre voussoirs" (recommendations
should be undertaken in parallel with that for intersegment waterproofing gasket) In the specific case of water conveyance
presented by A.F.T.E.S. Working Group 9 pressure tunnels, combined behaviour of
of the reinforcement in order to guarantee
(see T.O.S. Issue 116, March-April 1993). the ground / lining must be analysed before
the highest possible strength at these parti-
The remainder of this description applies to possibly modifying the position of the
cularly highly stressed segment sections.
so-called "conventional" waterproofing gas- imper vious gasket within the lining wall
Similarly, in cases in which lining waterproo- kets retained for the design of standard tun- (conventional well tested approach).
fing is to be provided by means of compres- nel projects involving low to medium over-
sible gasket sections, it should be ensured burden. 3.5.4.2 - Water-expansive gasket
that the groove receiving the gasket is posi- a) Properties
tioned sufficiently far away from the extra- N.B. These imper vious systems are not
transposable to other tunnel projects invol- It is recalled that these are elastomeric
dos to avoid the segment edges breaking off
ving very high overburden (e.g. major Alpine waterproofing gasket with water-expansive
when the system is compressed under load.
crossings). Research work (International properties, i.e. they swell in the presence of
Moreover, whilst it has been the practice to Eureka Contun) is in fact being conducted water.These cycles can alternate during the
provide a chamfer around the extrados concerning the design of TBMs and tunnel life of the works.
edges of both transverse and longitudinal linings suited to the special constraints
If necessar y, initial water tigntness can be
contact joints, this may give rise to certain imposed by such projects. On account of
achieved by compression. The presence of
drawbacks such as: the very high pressures liable to be exerted
water then triggers swelling of the water-
on these linings (loads induced by both
- risk of defective imper viousness of the ground and water), thoughts are very natu- expansive material, which allows the applied
TBM tail seal with respect to the back grou- rally tending towards seeking a reduction in hydrostatic pressure to be resisted.
ting product, water in the surrounding their rigidity by incorporating a degree of Watertightness of gasket is guaranteed for a
ground or slurry from the forward chamber deformability in par ticular at their water- permanent hydrostatic pressure laid down
(in cases involving hydraulic confinement); proofing gaskets. in the project specifications.

Water-expansive parts

Neutral parts
Figure 24 : Examples of compressible waterproofing gaskets Figure 25 : Examples of water-expansive waterproofing gasket

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


219
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

In some cases, these gasket can be reinfor- Double thickness gasket system Single thickness gasket system
ced by "neutral" (non water-expansive)
parts (see figure 25).
b) Construction configurations
The gasket is positioned on the segment
sides several centimetres from its extrados.
There are two types of construction confi-
guration (see figure 26).
In the double thickness system, gasket are
Direction of advance
fitted around the full perimeter of each seg-
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

ment.
Figure 26 : Layout principle for waterproofing gaskets
In the single thickness system, gasket are fit-
ted around half the segment perimeter with
a return of several centimetres at diagonally the combined section is fitted around the When they exist, assembly systems bet-
opposing corners. full perimeter of each segment and positio- ween segments in the same ring generally
As in the case of compressible sections, ned several centimetres from its extrados. comprise between one and three units.
waterproofing gasket dimensions must be In standard rings, longitudinal and trans-
compatible with erection tolerances and 3.5.5 - Segment assembly systems verse assembly systems are usually only
take into account ring out-of-roundness. essential during construction (except when
3.5.5.1 - Purpose of assembly systems wanting to take advantage of the contribu-
3.5.4.3 - Combined gaskets tion to rigidity of adjacent rings whose
Assembly mechanisms implemented at cir-
a) Principle cumferential (transverse) and radial (longi- radial contact joints are then combined).
These are products which combine both tudinal) contact joints are aimed at: As a general rule therefore, these assembly
types of gaskets described above. maintaining sufficient erection accuracy by systems can be removed when the TBM is
preventing gradual cumulative out-of-flush- more than 200 metres away and all additio-
The compressible gasket represents the nal grouting operations have been comple-
basic component and the water-expansive ness between segments and gaps at contact
joints; ted.
gasket is usually fitted into the groove for-
med in the former (see figure 27). keeping waterproofing gasket compressed In the vicinity of stations, longitudinal assem-
in the short-term, during construction, and bly systems are usually necessar y during
This composite product allows the water- tunnel operation to keep the waterproofing
proofing system offered by either the com- even in the long-term, during tunnel opera-
tion, especially in the vicinity of stations; gaskets compressed. They are therefore
pressible or the water-expansive gasket to kept in place over a minimum tunnel length
be complemented. ensuring segment stability at ring building of two or three diameters.
b) Construction configurations stage, even when there no load is exerted
by the TBM thrust cylinders. However, mea- The durability of all permanent assembly
As in the case of the compressible gasket, sures might be adopted to ensure this stabi- systems must be the same as that of the
lity without necessarily resorting to the use structure itself.
Removal of strip forming of assembly systems (e.g. a thrust cylinder
anti-retract system); 3.5.5.2 - Bolted assemblies
the groove

ensuring segments are kept in their rela- Bolts or threaded rods are fixed from poc-
tive positions (guidance role) in the specific kets provided on the intrados side of the
case of water conveyance tunnels, for which lining.
linings are required to "breathe" during tun- These bolts are generally of two types:
nel filling and emptying cycles. straight bolts fixed from hollows formed
In general, longitudinal assembly systems are in the intrados of segments:
regular ly spaced along each transver se - bearing directly on the concrete (see
State of compressible section contact joint (between consecutive rings). figures 28 and 29),
whilst "stripping" the groove
Their number varies from one project to - bearing on steel plates inserted in the seg-
another depending on: ments (see figure 30);
"Dovetailed" water-expansive section the forces to be balanced; curved bolts allowing the volume of the
the desired possibilities for relative rota- hollows to be significantly reduced (see
tion of a ring with respect to the last one figure 31).
installed (considering the constraints impo-
sed by the design, such as offsetting of longi- 3.5.5.3 - Inclined socket bolted assem-
Final state with "dovetailed" tudinal contact joints, small deviations in ali- blies
water-expansive section
gnment, etc.). This assembly system allows a reduction in
the number of pockets in the intrados of
Figure 27 : Example of combined waterproofing gaskets

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


220
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

Washer
Extrados Extrados

Intrados
Nut
Bolt Pocket
Washer Washer Pocket Intrados
Washer Threaded Nut
Nut
Pocket rod
Figure 28 : Example of removable assembly using straight bolts Figure 29 : Example of permanent assembly (straight bolts previously inserted into one
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

of the segments before placing the adjacent segment)

Pocket
Steel plate 3.5.5.4 - Assemblies using plugs, studs Plug
Extrados or other derivatives
Back grouting
Compared with the assemblies described Extrados
Excavation
above, such systems (see figures 33 and 34)
can offer a number of advantages such as:
no pockets in the intrados of segments, Plug
thereby providing the lining with improved
Intrados Connector insert air or water conveyance properties;
Nut
Washer Bolt reinforcement of ring par ts is often Intrados

Figure 30 : Example of steel plate assembly using short bolts


easier ; Pockets
Segment being placed Ring erected
simplified ring erection operations;

Curved bolt
good centring of rings with respect to
each other (reduced out-of-flushness); Plug
Extrados
high shear strength (with some types of
Back grouting
plug); Excavation
Extrados
greater safety of personnel (no human
intervention inside the ring).
Intrados Nut Apar t from the fact that most of these
Washer Pocket Bolt head
devices cannot be removed, they can fur-
Segment being placed Ring erected thermore inhibit cer tain degrees of free-
dom, which may result in excessive lining Intrados
Figure 31 : Example of assembly using curved bolts stresses. Pockets
When designing and sizing these assem- Segment being placed Ring erected
Socket blies, it is therefore essential to evaluate as
Extrados Figure 33 : Examples of assembly using plugs
closely as possible all the loads to which
such connections are likely to be subjected
(e.g. dissymmetry of thrust cylinder loads,
overhanging of segments, differential ring

Back grouting

Intrados
Pocket
Socket
bolt Anchor bolt Excavation
Segment being Washer head Extrados
placed Ring erected

Figure 32 : Example of assembly using inclined socket bolts

the segments.This design also allows tighte-


ning up operations to be carried out under Intrados
cover of a fully erected ring and no longer
under segments only held in place by the Segment
erector arm and the TBM thrust cylinders; being placed Ring erected
this system thereby ensures increased safety
of personnel (see figure 32). Figure 34 : Examples of assembly using pins

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


221
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

out-of-roundness, waterproofing gasket temporary functions: dimensional underestimation (see figure 35)
crushing and distortion loads, local stresses - handling, erection (e.g. for picking up units or an unsuitable layout.
capable of reducing the assembly capacity using "grippers" or "pins"), Materials used can be very different depen-
of the system, tendency for key ejection, ding on design philosophies retained. They
etc.) in order to prevent the appearance of - assembly (holes and boxes for inserting or
fixing assembly mechanisms, etc.), can be of low stiffness and even behave like
disturbances concentrated at these connec- "flowing" (e.g. bitumen-based) materials or,
tions, which could adverse affect the durabi- - grouting (holes through the segment wall), on the other hand, they can be relatively
lity of the structure. stiff (e.g. hard Isorel).
- precutting (e.g. to facilitate later formation
of openings at in-line structures).
3.5.6 - Connector inserts, pockets 3.5.8 - Back grouting behind ring
permanent functions
Pockets, as well as most connector inserts extrados
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

- traceability (recess for identification of


fitted to lining segments, represent sources
characteristic zones),
of reduced strength of the reinforced 3.5.8.1 - Purpose of back grouting
concrete ring elements. Their potential - building in of specific equipment,
The purpose of these grouting operations is
impact on segment structural behaviour - instrumentation (concrete control blocks, to fill the annular gap between the lining
(including during construction stages prece- etc.). extrados and the TBM-excavated ground
ding ring erection) as well as on the pur- profile.
pose of the tunnel must, therefore, be clo- These pockets can sometimes lead to struc-
sely examined. tural weakening of the segments concerned The grouting material therefore fulfils seve-
and very often complicated detailing of ring ral functions:
3.5.6.1 - Connector inserts par t reinforcement (local discontinuity of in the short term:
In general, connector inserts can fulfil two reinforcing bars, etc.). It is thus important to
- it ensures efficient blocking of the lining
sets of functions: limit their number and size to a minimum.
against the enclosing ground to reduce the
Moreover, in the case of designs involving
temporary functions : danger of ring displacement especially
high air- and water conveyance-based during TBM thrusting and passage of the
- handling, erection (socket for segment constraints, their presence on the segment back-up equipment, when support is essen-
pick-up bolts, etc.), intrados requires the adoption of often tial,
- adjustment, costly special measures (sealing of "boxes",
internal second lining, etc.). - it minimizes surrounding ground deforma-
- assembly (sockets for bolts, etc.), tions likely to cause disorders both above
- mating (pre-grouted sockets, etc.) and below ground (especially in urban
3.5.7 - Stuffings for distributing
and/or sensitive environments),
- grouting; loads at segment contact joints
- in the case of pressurized face TBMs, it
permanent functions: Incorporation of stuffings may be called for provides good control of confinement pres-
- traceability (identification of characteristic to distribute TBM thrust loads over ring sure (especially when using compressed air)
zones, etc.), interfaces (circumferential or transverse by ensuring imperviousness at the back of
contact joints), whilst "smoothing out" as the machine;
- fixing (pre-grouted sockets for supporting
service equipment or floors, etc.), much as possible inaccuracies resulting from in the long term:
both segment precasting tolerances (often
- mating, connection, - it ensures the most uniform bond bet-
ver y low) and erection tolerances during
ween the lining and the ground and there-
- instrumentation (vibrating wire extenso- ring building, or to "channel" these loads fore offers effective distribution of confine-
meters, total pressure measuring cells, etc.), towards specially reinforced sections of the ment loads at this interface; an essential
- inspection. segments. condition for guaranteeing the durability of
It should be stressed that their positioning These millimetre thick stuffings must pro- the structure, especially when it is a pres-
within the segments sometimes calls for vide sufficient surface area to fulfil their sure tunnel at operating stage,
alterations in segment reinforcement detai- function and, on the contrary, must not be a - in cer tain ver y special cases, it fulfils a
ling in order to: source of "load concentration" through "drainage" function (granular matrix).
comply with concrete coverage require-
ments;
Stuffings for distributing loads
avoid zones occupied by the connector in contact with segments
inserts;
reinforce the concrete immediately in
contact with these connector inserts (local
stresses, pulling out, etc.).

