Sie sind auf Seite 1von 111

KING KHALED INTERNATIONAL AIRPORT - KSA

MEGA PLANT A (LC1) - Pump Room


BILL OF QUANTITIES - SUMMARY

BILL NO. DESCRIPTION

1 Preliminaries & Site setup

2 Earth works

3 RCC works - Substructure

4 RCC Works (Super Structure)

5 Block work

6 Roofing & Waterproofing

7 Aluminum, Steel and Wood works

8 Architectural finishing works

A Structural & Architectural (Total Amount)

9 Plumbing Domestic water supply system

10 Drainage, Soil & Waste system

11 HVAC System

12 Fire Protection works

13 Building Electrical and Low Voltage system

B Building services (Total Amount)

Grand Total Amount in SAR (A+B)

Note:

The Lump sum Prices indicated by the contractor as above shall cover the entire scope of works detai
specifications, drawings and contractual documents which form part of the contract, whether or not itemiz

362490201.xlsx - Appendix A Summary Page: 1 / 111


Project No. 630922
Package: - C-2001.3
Date:23rd April 2017

KHALED INTERNATIONAL AIRPORT - KSA


MEGA PLANT A (LC1) - Pump Room
BILL OF QUANTITIES - SUMMARY

AMOUNT in SAR

contractor as above shall cover the entire scope of works detailed in the tender
l documents which form part of the contract, whether or not itemized above.

362490201.xlsx - Appendix A Summary Page: 2 / 111


TENDER FORM - APPENDIX - "A"

LC1 - KKIA - PUMP ROOM


BREAKDOWN OF LUMP SUM PRICE

Sl.No. Description Unit Qty

1 Preliminaries & Site setup


Site Mobilization & Demobilization and site clearance after Project
1.01 Lot
Completion
Contractor's Facilities

Provide, Maintain and take back after project completion contractor Porto
1.02 cabin office for this package and their subcontractors complete with Lot
water supply, drainage connection, electricity etc.

Site facilities for labours including shaded & air-conditioned rest area/meal
1.04 Lot
room and restrooms.
Supply & fix Project signboard for project information and light box for
1.05 Lot
perspective

1.06 Shop drawings & As-Built Drawings for Civil, Arch, MEP items etc., Lot

Co-ordination with Other Contractors and Obtain Construction NOC /


1.07 Lot
Permits / Approvals from Authorities (if required), Bonds & Insurance

1.08 Items not listed above but specified elsewhere in contract Lot

Section total carried to summary


2 Earth works

Complete Earth work for Pump room foundation including site leveling,
2.01 excavation, backfilling, etc.

Section total carried to summary

3 RCC works - Substructure

All RCC - In-situ Reinforced Cement Concrete all accordance with


Specification with shuttering, rebar, water stop and all associated
works, curing, testing etc.,

3.01 Blinding below raft foundation as per the structural drawings & details. m2

362490201.xlsx - Appendix-A 3 / 111 Printed on : 08/06/2017


TENDER FORM - APPENDIX - "A"

LC1 - KKIA - PUMP ROOM


BREAKDOWN OF LUMP SUM PRICE

Sl.No. Description Unit Qty

RCC for Raft foundation and all associated works as specified including
3.02 catch basins, embedded sleeves, conduits etc. Locations, sizes and number m
of such provisions to be confirmed during construction.

2 coats of bituminous paint as waterproofing system for raft slab including


3.03 m2
Polythene sheet.

RCC for all types of service pits, Electrical trenches/Duct Bank between LC-
3.04 m
1 Building to Primary Pump Building

3.05 Other works not listed above but specified elsewhere in contract Lot

Section total carried to summary


4 RCC Works (Super Structure)

All RCC - In-situ Reinforced Cement Concrete all accordance with


Specification with shuttering, rebar, water stop and all associated
works, curing, testing etc.,

RCC for columns and column heads at various levels As per the drawing &
4.01 m
details

4.02 RCC for beams at various levels m

4.03 RCC for roof slabs at various levels. m

4.04 RCC for Equipment foundation, bases and pads m

4.05 Other works not listed above but specified else where in contract LS

Section total carried to summary

5 Block work

Autoclaved aerated concrete (AAC) thermalite blocks and / or


CMU (Solid / Hollow) wall bedded and joined in cement mortar
including reinforcing bars, anchor, ties, lintels, compressive fillers or
fire stopping (if applicable) and other accessories, etc. complete as
per drawings.

5.01 All External Block Walls as per drawing / specification m2

362490201.xlsx - Appendix-A 4 / 111 Printed on : 08/06/2017


TENDER FORM - APPENDIX - "A"

LC1 - KKIA - PUMP ROOM


BREAKDOWN OF LUMP SUM PRICE

Sl.No. Description Unit Qty

5.02 All internal Block Walls as per drawing / specification m2

5.03 Items not listed above but specified elsewhere in contract LS

Section total carried to summary

6 Roofing & Waterproofing

Roof water proofing system with light weight concrete, 4mm water
proofing membrane, 70mm rigid poly foam, 350gm/Sqm Non woven
6.01 Geotextile Fabric layer, 50mm gravel for drainage system & 40mm Loosely m2
laid concrete tiles as finished surface all as per specification & drawings
with 10 years guarantee.

6.02 Items not listed above but specified elsewhere in contract LS

Section total carried to summary

7 Aluminum, Steel and Wood works

A Doors

Supply and install All doors with door frame, iron monogamies and all
accessories as per drawings, details & specifications

All steel doors are 2 hrs. fire rated & All wooden doors are 1 hr. fire rated.

7.01 Single leaf Steel Door (D03 - 1000 X 2200mm High) Nr.

7.02 Double leaf Steel Door (D04 - 2500 X 3000mm High) Nr.

B Windows

Supply and install All Windows with window frame, iron monogamies
and all accessories as per drawings, details & specifications

Powder coated Aluminum Framed sliding window with Double glazing


7.03 Nr.
glass (W01 - 1500 X 1300MM high)

362490201.xlsx - Appendix-A 5 / 111 Printed on : 08/06/2017


TENDER FORM - APPENDIX - "A"

LC1 - KKIA - PUMP ROOM


BREAKDOWN OF LUMP SUM PRICE

Sl.No. Description Unit Qty

Powder coated Aluminum Framed sliding window with Double glazing


7.04 Nr.
glass (W03 - 600 X 600MM high)

C Other Metal Works

Installation of embedded plates (Supply of plates by others). Contractor


7.05 has to fix all the embedded plates based on Detailed Engineering and in Lot
coordination with Mechanical Contractor.

Supply & Installation of Pipe Sleeves for Process requirement. Contractor


7.06 has to supply & fix all pipe sleeves based on Detailed Engineering and in Lot
coordination with Mechanical Contractor.

7.07 Access panels, steel covers, removable grating, closures for openings Lot

Supply and install steel - CAT Ladder/"Monkey Ladder " with all fixing
7.08 Nr.
accessories as per the drawing & details

7.09 Items not listed above but specified elsewhere in contract Lot

Section total carried to summary


8 Architectural finishing works
Floor Finishes including Skirting works.

Epoxy floor (Nito-floor FC 150 with Nito Floor Anti-slip grains or equivalent)
8.01 m2
finish -50 mm Thick for Pump area.

Epoxy floor finish over 100mm power floated sealed screed for electrical
8.02 m2
equipment rooms etc. as per drawing & finishing schedule.

Wall Finishes

Supply & apply Emulsion paint over AAC thermalite blocks and fair face
8.03 m2
concrete works as per the drawing & finishing schedule.

Ceiling Finishes

362490201.xlsx - Appendix-A 6 / 111 Printed on : 08/06/2017


TENDER FORM - APPENDIX - "A"

LC1 - KKIA - PUMP ROOM


BREAKDOWN OF LUMP SUM PRICE

Sl.No. Description Unit Qty

Supply & apply Emulsion paint over fair face concrete surface as per the
8.04 m2
drawing & finishing schedule.

External Finishes

Supply & apply Epoxy paint over 20mm thick plastered walls as per
8.05 m2
drawing & details.

8.06 Any other finishes specified elsewhere in the contract Lot

Section total carried to summary

9 Plumbing Domestic water supply system

Supply and Install Cold Water Pipe work with associated valves including
9.01 Lot
insulation (as applicable) etc., including Testing & Commissioning.

9.02 Items not listed above but specified elsewhere in contract Lot

Section total carried to summary

10 Drainage, Soil & Waste system

Internal process drainage pipes, fittings and accessories of various dia. for
10.01 Lot
building including insulation (as applicable) upto the TIE-IN Point

External process drainage pipes, fittings and accessories of various dia. for
10.02 Lot
plant as per the drawing & details.
Floor traps, gully traps, cleanouts, Man hole, floor drains, funnel drains,
10.03 Catch basins, flanges and covers at various locations as shown on drawing Lot
for drainage.

RAIN WATER DRAIN SYSTEM


Rainwater pipe work cast into concrete structure, Roof water outlet,
10.04 Lot
Discharge at ground level including joints, fittings, hangers supports and
accessories; all as Specification and drawings

10.05 Items not listed above but specified elsewhere in contract Lot

Section total carried to summary

11 HVAC System

362490201.xlsx - Appendix-A 7 / 111 Printed on : 08/06/2017


TENDER FORM - APPENDIX - "A"

LC1 - KKIA - PUMP ROOM


BREAKDOWN OF LUMP SUM PRICE

Sl.No. Description Unit Qty

Submittals, approvals, O&M Manuals, material supply, delivery to site,


fabrication and Installation, Painting & touch-up of the following Building
HVAC System related items, according to specifications, drawings, ASHRAE,
ASTM standards and local regulations.

Prices shall include all necessary works such as custom duty,


transportation, lifting, installation, mechanical and electrical connections,
11.01 spring isolators, condensate drain piping, performance testing for a fully
functional system as per project drawings and

Supply, Installation, Insulation, Electrical Connections and Terminations,


Commissioning and Testing of Chilled water Packaged Roof Top Unit (PU) / LS
DX Unit as per Project Specifications and Drawings

11.02 HVAC Ducting and Accessories Lot

HVAC Ducting and Accessories Complete with insulation, vapor Barriers,


flexibile connections, duct supports and aluminum cladding inclusive of all
Treminals, Grilles and Diffusers as per project specifications and drawings.

11.05 Electrical Power and HVAC Control System:

MCC for HVAC Equipment including Packaged Unit/Fans Power Starters


11.05.01 and Control Panels, Local Isolators, Switches & Emergency Push Button Lot
Stations.

Controllers to control each Packaged Unit/Fans, Temperature transmitters,


11.05.02 Temperature reset units, Modulating control valves, Differential pressure Lot
switches, Flow switches & Duct smoke detectors.

11.05.03 Supply and Install of a Centralized station for Control and monitoring Lot

11.05.04 Power & Control wiring including Cable Trunking/Conduits/Cable Lot


Trays/Raceways and respective item supporting system.

362490201.xlsx - Appendix-A 8 / 111 Printed on : 08/06/2017


TENDER FORM - APPENDIX - "A"

LC1 - KKIA - PUMP ROOM


BREAKDOWN OF LUMP SUM PRICE

Sl.No. Description Unit Qty

Communication/interface with Plant PLC through MODBUS RS 485


including Modifications at Existing DC Plant BMS.
11.05.05 Modifications at existing plant BMS main controller & Modbus Lot
communication gateway to integrate and allow remote monitoring and
control of the pump room DDCs/HVAC units.

Start-up & Commissioning - Plant Building Services only Excluding Process


11.06 Lot
equipment:

Provide labour, tools, documents and temporary/permanent material to


execute the Cleaning, Flushing, testing, adjustment, balancing, pre-
commissioning, start-up, recording, commissioning, Assistance to SNC
Lavalin Team & warranty period maintenance, according to Specifications,
Drawings, ASHRAE, ASTM, NFPA standards and local regulations.

Items not listed above but specified elsewhere in contract documents,


and/or required for the effective functional HVAC system as per client's
11.07 Lot
requirement. (Bidders should provide details of such items with
breakdown in a separate sheet)

Section total carried to summary.

12 Fire Protection works

Fire Protection/Fire alarm System - according to Drawings, Specifications,


Civil Defense, NFPA Regulation, Contract Documents and all applicable
codes & standards etc., but not limited to the following:
Works shall be carried out by Specilized FF Contractor

Approvals from local authority & client - Fire Protection and Fire alarm &
12.01 Lot
detection system etc.,

Supply and install a Standpipe - Automatic Fire Hose Reel with all relevant
12.02 Lot
piping, all supervised valves etc., as per the layout drawing.