3.5.6.2 - Pockets
In general, pockets can fulfil two sets of
functions:
Figure 35 : Example of distribution of stuffings for spreading TBM thrust loads over a segment flank

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


222
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

3.5.8.2 - Nature of infilling material grouting through the lining by means of


Except for materials with a granular matrix, holes incorporated in the segment struc-
the composition of an infilling material will ture (grouting operation generally not
controlled by the TBM);
determine:
continuous grouting at the rear end of the
its rheology:
shield tail through integrated grout pipes
the infilling material must, on the one hand, arranged longitudinally within the tail (grou-
be sufficiently fluid to facilitate its placement ting operation controlled by TBM).
and to fill completely the annular gap and, In general, the latter process provides grea-
on the other hand, be sufficiently firm to ter control of ground deformations.
avoid leakage through the shield tail seals
Grouting pressures to be implemented are
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

and segment waterproofing gaskets, as well


as to avoid seepage flows along the shield determined in relation to the type of infilling
material, geological and hydrogeological
tail towards the front of the TBM.
conditions (ground loads and stiffnesses,
Moreover, its setting time must suit the hydrostatic pressure), lining strength and
construction conditions; construction aims sought (formation of
ground-based suppor t, control of ground Figure 36 : Example of expanded ring
its short- and long-term structural proper-
ties: deformations, etc.).
During constr uction, it is impor tant to
the infilling material must suit the ground segments; the longitudinal travel of this key
monitor continuously the grouting pres-
and construction conditions (convergence can vary slightly depending on the ground
sures as well as the volume of material back
of ground, rate of penetration, etc.); its grouted. and the erected configuration of the first
modulus of deformation and compressive segments.
strength must be sufficient to prevent lining 3.5.8.4 - Additional grouting 2 to 3 cm thick pads feature on the extra-
out-of-roundness. dos of the segments allowing both a good
Should the primar y back grouting prove
There are currently two main types of grou- insufficient for the purpose of the structure, bond with the surrounding ground and the
ting material: possibility of light back grouting.
resorting to additional grouting through the
active material: lining may be contemplated. Other ring closure systems have also been
implemented on some projects: double key,
cement-based grout to which fly-ash, sand, 3.5.8.5 - Grouting quality control spring line jacking system.
filler, bentonite, lime and admixtures such as
In general, grouting quality control is prefe-
water-reducing plasticizer, retarder or acce- 3.6.2 - Advantages and draw-
rable to damaging the lining by taking core
lerator may be added; backs
samples. However, the latter do allow the
inert material: quality of annular gap infilling to be ascertai- The advantages of this expended ring solu-
cement-free material comprising a mixture ned, although they should obviously be limi- tion are:
of bentonite, polymers, filler and sand with ted to a minimum.
straightforwardness of implementation;
the possible addition of a plasticizer. The the simplicity of the structure (no water-
material will be termed "semi-inert" if lime 3.6 - Lining installed outsi- proofing gaskets);
or fly-ash is added. de the area occupied by
speed of progress in good ground, when
In the case of sufficiently stable enclosing the TBM
very regular excavation can be maintained;
ground, infilling can be carried out in two
It may be advantageous to erect segments segment erection is very regular and fol-
stages:
outside the area enclosing the TBM when lows the excavated profile because segment
primary infilling with a fine gravel "matrix" ground stability permits and water inflows contact surfaces are cylindrical;
to ensure blocking of the lining in step with are naturally low. saving due to no intersegment bolting.
TBM penetration;
However, there are also quite a number of
secondary grouting to improve bond bet- 3.6.1 - Ring design principle drawbacks to this solution:
ween the lining and the ground, which is
In this case, the ring is built outside the ring building and the TBM guiding system
often deferred and independent from TBM are not interrelated (no rear cylinders);
shield tail after placing the invert segment;
penetration.
ring stability is only ensured after longitudi- ring geometry does not allow them to be
3.5.8.3 - Back grouting implementa-
nal driving in of the key segment which, due deviated one way or the other ; shims have
tion to its trapezoidal shape, expands the ring to be slipped between rings to follow cor-
thereby pushing the segments against the rectly the excavation;
As detailed in Section 3.5.8.1, back grouting surrounding ground.
is carried out in step with TBM advance for "Wingdings" contact faces between rings
The length of the key in the longitudinal are no impervious and it is impossible to
reasons of efficiency.
direction of the tunnel is less than the undertake pressure back grouting to fill in
Two implementation processes are com- length of the ring enabling it to be driven in properly the gap left around the extrados
monly used: to a maximum between the two counter pads;

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


223
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

nothing at all can be done to ensure any confinement pressure; However, tests carried out have allowed the
degree of water tightness if water inflows external hydrostatic pressure; following main results to be brought to
are incompatible with tunnel operation; in light:
this case, a waterproofing membrane and a internal fluid pressure (including hydraulic
transient pressures, in some cases). application of the Colebrook formula is
cast in-situ lining should be implemented if possible with a segments lining;
possible; It should be noted that the geotechnical
parameters (E, c, CARSPECIAUX 102 \f loss of head can therefore be calculated
segment erection becomes highly proble- from an equivalent roughness Ks;
matical when the ground becomes unstable "Symbol" ) of the surrounding ground play a
during excavation or under the action of preponderant role in the relevant states of equivalent roughness can be related to
the grippers (overbreak and block falls); equilibrium and, as a result, they must be the absolute value (s) for the average out-
known for each geological formation cros- of-flushness between segment rings;
a void at the crown must be mortar-filled
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

sed. for 0.60 m long rings and for tunnels with


because the key segment is shorter than the
ring length in the longitudinal direction. In general, cases of adverse loading with diameters less than 3.60 m, the following
respect to opening of intersegment contact formula has been established:
This solution can be advantageous as long
joints are obtained for moderate overbur- Ks (mm) = 0.3 + 60 X (lsl)2/1
as, using the same TBM, it allows segment
den associated with low geotechnical para-
erection inside the shield tail when difficult where s (positive or negative "step") and l
meters.
ground is to be penetrated or water inflows (length of unit) are expressed in mm.
occur. Analysis of overall structural behaviour
must also take into account the presence of N.B.: it is advisable to use this formula with
back grouting which blocks the lining rings care because it has been established from a
3.7 - Specific aspects of limited number of cases and for 0.60 m long
within the surrounding ground.
water conveyance pressure concrete segments of various types
tunnels 3.7.2.2 - Functional aspects (smooth or incorporating pockets);
When the zones which will tend to open Unlike the behaviour of cast-in-place tun-
3.7.1 - Hydrogeological reminders the lining rings have been localized, the nel linings, smoothing by deposits of the
hydromechanical behaviour of the tunnel many out-of-flush locations will tend to
Knowledge of groundwater pressures reduce the equivalent roughness of a seg-
within the soil-rock mass is important when lining structure will then depend on:
ment-lined tunnel. However, estimating not
a tunnel is to be pressurized. This involves, the presence of bolting and its sizing; only this reduction but also that of bore
not only very conventional installation and the degree of contact joint opening with sectional area associated with the presence
reading at regular intervals of piezometers, respect to compression of the incorporated of these deposits (reduction in conveyance)
but also monitoring the regime of surroun- waterproofing gaskets. remains a delicate task for the engineer.
ding springs. The reader is referred to the
text entitled "recommandations pour le choix In general, take-up of tensile loads by bolts
des paramtres et essais gotechniques utiles can only be justified in the shor t-term, 3.8 - Construction tole-
la conception, au dimensionnement et except if suitable anti-corrosive material or rances
l'excution des ouvrages creuss en souter- protection is provided.
rain" (recommendations for the design, the Consequently, elimination of bolting in a 3.8.1 - Specification
sizing and the construction of underground tunnel subject to a tendency for its lining
excavated str uctures) presented by contact joints to open would appear desi- Construction tolerances for segments for-
A.F.T.E.S. Working Group 7 in T.O.S. Issue rable. Structural waterproofing is only then ming the permanent lining of an under-
123, June 1994. ensured if the lining gaskets open only par- ground structure must be specified on the
Once the pre-excavation hydrogeological tially with respect to their compressive basis of general service criteria and must be
conditions have been established, the strain. A factor of safety of 2 is desirable to laid down in the project specifications.
influence of tunnel excavation on behaviour allow possible self-adjustment of the seg- Moreover, they can vary depending on the
of the groundwater table(s) must be deter- ment rings during loading / unloading (tun- lining design retained (expanded segments,
mined. Tunnel-driving in fact often causes a nel pressurizing / depressurizing) cycles. bolted segments, etc.).
collapse of piezometer levels and therefore If such conditions cannot be ensured and Very often, these tunnel operation-related
alter s significantly the hydrogeological total watertightness is required, an additio- tolerances are complemented by other
conditions in the vicinity of the works. nal waterproofing system is then necessary tolerances, in this case associated with lining
(cast-in-place concrete ring, membrane or implementation to ensure correct structu-
3.7.2 - Tunnel lining structural any other suitable process). ral behaviour, as well as the required quality
behaviour of finish and imperviousness.
3.7.2.1 - Geotechnical aspects
3.7.3 - Roughness of segment-
lined tunnels 3.8.2 - Identification of main crite-
Behaviour of a segment ring therefore ria contributing to tolerance speci-
depends on the state of equilibrium of the Relatively few loss of head measurements fication
following forces, the first two tending to have been taken on segment-lined waste-
close intersegment contact joints and the water collectors due to the complex nature 3.8.2.1 - Criteria related to tunnel
third tending to open them: of the means to be implemented. function

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


224
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

Function-related criteria essentially com- ring length (taking into account its pos- - hydrocarbons,
prise: sible taper); - aggressive chemical agents contained in
tunnel internal sectional area flatness of intersegment contact surfaces the ground, in the groundwater and in the
The accuracy sought must satisfy the gene- within the same ring and between rings; liquid conveyed,
ral profile of the tunnel bore over its whole roughness; - micro-organisms,
route; layout and geometry of pockets provided - sulphate,
operating clearances (waterproofing gasket grooves, recesses for - condensation,
For this and for the last point, these criteria plugs or pins, etc.);
- frost,
influence specification of tolerances concer- layout of connector inserts (pick-up soc-
ning the tunnel construction axis with res- kets, bolts, connectors, etc.); - salts,
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