362490201.xlsx - Appendix-A 9 / 111 Printed on : 08/06/2017


TENDER FORM - APPENDIX - "A"

LC1 - KKIA - PUMP ROOM


BREAKDOWN OF LUMP SUM PRICE

Sl.No. Description Unit Qty

Supply and install a sprinkler fire protection network with all relevant
12.03 piping, all supervised valves, all sprinkler heads, etc., as per the layout Lot
drawing.
Supply and install a Clean Agent Fire Suppression System in All Electrical
Equipment rooms as per layout drawings.
12.04 LS
NOVEC Fire Suppression system in VFD room (Refer layout drawing for
room size).

Supply and install all portable fire extinguishers in accordance with NFPA
12.05 Lot
Standards and as per drawings

12.06 Supply and install Fire Detection & Alarm System with Control panel. Lot

Supply and install all cables with accessories between fire alarm panel and
fire detection devices, Remote fire alarm panel, Alarm valve, Flow
12.07 Lot
switches, Plant Control System, PLC, Clean Agent System and as required
by Drawings, Specifications and Standards.

Start-up and Commissioning, Flushing and cleaning, Testing, Room


12.08 Lot
Integrity Test & Recharge of Cylinders of Clean Agent System

Items not listed above but specified elsewhere in contract (Bidders should
12.10 Lot
provide details of such items with breakdown)

Section total carried to summary

13 Building Electrical and Low Voltage system

Detailed calculations, submittals, approvals, as-built, material supply, off-


loading, storage, handling, installation and testing & Commissioning.
Including all required fixation material and tags for the following as per
specification, drawings and local authority regulations.

Distribution boards including all mains and branch circuit protective


13.01 Lot
devices, instruments, instrument transformers, contactors, timers, etc.,

Indoor lighting / Roof Lighting fixtures including lamps with all required
13.02 Lot
accessories.

362490201.xlsx - Appendix-A 10 / 111 Printed on : 08/06/2017


TENDER FORM - APPENDIX - "A"

LC1 - KKIA - PUMP ROOM


BREAKDOWN OF LUMP SUM PRICE

Sl.No. Description Unit Qty

All kind of outdoor lighting fixtures including lamps with all required
13.03 Lot
accessories (Note : external light poles & lighting fixtures by others)

Emergency & Exit lighting fixtures with lamps and all required accessories
13.04 Lot
and lighting control devices as per Civil Defense requirements

Indoor / Roof Floor Power sockets with switches, lighting control switches.
13.05 Lot
including all required accessories and control devices.

Welding Socket / Three Phase Industrial type Power sockets with switches,
13.06 Lot
including all required accessories and control devices.

Cabling for all Light fixtures, UPS-SUBDB, all switches, all sockets and
13.07 control devices. Including required conduits/trays/trunking / race ways, Lot
junction boxes, fire stopping material at wall crossings and accessories.

Intercom system with sockets, outlets, cabinet, patch panels, junction


13.08 boxes, cover plates, conduits, cabling and necessary integration with DC Lot
Plant Intercom System

Public address system including Microphones, Speakers, cabling, conduits,


13.09 all necessary accessories and necessary integration with DC Plant Public Lot
Address System.

Access control system including Card readers, Door contacts, Magnetic


locks, Electrical latches, Emergency push button, cabling, conduits, all
13.10 Lot
necessary accessories, fittings and necessary integration with DC plant
Access Control System.

CCTV system including Fixed weatherproof camera Including cabling,


13.11 conduits, all necessary accessories and necessary integration with DC Plant Lot
CCTV System.

Main Grounding system, including earth pit, earth rods, copper bars, test
clamp and all necessary fixings as applicable and as shown on the
13.12 Lot
preliminary drawings and as specified including integration with DC Plant
Grounding system

362490201.xlsx - Appendix-A 11 / 111 Printed on : 08/06/2017


TENDER FORM - APPENDIX - "A"

LC1 - KKIA - PUMP ROOM


BREAKDOWN OF LUMP SUM PRICE

Sl.No. Description Unit Qty

Lightning Grid for TES Tanks Lightning protection system with necessary
13.13 accessories as applicable; as shown on the preliminary drawings and as Lot
specified. Including integration with DC Plant lightning Protection System.

Pre-commissioning, testing, commissioning of the complete building


13.14 Lot
electrical and low voltage system covered under this package.

Miscellaneous items such as connections to the drainage/sewage pumps,


13.15 Main power supply to Fire alarm & Gas detection Panels and Builders work Lot
as specified and shown on the drawings.

Items not listed above but specified elsewhere in contract and/or required
13.16 to complete the work. (The contractor shall provide detailed breakdown Lot
prices to justify the amount mentioned against this item.)

Section total carried to summary

362490201.xlsx - Appendix-A 12 / 111 Printed on : 08/06/2017


King Khaled International Airport
KSA, Mega plant A (LC1)

20-Apr-2017
630922
C-2001.3
Unit Rate Amount in SAR

N/A

Included

362490201.xlsx - Appendix-A 13 / 111 Printed on : 08/06/2017


King Khaled International Airport
KSA, Mega plant A (LC1)

20-Apr-2017
630922
C-2001.3
Unit Rate Amount in SAR

Included

Included

362490201.xlsx - Appendix-A 14 / 111 Printed on : 08/06/2017


King Khaled International Airport
KSA, Mega plant A (LC1)

20-Apr-2017
630922
C-2001.3
Unit Rate Amount in SAR

included

included

Rate Only

362490201.xlsx - Appendix-A 15 / 111 Printed on : 08/06/2017


King Khaled International Airport
KSA, Mega plant A (LC1)

20-Apr-2017
630922
C-2001.3
Unit Rate Amount in SAR

Rate Only

included

362490201.xlsx - Appendix-A 16 / 111 Printed on : 08/06/2017


King Khaled International Airport
KSA, Mega plant A (LC1)

20-Apr-2017
630922
C-2001.3
Unit Rate Amount in SAR

included

Included

By others

Included

362490201.xlsx - Appendix-A 17 / 111 Printed on : 08/06/2017


King Khaled International Airport
KSA, Mega plant A (LC1)

20-Apr-2017
630922
C-2001.3
Unit Rate Amount in SAR

Existing

362490201.xlsx - Appendix-A 18 / 111 Printed on : 08/06/2017


King Khaled International Airport
KSA, Mega plant A (LC1)

20-Apr-2017
630922
C-2001.3
Unit Rate Amount in SAR

Included

362490201.xlsx - Appendix-A 19 / 111 Printed on : 08/06/2017


King Khaled International Airport
KSA, Mega plant A (LC1)

20-Apr-2017
630922
C-2001.3
Unit Rate Amount in SAR

Included

362490201.xlsx - Appendix-A 20 / 111 Printed on : 08/06/2017


King Khaled International Airport
KSA, Mega plant A (LC1)

20-Apr-2017
630922
C-2001.3
Unit Rate Amount in SAR

N/A
(Part of TA
scope under
Consortium
agreement.)

362490201.xlsx - Appendix-A 21 / 111 Printed on : 08/06/2017


King Khaled International Airport
KSA, Mega plant A (LC1)

20-Apr-2017
630922
C-2001.3
Unit Rate Amount in SAR

included

362490201.xlsx - Appendix-A 22 / 111 Printed on : 08/06/2017


DC Scheme for Prince S
TENDER FORM -- APPENDIX "B" Medical Ce
C-2001

UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF


LUMP SUM WORK

Sl.No. Description Unit


LABOUR
1.01 Charge hand hr.
1.02 Ganger hr.
1.03 Mason hr.
1.04 Carpenter hr.
1.05 Steel Fixer hr.
1.06 Painter hr.
1.07 Pipe Fitter hr.
1.08 Fabricator hr.
1.09 Welder hr.
1.10 Steel Erectors hr.
1.11 Electrician hr.
1.12 Plumber hr.
1.13 Scaffolders hr.
1.14 Skilled Helper hr.
1.15 Unskilled Helper hr.
1.16 Labour hr.
1.17 Watch Man hr.
1.18 Light Duty Driver hr.
1.19 Office Attendant hr.
1.20 Secretary hr.
1.21 Store Keeper hr.

PLANT AND EQUIPMENT


2.01 Crane 20T hr.
2.02 Crane 30T hr.
2.03 Mobile crane less than 10 Tonnes hr.
2.04 Hiab / Wheel mounted crane hr.
2.05 Excavator (1.0m3 bucket capacity) hr.
2.06 Wheel loader / shovel (1.0m3 bucket capacity) hr.
2.07 JCB hr.
2.08 Bobcat hr.
2.09 Forklift hr.
2.10 Water tanker, with 3000gal water good for construction hr.
2.11 3T pickup hr.
2.12 5T pickup hr.
2.13 Van or utility pickup, max 1.50T capacity hr.
2.14 20m3 truck hr.
2.15 40m3 truck hr.
2.16 Open truck 40 ft hr.
2.17 Portable compressor, 4.6 m3 incl. Tools & hoses hr.
2.18 Air compressor 6m3/min incl. 2 hoses and tools hr.
2.19 Dumpers 1.0m3 capacity hr.

362490201.xlsx - Day Works Page: 23 / 111


2.20 Concrete vibrator/poker (petrol operated) hr.
2.21 Welding machine hr.
2.22 Electrical operated jack hammer hr.
2.23 Small power tools

362490201.xlsx - Day Works Page: 24 / 111


DC Scheme for Prince Sultan Cultural &
Medical Center
C-2001

Unit rate in SR Remarks

362490201.xlsx - Day Works Page: 25 / 111


362490201.xlsx - Day Works Page: 26 / 111
TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description Unit

1 EARTHWORK

1.01 Mass cut/ fill and compact m3

1.02 Grading and leveling m2

1.03 Excavate to receive foundations not exceeding 3.0m deep m3

1.04 Excavate to receive foundation 3.00m - 6.00m deep m3

1.05 Excavate trench to receive pipe or cable 1.5m-3.0m deep m3

1.06 Manual excavation to receive foundation m3

1.07 Rock excavation - hard rock m3

1.08 Rock excavation - Sedimentary rock m3

1.09 Soil improvement with stone piling M

1.10 Imported Gatch filling in making up levels & compaction m3

1.11 Imported structural filling in making up levels & compaction m3

1.12 Backfill using road base material (250mm thick) compacted to 98% MDD m3

1.13 Backfill using sorted excavated material and compaction m3

1.14 Cart away surplus excavated material m3

1.15 Gatch surfacing 150 mm thick with compaction m2

1.16 Geo-textile filter membrane 180g/m2 m2

2a Mass concrete using moderate sulphate resisting


cement, mix grade 20N/mm2 including shuttering works
2.01 In substructure 50mm thick. m2

2.02 In substructure 100mm thick. m2

2b Mass concrete using moderate sulphate resisting


cement, mix grade 40N/mm2 including shuttering works
2.03 Mass concrete for raft foundation (Rebar measured separately) m3

362490201.xlsx - Appendix - B Page: 27 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description Unit


Bored cast in-situ concrete piles; SRC concrete with rebar, Cutting
of pile head and Waterproofing etc., all as per specification
2c including mobilization, demobilization of piling equipments &
Testing. Unit Rates shall be indicated for 7.5 mtrs effective length
and any change in lengths shall be prorated.

2.04 600 mm Dia Piles - 7.5Mtrs effective Length Nr.

2.05 750 mm Dia Piles - 7.5Mtrs effective Length Nr.

2.06 900 mm Dia Piles - 7.5Mtrs effective Length Nr.

3 Reinforced concrete using moderate sulphate


resisting cement, mix grade 40N/mm2 including
reinforcement (N.E 175 kg/m3)and form work complete
3.01 In foundations m3

3.02 In pile cap m3

3.03 In Retaining Wall m3

3.04 In Tie beams m3

3.05 In Neck columns, Columns, column heads & pilasters m3

3.06 In flooring concrete 150mm thick m3

3.07 In flooring concrete 200mm thick m3

3.08 In Water tank with waterproof additive added in concrete m3

3.09 In equipment bases m3

3.10 250mm wide PVC water stop cast into concrete LM

3.11 600 x 600 heavy duty manhole cover and frame Nr.

3.12 Access hatch cover 900 x 900 mm Nr.

4 Reinforced concrete in Superstructure using OPC


cement mix grade 40N/mm2 including reinforcement
(N.E. 175 kg/m3) and form work complete
4.01 In columns, column heads, beams and Core walls m3

4.02 Solid Slab 150 mm thick m2

4.03 Floor Solid Slab 250 mm thick m2

362490201.xlsx - Appendix - B Page: 28 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description Unit


4.04 Solid slab in various thickness m3

4.05 RCC of any nature other than the above stated m3

5 FORMWORK

5.01 To sides of foundation, beds or the like m2

5.02 To sides of RCC walls m2

5.03 To columns m2

5.04 To sides & soffits of suspended slabs or beams m2

5.05 To soffits of staircase including risers & strings m2

6 REINFORCEMENT

6.01 Mild steel bar reinforcement supply and installed incl. Wastage kg

6.02 High tensile steel bar reinforcement, S & I include. Wastage kg

6.03 Mild steel mesh reinforcement supply and fixing kg

7 BLOCK WORK
Autoclaved aerated thermalite block work laid in mortar,
including all ties to concrete and DPC complete as per particular
specification.
7.01 100mm thick wall m2

7.02 200mm thick wall m2

7.03 250mm thick wall m2

Pre-cast concrete block work laid in mortar, including all ties to


concrete and DPC complete as per particular specification.

7.04 100mm thick solid block work m2

7.05 200mm thick solid block work m2

7.06 100mm thick hollow concrete block work m2

7.07 200mm thick hollow concrete block work m2

8 ROOFING & WATERPROOFING


Waterproofing to Foundations

362490201.xlsx - Appendix - B Page: 29 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Prepare,
Descriptionprimer and apply two coats of solvent free rubberized bitumen Unit
8.01 m2
emulsion to horizontal
Prepare and lay one layer of polythene membrane 1000 gauge, with
8.02 m2
laps.
Concrete structure waterproofing using 1.50mm self-adhesive
8.03 m2
membrane with 3mm protection board
Concrete structure waterproofing using 1.50mm self-adhesive
8.04 m2
membrane with 50mm thick protection screed
8.05 Water tank internal water proofing with 4 mm thick GRP Lining m2

8.06 Water tank internal water proofing with 2 mm thick GRP Lining m2
4mm torch applied waterproofing membrane to floor / wall with 3mm
8.07 m2
protection board/plywood/screed, complete with primer
Liquid applied waterproof membrane 1.50mm thick Master seal 180 or
8.08 m2
equivalent
8.09 4mm torch applied waterproofing membrane to floor / wall m2

8.10 Light weight foam concrete/Screed m2

8.11 Torch applied SBS bitumen membrane m2

8.12 50mm thick expanded polystyrene insulation board m2

8.13 Geo-textile separation layer 110g/m2 m2

8.14 Terrazzo roof tiles laid with Cement sand mortar m2

8.15 40mm thick concrete tiles over water proofing system m2

8.16 Skirting, flashing and termination m

9 GROUTING

9.01 To underside of base and machinery bed plates not exceeding 0.50m2 (Ep Nr.

9.02 To underside of base and machinery bed plates not exceeding 0.50m2 (non Nr.

9.03 To underside of base and machinery bed plates (epoxy) m2


9.04 To underside of base and machinery bed plates (non shrink grout ) m2

10 ANCHOR BOLTS

10.01 Mild steel anchor bolt n.e 1 Kg weight each KG

10.02 High tensile steel n.e 1 Kg weight each KG

10.03 High tensile steel over 1 Kg weight each KG

362490201.xlsx - Appendix - B Page: 30 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description Unit


10.04 16mm dia hilti bolts Nr.

10.05 20mm dia hilti bolts Nr.

10.06 Chemical anchor bolts 20mm dia. Nr.

11 STEEL WORK & CLADDING

11.01 Primary steel work in stanchions, beams columns, runway beams & the lik Kg

11.02 Secondary steelwork in rails bracings, channels and the like Kg

11.03 Prefabricated mild steel hand railing, ladders and the like including fixings Kg

11.04 Galvanized angle iron for concrete embedment cut to size and shape with Kg

11.05 10 mm mild steel chequer plate cover measured nett m2

11.06 Extra over for galvanization Kg

11.07 GI Electrical trench grating 50mm high, 6mm thick kg

11.08 Supply and fix G.I.angle iron /channel supports Kg

Rigidal composite panel roof cladding-Outer sheet 0.7 mm gauge,


11.09 Insulation 100 mm thick rigid closed cell, Inner sheet 0.5 mm gauge m2
lightly ribbed profile
11.10 Sealing of roof openings m2
11.11 Flashing: External 0.7 mm plain Aluminum sheet polyester m2
11.12 Flashing: Internal 0.5 mm plain Aluminum sheet polyester m2
Rigidal composite panel wall cladding-Outer sheet 0.7 mm gauge,
11.13 Insulation 100 mm thick rigid closed cell, Inner sheet 0.5 mm gauge m2
lightly ribbed profile

12 METALWORK AND GLAZING


Polyester powder coated aluminium framed doors and
windows with glazing including fly screen
sealants, ironmongery and the like fixing in position
In windows n.e.1 m2 m2
12.01 In windows exceeding 1 m2 m2

12.02 In doors area not exceeding.2m2 m2

12.03 In doors, area exceeding 2m2 m2

12.04 Louvered doors, area n.e.2m2 m2

362490201.xlsx - Appendix - B Page: 31 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description Unit


12.05 Louvered doors, area exceeding 2m2 m2
Powder coated air intake Aluminium Louvers in the cooling tower area
12.06 m2
with all the supporting steel structures
12.07 Aluminium tubular handrail and balustrades m

Steel door and Rolling shutters


Heavy duty steel doors as per tender drawings including Ironmongeries
12.08 m2
etc.area n.e.2m2
Heavy duty steel doors as per tender drawings including ironmongeries
12.09 m2
etc. area exceeding 2m2
Heavy duty steel doors with insulation as per tender drawings including
12.10 m2
Ironmongeries etc. (area n.e.2m2)
Heavy duty steel doors with insulation as per tender drawings including
12.11 m2
Ironmongeries etc. (area exceeding 2m2)
Heavy duty rolling shutters with electrical operation as per tender
12.12 m2
drawings including Ironmongeries etc.area n.e.10m2
Heavy duty rolling shutters with electrical operation as per tender
12.13 m2
drawings including Ironmongeries etc.area exceeding 10m2

13 CARPENTRY AND JOINERY


DOORS
45 mm thick overall semi solid flush door; 4 mm thick plywood decking
teak veneered, teak beading from both sides finished with 3 coats of
13.01 Nr.
varnish & 200mm door frame with Ironmongeries: Door size: 1000 x
2200mm

13.02 Same as above but with frost glass panel Nr.

13.03 same as above with aluminium louvers fixed at bottom Nr.

14 ARCHITECTURAL FINISHES
14.01 Non slip ceramic floor tiles (CERYPSA SPAIN) m2

14.02 Ditto for skirting 100mm high m


Vertified Porcelain merrazi polished tiles, Non slip Antistatic
14.03 m2
(40X40X1cm)
14.04 Ditto for 100mm high Skirting m

14.05 Epoxy flooring, Master top 1210 / equivalent (industrial type) m2

14.06 Epoxy resin coating - Master top 1110T / equivalent m2

14.07 Floor hardener and dust inhibitor m2

14.08 Heavy duty Vinyl flooring m2

14.09 Vinyl skirting 100mm ht. m

362490201.xlsx - Appendix - B Page: 32 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. 15mm
Description
thick cement and sand plaster to concrete and block work walls, Unit
14.1 including all angle beads, expanded metal lathe and the like, to receive m2
paint.
14.11 Glazed ceramic wall tiles m2

14.12 15mm thick cement and sand plaster to concrete soffits to receive paint m2

Aluminium false ceiling Size: 60 x 60 cm including adjustable suspension


14.13 m2
system fixed to concrete soffits / steel members ;
Gypsum ceiling 600x600mm including adjustable suspension system
14.14 m2
fixed to concrete soffits / steel members ;

14.15 Marble thresholds to full width of door frame m

External plaster 15mm -20mm thick cement and sand plaster to concrete
14.16 m2
and block work walls to receive paint.

Prepare, primer, putty and apply one undercoat and 2 top coats of
14.17 m2
washable plastic emulsion paint to plastered walls / ceiling

Prepare, putty as required primer and two coats of Oil paint to plastered
14.18 m2
walls & ceiling
Prepare, primer, putty and apply polyurethane epoxy (texotile) paint over
14.19 m2
plastered wall / ceiling
Prepare, primer, putty and apply acrylic epoxy paint over plastered wall /
14.2 m2
ceiling
14.21 Matt Emulsion Paint on internal concrete and blocks m2

14.22 Exterior stone paint finish over plastered & concrete wall / columns m2
PAVING AND SURFACING

14.23 Interlocking concrete tile paving 50mmthick including ground preparatio m2

14.24 Interlocking concrete tile paving 75mmthick including ground preparatio m2

14.25 Asphalt paving including leveling, compaction, 200mm subgrade, 150mm m2

200 x 300 chamfered precast concrete kerb stone with bedding, haunch
14.26 m
and paint
FENCING
Chain link fencing using PVC coated Post, wires, fence and barbed wires,
14.27 m
2.20m high
Chain link fencing using PVC coated Post, wires, fence and barbed wires,
14.28 m
3.00m high

Chain link fencing using concrete Post at every 3.00m, tie beam, wires,
14.29 m
fence and barbed wires, 2.20m high

362490201.xlsx - Appendix - B Page: 33 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description Unit


14.30 Removal of existing fence including making good m

14.31 Single personnel Access Gate 1.00m wide with post Nr.

14.32 Double Gate 8.0m wide with roller, post and accessories Nr

14.33 Installation of crash barriers Nr


15 ELECTRICAL ITEMS

SCHEDULE OF RATES FOR SUPPLY AND INSTALLATION OF


NECESSARY ITEMS AS AND WHEN REQUIRED; RATES SHALL BE
INCLUSIVE TO CATER OF ALL MATERIAL, WASTAGE,
TRANSPORTATION, LABOUR WITH SMALL TOOLS AND
EQUIPMENT, OVERHEAD & MARKUP, ETC.

15.1 Cable trays

15.101 Cable Tray 400mm, Hot Dip Gal., Max load =1.5kN meter

15.102 Cable Tray 200mm, Hot Dip Gal., Max load =3.0kN meter

15.103 Cable Tray 600mm, Hot Dip Gal., Max load =3.0kN meter

15.104 Wall Bracket 410mm, Hot Dip Gal., Max load =3.0kN each

15.105 Wall Bracket 510mm, Hot Dip Gal., Max load =3.0kN each

15.106 Wall Bracket 510mm, Hot Dip Gal., Max load =5.5kN each

15.107 Wall Bracket 710mm, Hot Dip Gal., Max load =5.5kN each

15.108 90 Deg. Bend for 200mm Cable Tray each

15.109 90 Deg. Bend for 400mm Cable Tray each

15.110 90 Deg. Bend for 600mm Cable Tray each

15.111 91 Deg. Bend for 600mm Cable Ladder each

15.2 Conductors

15.201 4C 150 sq.mm XLPE/SWA/PVC meter

15.202 4C 185 sq.mm XLPE/SWA/PVC meter

15.203 4C 50 sq.mm XLPE/SWA/PVC meter

15.204 4C 35 sq.mm XLPE/SWA/PVC meter

15.205 4C 25 sq.mm XLPE/SWA/PVC meter

15.206 4C 16 sq.mm XLPE/SWA/PVC meter

15.207 4C 10 sq.mm XLPE/SWA/PVC meter

15.208 4C 6 sq.mm XLPE/SWA/PVC meter

15.209 1C 120 sq.mm PVC (G/Y) meter

362490201.xlsx - Appendix - B Page: 34 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
15.210 1C 95 sq.mm PVC(G/Y) Unit
meter

15.211 1C 70 sq.mm PVC(G/Y) meter

15.212 1C 25 sq.mm PVC(G/Y) meter

15.213 1C 16 sq.mm PVC(G/Y) meter

15.214 1C 10 sq.mm PVC(G/Y) meter

15.215 1C 6 sq.mm PVC(G/Y) meter

15.216 1x1 pair - 1mm2 meter

15.217 1x2 pair - 1mm2 meter

15.218 1x3 pair - 1mm2 meter

15.219 1x4 pair - 1mm2 meter

15.220 1x8 pair - 1mm2 meter

15.221 7T x 1mm2, cable meter

15.222 10T x 1mm2, cable meter

15.223 Compression lugs for 1.5mm2 to 50mm2 cables each

15.223 Compression lugs for 51mm2 to 185mm2 cables each

15.3 Lighting controls and light fittings each

15.301 Lighting points internally each

15.302 Lighting points externally each

15.303 13 amp single socket outlet each

15.304 13 amp twin socket outlet each

15.305 13 amp single socket outlet (weather proof) each

15.306 16 amp SPN+E Industrial type switched socket outlet each

15.307 15 amp switched socket outlet each

15.308 32 amp 3 phase socket outlet (industrial type) each

15.309 32 amp single phase socket outlet (industrial type) each

15.310 32 amp TPN+E socket outlet with local isolator for Welding Equip. each

15.311 20 - amp. Double pole switch for water heater each

15.312 13 amp Spur outlet each

15.313 One way, one gang each

15.314 One way, two gang each

15.315 Two way, one gang each

15.316 Two way, three gang each

362490201.xlsx - Appendix - B Page: 35 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
15.317 Switch bank with phase barrier Unit
each