pect to the design theoretical axis; clearances allowed for assembly devices; - fire, etc.
water and air conveyance flows dimensions of reinforcing cages and The use of admixtures influencing the
It is important that project specifications lay layout of the different reinforcing bars to strength of concrete mixes must be chec-
down geometrical criteria (surface rough- ensure: ked to ensure satisfactory performance in
ness, out-of-flushness, etc.) allowing accep- relation to the various forms of attack men-
- suitable corrosion protection, tioned above.
table structural head losses;
- proper operation of parts with respect to Selection criteria referred above must take
layout of equipment fixings or pockets.
contact pressures, into account the requirements of both the
3.8.2.2 - Tolerances associated with - efficient edge reinforcement. contract specifications and current stan-
segment implementation dards.
It is very difficult to recommend the exact
These tolerances can be broken down in tolerance values to be complied with on a Specific impervious treatment (mineraliza-
terms of the following two construction finished product because they depend on tion, impregnation, etc.) can be applied to
stages: numerous parameters such as the overall the extrados of segments to provide pro-
casting: dimensions of the structure to be built, the tection against particular forms of attack.
method of erecting segments and their
- mould geometry, shape.
- bending and fixing of reinforcing steel; 3.9.2 - Steel reinforcing bars
To achieve the levels of accuracy sought, it is
installation: clear that concrete shrinkage and tempera- Durability of steel bars used for segment
- ring building, ture are parameters which must be consi- reinforcement cages is related to the per-
dered, especially during segment inspection meability of the encasing concrete and
- lining deformation under the action of at the precast plant. depth of concrete cover, as well as to the
back grouting and surrounding ground. internal and external aggressive environ-
3.9 - Durability ments mentioned above.
3.8.3 - Accuracy
The choice of cement types and their
All criteria defined above must be conside- 3.9.1 - Segment concrete contents influence passivation of steel rein-
red in order to specify tolerances in the forcing bars.
construction axis with respect to the struc- Segment concrete durability depends on
Chemical composition and surface condi-
tural design axis. the purpose of the tunnel and may be asso-
tion of these steel bars must ensure good
ciated with the following criteria:
The required means should then be imple- weldability for reinforcing cage fabrication.
mented to ensure compliance with tole- compactness of concrete mixes;
Depth of concrete cover to reinforcement
rances for the segments forming the rele- concrete mix proportions: must be specified with respect to conditions
vant ring. Successive combinations of these of structural exposure laid down in the pro-
tolerances mean that dimensions must be - fine aggregate,
ject specifications. It may vary depending on
kept within small variations at mould strip- - coarse aggregate, application zone for the stresses encounte-
ping. Geometrical proper ties foreseen at - cement, red and the level of protection sought in
construction study stage should be repro- relation to the relevant forms of attack
duced to obtain contact faces between seg- - admixtures,
(intrados fire resistance, inter segment
ments or rings which are capable of trans- - water, contact, TBM thrust cylinder bearing sur-
ferring loads between ring par ts and face, etc.).
ensuring proper watertightness. all require physical chemical analysis of their
constituent materials; In general, these depths of concrete cover
It is therefore essential to identify clearly can vary from approximately 20 mm (iron-
the segments sections requiring par ticular active alkaline balance;
banded reinforced zones) to approximately
levels of geometrical accuracy and to quan- permeability; 30 mm (standard intrados and extrados
tify them. environment-related internal and exter- zones).
The main criteria to be examined are: nal forms of attack: In some cases, steel protection systems can
general dimensions of the assembled ring; - temperature, be applied:

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


225
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

painting; tions must allow standardization in favour of after mould stripping (both when casting
metallization (galvanization, cataphoresis, one or two possible ring lengths. Creation horizontally - cf. conditions annexed to the
metal-coating); of several ring lengths on a project effecti- present recommendations - and vertically),
vely multiplies the number of mould and for the handling stages from precast plant to
epoxy-coating; reinforcing cage types, leading to more preliminary storage then storage areas (e.g.
cathodic protection (electrical links). complicated and therefore more expensive using a lifting beam fitted with grippers, suc-
precasting, control and handling. tion pads or slings, etc.), for the storage
3.9.3 - Waterproofing gaskets stages involving segment stacking and inser-
These considerations are also linked to the
tion of timber blocks between units, for the
type of TBM used (existing machine possibly
In material terms, durability in gasket water- stages of removal from storage and unloa-
modified for the project, new TBM designed
tightness is associated with the same crite- ding on site, or for the stage involving seg-
and built for the project).
ria as those listed above for short- or long- ment supply to the workface (by trailer or
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

term concrete attack. Reuse of TBMs and segment moulds railcar).


undoubtedly provides substantial savings on
Once these criteria have been checked, the The impact of each of these stages must be
similar projects, even if servicing, adaptation
rate of long-term relaxation of the water- subjected to a reinforced concrete design
proofing system should be ensured. and overhaul is always required. check in terms of internal stresses induced
Gluing of gaskets is only carried out to Thus, on projects such as: in the segments. These design calculations
ensure that they remain in their grooves mass transit railway tunnels, especially for must consider not only the possible dyna-
during segment handling, storage and erec- the Val system; mic effects of handling (e.g. placing a seg-
tion. Adhesive used must be compatible ment on a stack during lifting or storage
rail and high-speed rail tunnels; stages) and implementation tolerances (e.g.
with the type of gasket.
road tunnels; accuracy of intersegment block positioning
3.9.4 - Connector inserts at the storage area), but also the true age of
wastewater collectors, etc., the concrete (and thus its characteristic
Connector inser ts must be durable and it would appear desirable to retain geome- strength) when carr ying out the relevant
neutral with respect to their environment. trical and equipment standards on a project operation.
In all cases, they must comply with safety basis at national level.This would allow pro- In most cases, the process only involves
standards in force. duction capacities to be increased and costs design checking because the sectional areas
to be reduced. These standards could be of reinforcement and concrete proper ties
They must be positioned in accordance based on the "rcommandations sur la stan-
with values of concrete cover to reinforce- for the segments are most often designed
dardisation des profils des tunnels circu- for tunnel service or TBM-excavation stages
ment. laires" (Recommendations for the standar- (thrust cylinder applied loads). However,
They must cause neither structural weak- dization of circular tunnel profiles) certain cases can become dimensionally cri-
nesses nor preferential water seepage or presented by A.F.T.E.S. Working Group 11 tical and lead to either improving shor t-
electrical flux paths. (see T.O.S. Issue 88, July-August 1988): this term concrete proper ties or increasing
principle is already in hand in several reinforcement sectional areas, or to more
3.10 - Economic considera- European Community countries and in suitable redesigning of cer tain process
those under Anglo-saxon influence.
tions stages.

Right from the start of the project, tunnel 4.1.1.2 - Ring building (erection and
4 - TUNNEL LINING DESIGN bolting)
lining design must integrate construction
methods and take into account factor s Assembly of segments behind the TBM is
involving its adaptation to the tunnel 4.1 - Main parameters carried out using an erector. During erec-
construction location (influence on mate- influencing sizing tion, segments are subjected to a number of
rials, labour, management and supervision, loads such as:
etc.) with both engineering optimization the load applied by the segment pick-up
and cost-saving in mind. 4.1.1 - Implementation conditions
and lifting system (dead weight of the seg-
From the beginning, it is important to deter- 4.1.1.1. - From segment precasting to ments modified by a dynamic coefficient);
mine the type of ring best suited to the pro- workface supply loads applied to compress waterproofing
ject (universal or "left"/"right" rings), the Between casting in the precast plant and gaskets;
most appropriate ring length, the taper and supply to the tunnel workface in view of
the number of types of ring required for the possible bumping impact loads;
erection at the TBM, segments are subjected
project. to a series of operations which can induce loads associated with accidental impacts
In general, the universal ring is the most appreciable stresses in some. during approach;
economical from the segment fabrication Whilst it is difficult to describe all these loads applied by the assembly systems
point of view (less moulds required, smaller operations, which depend on a process retained (bolts, anchor bolts or plugs).
precast plant area, less types of segment varying from one project to another, a large Although impact loads are very difficult to
reinforcing cage). number of operations never theless recur estimate and thus to integrate in the lining
Analysis of the tightest curves on a project on a systematic basis. For example, this is design, the segments must nevertheless be
alignment compared with the straight sec- the case for the segment turning stages designed to withstand other types of load.

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


226
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

Special care must be given to checking sec- strength, rock mass characteristic parame- tive humidity and shrinkage;
tions near connector inserts (unsupported ters; Poisson's ratio.
thrusts, local stresses, risks of bursting), deformation capacity parameters:
which often result in special construction b) Intersegment contact joint structural
requirements or local additional reinforce- - Young's modulus E(x, t), properties:
ment. - Poisson's ratio . sectional area, inertia
In surrounding rock, a reduced value of These properties allow the capacity for load
4.1.2 - Parameters for analysing
Young's modulus, compared with labora- transfer between contact joint sectional
ring stresses
tory-measured values, should be considered areas to be deduced;
Reference may usefully be made to the to take into account the potential deforma-
ring composition
summary table provided under 4.3.5. tion capacity of discontinuities influencing
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

the rock matrix. The discontinuous nature of a ring (an


4.1.2.1 - Parameters associated with assembly of elementary segments) leads to
Good command of this parameter is of
the surrounding ground a reduction in its stiffness in bending, whilst
prime importance for the design of struc-
tures such as water conveyance internal its stiffness in compression is, in general,
The main parameters concerning the sur-
pressure tunnels (danger of intersegment only slightly affected by the presence of
rounding ground, which can come into play
contact joints opening); intersegment contact joints.
in terms of analysing the behaviour of a pre-
cast concrete segmental tunnel lining, are seismicity On the other hand, installation of adjacent
recalled hereunder on the basis of the rings incorporating combined radial contact
A.F.T.E.S. recommendations entitled "le Evaluation of the surrounding ground dyna- joints, associated with rigid assembly sys-
choix des paramtres et essais gotech- mic characteristics may be necessary in high tems between rings, such as plugs, enables
niques utiles la conception, au dimension- seismic risk areas. this effect of reduced ring stiffness in ben-
nement et l'excution des ouvrages creu- d) Hydrogeological parameters ding to be limited.
ss en souterrain" (the choice of
Knowledge of groundwater pressures
geotechnical parameters and tests of use in 4.1.2.4 - Soil - structure interaction
within the soil-rock mass is essential in
the design and constr uction of under- The main parameters influencing behaviour
ever y underground structure project. In
ground excavated structures). of the tunnel lining in contact with the
particular, it is necessary to determine the
a) Parameter s associated with natural influence of tunnel driving on the behaviour ground are:
constraints of the groundwater table(s) (drainage, bar- lining/back grouting material and ground/
The geological history of the soil-rock mass rier effect, danger of a collapse in ground- back grouting material contact conditions.
must be known; it may have been influenced water pressures, etc.).
These can vary between total slippage and
by tectonics, consolidation or erosion. e) Ground characteristic curves total adherence; however, they tend
The basic parameters are: Ground behaviour can be represented by towards total adherence with the use of
intensity of principal stresses (in particu- shor t- and long-term convergence curves mortars grouted under good conditions.
lar, evaluation of the term based on the geological, hydrogeological Under cer tain ground and groundwater
and geotechnical parameter s identified pressure configurations, the idea of separa-
Ho above.
Ko = ( ); tion can complement these conditions (lack
Vo
of contact between lining and surrounding
4.1.2.2 - Parameters associated with
direction of stresses (effects of slope and TBM characteristics ground).
dipping of ground layers, etc.). environment
The table below reveals the main functions
b) Physical parameters of each TBM structural parameter and its - nearness of existing or planned structures
It is essential to have good knowledge of potential impact on stress analysis. underground or at the surface (buildings,
parameters such as: utilities, existing tunnels or shafts, deep
4.1.2.3 - Lining structural properties foundations, etc.),
the swelling potential;
The tunnel lining is discontinuous and its - superimposed loads (traffic, buildings
the aggressivity of the surrounding envi- structural proper ties depend on those of foundations, etc.).
ronment; the segments and contact joints between
the interfaces between ground layers, lining parts.
anomalies such as discontinuities, non-uni- 4.2 - Design assumptions
a) Segment structural properties:
formities (voids, blocks, faults, etc.).
sectional area, inertia 4.2.1 - Regulations and references
c) Engineering parameters
The inclusion of more or less large pockets 4.2.1.1 - Foreword
Two types of engineering parameter are needs to be taken into consideration in the
usually characteristic of the soil-rock mass: evaluation of these parameters; It should be recalled that limit states analysis
strength parameters: allows checking of both the structure's fac-
modulus of deformation tor of safety with respect to failure and its
- soil shear strength properties (Cu, ', C') This depends essentially on concrete satisfactory behaviour with respect to servi-
- direct compressive strength and tensile strength and parameters such as creep, rela- ceability.