15.320 Normal Fluorescent lamps No

15.321 Normal fluorescent but connected to emergency No

15.322 Normal Fluorescent lamps recessed mounting No

15.323 Normal Fluorescent lamps recessed mounting to emergency No

15.324 Normal Fluorescent lamps recessed mounting to Central battery No

15.325 Wall mounted fluorescent lamp No

15.326 Wall mounted metal halide high bay lamp No

15.327 Recessed shower lighting No

15.328 1 Way switch gang No

15.329 2 Way switch gang No

15.330 Inside plant light circuit with contactor No

15.331 Light Wiring points No

15.332 400W metal halide Flood light fixture with IP-65 No

15.333 70W metal Halide high bay light fixture with IP-65 No

15.334 Compact fluorescent lamps No

15.335 External light circuit photocell (Timer) No

15.336 Light wiring points No

15.4 DISTRIBUTION BOARDS

15.401 SMDB each

15.402 Welding DB each

15.403 LDB each

15.404 DB-UPS-01 each

15.405 PDB each

15.5 PIPES / SLEEVES

15.501 uPVC class 16 drainage pipe 100mm dia with fittings m

15.502 uPVC class 16 drainage pipe 150mm dia with fittings m

15.503 uPVC class 16 drainage pipe 200mm dia with fittings m

15.504 Build drainage manhole complete, 1.50m deep with DI cover Nr.

15.505 Build drainage manhole complete, > 1.50m deep with DI cover Nr.

15.506 GI sleeve with puddle flange, 600mm long, 200 mm dia. Nr.

362490201.xlsx - Appendix - B Page: 36 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
15.507 1" PVC conduit / sleeve pipe and accessories Unit
m

15.508 2" PVC conduit / sleeve pipe and accessories m

15.509 3" PVC conduit / sleeve pipe and accessories m

15.510 4" PVC conduit / sleeve pipe and accessories m

15.511 6" PVC conduit / sleeve pipe and accessories m

15.512 8" PVC conduit / sleeve pipe and accessories m

15.513 E/O concrete encasement where necessary complete m3

16 FIRE ALARM & FIRE FIGHTING SYSTEM

SCHEDULE OF RATES FOR SUPPLY AND INSTALLATION OF


NECESSARY ITEMS AS AND WHEN REQUIRED; RATES SHALL BE
INCLUSIVE TO CATER OF ALL MATERIAL, WASTAGE,
TRANSPORTATION, LABOUR WITH SMALL TOOLS AND
EQUIPMENT, OVERHEAD & MARKUP, ETC.

16.1 Threaded Pipes & Fittings

16.101 1" dia. - Threaded type pipe and fittings meter

16.102 11/4" dia.- Threaded type pipe and fittings meter

16.103 11/2" Dia - Threaded type pipe and fittings meter

16.104 2" dia. - Threaded type pipe and fittings meter

16.2 Grooved type Pipes & fittings

16.201 21/2" dia. Victaulic Grooved type pipe meter

16.202 21/2" dia. Victaulic Grooved Coupling each

16.203 Elbows- 2 1/2" Dia each

16.204 Tee - 2 1/2" Dia each

16.205 3" Dia.. Victaulic Grooved type pipe meter

16.206 3" Dia.. Victaulic Grooved Coupling each

16.207 Elbows- 3" Dia each

16.208 Tee - 3" Dia each

16.209 4" Dia.. Victaulic Grooved type pipe meter

16.21 4" dia. Victaulic Grooved Coupling each

16.211 6" dia. Victaulic Grooved type pipe meter

16.212 6" dia. Victaulic Grooved Coupling each

16.213 Elbows- 6" Dia each

362490201.xlsx - Appendix - B Page: 37 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
16.214 8" dia. Victaulic Grooved type pipe Unit
meter

16.215 8" dia. Victaulic Grooved Coupling each

16.216 Concentric Reducer -8" x 1 1/2" each

16.3 Valves

16.301 25mm dia Ball valve with all accessories each

16.302 50mm dia Ball valve with all accessories each

16.303 50mm dia Gate valve with all accessories each

16.304 100mm dia -OS & Y gate valve-Supervised Type with all accessories each

16.305 150mm dia OS & Y Supervised type gate valve with all accessories each

16.306 50mm dia Non return valve with all accessories each

16.307 100mm dia Non return valve with all accessories each

16.308 200mm dia Non return valve with all accessories each

16.4 Others

16.401 Pendant Sprinklers - Std Orifice - 79 deg c each

16.402 Upright Sprinklers - Std Orifice - 79 deg c each

16.403 Sidewall Sprinklers - Extended Coverage each

16.404 Open Type Sprinklers each

16.405 Pilot Sprinklers each

16.406 Alarm check Valve- 100mm dia with all accessories each

16.407 Deluge Valve- 100mm dia with all accessories each

16.408 Deluge Valve- 80mm dia with all accessories each

16.409 Alarm check Valve- 80mm dia with all accessories each

16.410 Flexible coupling (Expansion Bellows)- 100mm dia with all accessories each

16.411 Flexible coupling (Expansion Bellows)- 50mm dia with all accessories each

16.412 Extinguisher - CO2 10lbs each

16.413 Extinguisher - CO2 5lbs each

16.414 Extinguisher - DCP 6 Kgs each

16.415 Extinguisher - Water 10ltr. each

16.416 Extinguisher - foam 6ltr. each

16.417 Extinguisher - foam 35 gal trolley mounted each

16.418 Extinguisher - CO2, 50 lbs trolley mounted each

362490201.xlsx - Appendix - B Page: 38 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
16.419 Double cabinet Unit
each

16.420 1" Dia - 30 mtr Long fire Hose reel each

16.421 21/2" Dia Landing Valve each

16.422 Pressure Regulating valve - 21/2" Dia each

16.423 Pressure Regulating valve - 1" Dia each

16.424 21/2" Dia Fire hose - 30 mtr long each

16.425 1 1/2" Dia Fire Hose Rack x 30 mtr long each

16.426 Double cabinet -weatherproof type each

16.427 Zone control valve -Supervised type -2 1/2" Dia each

16.428 Zone control valve -Supervised type -3 " Dia each

16.429 Zone control valve -Supervised type -4" Dia each

16.430 Zone control valve -Supervised type -6 " Dia each

16.431 Flow Switch -4 " Dia each

16.432 Flow Switch -6 " Dia each

16.433 100 mm dia 'Y' Type strainers each

16.434 150 mm dia 'Y' Type strainers each

16.5 Fire Alarm System

16.501 Ionization Smoke Detectors each

16.502 Optical/Photoelectric Smoke Detectors each

16.503 Heat Detector each

16.504 Duct Smoke Detector each

16.505 Manual Pull Station each

16.506 Alarm Bell -weather proof each

16.507 Fire Horn/Strobe each

16.508 Fire Horn/Strobe-weather proof each

16.509 Break Glass Unit -Weather Proof each

16.510 Monitor Module each

16.511 Isolator each

16.512 Interface Unit each

16.513 Control Module each

16.514 Input Module each

16.515 Fire Alarm Panel each

362490201.xlsx - Appendix - B Page: 39 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
16.516 Mimic Panel Unit
each

16.517 Fire Alarm Repeater Panel each

16.518 2c x 1.5 sq.mm Cable meter

16.519 3c x 1.5 sq.mm Cable meter

16.520 Flasher-Refrigerant Leak each

16.521 Sounder-Refrigerant Leak - weather proof each

16.522 Auto Dialer each

16.6 Clean Agent Fire suppression System

16.601 180 deg Spray Nozzle -25 mm dia each

16.602 180 deg Spray Nozzle -50 mm dia each

16.603 360 deg Spray Nozzle - 15 mm dia each

16.604 360 deg Spray Nozzle -50 mm dia each

16.605 Single Hazard Panel each

16.606 Ionization Smoke Detectors each

16.607 Optical/Photoelectric Smoke Detectors each

16.608 Abort Switch each

16.609 Sounder/Alarm Bell each

16.610 Sounder/Alarm Bell - Weatherproof each

16.611 Fire Horn / Strobe each

16.612 Fire Horn / Strobe - Weatherproof each

16.613 Manual Release Station each

16.614 Gas Cylinder with all accessories - Type 1-650 LBS without gas each

16.615 Gas Cylinder with all accessories - Type 2-375 LBS without gas each

16.616 Gas Cylinder with all accessories - Type 3-215 LBS without gas each

16.617 Gas Cylinder with all accessories - Type 4-125 LBS without gas each

16.618 Clean Agent Gas (FM200) Kg

16.619 Liquid Level Indicator each

16.620 Check Valve - 150 mm each

16.621 Check Valve - 100 mm each

16.622 Check Valve - 50 mm each

16.7 Pipes & fittings -Clean Agent Suppression System

16.701 1" dia. - Threaded type pipe and fittings meter

362490201.xlsx - Appendix - B Page: 40 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
16.702 11/4" dia.- Threaded type pipe and fittings Unit
meter

16.703 11/2" Dia - Threaded type pipe and fittings meter

16.704 2" dia. - Threaded type pipe and fittings meter

16.705 2 1/2" dia. - Pipe meter

16.706 3" dia. - Pipe meter

16.707 4" dia. - Pipe meter

16.708 6" dia. - Pipe meter


17 HVAC SYSTEM

SCHEDULE OF RATES FOR SUPPLY AND INSTALLATION OF NECESSARY


ITEMS AS AND WHEN REQUIRED; RATES SHALL BE INCLUSIVE TO CATER
OF ALL MATERIAL, WASTAGE, TRANSPORTATION, LABOUR WITH SMALL
TOOLS AND EQUIPMENT, OVERHEAD & MARKUP, ETC.

17.1 HVAC Equipments

17.101 AHU-01, BASEMENT FLOOR - PUMP HALL each

17.102 AHU-02, BASEMENT FLOOR - PUMP HALL each

17.103 AHU-03, BASEMENT FLOOR - VFD ROOM each

17.104 AHU-04, MEZZ. FLOOR - TRANSFORMER ROOM each

17.105 AHU-05, MEZZ. FLOOR - TRANSFORMER ROOM each

17.106 AHU-06, MEZZ. FLOOR - SWITCH GEAR ROOM each

17.107 AHU-07, MEZZ. FLOOR - SWITCH GEAR ROOM each

17.108 AHU-08, MEZZ. FLOOR SOFT STARTER each

17.109 AHU-09, MEZZ. FLOOR CHILLER HALL each

17.110 AHU-10, AHU WITH HEAT RECOVERY each

17.111 AHU-11, MEZZ. FLOOR PUMP HALL each

17.112 AHU-12, MEZZ. FLOOR PUMP HALL each

17.113 AHU-13, MEZZ. FLOOR LV MCC ROOM each

17.114 AHU-14, GROUND FLOOR. GENERATOR BUILDING each

17.115 AHU-15, SECOND FLOOR OFFICES each

17.116 AHU-16, SECOND FLOOR OFFICES each

17.117 AHU-17, SECOND FLOOR OFFICES each

17.118 AHU-18, SECOND FLOOR OFFICES each

17.119 EF - 01 TOILETS each

362490201.xlsx - Appendix - B Page: 41 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
17.120 EF - 02 TOILETS Unit
each

17.121 EF - 03 PANTRY each

17.122 EF - 04 TOILETS each

17.123 EF - 05 GENERATOR ROOM each

17.124 EF - 06 CYLINDER ROOM each

17.125 EF - 07 PANTRIES each

17.126 EF - 08 PANTRIES each

17.127 FCU -01 LOBBIES each

17.128 FCU -02 ELE.ROOM, TELECOM ROOM, FIRE PUMP ROOM, AHU ROOM each

17.129 FCU -03 BATTERY ROOM each

17.130 INLINE EXHAUST FAN- BATTERY ROOM each

17.131 INLINE EXHAUST FAN- PANTRY/TOILET/URINAL each

17.132 PRESSURISATION FAN-STAIR CASE- TERRACE each

17.133 PRESSURISATION FAN-STAIR CASE - ROOF each

17.134 WALL MOUNTED FAN - RMU ROOM each

Piping - Contractor Should provide separate list of unit prices for the,
Piping, insulation and cladding flanges, Joints, Bends, support materials
17.135
used for this project (But not limited to the follows). The price shall be
included with Labor and complete material for the each Item Unit.

17.136 1" dia. - Pipe with fittings meter

17.137 11/4" dia.- Pipe with fittings meter

17.138 11/2" Dia - Pipe with fittings meter

17.139 2" dia. - Pipe with fittings meter

17.140 2 1/2" dia. - Pipe meter

17.141 Elbows- 2 1/2" Dia each

17.142 Tee - 2 1/2" Dia each

17.143 3" dia. - Pipe meter

17.144 Elbows- 3" Dia each

17.145 Tee - 3" Dia each

17.146 4" dia. - Pipe meter

17.147 Elbows- 4" Dia each

17.148 Tee - 4" Dia each

362490201.xlsx - Appendix - B Page: 42 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
17.149 6" dia. - Pipe Unit
meter

17.150 Elbows- 6" Dia each

17.151 Tee - 6" Dia each

17.152 Grills 600mm X 200mm each

17.153 Grills 600mm X 300mm each

17.154 Grills 1800mm X 300mm each

17.155 Diffuser 200mm X 200mm each

17.156 Diffuser 600mm X 300mm each

17.157 Diffuser 1800mm X 300mm each

17.158 Registers 600mm X 300mm each

17.159 VCD 150mm X 150mm each

17.160 VCD 250mm X 200mm each

17.161 VCD 300mm X 200mm each

17.162 VCD 800mm X 650mm each

17.163 VCD 1000mm X 550mm each

17.164 VCD 2500mm X 2000mm each

17.165 VCD 4500mm X 4000mm each

17.166 Fire damper 150 mm X 150 mm each

17.167 Fire damper 250 mm X 200 mm each

17.168 Fire damper 300 mm X 200 mm each

17.169 Fire damper 450 mm X 450 mm each

17.170 Fire damper 700mm X 500mm each

17.171 Fire damper 900mm X 650mm each

17.172 Fire damper 1000mm X 550mm each

17.173 Fire damper 1200mm X 1000mm each

17.174 Motorized damper 200 mm X 200 mm each

17.175 Motorized damper 450 mm X 350 mm each

17.176 Motorized damper 800mm X 550mm each

17.177 Motorized damper 1000mm X 600mm each

17.178 Temperature Gauge each

17.179 Pressure Gauge each

17.180 Differential Pressure Gauge each

362490201.xlsx - Appendix - B Page: 43 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
17.181 1" Double Regulating Valve Unit
each

17.182 2" Double Regulating Valve each

17.183 2 1/2" Double Regulating Valve each

17.184 3" Double Regulating Valve each

17.185 4" Double Regulating Valve each

17.186 1" Flexible coupling each

17.187 2" Flexible coupling each

17.188 2-1/2" Flexible coupling each

17.189 3" Flexible coupling each

17.190 4" Flexible coupling each

17.191 1" Ball Valve each

17.192 2" Ball Valve each

17.193 2-1/2" Butterfly Valve each

17.194 4" Butterfly Valve each

17.195 6" Butterfly Valve each


Ducting - Contractor should provide separate list of unit prices for the,
Ducting, Insulation, Cladding, flanges, Joints, support materials, Sound
17.196 attenuators & acoustic duct lining used for this project-(But not limited to
the following). The price shall be included with Labor and complete
material for the each Item Unit.
17.197 Duct Work sq.ft

17.198 Duct Work kg

17.199 Insulation sq. mtr

17.200 Acoustic Lining sq. mtr

17.201 Aluminium cladding sq. mtr

17.2 HVAC Controls.

17.201 1" Modulating Control Valve With Actuator each

17.202 2" Modulating Control Valve With Actuator each

17.203 2-1/2" Modulating Control Valve With Actuator each

17.204 4" Modulating Control Valve With Actuator each

17.205 6" Modulating Control Valve With Actuator each

17.206 Modulating damper actuator (4NM) each

17.207 Modulating damper actuator (16NM) each

17.208 Modulating damper actuator (32NM) each

362490201.xlsx - Appendix - B Page: 44 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
17.209 Open/Close Spring Return Damper Actuator (16NM) Unit
each

17.210 Open/Close Spring Return Damper Actuator (64NM) each

17.211 Duct Temperature Transmitter each

17.212 Space Temperature Transmitter each

17.213 Remote temperature reset unit each

17.214 Electronic digital controller each

17.215 Power/Control Panel for AHU each

Cabling - Contractor Should provide separate list of unit prices for the
17.216 Cabling, Conduits/Trays. The price shall be included with Labor and
complete material for each Item Unit.

18 Drainage System
SCHEDULE OF RATES FOR SUPPLY AND INSTALLATION OF NECESSARY
ITEMS AS AND WHEN REQUIRED; RATES SHALL BE INCLUSIVE TO CATER
OF ALL MATERIAL, WASTAGE, TRANSPORTATION, LABOUR WITH SMALL
TOOLS AND EQUIPMENT, OVERHEAD & MARKUP, ETC.

18.101 Floor Drain each

18.102 Roof Drain each

18.103 Roof Drain with side outlet each

18.104 Water Closet each

18.105 Wash Hand Basin each

18.106 Kitchen sink each

18.107 Janitors sink each

18.108 Electric Hand Drier each

18.109 Foul Water manhole each

18.110 Storm Water Manhole each

18.111 Pressure Reducing Manhole each

18.112 Break Chamber each

18.113 Vent Cowl each

18.114 Gully Trap each

18.115 Catch Basin each

18.116 Drainage system Pipe - 3" dia - Above ground meter

18.117 3" dia Elbow each

18.118 3" dia "Y" Branch each

362490201.xlsx - Appendix - B Page: 45 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
18.119 3" dia Tee Branch Unit
each

18.120 Drainage system Pipe - 4" dia - Above ground meter

18.121 4" dia Elbow each

18.122 4" dia "Y" Branch each

18.123 4" dia Tee Branch each

18.124 Drainage system Pipe - 6" dia - Above ground meter

18.125 6" dia Elbow each

18.126 6" dia "Y" Branch each

18.127 6" dia Tee Branch each

18.128 Drainage system Pipe - 8" dia - Above ground meter

18.129 8" dia Elbow each

18.130 8" dia "Y" Branch each

18.131 8" dia Tee Branch each

18.132 Drainage system Pipe - 6" dia - Under ground meter

18.133 6" dia Elbow each

18.134 6" dia "Y" Branch each

18.135 6" dia Tee Branch each

18.136 Drainage system Pipe - 8" dia - Under ground meter

18.137 8" dia Elbow each

18.138 8" dia "Y" Branch each

18.139 8" dia Tee Branch each

19 Plumbing - Water Supply Services

SCHEDULE OF RATES FOR SUPPLY AND INSTALLATION OF NECESSARY


ITEMS AS AND WHEN REQUIRED; RATES SHALL BE INCLUSIVE TO CATER
OF ALL MATERIAL, WASTAGE, TRANSPORTATION, LABOUR WITH SMALL
TOOLS AND EQUIPMENT, OVERHEAD & MARKUP, ETC.

19.101 Hose Bib each

19.102 Pressure Reducing valve - 2" Dia each

19.103 Non Return Valve - 2" dia each

19.104 Isolating Valve - 2" dia each

19.105 Float Valve-1" Dia each

19.106 Float Valve-4" Dia each

362490201.xlsx - Appendix - B Page: 46 / 111


TENDER FORM -- APPENDIX "B" King Khaled Internation
C-2001.
UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF LUMP
SUM WORK

Sl.No. Description
19.107 Air Release Valve Unit
each

19.108 Water meter each

19.109 Strainer each

19.110 Water Service System pipe - 1" Dia with all fittings meter

19.111 Water Service System pipe - 1 1/4" Dia with all fittings meter

19.112 Water Service System pipe - 1 1/2" Dia with all fittings meter

19.113 Water Service System pipe - 2" Dia with all fittings meter

19.114 Water Service System pipe - 4" Dia with - Underground meter

19.115 4" dia Elbow each

19.116 4" dia Tee each

19.117 Water Service System pipe - 6" Dia with - Underground meter

19.118 6" dia Elbow each

19.119 6" dia Tee each

19.120 Water Service System pipe - 8" Dia with - Underground meter

19.121 8" dia Elbow each

19.122 8" dia Tee each

19.123 Emergency Shower Station each

19.124 Eye Wash each

362490201.xlsx - Appendix - B Page: 47 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 48 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 49 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 50 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 51 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 52 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 53 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 54 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 55 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 56 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 57 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 58 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 59 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 60 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 61 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 62 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 63 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 64 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 65 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 66 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 67 / 111


King Khaled International Airport - KSA
C-2001.3

Unit rate in SAR.


(Supply, Install, OH & Remarks
Profit)

362490201.xlsx - Appendix - B Page: 68 / 111


King Khaled International Airport -
TENDER FORM -- APPENDIX "B"
KSA, Mega plant A (LC 1)

UNIT PRICES FOR EVALUATION OF CHANGES TO SCOPE OF


LUMP SUM WORK C-2001.3

Sl.No. Description Unit Unit rate in SAR. Remarks


LABOUR
1.01 Charge hand hr.

1.02 Ganger hr.

1.03 Mason hr.


1.04 Carpenter hr.

1.05 Steel Fixer hr.


1.06 Painter hr.

1.07 Pipe Fitter hr.

1.08 Fabricator hr.


1.09 Welder hr.
1.10 Steel Erectors hr.

1.11 Electrician hr.

1.12 Plumber hr.

1.13 Scaffolders hr.

1.14 Skilled Helper hr.


1.15 Unskilled Helper hr.

1.16 Labour hr.

1.17 Watch Man hr.


1.18 Light Duty Driver hr.

1.19 Office Attendant hr.

1.20 Secretary hr.

1.21 Store Keeper hr.

PLANT AND EQUIPMENT

2.01 Crane 20T hr.

2.02 Crane 30T hr.

2.03 Mobile crane less than 10 Tonnes hr.


2.04 Hiab / Wheel mounted crane hr.

2.05 Excavator (1.0m3 bucket capacity) hr.


2.06 Wheel loader / shovel (1.0m3 bucket capacity) hr.

2.07 JCB hr.

2.08 Bobcat hr.


2.09 Forklift hr.

2.10 Water tanker, with 3000gal water good for construction hr.

2.11 3T pickup hr.


2.12 5T pickup hr.

2.13 Van or utility pickup, max 1.50T capacity hr.


2.14 20m3 truck hr.
2.15 40m3 truck hr.

2.16 Open truck 40 ft hr.


2.17 Portable compressor, 4.6 m3 incl. Tools & hoses hr.
2.18 Air compressor 6m3/min incl. 2 hoses and tools hr.

2.19 Dumpers 1.0m3 capacity hr.

2.20 Concrete vibrator/poker (petrol operated) hr.


2.21 Welding machine hr.

2.22 Electrical operated jack hammer hr.


2.23 Small power tools

362490201.xlsx - Day Works Page: 69 / 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.

PRICING PREAMBLES

GENERALLY

1 The Bills of Quantities herein, including all notes and instructions, form an integral part of t
Documents. However, the descriptions contained in the Bills of Quantities for each item are not
complete. The Contractor is referred to the Conditions of Contract and other Documents, Specifi
Drawings as well as relevant Standards and Codes of Practice for further information as no claim
will be considered on account of the Contractor's failure so to do.

2 The Contractor is cautioned to familiarize himself with the full content of other Contract Documen
the Drawings and Specification (or any other information that can be reasonably inferred from a
and all obligations contained in the documents shall be included in the tender prices, even if sp
relating to them are not listed in this Bills of Quantities.

3
The Contractor's unit rates are to be the fully inclusive value of the work described and mus
related work, accessory or consumable materials, incidental labour, supervision, administr
construction equipment, overhead and profit and all costs and expenses which may be required in
completion of the work described together with all costs and expenses in complying with all g
liabilities and obligations set forth or implied in the Drawings, Specification and Conditions of
rates and amounts shall be gross and shall include for main contractor's overheads, profit and
special attendances.

4 Drawings, Specifications and Bills of Quantities and all other Contract documents are compleme
any item is included in any of them, it shall be deemed included in all.

The provisions of General Conditions/preliminaries of the Specification and the Conditions of C


prevail over those of any other documents forming part of the contract. Subject to the foregoin
item be included or implied in any of the Contract Documents, then it shall be considered as nece
proper execution of the Works and deemed to be included in the Contract Sum. Should an item
the proper execution of the works not be included or implied in any of the Contract Documents, th
shall be considered as variations to the Contract requiring approval of the Employer.