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


227
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

Impact on stress analysis The main characteristics of the two limit


Parameters Main functions states are recalled in the following table.

a) Confinement pressure 4.2.1.2 - Applicable regulations and


- to ensure excavation face sta- - increase in ground deconfine- recommendations
bility, ment at lining installation,
- to limit ground deformations. decrease in ground loads on
The following regulations or recommenda-
lining. tions apply to limit state analyses of reinfor-
ced concrete lining segments:
b) Overcut "Fascicule n 62 Titre I section 1 - Rgles
- to reduce pressure on TBM - augmentation du dconfinement
shield tail and lining, especially du terrain la pose du revtement techniques de conception et de calcul des
when advancing in a curve, ouvrages et constructions en bton arm
diminution des charges de ter-
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

rain sur le revtement


suivant la mthode des tats limites (Rgles
BAEL 91)" (Engineering rules for limit state
design and analysis of str uctural and
c) Shield tail conicality - to allow a degree of ground - increase in ground deconfine- constructional reinforced concrete based)
convergence over the length of ment at lining installation (French reinforced concrete code of prac-
TBM shield tail to reduce fric- decrease in ground loads on tice).
tion (especially in expansive lining.
ground) Eurocode 2, published and annotated by
AFNOR (French Standards Institute) in
December 1992;
d) TBM length - to reserve space for fitting - when ground is not in conti-
different mechanical equipment nuous contact with the TBM "Instruction technique sur les Directives
from head to thrust mecha- shield tail extrados, ground loads Communes relatives au calcul des construc-
nisms. on the lining are increasingly tions" (Engineering guide to Common
reduced as the shield tail length is Directives covering str uctural design)
increased, (French Govt. Circular n 79-25 of 13th
- conversely, ground convergence
is limited to the annular gap bet-
March 1979);
ween excavation and shield tail CEB-FIP International Recommendations,
extrados. 1990;
NCF (French national railway company)
"Livret 2.01" covering railway loadings and
e) TBM thrust - to ensure longitudinal advan- - depends on thrust loads imple- reinforced concrete design rules;
ce, mented and thrust cylinder ram CPC Fascicule n 61 Titre II covering road
- to ensure a reaction to the pad/segment contact conditions imposed loadings (French code of practice);
confinement pressure, (eccentricities due to installation
- to guarantee temporary stabi- tolerances, curved alignment, AFTES Recommendations currently in
lity of lining segments, buoyancy, localized loads) and force;
- to ensure compression of ring/ring contact conditions (geo-
impervious gaskets between metrical defect in segments, and, in some cases:
rings prior to installing assem- eccentricities due to installation "CCTG Fascicule n 62 Titre V - Rgles
bly system, tolerances, localized loads). techniques de conception et de calcul des
- to ensure key segment can be
driven in.
fondations des ouvrages de gnie civil"
(Engineering rules for design and analysis of
civil engineering structures) (French code of
f) Back grouting - to ensure blocking between - local pumping thrust, grouting practice);
lining and ground, pressure, strength properties of
- to limit ground deformations. back grouting material (modulus, "Rcommandations provisoires relatives
Rc, etc.), la modification des rgles de prise en
- reduction in ground deconfine- compte de la fissuration et l'emploi des
ment, btons hautes performances" (Provisional
increase in ground loads on recommendations for the amendment of
lining.
rules for considering cracking and for the
use of high-strength concrete), edited and
circulated by SETRA (French national high-
way engineering agency) in June 1997;
Ultimate limit state Serviceability limit state "DTU n 14.1 - Travaux de cuvelage"
(French unified code of practice - Lining and
Failure of a section due to crushing of concrete Excessive opening of cracks (infiltration, corrosion) tanking work), October 1987.
Excessive deformation of steel Excessive compression of concrete causing micro- The project specification must detail the
Instability of shape (buckling, bulging) cracking regulator y documents applicable to the
Excessive ring deformations
contract, as well as their priority of applica-
Loss of static equilibrium at ring erection
tion.

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


228
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

4.2.2 - Material properties These methods and their conditions of they must be considered when sizing the
application are described in detail in "texte segments.
4.2.2.1 - Lining concrete des rflexions sur les mthodes usuelles de For example, in the case of water
Reinforced concrete properties to be intro- calcul du revtement des souterrains" conveyance tunnels, the contract should
(recorded thoughts on the usual design specify, if necessary, the value representing
duced in design analyses are those specified
methods for tunnel linings) presented by the variation in internal hydraulic pressure
by the BAEL and Eurocode rules in force,
A.F.T.E.S.Working Group 7 in T.O.S. Issue 14, to be considered and the manner in which
i.e.: March-April 1976. it is to be taken into account.
the characteristic compressive strength Actions thus determined are then used to
Fcj; b) Loads applied to the ground surface
analyse lining stresses by the different
the characteristic tensile strength Ftj; methods reviewed in Section 4.3 below. Most frequently, these are pedestrian or
vehicle loads.
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

longitudinal instantaneous and long-term c) Loads induced by neighbouring struc-


moduli of deformation; tures c) Loads applied during construction
stress-strain diagrams; These loads are determined from drawings Loads induced from precasting to ring
of neighbouring structures (foundation dra- building
Poisson's ration, which is usually taken as wings, etc.) passed on by the Owner. The sizing of each tunnel segment should be
0.20.
d) Hydrostatic and hydraulic pressures checked in relation to the different
construction stages: segment handling, pos-
4.2.2.2 - Steel for passive reinforce- With regard to the external hydrostatic sible turning, storage, transpor t, loading
ment pressure exer ted by the hydrogeological onto cars, unloading, pick-up by erector and
Steel properties to be introduced in design environment, this will be determined on the installation.
analyses are those specified by the BAEL basis of maximum and minimum water
levels. Loads induced by TBM penetration
and Eurocode rules in force, i.e.:
In this connection, the potential impact of TBM thrust cylinder loads represent longi-
the guaranteed elastic limit Fe; tudinal forces applied to the lining segments
buoyancy on the lining and its assembly
the modulus of longitudinal elasticity, mechanisms, especially during construction through the load distribution pads.
which is taken as 200,000 MPa; at ring break-away from the TBM, should be Each thrust load distribution pad is acted
stress-strain diagrams. recalled. upon by one or more cylinder s, whose
In the special case of water conveyance tun- resultant thrust is eccentrically exerted.This
4.2.3 - Nature of actions and loa- nels, the contract must detail values repre- eccentricity, which is measured with respect
dings senting internal fluid loads to be considered to the centre of gravity of the ram pad bea-
and how they should be taken into account. ring surface, comprises a known structural
component and an additional random com-
4.2.3.1 - Permanent actions (G) e) Annular gap back grouting pressures ponent. It should be recalled that when the
Permanent actions include the following If back grouting pressures exer ted on the TBM follows a curved alignment (horizontal
loads: lining extrados are higher than the ground or ver tical), the structural eccentricity of
pressure, they should be considered when the resultant thrust from the cylinder(s)
a) Dead weight of the structure and weight sizing the segments. with respect to the ram pad bearing surface
of fixed equipment, is often increased and must consequently
b) Surrounding ground loads. 4.2.3.2 - Variable actions (Q) be integrated in the analysis.
The convergence-confinement method Variable actions include
EXAMPLE OF ECCENTRIC PLANE TRANSVERSE CONTACT JOINT
evaluates ground actions on the lining. This the following loads:
extrados
method has already been described in seve- a) Operating loads inside
ral publications. Recommendations on the the tunnel peripheral groove extrados side
use of this method, presented by A.F.T.E.S. When these are wheel-
Wor king Group 7 in T.O.S. Issue 59 of induced rolling loads
September-October 1983, will be updated applied directly to the half lining wall
thickness
in the near future. tunnel inver t slab, their
Moreover, in the case of shallow soils and influence is usually ver y
structures, various authors have proposed modest and they can the- width of transverse contact joint

semi-empirical formulae, derived from refore be neglected in


theor y or experience, for calculating the the design of the lining Centre of gravity of thrust cylinder
vertical load exerted by the ground on the cross-section. ram pad bearing surface
lining in terms of the density, cohesion and On the other hand, when half lining wall eccentricity resultant load exerted by a
angle of internal friction of the soils, the these loads are applied thickness of thrust thrust cylinder group
excavation radius and the depth of overbur- to a road pavement or
den above the crown (notably the TERZA- rail trackbed suppor ted
GHI, PROTODIAKONOV and LAUFFER by a slab bearing or built peripheral groove intrados side

methods). into the tunnel lining, intrados

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


229
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

The load exerted by each group of thrust Note: dead weight loads), it is very important to
cylinders and its eccentricity are two para- In the case of certain structures, for which ensure the validity of both the ground engi-
meters for which rated working and excep- temperature gradient-based effects must be neering properties taken into account and
tional values must be specified. considered, the contract shall detail values the stress analysis method. The non-unifor-
In a basic combination, the values of these representative of the corresponding actions mity, anisotropy, jointing and fissuration of
two parameters to be considered are the and how they should be taken into account. the soil-rock materials and the difficulty in
rated working values. forecasting their long-term behaviour must
4.2.3.3 - Accidental actions (FA) also be considered.
In an accidental combination, only one of
these parameters reaches its exceptional In the case of certain structures, for which The 1979 Common Directives are ver y
value, the other parameter maintains its accidental actions (e.g. earthquakes, explo- clear on this subject: Section 4.1.3 states
sions, vehicle impacts or "waterhammer" in that "the maximum and minimum characte-
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

rated value. It is acknowledged that both


parameters cannot reach their exceptional water conveyance tunnels) must be consi- ristic values of actions corresponding to
value at the same time. dered, the contract shall detail values repre- ear th pressures shall be evaluated taking
sentative of the corresponding actions and into account the uncer tainties resulting
Whilst it is rare for the rated thrust to be how they should be taken into account. from their method of calculation".
reached simultaneously by all cylinders, it is
frequently so for each group of cylinders. However, when detailed analysis is not
4.2.4 - Combined actions
required or when a calculation process
Those data are used to prove the strength does not allow the effects of the ground
of the concrete and reinforcement, in parti- 4.2.4.1 - Design stresses with respect and water to be separated, the following
cular under the localized loads exerted by to strength ultimate limit states combined actions shall be retained:
each group of thrust cylinders.
a) Foreword 1,35xS{Gground + Gwater + (1,50/1,35)xQ1}
Fur thermore, segment sizing must also be
In the case of models which introduce a
checked under the loads exer ted by the obtained by multiplying the infrequent com-
non-elastic law in terms of ground beha-
passage of the TBM back-up equipment. viour (occurrence of zones in a plastic bined action by 1.35:
Loads induced by the grouting material state), soil-structure analysis should be car- S{Gground + Gwater + (1,50/1,35)xQ1}
when filling the annular gap between the ried out, without uplifting the actions invol-
lining and the surrounding ground ved, and the ultimate limit state weighting For checking the lining under construction,
These transient-type loads result from a coefficients detailed below should be the basic combined action is expressed as:
applied to the resulting forces.
localized increase in grouting pressure 1.35Glining dead weight + 1.35QI
("local pumping thrust") directly behind the b) Basic combined action put forward by
segment grouting holes. BAEL 91 and Eurocode 2 QI : TBM thrust cylinder load, back grouting
1,35Gmax + Gmin + Q1 Q1 + Qi Oi Qi pressure or weight of back-up train.
In certain special cases, where total control
of this phenomenon is essential, the impact Gmax : total unfavourable permanent c) Basic combined action derived from
of these actions on the lining should be actions (e.g. lining dead weight, ground pres- 1979 Common Directives
checked. Data is then required on the grou- sure); A combined action more directly derived
ting system incorporated in the TBM (num- from 7.2.1 of the 1979 Common
Gmin : total favourable permanent actions; in
ber of grouting points, grouting process, some cases, water pressure can be favou- Directives and featuring in BAEL 91
etc.) and on the procedure for implemen- rable and should then be weighted by 1 ; in Fascicule n 62 - Titre V "Rgles techniques
ting these grouting operations retained by other cases, it should be weighted by 1.35; de conception et de calcul des fondations"
the contractor. (engineering rules for the design and analy-
Q I : basic variable action; in the present
d) Climatic temperature-induced actions sis of foundations) can also be put forward.
case, such actions would be road, rail or
(t) water conveyance operating loads or loads Characteristic values of actions are increa-
Uniform temperature variations applied during construction; sed by two coefficients F3 et F1 :
In general, uniform temperature variations Q1 is equal to 1.5 in general, except for rail- F3S{ F1GmaxGmax+ F1Gmini Gmini
do not require consideration. way loads (1.45).
+ F1Q1Q1 + F1Q1OiQi }
Note: Qi OiQ i are the accompanying variable
actions. - the coefficient F3 must enable one to
In the case of certain structures (very deep take into account the uncer tainty of the
tunnels, energy conveyance tunnels, etc.), The basic combined action can therefore be
expressed as: stress calculations and the simplifications
uniform temperature variations must be resulting from the models and diagrams; its
considered; the contract shall detail values 1,35Gground + 1,35(ou l)Gwater + 1,50Q1 value usually lies between 1.125 and 1.15;
representative of the corresponding actions The largest contributor y factors in this
and how they should be taken into account. - the coefficient F1 must allow one to take
expression are obviously the actions on the into account the risk of exceeding the cha-
Temperature gradients () lining due to water and ground. racteristic value of the action; it can take a
In general, temperature gradients do not Because the action due to the ground is value very close to 1 for the action due to
require consideration. only weighted by 1.35 (e.g. for permanent water if, for example, it represents a hydro-