6 The Contractor's bid for the entire work shall provide for supervision of any or all trades that is not
be performed with his own forces. No extra compensation for services as a General Contractor wil

7
The lump sum amount entered by the Contractor in this Bills of Quantities shall constitute the ent
compensation for the work under this Contract in accordance with the Conditions of Contract. The
not be remeasured and will be subject to adjustment only as a result of changes in the scope of w
changes in drawings and/or specifications.

8 The Contractor shall check the quantities contained within the Bills of Quantities and confirms his
thereof by submission of this Tender. Any discrepancy between billed quantities and actual quan
shall not be subject to remeasurement on completion.

362490201.xlsx - Pricing preambles Page 70/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.
9 Any error in description or in quantity or in omission of items from the Bills of Quantities shall no
Contract nor release the Contractor from the execution of the whole or any part of the Work
therein according to the Drawings and Specifications or from any of his obligations or liabilitie
Contract. Any error in or omissions from the Bills of Quantities shall not be corrected by a variati
the Engineer.

10 The Contractor shall request written clarification from the Engineer of any point he consid
discrepancy or ambiguity and append the value (if any) to the Bills of Quantities as a Tender adjust

11 The Bills of Quantities shall be used for evaluating progress payments due to the Contractor.

12 The Contractor is required to check the numbers of the pages of the Bills of Quantities and sh
found missing or in duplicate or the figures or writing indistinct, the Contractor must notify the
once and have the matter rectified before the tender is submitted. No liability whatsoever will be
in respect of any claim for errors in the Contractor's tender resulting from failures to comp
foregoing.

13 The Contractor is required to provide with his tender two complete sets of the Bills of Qua
quantified and priced out in waterproof ink with summation sheets properly completed.

Provision has been made for the total of each page to be collected at the end of each bill of
14 Quantities.

15 The Contractor should allow against the items or in the prices for everything contained in th
Quantities which has a monetary value.

16
A rate shall be entered by the Contractor against each item in these Bills of Quantities. Items a
no price or rate is entered will be considered as covered by other prices or rates in the Bills of
Irrespective of whether the Contractor includes a price or rate against an item he shall insert
quantity.

17 Lump sums shall not be given where unit rates are applicable.

18
Unit rates may be used reciprocally in the settlement of accounts unless conflict between them
Contractor is, therefore, to ensure that identical items occurring in separate bills are not priced
rates unless this is his deliberate intention.

19
This Bills of Quantities shall be measured generally in accordance with the Rules of POM (I) (as
defined). In any case in the Bills of Quantities where the method differs then the method expres
accepted and measured in accordance therewith. Notwithstanding the above, the following pricin
are included as an amplification or clarification of the method of measurement required.

20 Items in the Preambles Section of these Bills of Quantities are deemed to qualify and to form p
description of measured work to which they refer including composite descriptions.

21 Amendment shall not be made to the Bills of Quantities without the authority, in writing, of the Eng

362490201.xlsx - Pricing preambles Page 71/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.
22
The Contractor shall not use these Bills of Quantities as a construction programme or for the
ordering materials or arranging sub-contracts. The references for these activities shall be th
specification and instruction issued by the Engineer.

FORMAT OF DESCRIPTIONS

In addition to common abbreviations the following have been adopted:

POM(I) - Principles of Measurement (International) for works of construction


1979 and published by the Royal Institution of Chartered Surveyors, Lo

m - Metre

m2 - Square Metre

m3 - Cubic Metre

No - Number

Kg - Kilogram

KN - Kilo Newton

DEFINITIONS

A "Prices also to include"; items under this heading fall into two categories:

(i) Those which are deemed to be included in descriptions and, therefore, in prices.

(ii) Those for which the Contractor shall allow for in his prices.

B "Falls", "Slopes", "Weathered": inclined from the horizontal in one plane.

C "Cross Falls", "Cross Slopes", "Cross Weathered" : inclination from the horizontal in more than one p

Prices also to Include


D Rates shall be comprehensive and include but not limited to the following matters:

(i) All obligations imposed by the Contract.

(ii) All costs in connection with Supervision, Co-ordination and Quality Control of the Work.

(iii) Complying in every respect with the requirements of the specifications and drawings.

(iv) Labour for fixing and all associated costs.

(v) Materials and goods and all associated costs.

(vi) Fitting and/or fixing materials and goods in position : hoisting to any height.

362490201.xlsx - Pricing preambles Page 72/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.

(vii) Use of scaffolding, plant, equipment and tools.

(viii) Any additional labours usually associated with measured items.

(ix) All site and head office overheads and Profit

(x) Provision of samples and mock ups as required by the specification.

(xi) Preparation of shop drawings as required by the specification.

(xii) Provision of spares as required by the specification.

E All measurements are net and the rates shall include for all laps, waste, working space and trade
allowances.

F The pricing of materials shall take account of the following:

(i) Pricing Preambles and Specifications shall apply reciprocally between sections of the w
otherwise described.
(ii) Materials shall be of the quality specified unless otherwise directed by the Engineer.
(iii) All materials shall be transported, handled, stored and fixed in accordance with the printed
or recommendations of their manufacture or suppliers.

(iv) Protection of completed work, all casings and temporary coverings and making good and c
upon completion.

A Building paper, damp proof membrane, quilts and all non-rigid sheet materials shall include cuttin
holes and notching and the extra labour of turning up at edges and the like.

B Ducts shall include draw wires.

C Holes, mortises, pockets, grooves, chases and the like and items described as "built in" and "c
include making good in its fullest sense and through, around, into, over and up to the items concer

D Items described as "cut" shall include general making good similarly.

E Where the word "allow" is used, the cost of the items shall be the responsibility of the Contractor.

F The amounts set against any items of profit shall include for all costs in connection with letters of
charges, interest charges and insurance after the materials come under the control of the Contract

G The Contractor shall leave the whole of the works ready for immediate occupation to the satisfa
Engineer including but not limited to the following:

(i) Cleaning and touching up the buildings both inside and out, leaving all surfaces fre
blemishes or splashes.

362490201.xlsx - Pricing preambles Page 73/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.
(ii) Easing, oiling and adjusting and making good of finishes to all fittings, doors, windows,
and the like.

(iii) Cleaning and polishing all glass, marble, ceramics, anodized aluminium and sanitary wa
the removal of all protective coverings, paint splashes and the like.

(iv) Replacement of all or any chipped, cracked or broken items mentioned in Item (iii) above.

(v) Balancing of air conditioning installations where applicable.

(vi) Removal of rubbish, debris or excess spoil from the site area and raking over and cleanin
parts of the site area.

Fix Only
H The expression "fix only" used in these Bills of Quantities means that the contractor shall provide t
(i) Fixing as defined in Clause GP7.2 of POM (I).

(ii) All requirements of Pricing Preambles page PM/3 Clauses D and F above

(iii) Supplying full size templates.

(iv) Giving and marking dimensions and taking responsibility for their accuracy.

(v) Getting in, protecting, handling, distribution and placing in position.

(vi) Assembling as required.

(vii) Casing up and protection, including clearing away protection on completion of the works.

(viii) Full cost of replacement of any items which are damaged, broken, lost or stolen after the ac
the items from the supplier or client and until handling over the complete works.

(ix) Other necessary and usual facilities and documentation.

Prices also to Include (Cont'd)

Supply Only

A The expression "supply only" used in these Bills of Quantities means that the Contractor is to
everything as defined in Clause GP4.1 of POM (I) in connection with such items except fixing in pos

Sub-Contractors

B Any sub-contractors which the Contractor proposes to use for the works are subject to the app
Engineer and Employer.

C The Contractor should ascertain from sub-contractors and suppliers before the work is put in han
of positions in which chases, holes, mortises, and the like will be required to be formed or left.
the extra costs of cutting away
362490201.xlsx - Pricing preambles Page 74/ 111
King Khaled International Airport

PRICING PREAMBLES

ITEM The Contractor should ascertain from sub-contractors and suppliers before the work is put in han
DESCRIPTION
REF. of positions in which chases, holes, mortises, and the like will be required to be formed or left.
the extra costs of cutting away

D Any sub-contractor who has not been approved by the Engineer and Employer shall not be used in
with the carrying out of the Works.

E The Contractor shall allow for any additional costs incurred due to sub-contractors working diff
from and extended hours to those worked by the Contractor.

F The word "attendance" means the following:

Attendances to be provided by the Main Contractor

G The Main Contractor shall be responsible for providing, including but not limited to, the following at

(i) Use of Main Contractors administrative arrangements.

(ii) Use of Constructional Paint.

(iii) Use of Contractor's Mess Room, Sanitary and Welfare Facilities.

(iv) Co-ordination and scheduling of all works related to each sub-contract.

(v) Use of Standing Scaffolding.

(vi) Use of Temporary Works including water and electricity.

(vii) Supplying full size setting out templates.

(viii) Giving and marking dimensions and taking responsibility for their accuracy.

(ix) Space for Sub-Contractors Offices and Stores.

(x) Providing working space.

(xi) Offloading Sub-Contractors materials and placing in Stores.

(xii) Clearing away rubbish.


Other necessary and usual facilities, documentation, general intertrades attendances,
(xiii) assistance.

Sub-Contractors (Cont'd)

A Attendance to be provided by the Sub-Contractor shall include but not limited to the following

(i) All special scaffolding required by him in the execution of his works.

(ii) Taking from stores, distributing, hoisting and placing in position, all items of plant, equ
materials required by him in the execution of his works.
362490201.xlsx - Pricing preambles Page 75/ 111
King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF. Taking from stores, distributing, hoisting and placing in position, all items of plant, equ
materials required by him in the execution of his works.

(iii) All labour, plant, etc., (other than included in Attendances to be provided by Main Contracto

(iv) Site offices and stores required by him for the execution of his works.

(v) Obtaining security passes for access of work people to the Site.

SECTION ; SITEWORK

EARTHWORKS

Method of Measurement

A The method of measurement and remeasurement will be entirely at the discretion of the E
generally will be as follows:
Where there is no reduced level excavation, other excavations will be measured from na
(i) level.

(ii) In instance where there is excavation to reduce levels, other excavations will be measur
reduced level.

B Should the Contractor be able to use any excavated material arising from the works as general fi
shall be measured as material backfilled in making up levels with a deduction of items for fi
material removed from site.

Prices

C In addition to the provisions of POM (I) Section B8 rates for excavation shall include, but not lim
following:
Excavating by whatever means are necessary including hand excavation in any kind
(i) including rock.

(ii) Over break including filling with mass concrete to the levels required by the Engineer.

(iii) Forming temporary spoil heaps where required and multiple handling.

(iv) Working space

(v) Trimming or grading ground to produce level surfaces or surfaces to falls or slopes.

(vi) Ramming and compacting sides and bottoms of excavations.

SECTION : CONCRETE WORK

Prices
A
The Contractor should ascertain from the Engineer the total number of locations of items to be fo
cast into in-situ and precast concrete including those which are not specifically shown on the dr
cutting away of concrete shall be carried out without the approval of the Engineer. All remedial w
carried out at the Contractor's expense.
362490201.xlsx - Pricing preambles Page 76/ 111
King Khaled International Airport

PRICING PREAMBLES

ITEM
The Contractor should ascertain from the Engineer the total number of locations of items to be fo
DESCRIPTION
cast into in-situ and precast concrete including those which are not specifically shown on the dr
REF.
cutting away of concrete shall be carried out without the approval of the Engineer. All remedial w
carried out at the Contractor's expense.

B The rates for all concrete work shall include, but not limited, for the following:

(i) Concrete testing and testing costs.

(ii) All considerations arising from the specification.

(iii) Mixing, hoisting and placing and compacting on the surfaces of any material or on f
whatever means necessary.

(iv) Pouring in hot weather conditions in accordance with the Specification.

(v) Forming any construction joints.

(vi) Shuttering to upper surfaces not exceeding 15 degrees from horizontal.

(vii) Curing and protecting concrete surfaces from harmful weather conditions.

(viii) Finishing to floor slabs as specified.

(ix) All costs in connection with the construction of "kickers".

(x) Grooves and mortices.

(xi) Placing and supporting water bars and the like.

C The rates for plain concrete foundations and concrete blinding shall include, but not limited, for the

(i) Any extra volume of concrete used in lieu of formwork.

(ii) Forming sloping surfaces where required.

D The rates for reinforced concrete shall include for working concrete around reinforcement.