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


230
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

static pressure corresponding to an accura- accident-related situation corresponding to 4.2.5.2 - Shape stability ultimate limit
tely known water level and can never be loss of lining permeability; the check will state
exceeded; but, for the action due to the then be carried out using the following acci- This involves proving the strength of the
ground, it can attain values near to 1.2, and dental combined action: segment ring with respect to the ultimate
even higher if the ground investigation is Gwithout water ground + Gtotal water pressure states without neglecting so-called second
limited and risky. order effects such as buckling, bulging, etc.
+ 0.6QI
The resulting combined action can be This proof is only to be considered for very
expressed as: 4.2.4.2 - Design stresses with respect thin linings installed in ground with very low
to serviceability limit state moduli of deformation.
1,35*Gground + 1,15Gwater + 1,50Q1
Gmax + Gmin +Q1 +oiQi
4.2.5.3 - Static equilibrium limit state
* this coefficient can be higher if the action
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

When the tunnel is in operation, this combi- In some cases, non-buoyancy checking
due to the ground is difficult to estimate.
ned action is expressed as: should be anticipated.
This type of combined action must be laid
Gground + Gwater + QI Nominal permanent downward ver tical
down in the project specification.
or loads associated with permanent actions
d) Accidental combined action put forward Gground + Gwater must be at least 1.05 x the water-induced
by BAEL 91 and Eurocode 2 upward loads resulting from exceptional
Gmax + Gmin +FA +11Q1 + 2iQi 4.2.5 - Sizing criteria water level conditions. Possible time-depen-
dent variations in structural overburden
FA : nominal value of accidental action; 4.2.5.1 - Strength ultimate limit state (e.g. sinking of a riverbed, etc.) must also be
Design stresses derived from basic or acci- taken into account.
Qi : variable accompanying actions.
dent-related combined actions must not
The maximum capacity of the TBM thrust 4.2.5.4 - Ser viceability limit states
exceed the ultimate limit capacities for rein-
cylinders is to be considered as an acciden- with respect to structural durability
forced concrete sections specified by
tal action. a) Crack opening limit state
A.4.3 of the BAEL 91 rules or Eurocode 2
In the case of an earthquake or explosion: and resulting from the following limiting Because concrete is highly alkaline (pH 12),
Gground + water + Earthquake (or explosion) strains established for the relevant mate- reinforcing steel is normally protected by
rials: passivation (formation of Fe(OH) 2 at the
+ 0.6QI
10 x 10-3 for the elongation of reinforcing surface of the reinforcing bar).
Notes : bars; However, care must be taken to ensure that:
Another type of stress, comparable to an 3.5 x 10-3for the shortening of partially cracks are not excessively open;
accidental stress, can be provided in the compressed sections comprising concrete
project specifications. concrete cover is sufficient in relation to
with a strength fcj of less than 60 MPa; for the environment;
This is the total overburden load and is high-strength concrete (fcj 60 MPa), the
usually considered for shallow tunnels limit for shortening is given by the relation: the concrete mix is satisfactory.
(overburden of 1 to 2 diameters) or deeper (4.5 - 0.025fcj) x 10-3 ; The r ules specify conditions governing
tunnels likely to be subjected to long-term 2x 10-3
for the shortening of concrete in concrete cover and cracking.
effects which are difficult to predict in a fully compressed section. In accordance with the new recommenda-
ground surveys (creep, swelling, etc.).
Material design stresses are obtained by tions amending Section A.5.3. of BAEL 91,
This action is therefore considered with a applying the following coefficients to their reinforcement tensile stresses are limited as
coefficient of 1: characteristic strengths: follows:
Goverburden weight + 0.6QI for detrimental cracking (lining in the pre-
s = 1.15 for steel under basic combined sence of moderately aggressive water):
In this combined action, accompanying action;
actions are usually neglected and the action s=sup[240MPa,110ftj]
due to the ground is often assumed to be s = 1 for steel under accidental combined
uniformly distributed over the lining. action; : cracking coefficient equal to 1.6 for high-
b = 1.5 for concrete under basic combined tensile deformed bars ( > 6 mm), 1.3 for
This combined action has no geotechnical high-tensile deformed (high bond) bars (
significance but it has the merit of testing action;
6 mm) and 1 for plain (hot-rolled) reinfor-
the factor of safety associated with the b = 1.15 for concrete under accidental cing bars;
lining bearing capacity with respect to the combined action.
weight of overburden. for highly detrimental cracking (lining in
Because segments are concreted in a pre- highly aggressive environment):
It does not apply to very deep tunnels in cast plant, coefficient b can be reduced
ground with a high modulus of deformation (only in strength ultimate limit state analy-
s=sup[200MPa,90ftj]
(e.g. Alpine tunnels). sis) to 1.3 under basic combined action as In addition to the above limiting tensile
Finally, in the case of impervious jointless long as quality inspections comply with an stresses, Section A.4.5. of BAEL 91 specifies
precast concrete lining installation, project ISO system; these special provisions must the maximum diameters and spacings for
specifications can suggest considering an be laid down in the project specifications. reinforcing bars.

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


231
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

b) Concrete compression limit state Moreover, this method of analysis remains to be determined. The normal force can be
In accordance with Section A.4.5.2. of BAEL equally applicable in the following situations: directly derived from this.
91, the concrete compressive stress at the tunnel located at shallow depth; In this case, initial stresses are considered
serviceability ultimate limit state is limited non-uniform surrounding ground (several uniform and isotropic, but the surrounding
to 0.6 fcj. ground can be considered as obeying a law
different formations);
of elastic-plastic behaviour.
4.2.5.5 - Fire resistance dissymmetrical external loads (dissym-
Characteristic of soil-structure interaction
metrical existing structures, load transfers
Project specification requirements in rela- and contributing to the application of this
due to excavation of nearby structures, method, the impor tant parameter is the
tion to fire resistance must state the level of etc.);
fire stability for the lining and this must be deconfinement ratio CARSPECIAUX 108
justified by the organization and emergency dissymmetrical lining (dissymmetrical dis- \f "Symbol" . Among its current methods of
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

facilities in the event of fire in the tunnel(s). tribution of radial joints). determination, we find those of:
The main simplifying assumptions associa- Panet;
ted with this type of model are as follows: Corbetta;
4.3 - Determination of
stresses in the tunnel lining ground behaves elastically; Bernaud;
"springs" modelling the surrounding Minh-Guo.
4.3.1 - Introduction ground are mutually independent. The last two methods allow the stiffness of
Because this method is quick, it is used for the support to be considered.
Given the circular shape of the tunnel lining, the selection of critical sections and for
several methods of analysis are possible for Because of the simplifying assumptions
impact studies of certain parameters, espe- referred to above, analytical solutions are
determining the stresses due to interaction cially when the analytical resolution method not valid in the following situations:
of the soil and the structure. cannot be applied. It is used at preliminary
design, design or construction study stage. tunnel located at shallow depth;
The two main methods are:
Naturally, this method does not allow pos- non-uniform surrounding ground (several
the hyperstatic reaction method
sible surface settlements to be tackled. different formations);
the composite solid method. dissymmetrical external loads (dissym-
4.3.3 - Composite solid method metrical existing structures, load transfers
4.3.2 - Hyperstatic reaction due to excavation of nearby structures,
method This method enables the behaviour of the
etc.);
ground-structure system to be studied.
The hyperstatic reaction method studies dissymmetrical lining (dissymmetrical dis-
It considers the surrounding soil-rock mass
the behaviour of the lining alone by likening tribution of radial joints).
as a continuous medium (basic assumption
the action of the ground to external loads. It often made). However, because these methods are very
therefore favours the role of the lining. As a quick, they are often applied for the selec-
result, it should preferably be applied to a 4.3.3.1 - Analytical solutions tion of critical sections and for impact stu-
rigid lining located at shallow depth and in dies of certain parameters.
enclosing ground comprising weak soils or Based on soil and rock mechanics theories
for continuous media, analytical solutions
very closely fractured rocks. 4.3.3.2 - Numerical resolution
allow the lining forces (normal forces, shear
The drawback of this method is that it does forces, bending moments) and elastic line to Based on the use of finite element, or some-
not take into account: be determined. times finite difference, numerical models,
this method allows 2- and 3-dimensional
the behaviour of the ground after failure Standard assumptions are as follows:
problems to be tackled. It favours neither
and with respect to time; lining geometry is circular and uniform the role of the lining nor that of the sur-
the deformation the surrounding ground (joints not directly considered); rounding ground. As a result, it applies to a
has already reached when the lining is instal- loads are uniform isotropic or anisotropic lining of any stiffness located at any depth in
led; (Ko 1); they can be derived using the uniform or non-uniform surrounding
the different excavation stages. convergence-confinement method or take ground comprising several different forma-
into account the total stress exer ted tions and in the presence of symmetrical or
However, a number of specific assumptions (Erdmann formula); dissymmetrical existing structures.
made for modelling the structure and the
the assumed single layer of ground This method of analysis has the advantage
external loads enable the principles of the
behaves elastically; of taking into account:
composite solid method to be approached
(e.g. maintaining of "springs" in tension) contact between the lining and the the deformability of the ground and, in
when conditions of application are satisfied. ground can either be considered as in total par ticular, its behaviour after failure and
adherence or as in total slippage. with respect to time;
Stresses and strains are calculated using a
numerical resolution method usually based Convergence-confinement method the redistribution of loads resulting from
on a 2-dimensional model made up of wire- The convergence-confinement method lining deformation;
frame elements with straight or cur ved allows, on the one hand, the loading and, on the 3-dimensional nature of the excava-
members. the other hand, the ring radial displacement tion associated with the presence of a cut-

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


232
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

ting face, through the concept of a deconfi- estimation methods, which are easy to Impacts of specific structural characteristics
nement ratio C ARSPECIAUX 108 \f implement but for which the area of appli- on design assumptions are as follows:
"Symbol" introduced either in the 2-dimen- cation is limited to situations considered
installation of lining at a certain distance
sional model or directly in a 3-dimensional through the feedback of experience on
from the excavation face: lining sustains loa-
model; which they depend (cf. Recommandations
relatives aux tassements lis au creusement ding from par t of the ground deconfine-
the excavation stages. ment, from the back grouting pressure and
des ouvrages en souterrain -
In standard cases analysis is limited to 2- Recommendations concerning settlements from delayed effects;
dimensional modelling in which the associated with the excavation of under- the lining is not monolithic: reduced iner-
influence of the cutting face is considered ground str uctures - T.O.S. Issue 132, tia at the contact joints is reflected in redu-
by applying the convergence-confinement November-December 1995), numerical ced lining flexural stiffness. This phenome-
method referred to in the above section. resolution is the only method of analysis non can be taken into account either by
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