E The rates for bar reinforcement shall include, but not limited, for the following:

(i) Hooks, laps and the like as required by the Specification.


(ii) Positioning and protecting starter bars.
(iii) Straightening (if required) cutting to length and bending reinforcement to required
complying with the Specification.
(iv) Fixing in any position including any necessary hoisting.
(v) All considerations arising from the specification.
(vi) Supporting in position during concreting: Provision of supports, steel binding wire and
approved/proprietary distance pieces.
Additional cutting and bonding in connection with holes, mortices, pockets, grooves, cha
(vii) like.

362490201.xlsx - Pricing preambles Page 77/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.
A The rates for fabric reinforcement shall include, but not limited, for the following:

(i) Straight, raking, curved and circular cutting and waste.

(ii) Bending to profiles.

(iii) Laps of one full square/rectangular module or as noted.

(iv) All considerations arising from the specification.

(v) Supporting in position during concreting : provision of supports, steel binding


approved/proprietary distance pieces.

(vi) Cutting, bending and notching around all obstructions.

B The rates for formwork or moulds shall include, but not limited, for the following:

(i) Small quantities.

(ii) All cutting and waste including raking curved or circular cutting and cutting and notching a
ducting and fittings.

(iii) Setting up, strutting and supporting at any height above the structure subject to any
imposed by the Engineer.

(iv) All considerations arising from the specification.

(v) Carefully coating with shutter oil ensuring that no shutter oil is applied to surfaces of reinfor

(vi) Easing, striking, removing and cleaning and preparing for re-use and removal when no long

(vii) The provision of all props, stays, struts, wedges and bolts.

(viii) Overlaps and passing at angles and labours at intersections.

(ix) Shortening struts or shapes and re-strutting or restoring where required.

(x) Rubbing down, filling and making good the surface of concrete after removal of shuttering.

(xi) Cutting or notching shutters or moulds to in-situ or precast concrete around projecting reinf

C The rates for wrought formwork to produce a special finish shall include, but not limited, for the fol

(i) Any necessary rubbing down or fillings allowed by the specification to produce the finish d
the specification.

Cutting out and re-casting unsatisfactory work or work not fulfilling the requirem
(ii) specification.

362490201.xlsx - Pricing preambles Page 78/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.
(iii) Carrying out remedial or any other work required by the Engineer as an alternative to
substandard work.

(iv) All considerations arising from the specification.

A The rates for precast concrete shall include, but not limited, for the following:

(i) The provision of moulds.

(ii) Forming a fair face in accordance with the specification to all exposed surfaces.

(iii) Hacking or forming keys to all other surfaces.

(iv) All considerations arising from the specification.


Hoisting to any height including the provision of lifting hooks or other devices appro
(v) Engineer.

(vi) Bedding jointing in mortar as specified.

(vii) All necessary temporary struts or supports.

(viii) Sills and copings etc. shall include for plain ends and mitred angles where necessary.

B Reinforcement to Masonry

The contents of this section equally apply to reinforcement included within the Masonry section o
Quantities, unless otherwise stated.

C Reinforcement and shuttering to insitu concrete works

Notwithstanding clauses C3 and C4 the reinforcement and shuttering to insitu concrete works shal
to be included in the relevant concrete item. All the requirements detailed above shall be deemed
the insitu concrete volume rates.

SECTION : MASONRY

Prices

A The rates for block walls shall include, but not limited, for the following:

(i) Block testing at a recognized laboratory, provision of certificates.

(ii) All considerations arising from the specification.

(iii) Building at any level or height off slabs or beams.

(iv) Small quantities and any extra labour in forming kerbs.

(v) Straight raking curved and circular rough or fair cutting.

362490201.xlsx - Pricing preambles Page 79/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.

(vi) Forming bull nose edges to quoins and the like.

(vii) All labour and materials necessary for closing wall cavities.

(viii) Plumbing at angles.

(ix) Cutting and bonding at angles, openings and intersections.

(x) Building into and/or against adjacent work.

(xi) Wedging and pinning up to soffits.

Special or concrete filled blocks at angles, openings and intersections, and soffits junction a
(xii) walls.

(xiii) Providing any means necessary to prevent concrete cast on hollow block work or over c
falling into voids or cavities (subject to the approval of the Engineer).

(xiv) All necessary keys for in-situ finishings.

(xv) Grouting up at back of walls built against other construction.

(xvi) All necessary cast in wall ties at junctions between block work and in-situ concrete.

(xvii) All horizontal expanded reinforcement to load bearing block work in accordance with the Sp
All necessary expansion joints, control joints and termination bars as required by t
(xviii) Documents.

(xix) Block wall anchorage (temporary and permanent).

B The rates for block walls shall include, but not limited, for the following additional labours:

(i) Cutting or forming chases or grooves for slabs, partitions, staircases, etc.

(ii) Cutting grooves for water bars, flashings and the like and making good and pointing in simi

(iii) Building in or cutting and pinning in and making good ends of lintels, brackets, timbers
holder bats and the like.

(iv) Building in or cutting for and making good around pipes, ducting, fittings and the like.

SECTION : METALWORK

Prices

A The rates for metal work shall include, but not limited, for the following:

362490201.xlsx - Pricing preambles Page 80/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.
(i) Allowance for rolling margin.

(ii) The weight of weld metal in welded constructions.

(iii) Members of any length.

(iv) Cutting to size and shape and joints in the running length.

(v) Notches, holes, slots, mitres, angles, ends and for all drilling and splay cut ends.

(vi) Grinding welds to a smooth finish, unless otherwise required.

(vii) Fixing with appropriate non-corroding countersunk screws including holes unless otherwise

(viii) Riveted and bolted work shall include rivets, bolts and holes.

(ix) Approved protection to cut ends or holes in galvanized work or other applied finish.

(x) All considerations arising from the specification.

(xi) Metal door frames shall include for assembling, fixing with clamps, filling with mortar
supports and removal of base ties.

(xii) Floor plates, duct coves and the like shall include narrow widths laying in position and f
slots and the like making good.

Definitions

B
"Welding" is deemed to be in accordance with the specification and for the material to which it is
Base plates, ends, caps, cleats, brackets, stiffeners, bolts, etc., have been included in the we
associated steelwork in which they occur.

SECTION : WOODWORK

Generally

A Sizes of sawn timber are basic.

B Sizes of milled (wrot) timbers are finished.

C Woodwork shall be deemed to be fixed with non-corroding nails unless otherwise described.

D Screwed woodwork shall be so described according to convention except that grooves, rebates
shall include for splayed grooves, rebates and the like.

E Special millings shall be described according to convention except that grooves, rebates, and t
include for splayed grooves, rebates and the like.

362490201.xlsx - Pricing preambles Page 81/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.
Prices

F The rates for woodwork shall include, but not limited, for the following:

(i) Working to size and shape.

(ii) Short lengths, mitres and ends.

(iii) All joints in the running length including structural joints.

(iv) Cutting and fitting to steelwork.

(v) All considerations arising from the specification.

(vi) Trimming around openings.

(vii) Notching, boring and sinking.

(viii) Treating backs of woodwork in contract with structure.

G The rates for framed woodwork shall include but not limited, for the following:

(i) Proper framed joints.

(ii) Gluing joints.

(iii) Dowelling and/or screwing joints.

H The rates for milled woodwork shall include, but not limited, for the following:

(i) Punching fixings below exposed surfaces and filling flush.

(ii) Any necessary sanding to remove "rippling" caused by milling machines.

(iii) Special returned ends.

(iv) Wreaths, ramps and the like.

A The rates for woodwork described as "selected" shall include, but not limited, for the following:

(i) Keeping clean and clear finishes.

(ii) Punching nails and pins below exposed surfaces and filling with an approved coloured fil
the woodwork.

(iii) Where described also as "screwed" the woodwork shall be fixed with screws recessed and
match the woodwork.

B The rates for frames and linings shall include for bedding in specified mortar where required.

362490201.xlsx - Pricing preambles Page 82/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.

C The rates for plywood, block board and the like shall include for straight raking curved and circular
all consequent wastage.

D The rates for ironmongery shall include, but not limited, for the following:

(i) Mortises, sinkings and the like.

(ii) All considerations arising from the specifications.

(iii) Removing before and replacing after decoration.

(iv) Testing and easing and adjusting.

(v) Oiling and leaving in perfect working order.

(vi) Adhering strictly to mastering and sub-mastering schemes.

(vii) Supplying and labeling at least two keys for each and every lock and handing the Engineer.

(viii) Master key if required by the specification or drawings.

E The rates for ironmongery described as "fixed to hardwood" shall include for fixing to plywood, blo

SECTION ; ROOFING AND WATERPROOFING

Prices

A The rates for work in this section shall include, but not limited, for the following:

(i) Laps, seams and narrow widths.

(ii) Straight raking curved and circular cutting and all consequent wastage.

(iii) All considerations arising from this specification.

(iv) Angles, returned ends and dressed ends on flashings.

(v) Dressing up and over up stands and around and into gargoyles, vent pipes and the like.

(vi) Tropical grade mastic pointing to all flashings.

(vii) Clearing rubbish and cleaning areas on completion.

(viii) Testing in accordance with the specification and to the approval of the Engineer.

(ix) Providing a 10 year guarantee.

Finishes

362490201.xlsx - Pricing preambles Page 83/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.

Applied finishes described in this section are deemed to be measured as the relevant preamble in
B occur.

Insulation

C Prices to be inclusive of all items as described above, where applicable.

SECTION : DOORS AND WINDOWS

Generally

A This section shall be read particularly in conjunction with the woodwork and metalwork sections:

Prices also to include

B The rates for glazing shall include, but not limited, for the following:

(i) Panes of any size.

(ii) All straight raking, curved and circular cutting and all consequent wastage.

(iii) Patterned and wired glass shall include aligning adjacent panes.

(iv) Wash-leather bedding strips in conjunction with glazing beads.

(v) Glazing fillets shall include clipping to metal unless otherwise stated.

(vi)
Patent glazing shall include accessories and shall be fixed with screws or by the method
the system used, hardwood framing to either be inclusive of the window unless measured

Glazing shall include blocks, setting blocks, locating blocks, distance pieces and the like ac
(vii) fixing.

(viii) Cleaning off protective coatings prior to glazing aluminium windows, screens and doors.

(ix) Glazing to metals shall include setting in glazing compound, as specified.

(x) Replacing cracked or broken panes and cleaning on both sides on completion of project.

SECTION : FINISHES

Generally

A All finishings, screeds and backings have been measured net.

Prices

362490201.xlsx - Pricing preambles Page 84/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.
B Rates for finishes shall include, but not limited, for the following:

(i) Well wetting solid surfaces to be plastered or screened.

(ii) Raking out joints of block work partitions, hacking surfaces of concrete or applying bond
form a key and any necessary dubbing out.

(iii)
All cutting and waste, arises, short lengths, angles, ends, etc., making good or cutting
around pipes conduits trunking pipe brackets and the like and making good up to door
frames skirtings etc., all temporary rules and working around buried pipes cables conduits e

(iv) Angle beads, plaster stops, expanded metal strips, glass fibre scrims, aluminium channels
to all plasterwork around doors, windows at vertical abutments etc., and secure
backgrounds.

(v) All setting out, temporary rules, screeds, templates and supports.

(vi) Curing and cleaning off/down upon completion.

(vii) Dubbing out as necessary to take up tolerances in the structure and cambers in floors and t

C Rates for screeds shall include, but not limited, for the following:-
(i) Finishing with a tamped floated or trowelled surface as required.

(ii) Laying level or to falls or slopes as required.

(iii) Laying in bays where required including formwork to all edges, reinforcement, joint filler a
as detailed and specified.

(iv) Provision of expansion joints where required.

D Rates for wall and floor tiles and the like shall include, but not limited for the following:-
(i) Fixing with an approved adhesive.

(ii) Pointing up joints with mortar and cleaning off as required.

(iii) Rounded, beveled and fair edges as required.

(iv) Metal edge strips, dividers etc.

(v) Straight, raking and curved cutting.

(vi) Provision of expansion joints and sealant as indicated on the drawings.

(vii) Provision of slurry protection or the like including removing same in floor areas subjected t
of labour and materials.

(viii) General protection of finished work to Engineers approval.

362490201.xlsx - Pricing preambles Page 85/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.

A Rates for ceiling finishes shall include, but not limited for the following:-

(i) Finishing with trowelled surface or other as required.

(ii) False ceiling to include for all hangers, ceiling grid, tiles and insulation layers.

(iii) Bulkheads as shown on drawings.

(iv) Work to sloping, curved, straight soffits as required.

(v) Straight, raking and curved cutting.