This numerical resolution method of analy- valid for approaching surface settlements. modelling contact joints directly or by desi-
sis is also valid for non-uniform and aniso- gning an equivalent ring with a smaller iner-
tropic initial stresses, i.e. even when a dis- 4.3.4 - Adaptation of analysis tia (Muir-Wood formula); however, it should
symmetrical feature is present in the methods to a segments lining and be noted that this behavioural assumption is
structure (dissymmetrical distribution of to TBM-based excavation no longer borne out in the case of adjacent
radial intersegment contact joints), in the
The specific nature of designing a tunnel rings incorporating combined radial contact
surrounding ground (several different for-
mations, etc.) or in the external loads lining to be installed behind a TBM arises, on joints in association with rigid assembly sys-
(nearby existing structures, etc.). the one hand, from the tunnelling method tems between rings (e.g. plugs or tenon-
and, on the other hand, from the nature of and-mortises) nor in the presence of very
Several types of ground behaviour can be soft ground.
modelled: elastic, fully elastic-plastic, elastic- the structure.
brittle with softening (uncommon), aniso- When it allows confinement of the excava- 4.3.5 - Parameters which can be
tropic with respect to deformation and/or tion face, the tunnelling method can be integrated in the different methods
strength, etc.. reflected in the analyses by:
of analysis
The simplifying assumptions remain as fol- either using a deconfinement cur ve,
lows: based on a (0 - ps) stress condition, combi- Based on the design stage and the context
initial deformation after lining installation ned with the application of a pressure p s of the project, the following table shows the
is neglected; representing the confinement pressure possible status of taking into account para-
applied at the workface; meter s for the different considered
every segment is not usually considered approaches to analysis.
individually; or adopting an extension in space of the
deconfinement curve behind the excavation These modes of parametric consideration
segment blocking tolerances are not
face; thus, the deconfinement ratio taken are identified by the following coding:
taken into account;
into account at a certain distance from the 0 not necessary
the lining is installed behind the cutting workface (i.e. at the last ring installed) is
face and becomes effective at a certain dis- much lower than the value used in the 1 desirable
tance from it; conventional method (or when tunnelling 2 necessary
concrete shrinkage is neglected. using a TBM in open face conditions).
I indirect consideration
In general, this more elaborate method is Moreover, confinement can result in addi-
restricted to the final design of a few critical tional excess porewater pressures in the D direct consideration
sections. Apar t from empirical settlement surrounding ground. N not considered

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


233
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

Project stage / context Methods of analysis

Preliminary Design Construc- Urban Hyper- Composite Composite


Parameters Studies tion / static solid solid Comments
studies Sensitive reaction method. method.
method. Analytical Numerical
solutions resolution

- Definition of loading and/


or actions
* Initial constraints
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

- levels of ground layers 1 2 2 2 I I D


- groundwater level
minimum groundwater level 0 1 2 2 I I D
maximum groundwater level 2 2 2 2 I I D
- dry unit weight 2 2 2 2 I I D
- Ko 2 2 2 2 D D D - Ko obeys Jaky's law for sands and
normally consolidated clays;
- Ko depends on tectonics, consolidation
and erosion for rocks and overconsolidated soils.
- superimposed load:
uniform superimposed load 1 2 2 2 D I D
linear superimposed load
(Bc truck, load-bearing wall), 0 1 2 2 D N D
surface superimposed load
- direction of principal stresses 1 2 2 2 D D D - slope effect
- dip effect (ground layers)
- continuous medium assumption:
continuous medium 2 2 2 2 D I D
fissured medium 0 1 2 2 D N D

* Loading:
- segment installation distance 2 2 2 2 I I I in 2-d. Shield tail effect only to be considered in
D in 3-D. very soft ground and in an urban/sensitive context
- confinement pressure - max. value for stress calculations;
- min. value for settlement calculations.

considered as artificial support 2 2 2 2 I I I


considered by means of equivalents 0 0 0 1 D D D
stress condition
- back grouting pressure 0 1 2 2 D I D
- overcutting, shield tail conicality 0 0 0 2 I I I Effect only to be considered in very soft ground
and in an urban/sensitive context
- ground deconfinement law:
convergence-confinement method 2 2 2 2 I I I in 2-d.
D in 3-d.
method of similarities (Corbettas law) 0 0 0 1 I I I in 2-d.
D in 3-d.
- ground convergence curve:
unsupported (elastic-plastic behaviour) 2 2 2 2 I I I in 2-d.
D in 3-d.
supported (Bernauds law) 0 0 0 1 I I I en bi-dim
D in 3-d.
- delayed effects (behaviour law):
E(x,t) 1 2 2 2 I I Iin 2-d.
D in 3-d.
long-term shear parameters 1 2 2 2 I N D
effective stress analysis (excluding 2 2 2 2 D D D
porewater pressures)
physical chemical swelling 1 2 2 2 I I I
- change of groundwater pressure
drainage 1 2 2 2 D D D

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


234
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

Paramtres Phase / Contexte Mthodes de calcul Commentaires


Etudes Projet Excut Urbain Mthode Mthode Mthode
Prlim / des du solide du solide
Sensib ractions composite composite
hyperst. Solutions Rsolution
analytiques numrique

restoration of hydrostatic pressure 2 2 2 2 D D D Application of pressure:


- to ground and to lining;
- to lining only;
II - Structure disign
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

- overall structural design (possible 1 2 2 2 I I I Ring inertia is reduced by applying the Muir-Wood
consideration of contact joints, etc.) formula, except in the case of combined contact
joints in very soft ground or rigid assembly systems
between rings
- section and inertia of segments 2 2 2 2 D D D
- properties of each contact joint 0 0 0 1 D N D
- moduli:
short-term modulus >< long-term 1 2 2 2 N N D
lmodulus
use of average modulus 1 1 1 1 D D D
- back grouting material (model) 0 0 1 1 N N D

III - Soil-structure contact conditions


- adhrence 2 2 2 2 I D D
- slipping 1 1 1 2 I D D
- friction (Coulombs law) 0 1 1 2 I N D
- separation 0 1 2 2 I N D

IV - Environnment
- nearness of other underground 1 2 2 2 I I D
structures
- existence of transition structures 1 1 2 2 I N I in 2-d.
D in 3-d.

4.4 - Proof of concrete and contact joints between units: bearing sur- ments can be dimensionally critical (burs-
reinforcement face area, installation of waterproofing gas- ting forces due to spreading of this thrust);
ket, chamfers, etc.; minimum percentage of reinforcing steel
4.4.1 - Choice of segment wall the minimum segment wall thickness considerations:
thickness must be compatible with the bearing sur- - for units in compression (BAEL 91, Section
face area of TBM longitudinal thrust cylin- A.8.1,21),
Segment wall thickness must satisfy several ders.
criteria: - for units in bending: especially under the
4.4.2 - Circumferential reinforce- action of TBM main cylinder thrust (BAEL
the segment strength capacity with res- 91, Section A.4.2.).
ment (hoops)
pect to combined circumferential bending Hoop diameter s and arrangement
must be sufficient when the percentage of The sectional area of circumferential rein- (concrete cover and spacing) must be deri-
longitudinal reinforcing bars contributing to forcing bars arranged behind the internal ved in accordance with Section A.8.1,22 for
this strength is less than 1 % and is generally and external segment faces shall be derived units in compression, Section A.7.1. for
close to the minimum percentage; if seg- from: concrete cover protection of reinforcing
ment wall thickness is constant throughout bars and Section A.4.5,3 for cracking. It
analysis of combined bending (normal
the tunnel alignment, an economic study load - bending moment interaction dia- should be noted that the use of high-
shall be conducted to examine whether it gram) in relation to anticipated loadings in strength concrete mixes of very high com-
would be preferable to vary the concrete ultimate limit state and serviceability limit pactness allows the concrete covers pres-
strength (new mix design, alteration of cribed by Section A.7.1. to be reduced.
state combinations. If bending moments are
mixing plant parameter s, feasibility of low compared with the normal force, the
increasing strength) or, on the other hand, sectional area can be justified in "simple 4.4.3 - Longitudinal reinforcing
the percentage of steel in order to satisfy compression" (BAEL 91, Section B.8); bars (arranged parallel to the tun-
the calculated stress variations along the nel axis)
analysis of simple bending during handling
tunnel;
and storage of segments. It should also be Outside segment end zones subjected to
the minimum segment wall thickness noted that the loading case involving thrust localized loads requiring iron-banding rein-
must satisfy the conditions imposed by the of the TBM main cylinders on the lining seg- forcement, these longitudinal bars must

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


235
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

satisfy both the requirement of BAEL 91 bridges and civil engineering structures; c) Accidental combined action put forward
Section A.5 concerning shear force if this is French standards NF P 22-430 and NF P by the CM 66 rules and Eurocode 3
large in relation to the accompanying nor- 22-431 for non-prestressed (plain) bolted Gmax + Gmin + FA
mal force ( u >0,07f cj / b ) and Section assemblies;
A.8.1.3. concerning transverse reinforcing 5.2 - Proof of assembly
links for units in compression. French standards NF P 22-460 and NF P
and pick-up components
22-469 for control-tightened bolted assem-
It is perfectly acceptable not to incorporate
blies; using materials other than
transverse reinforcing links around circum- steel
ferential bars with a diameter less than 20 Eurocode 3 "Design of steel structures"
mm, which are not in corners and not taken adopted by the European Standardization
Committee in 1992. 5.2.1 - Introduction
into account in the relevant strength calcu-
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

lations (i.e. only derived from minimum per- Amongst the assembly systems most often
centages of reinforcing steel). 5.1.2 - Nature of actions and loa- used can be mentioned sockets for bolts
In some rather exceptional cases, such as dings and pick-up bolts or plugs positioned bet-
fire resistance checking, stirrups must also ween consecutive rings.
be checked in relation to their potential 5.1.2.1 - Permanent actions (G) Although the design and analysis of steel
role in preventing unsuppor ted thrust of These actions are associated with keeping assembly systems is based on regulator y
cur ved bar s under tension (BAEL 91, the waterproofing gaskets compressed and documents and standards, the use of diffe-
Section A.7.4,2). are to be considered especially near sta- rent materials is not necessarily included in
Finally, correctly designed longitudinal rein- tions. an engineering regulation framework cove-
forcing bars contribute to balancing the ring the behaviour of the components
They will be determined from crushing
shear force resulting from the TBM cylinders concerned.
force - deformation curves provided by the
thrust loads. waterproofing gasket supplier. The forces likely to be imposed by such
At unit ends, the loads transferred from one components must therefore be surveyed,
segment to another through each localized 5.1.2.2 - Variable actions (Q) then factors of safety to be applied to the
reduced bearing zone are spread through inherent strength of these elements as well
These are represented by loads applied
the total thickness of the segment. Surface as their behaviour under service conditions
during construction. In par ticular, those
and bursting reinforcement must be provi- must be evaluated on the basis of suitable
associated with:
ded in these bearing zones. These can be mechanical tests.
designed in accordance with the recom- - crushing of waterproofing gaskets,
It should be recalled that, because of the
mendations provided in BAEL 91, Annex E.8 - segments overhanging from the previously actions applied, these different segment-
(not taking into account the minimum sec- installed ring during erection, when a thrust inser ted components transmit often high
tional area of bursting reinforcement under ring is used for TBM penetration (rare), local stresses to the concrete. Additional
TBM thrust cylinder temporar y loading). reinforcement may be required to balance
Reinforcement can comprise small diameter - action resulting from the erector arm
(possible). these stresses and ensure concrete integrity.
bars bent into coils or welded bars ( 5.25
of Eurocode 2).
5.1.2.3 - Accidental actions (FA)
5.2.2 - Actions to be considered
Possible accidental actions will be detailed
in the project specifications. The same type of actions as for steel assem-
5 - DESIGN OF ASSEMBLY bly systems (cf. 5.1) are found in relation
SYSTEMS It should be recalled that a commonly retai-
to bolt sockets and plugs.
ned accidental loading case is that associa-
ted with overhanging of a segment espe- Attention should be drawn to the following
5.1 - Design assumptions cially following a hydraulic failure in the TBM specific characteristics associated with the
for bolts and socket bolts thrust cylinders. use of plugs in relation to the actions
already referred to:
This loading case must also be combined
5.1.1 - Regulations high local pressures around interlock poc-
with possible action resulting from the
The following regulations or standards apply waterproofing gaskets. kets when installing segments;
to the design of steel bolts or anchor bolts: structural continuity of the lining between
5.1.3 - Combined actions - Design consecutive rings ensuring greater longitu-
Design rules for structural steelwork or stresses
CM 66 design rules for steel buildings; dinal rigidity (limited relative mutual displa-
cement of components);
Additional Clause 80, which takes into a) Basic combined action put forward by
account the concepts of plasticity and limit the CM 66 rules systematic permanent presence.
states; 4/3 Gmax + Gmin + 3/2 Q Structural continuity may be the cause of
CPC Fascicule n 61 Titre V "Conception stresses which are difficult to quantify:
b) Basic combined action put forward by
et calcul de ponts et constructions mtal- Thus, when an inert or semi-inert grout is
Eurocode 3
liques en acier" (Design and analysis of used for back grouting behind the segments
bridges and str uctural steelwor k) for 1.35 Gmax + Gmin + 1.5 Q at the rear end of the shield tail, overriding

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


236
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

buoyancy with respect to the lining weight This file will focus specifically on: refuges for vehicles;
can induce significant loads in assembly sys- a description of tests carried out; wastewater drainage;
tems;
the statistically aspect of the results; collection and discharge of groundwater ;
It should also be noted that in small
radius cur ves, thrust cylinder action can technical data-sheets for the products maintenance of the structures.
induce large forces resulting from the trans- used.
Internal sizing and spacing of in-line works is
verse component of thrust. often codified under reference documents.
Most of these actions occur in the shor t- Thus, in France, the following documents
term. One should also mention long-term 6 - TRANSITION AND apply:
actions which can be associated with, for ANCILLARY WORKS the Dossier Pilote des Tunnels (guidelines
example, local defects or losses of contact
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

Design of underground works is not limited for tunnels) published by CETu and the
between lining and surrounding ground due to designing just the running tunnel; civil latest circulars in force covering road and
to par ticular geological conditions (dissol- works for an underground project usually motorway tunnels (and, by extension, all
ving of gypsum, presence of karsts, etc.) or comprise: roads);
resulting from the construction of later
structures. tunnels, which are continuous structures Owner-published (SNCF, RATP, etc.) rules
allowing circulation of trains, vehicles, fluids for rail tunnels;
or transmission of energy;
5.2.3 - Combined actions - Stresses the Instruction technique relative aux
transition works: rseaux d'assainissement des agglomra-
The different combined actions must be - with the surface: specific examples are sta- tions (Engineering directive covering waste-
quantified on the basis of project data. tions, ventilation shafts, emergency shafts, water systems for urban areas) (Circular n
If no regulation applies, a factor of safety of inspection shafts and galleries, etc., 77.284 INT of 22 June 1977).
one is applied to each action. Stresses - between tunnels: specific examples are
applied to assemblies are then evaluated by branches providing communication, piston 6.2 - Construction of transi-
considering models and simple behaviour. relief, ventilation, rolling stock depot and tion and ancillary works
turning galleries, etc.;
5.2.4 - Behaviour of materials and
ancillary works: specific examples are Communication between transition ans
assemblies - Tests
- ventilated refuges or collection areas, ancillary works and the running tunnel inva-
In practice, actual material and assembly riable requires the construction of various
- safety recesses,
behaviour can only be fully understood size openings in the running tunnel lining.
through static and dynamic testing (shear, - fire recesses,
For example, construction of a transverse
tension, etc.). These types of test can go as - plantrooms, opening from inside the running tunnel
far as testing the capacity of the whole - vehicle turning galleries, usually involves the following operations:
assembly chain including the surrounding
concrete (with its design strength), as well - sand traps, special spacing of the lining rings;
as the reinforcement measures adopted which are essential for the operation of the temporary support of rings to be cut into
around the connector inserts. structure. by propping or bolting;
In general, test stresses differ from actual The present section is simply aimed at dra- possible treatment of ground around the
stresses; consideration of factors of safety wing attention to a number of design and future opening;
which are adequate with respect to test construction aspects of these transition and
ancillary works, which commonly represent in one or several stages, cutting out and
results and conditions particular to the pro-
unusual points in terms of precast concrete removal of segments in front of the opening
ject therefore appears necessary.
segmental lining design. Moreover, they under construction;
5.2.5 - Conclusions represent a major burden on the project in in one or several stages, excavation and
terms of cost and time. concreting of the final reinforced concrete
Tests on anchor and pick-up sockets, for lining of the strengthening structure around
example, fall within the scope of conventio- 6.1 - Design of ancillary the opening;
nal testing. On the other hand, because the works removal of temporary support.
plug system is relatively recent, experiments
should be pursued to define more accura- Construction of in-line works must be fore-
Design of ancillary works is closely depen-
tely the sizing problems and advantage seen as early as possible; consequently, their
dent on their functions.
should be taken of experience feedback geometrical proper ties and method of
from different projects in order to extend In particular, functions resulting in extensive construction must be fully defined by the
knowledge in relation to the operation of geometry can involve: Engineer and Owner's Representative right
this intersegment connection system. transfer and safety of the public; from design stage.
However manufacturers must supply a full ventilation (with respect to its twin Their construction stage must have a mini-
engineering file covering whatever systems aspects of health-related ventilation and fire mum impact on progress of TBM-excavated
are adopted. safety); construction of the main works.

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


237
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

7 - INSTRUMENTATION 7.2 - Monitoring methods rapid and virtually simultaneous measure-


ments; data acquisition from a large number
of sensors therefore provides an "instanta-
7.1 - Aims To achieve the above aims, the principal
effects to be measured are as follows: neous picture" compared with TBM pene-
tration rates;
Precast concrete segments lining instru- stresses and pressures:
mentation and monitoring schemes must scheduled frequency of measurement sui-
- measurement of pressures exerted by the ted to both the nature or variability of
satisfy several aims: back grouting material and ground on the actions concerned and data sought during
to check that lining actual behaviour com- lining extrados, different construction stages;
plies with forecasts resulting from planned - measurement of pressures exerted at seg-
data acquisition facilitated, in par ticular,
theoretical sizing and, in turn, to verify the ment contact joints.
when instrumented rings are within the
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

level of safety of the structure in terms of These measurements are often disrupted area enclosing the TBM back-up equipment.
forces and deformations; by the effect of sensor interaction (total
pressure cells) with the medium in which it Conversely, several drawbacks inherent in
to gain greater knowledge of: the use of automatic data acquisition should
has been installed. Results should always be
- the intensity and distribution of external subjected to careful analysis; be mentioned:
actions impacting on the lining during the danger of a systematic loss of data due to
segment deformations:
different stages construction progress (TBM defective installation or malfunction of a
thrust, annular gap back grouting, short- and These are often measured using vibrating component after fixing (closely supervised
long-term pressures exer ted by the sur- wire tensometers embedded in the seg- installation then periodic checking to be
rounding ground), ments and arranged: carried out by body in charge of measure-
- the intensity and distribution of segment - in a longitudinal direction, with a view to ment);
analysing stresses induced by TBM main
internal loads, especially: compatibility of recording box spatial
cylinder thrust,
resulting from TBM thrust (presence or requirements with respect to clearances to
- in a radial direction, with a view to analy- be provided temporarily for shor t-term
absence of defects in bearing between diffe- sing stresses induced by back grouting, the (erector arm, segments being erected, tem-
rent elements, evaluation of TBM length surrounding ground and possible disruptive porary equipment, back-up equipment, etc.)
influencing the lining), effects associated with TBM thrust. and long-term (rolling stock, permanent
resulting from successive actions involving A concrete control block fitted with sensors equipment, etc.);
back grouting and the surrounding ground is often provided as a reference, although its possible problem of energy supply and
under par tial cutter section confinement behaviour is somewhat different of that of independence; depending on the quantity of
and showing, for example, possible load the lining segments. data to be collected, various options can be
redistribution due to alternation of radial convergences: envisaged: large-capacity batteries, sophisti-
contact joints over a succession of rings. cated power plant controlled by energy-
- Invar wire or optical convergence measu-
In any case, Owners and contractors should rement, with a view to evaluating short- and saving electronics).
be made aware that these instrumentation long-term deformations withstood by lining In particular, all monitoring schedules must
schemes do not originate from the research rings. specify who is responsible for interpreting
field but must be regarded as a driving fac- Temperature probes and relative humidity results, the timescale and the data transmis-
tor in terms of fur thering the technical sensors must also be implemented at ins- sion chain. The validity of the monitoring
nature of this type of lining and allowing trumented sections in order to comple- system must be questioned if this often
both acquisition of quantifiable reference ment effectively the data collected. neglected interpretation stage does not
data, concerning the quality of the comple- exist.
Whilst tunnel lining monitoring has, until
ted tunnel, and advantage to be gained from now, been carried out conventionally by a In general, reference should be made to
analysing information fed back in order to technician, this method is now being chal- A.F.T.E.S. "Auscultation" (Monitoring)
refine the actual behaviour of this form of lenged by automatic data acquisition, which Working Group n 19 recommendations on
discontinuous lining. offers many advantages such as: tunnel monitoring measurements.

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


238
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

REFERENCES

TERZAGHI K. - Rock defects and loads on tunnel support - Rock Tunnelling with Steel Supports, Commercial Shearing Co - Youngstown,
Ohio, pp. 15-99, 1946.
PROTODIAKONOV M.M. - Klassifikacija Gornych Porod - Tunnels et Ouvrages Souterrains I, pp. 31-34, 1974.
LAUFFER H. - Gebirgsklassifizierung fr den Stollenbau - Geologie Bauwesen, 74, pp. 46-51, 1958.
DUDDECK H., ERDMANN J. - On structural Design Models for Tunnels in Soft Soil - Underground Space,Vol 9, pp. 246-259, 1985.
CORBETTA F., BERNAUD D., NGUYEN-MINH D. - Contribution la mthode convergence-confinement par le principe de la
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

similitude. Revue Franaise de Gotechnique n 54, pp. 5-12, 1991.


BERNAUD D., ROUSSET G. - La nouvelle mthode implicite pour l'tude du dimensionnement des tunnels - Revue Franaise de
Gotechnique n 60, 3e trim., pp. 5-26, 1992.
PANET M. - Le calcul des tunnels par la mthode convergence-confinement - Presses de l'Ecole Nationale des Ponts et Chausses, 1995.
NGUYEN-MINH D., GUO C. - Sur un principe d'interaction massif-soutnement des tunnels en avancement stationnaire - Eurok'93,
Lisbon, Portugal, 1993.
NGUYEN-MINH D., GUO C. - Tunnels creuss en milieu viscoplastique - Gotechnique et Environnement, Colloque Franco -Polonais,
Nancy, 1993.
MUIR WOOD A.M. - The circular tunnel in elastic ground - Geotechnique 25, n 1, 1975.
HOEK E., KAISER P.K., BAWDEN W.F. - Support of Underground Excavations in Hard Rock - A.A. Balkema, Rotterdam, Brookfield,
1995.

ANNEX : impervious seals of the mould are then cor- 2.2.1 - Cage preparation
rectly positioned.
Each reinforcing cage will be fitted with spa-
TUNNEL LINING CONSTRUC- Concrete contact surfaces are spray-lubri-
cers designed to ensure its accurate positio-
TION - PRECASTING AND INS- cated with a release agent.
ning in the mould and, thus, compliance with
TALLATION 2.1.2 - Reassembly of mould ele- specified concrete cover to the reinforcing
ments bars.

1 - GENERAL The mould will be reclosed in accordance 2.2.2 - Self-inspection and placing
with the specified flank and end closing of the reinforcing cage
The aim of the present section is to des- order.
cribe the main tunnel lining construction Before placing the cage in the mould, the
stages in such a way that actions applied to 2.1.3 - Self-inspection operator will ensure, in accordance with the
the segments during constr uction are reinforcing cage production Q.A.P., that this
recorded. After closing the mould, the operator will cage:
ensure proper closure of the mould by kee-
In general, these operations are covered by is not deformed in any way;
ping a watch on alignment of flank and end
construction procedures describing general reference marks and by undertaking other corresponds perfectly with the mould for
and specific requirements for production checks detailed in the Q.A.P.. which it is intended;
organization and which are consolidated is fitted with all the designed spacers, both
The operator will then examine visually
under a single more general document: the in number and in position.
each mould; these operations will be ente-
project Quality Assurance Plan (Q.A.P.).
red on the compliance inspection record After placement of the reinforcing cage in
specified in the Q.A.P.. the mould, the operator will ensure that the
2 - DESCRIPTION OF SEG- cage is correctly centred with respect to the
MENT PRECASTING 2.2 - Placement of reinfor- mould and will then fill in the compliance
cing cages inspection record.
2.1 - Mould preparation
With respect to the logical sequence of 2.3 - Mounting of connector
2.1.1 - Cleaning precasting operations, it is assumed that inserts and accessories
reinforcing cage production has followed its
Careful brush-cleaning of the peripheral own fabrication Q.A.P., incorporating all Whatever the systems selected, they will be
ends and flanks (especially their bearing joint contracting and subcontracting fabri- positioned generally after installing the rein-
faces) and mould bottom is under taken cation Q.A.Ps. as well as all the supply items forcing cage in the mould.They usually /
com-
with the mould in an open position. The entering into the composition of a cage. prise:

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


239
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

a pick-up device; 2.4.4 - Heat treatment, preheating - inspection of first reinforcing cages fabri-
sockets and pins for implementing socket of concrete cated in accordance with mass production
bolts or any other connection system; procedures.
Depending on the type of concrete thermal During production
a system for possible grouting behind seg- maturing selected, several methods can be
ments, etc.. envisaged: Segment precasting involves mass produc-
tion, therefore procedures specifying details
As in other fabrication operations, self-ins- hot water mixing of concrete (maximum of inspections to be carried out at regular
pection will be carried out by the operator, water temperature 80 C); intervals throughout the production period
who will check the correct positioning of all heating of mould underside; should be established to ensure that tole-
these connector inser ts and accessories rances for moulds, segments and reinforcing
before filling the compliance inspection steam curing under controlled tempera-
ture and relative humidity. cages, as well as concerning reinforcing cage
record.
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

assembly quality, always remain less than the


initially established values.
2.4 - Concreting 2.5 - Mould stripping -
- inspection of moulds approximately every
Handling - Pre-storage 50 casting operations,
The concrete Q.A.P. or CONCRETE FILE - same frequency inspection of correspon-
specifies the type of concrete, its proper- Unbolting and removal of connector insert
and accessory supports; ding segments at line output and correction
ties, constituent materials and, in particular : of mould adjustment if deviations are
the concrete mix; Release of lock-bolts for opening flanks and observed.
ends of mould;
the physical chemical analysis of consti- These inspections are essentially based on:
tuent materials: fine aggregate, coar se Positioning of lifting beam fitted with suc-
overall dimensions of the assembled ring;
aggregate, cement, water ; tion pads, or other gripper- or sling-based
handling system. lengths of segments generating ring taper ;
the active alkali balance; segment wall thickness;
After mould stripping, segments will be set
admixture engineering data sheet(s); down and stacked on suppor ts located in flatness of ring/ring contact surfaces;
test results for trial mixes produced for prepared sections of the pre-storage roughness;
design and suitability purposes; (curing) area inside the precasting shop or geometry of designed pockets and their
outside under suitable protection. Timber layout (impervious gasket grooves, etc.);
the Q.A.P. for the approved testing labora- blocks will be placed between segments
tory. taking care that they are aligned with the positioning of connector inserts (pick-up
supports. Curing time will be approximately socket, connection system, etc.);
2.4.1 - Concrete production and 8 hours and in general imposed by the geometry of reinforcing bars, quality of
preliminary checks sequencing of mould stripping, storing, reinforcing cages and their position in the
gluing, turning, packing and then loading-out moulds.
At the star t of each concreting shift, the operations.
operator will check proper operation of:
Self-inspection 2.7 - Repairs
the concrete plant PLC-controlled system
for weighing and accurately recording the The operator will then carry out the neces-
sary inspections and fill in the relevant com- A repair report, which will be attached to
weights of constituent materials; the relevant compliance inspection report,
pliance inspection report.
the water, admixture, plasticizer, accelera- will be drawn up for every repair.
tor, etc., regulation system; The Q.A.P. will specify repair procedures
2.6 - Inspections
the mixing time control system. and materials to be used for the different
cases encountered:
Moulds for the same lining ring must be
2.4.2 - Concrete placement fabricated and inspected from every angle honeycombing;
in relation to the ring. Similarly, in the case bubbles in waterproofing gasket grooves;
Continuous uniform placement in the
mould of the segment concrete volume will of several ring moulds, the type of mould spalling at edges, etc.
must be identical irrespective of the ring it
be ensured. Self-inspection after repair
forms.
inspection of waterproofing gasket groove
2.4.3 - Finishing of extrados or The following inspections are usually car- surface condition;
non-shuttered surfaces ried out:
inspection of extrados surface condition;
Prior to starting mass production of seg-
On completion of concreting, the free sur- inspection of bearing surfaces.
ments
face of the concrete will be floated as accu-
rately as possible. - inspection of mould fabrication,
2.8 - Installation of water-
After waiting for the initial set of the - inspection of ring geometry and assembly proofing gasket
concrete (approximately 20 - 40 minutes), using reinforced concrete segments from
final trowelling of the top of the segment initial precast shop casting, In the case of a glued waterproofing gasket
will be carried out to eliminate bug holes - inspection of moulds on delivery to pre- section, gluing will be carried out using an
and unevenness. cast plant, adhesive payer recommended by the sup-

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


240
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

plier of the gasket and installed in accor- Segments will be positioned at the precast copy will be returned to the segment manu-
dance with his instructions and procedures. plant storage yard to avoid a segment tur- facturer.
ning operation between yard storage and
2.9 - Packing and marking pick-up by the segment erector, whose suc-
tion pads or handling mechanisms pick up
the segment from the intrados side. 5 - SEGMENT SUPPLY TO
In general, segments of the same ring will be THE WORKFACE
packed together on timber blocks. When the erector is supplied in the upper
section of the TBM, segments are stored After segment acceptance, unloading and
Timber blocks between segments must be intrados lowermost. storage in an area near the tunnel access
perfectly aligned. (shaft, adit, etc.), supply to the workface
When the erector is supplied in the lower
Each segment will be marked according to section of the TBM, segments are stored usually depends on the area available and it
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

instructions given on the contract drawings intrados uppermost and, in this case, a seg- represents a minimum stock.
(intrados bearing face), to enable it to be ment turning machine enables this opera- Storage can be organized by:
identified and cross-referenced with the tion to be carried out at the precast plant.
relevant inspection record (traceability). segment;
In its storage position, the segment rests on
by segment pair ;
two timber blocks of the same length as the
2.10 - Internal preshipment segment itself and positioned directly in line by rings palletized on steel frames.
inspection with the longitudinal assembly systems. Storage design is therefore based on the
Segments are stored by stacking each set of selected transport methods within the tun-
The segment loading supervisor will indi- segments comprising a ring. nel and to the TBM, where the segments are
cate the transported ring number, as well as unloaded, then placed on a belt or roller
the precasting date of its component seg- Segments must be stored after precasting
and can only be installed if their strength feed conveyor which delivers them to the
ments, on the preshipment inspection front where they are picked up by the seg-
report. exceeds or is equal to that required by the
project specifications. ment erector.
He will check that connector inser ts and
accessories are clean and protected, that
there is no concrete spalling, that water- 6 - LINING RING BUILDING
proofing gaskets and possibly pads are pro- 4 - SEGMENT COLLECTION,
perly glued. TRANSPORT AND ACCEP- Section 3.5.5 "Segment assembly systems"
He will also check segment packing, align- TANCE ON SITE of the present recommendations specifies
and describes:
ment of timber blocks and the size of the In principle, the precast plant loading super-
pack. visor is responsible for collecting segments the different assembly systems;
A copy of the inspection report will be sent from the plant storage yard and the haulage the aims sought under construction and
to site along with the delivery note. contractor is responsible for transport. service conditions.
Segments are picked up at the precast plant The following table complements this infor-
storage yard by lifting beam fitted with suc- mation by considering an example of buil-
3 - STORAGE AT PRECAST tion pads, grippers or slings and they are ding a lining ring comprising rectangular-
then loaded onto lorries or another means (standard) and trapezoidal-shaped (key and
PLANT YARD of transport. counter) segments. It details:
Special care is required in relation to sto- On-site segment inspection for acceptance the successive segment erection stages;
rage and possible thermal protection condi- purposes will be conducted on the lorry or
tions to prevent segment concrete micro- recommendations associated with the
other means of transpor t. Prior to unloa-
cracking at the precast plant storage yard. ding, the site representative will sign and operating environment for each erection
make any written remarks on the delivery stage;
Handling will be undertaken using a lifting
beam fitted with either suction pads or note. A few remarks of a general nature comple-
slings, which allows a pack of several seg- Detailed observations will be included on ment the table.
ments to be picked up. the pre-unloading inspection report and a

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


241
The design, sizing and construction of precast concrete segments
installed at the rear of a tunnel boring machine (TBM)

SCHEDULE OF OPERATIONS RECOMMENDATIONS REMARKS


1) Supply of first segment to erector. Supply possible from:
- upper level;
- lower level.

2) First segment pick-up. Pick-up possible using suction pads, grippers, bolts.
3) Retraction of thrust cylinders corresponding
to placement of first segment.
All reproduction, translation and adaptation of articles (partly or totally) are subject to copyrigth.

4) Positioning of first segment by Detailed analysis of loads in each pick-up system Light ray guidance systems can facilitate
rotating erector. position and of indirect loads on segments. approach and final positioning of segment.

5) Radial approach of first segment.

6) Final approach with rotational, longitudinal and Control of approach speeds by selection of
transverse balance adjustment. proportioning hydraulic controls.

7) Holding of first segment on ring. Pads of other thrust cylinders remain under pressure TBM main cylinder thrust on the other segments
in contact with other segments to safely ensure: must prevent any forward displacement of
- segments holding and assembly, the machine.
- compression of waterproofing gaskets and At this time, the segment is simultaneously held by
prevention of their decompression, the erector and the thrust from the main cylinders.
- stability of the machine under the confinement p
ressure.

8) Fixing of first segment see 3.5.5 "Segment assembly systems" By ring/ring (longitudinal), segment/segment
(transverse) connection.

9) Installation and fixing of standard segments. Same recommendation as for the first segment. ame remark as for the first segment.
Provide alternate installation of segments in each
ring to minimize tube roll effects.

10) Installation of counter segments. Use of template to calibrate gap between Same remark as for first segment.
counter segments.

11) Key segment installation. Use of template prevents: It should be noted that on completion of erection,
- tearing of waterproofing gaskets, the ring is stabilized by the prestress between the
- concrete chipping. erection jacks and the previously installed ring.
- greasing of waterproofing gaskets. The only contact between the shield tail and
the segmental lining is the shield tail seal.

TUNNELS ET OUVRAGES SOUTERRAINS HORS-SERIE N 1 2005


242
www.aftes.asso.fr

All rights for reproduction or adaptation in whatever format are expressly reserved

Das könnte Ihnen auch gefallen