(vi) Cutting and fitting around light fittings, A/C equipment etc.

PAINTING AND DECORATION

Generally

B Painting to Structural Steelwork and Metalwork may either be included in this section or within e
to which it occurs and may be measured either as m2 or kg of Steel/Metalwork.

Prices

C The rates for painting and decorating shall include, but not limited, for the following:

(i) Painting either internally or externally.

(ii) All cleaning and preparatory work to the surface to be painted including rubbing down betw

(iii) Priming shall include for using a primer appropriate to the surface to which it is being applie

(iv) Preparation of manufactured boards and wood products shall include for surface filling.

(v) Work on "Woodwork" shall include both softwood and hardwood.

(vi) Extra preparation on metal trims and the like over that of general surfaces in which they ar

(vii) Unless of a differing specification, work shall be deemed to cover internal or external painti

(viii) Use of differing colours within areas.

(ix) Work to curved surfaces.

(x) All cutting into edges.

(xi) Scaffolding as required.

SECTION : MECHANICAL ENGINEERING INSTALLATION

362490201.xlsx - Pricing preambles Page 86/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.

Prices

A The rates of pipe work and gutter work shall include, but not limited, for the following:

(i) All cuttings, short lengths and small quantities.

(ii) Made bends on copper pipe work.

(iii) Couplers and/or joints in the running length.

(iv) Splay cut ends.

(v) All considerations arising from the specification.

(vi) Fixing with approved holder bat or pipe clips cut and pinned, built in or plugged and screwe

(vii) Pipe sleeves through walls.

(viii) Bends and fittings on pipes whatever the diameter.

B The rates for sanitary fittings and the like shall, unless otherwise described or implied, shall incl
limited, for the following:

(i) Assembling component parts including suitable bedding compounds.

(ii) All necessary plugging and screwing.

(iii) Joints to water services with straight or bent proprietary connectors.

(iv) Cleaning off all protective wrappers and leaving ready for use.

(v) Leaving taps and valves greased, clean and in full working order.

(vi)
The Contractor shall include for the supply of manufacturers recommended spares as req
Specification for all mechanical engineering installations and shall submit details of s
provided by him on a separate sheet accompanying his tender submission.

(vii) All rates and amounts shall be gross and shall include for main contractor's overheads
general and special attendances.

(viii) The Contractor shall particularly note any list of approved sub-contractors. No other sub
shall be used for the project.

SECTION : ELECTRICAL ENGINEERING INSTALLATIONS

Prices

362490201.xlsx - Pricing preambles Page 87/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.
A The rates in general shall include, but not limited, for the following:

(i) All cutting, short lengths and small quantities.

(ii) All joints in the running length and all connections.

(iii) All considerations arising from the specification.

(iv) Fixing conduits/cable trays, etc., by approved methods.

(v) Pipe sleeves through walls.

(vi) Assembling component parts.

(vii) Cleaning off all protective wrappers and leaving ready for use.

(viii) Leaving all equipment etc., clean and in full working order.

(ix) Draw wires in empty conduits.

(x) Rates for cable and duct trench excavation shall include for all excavation, bedding,
disposal as required by the Statutory Authority standard specification.

Main Circuits

B Definition is as Clause R.2.1 of POM (I).

C Cabling and conduiting shall be described as an item, and be inclusive of all sleeves, joints, etc., a
connect the incoming supply to the Main Distribution Board.

General

D The Contractor shall particularly note any list of approved sub-contractors. No other sub-contrac
used for the project.

E All rates and amounts shall be gross and shall include for main contractor's overheads, profit and
special attendances.

F
The Contractor shall include for the supply of manufacturers recommended spares as requ
Specification for all electrical engineering installations and shall submit details of spares to be prov
on a separate sheet accompanying his tender submission.

G The cable lengths/routes where quantified are measured from point to point on the drawing
required for connections, loops, etc., at equipments, appliances, control gear or the like will be de
included.

SECTION : EXTERNAL WORKS

362490201.xlsx - Pricing preambles Page 88/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.
Generally

A The preceding and following clauses of all sections shall apply equally to relevant items within this

DRAINAGE

Generally

B The preceding clauses of all sections shall apply equally to relevant items within this section.

Drains

C The rates for trench excavation for pipes are to include for deepening/widening the trench as n
enable the barrels of pipes to rest on firm ground and to facilitate jointing.

D The rates for rock excavation in trench excavations are to include for imported selected materia
any excavated material which is unsuitable for backfilling.

The rates for trench excavation shall include for disposal of surplus excavated material as dire
E Engineer.

F The rates for concrete beds and surrounds to pipes are to include for flexible joints and an
formwork where required by the Specification.

G The rates for pipes are to include for all short lengths, joints and couplers as necessary and for a
manholes and the like, and all testing.

H The rates for fittings on pipes are to include for jointing to pipes with all necessary additiona
flanges, etc., and any necessary cutting of pipe work.

SECTION : PROVISIONAL AND PRIME COST (PC) SUMS

Generally

A Provisional and Prime Cost sums are included for use as directed by the Engineer in accordance wi
of the General Conditions of Conditions of Contract for Works of Civil Engineering Construction issu
Federation Internationale Des Ingenieurs-Conseils (FIDIC) Fourth Edition 1987 as amended

B Where the Contractor is required to add for "Profit" a Lump sum figure shall be inserted as indicate
lump sum shall include all profits and for site office, head office and other overheads

C Where the Contractor is required to add for "Attendances" and "Ancillary Work" a Lump sum figure
inserted as indicated. This lump sum shall include the following where work is to be executed by a
Contractor:

(i) Use of temporary roads, pavings, paths, standing and special scaffolding, hoisting/cranage
lighting and water, offices, office facilities and sanitary facilities.

362490201.xlsx - Pricing preambles Page 89/ 111


King Khaled International Airport

PRICING PREAMBLES

ITEM DESCRIPTION
REF.
(ii) Unloading, distribution, hoisting/lifting and placing in position (if not carried out by the Sub-

(iii) Providing secure storage facilities with lighting and power.

(iv) Providing power (if required).

(v) Protecting the work on completion.

(vi) Necessary supervision, coordination and shop drawings as applicable or required.

(vii) Any other attendances specifically required.

(viii) Builder's work in connection such as cutting, forming holes, chases and channels, etc. and m
as described under the relevant trade preambles.

(ix) Opening and maintaining Letters of Credit, pre-payment etc. As applicable or required

(x) Unloading delivered items to site, checking for damage and supplying replacements (if nece
processing of insurance claims as applicable or required.

D It is an express obligation of this Contract that the Main Contractor undertakes to coordinate all ma
relating to engineering, construction, programming and commissioning with all nominated Sub-Con
and Suppliers instructed to carry out work under this Contract. The cost of this coordination should
for in the attendance item above.

E The lump sum values included against Items B and C above shall not be the subject to any change
increase in the value of the Provisional and Prime Cost Sums

F Where a Prime Cost sum is included for the supply only of a material the Contractor shall include in
or prices the stated amount to cover the supply of the specific material mentioned delivered to site
costs for labour, plant, ancillary materials, profits, overheads, attendances and ancillary works as d
above shall be included in the Contractor's rate or price for the Work and shall not be the subject t
change should the amount of the Prime Cost sum vary.

362490201.xlsx - Pricing preambles Page 90/ 111


rnational Airport - KSA

egral part of the Contract


ch item are not necessarily
uments, Specifications and
on as no claim or variation

ntract Documents including


inferred from any of them)
ices, even if specific items

ribed and must include all


ion, administration, tools,
y be required in and for the
lying with all general risks
Conditions of Contract. All
ads, profit and general and

are complementary and if

Conditions of Contract shall


to the foregoing, should an
idered as necessary for the
Should an item required for
Documents, then the items
.

ades that is not intended to


l Contractor will be paid.

nstitute the entire claim for


f Contract. The works shall
n the scope of work through

nd confirms his acceptance


nd actual quantities on site

362490201.xlsx - Pricing preambles Page 91/ 111


rnational Airport - KSA

antities shall not vitiate this


rt of the Works comprised
ons or liabilities under the
ed by a variation issued by

oint he considers to be a
a Tender adjustment.

antities and should any be


must notify the Engineer at
atsoever will be entertained
ailures to comply with the

he Bills of Quantities fully


ted.

of each bill of this Bills of

contained in these Bills of

tities. Items against which


in the Bills of Quantities.
he shall insert the relevant

between them occurs. The


are not priced at different

of POM (I) (as here below


method expressed must be
following pricing preambles
ired.

and to form part of every

iting, of the Engineer.

362490201.xlsx - Pricing preambles Page 92/ 111


rnational Airport - KSA

me or for the purposes of


ies shall be the drawings,

of construction dated June


d Surveyors, London.

more than one plane.

362490201.xlsx - Pricing preambles Page 93/ 111


rnational Airport - KSA

space and trade or traditional

ctions of the works unless

with the printed instructions

ing good and clearing away

l include cutting or forming

built in" and "cast in" shall


he items concerned.

he Contractor.

with letters of credit, bank


of the Contractor.

n to the satisfaction of the

all surfaces free of cracks,

362490201.xlsx - Pricing preambles Page 94/ 111


rnational Airport - KSA

ors, windows, ironmongery

nd sanitary ware, including

m (iii) above.

ver and cleaning all unused

r shall provide the following

of the works.

olen after the acceptance of


orks.

Contractor is to provide for


ept fixing in position.

ject to the approval of the

rk is put in hand particulars


ormed or left. No claim for

362490201.xlsx - Pricing preambles Page 95/ 111


rnational Airport - KSA

l not be used in connection

ors working different hours

the following attendances:-

s attendances, labour and

s of plant, equipment and

362490201.xlsx - Pricing preambles Page 96/ 111


rnational Airport - KSA

Main Contractor).

etion of the Engineer but

asured from natural ground

will be measured from the

ks as general filling then it


of items for filling and for

de, but not limited, for the

on in any kind of ground

f items to be formed in and


hown on the drawings. No
All remedial works shall be

362490201.xlsx - Pricing preambles Page 97/ 111


rnational Airport - KSA

aterial or on formwork by

limited, for the following.

t to required shapes and

wire and

s, grooves, chases and the

362490201.xlsx - Pricing preambles Page 98/ 111


rnational Airport - KSA

steel binding wire and

and notching around pipes,

subject to any limitations

rfaces of reinforcement.

al when no longer required.

of shuttering.

projecting reinforcement.

ited, for the following:

uce the finish demanded by

the requirements of the

362490201.xlsx - Pricing preambles Page 99/ 111


rnational Airport - KSA

alternative to cutting out

devices approved by the

sonry section of the Bills of

rete works shall be deemed


hall be deemed included in

362490201.xlsx - Pricing preambles Page 100/ 111


rnational Airport - KSA

offits junction and heads of

work or over cavities from

nce with the Specification.


required by the Contract

pointing in similar mortar.

ackets, timbers, steelwork,

362490201.xlsx - Pricing preambles Page 101/ 111


rnational Airport - KSA

less otherwise described.

ng with mortar, temporary

position and for all holes,

al to which it is to be used.
uded in the weights of the

ooves, rebates and the like

rebates, and the like shall

362490201.xlsx - Pricing preambles Page 102/ 111


rnational Airport - KSA

e following:

ed coloured filler to match

ws recessed and pelleted to

362490201.xlsx - Pricing preambles Page 103/ 111


rnational Airport - KSA

ved and circular cutting and

g the Engineer.

to plywood, blockboard and

nd the like.

362490201.xlsx - Pricing preambles Page 104/ 111


rnational Airport - KSA

ant preamble in which they

ork sections:

by the method required by


ess measured separately.

and the like accessories for

s and doors.

n of project.

362490201.xlsx - Pricing preambles Page 105/ 111


rnational Airport - KSA

applying bonding agent to

good or cutting and fitting


od up to door and window
ables conduits etc.

nium channels and the like


., and securely fixing to

s in floors and the like.

ent, joint filler and sealants

eas subjected to movement

362490201.xlsx - Pricing preambles Page 106/ 111


rnational Airport - KSA

ion or within either section

bing down between coats.

t is being applied.

n which they are decorated.

external painting.

362490201.xlsx - Pricing preambles Page 107/ 111


rnational Airport - KSA

ged and screwed.

plied, shall include, but not

d spares as required by the


mit details of spares to be

tor's overheads, profit and

. No other sub-contractors

362490201.xlsx - Pricing preambles Page 108/ 111


rnational Airport - KSA

tion, bedding, backfill and

s, joints, etc., as required to

her sub-contractors shall be

ads, profit and general and

spares as required by the


pares to be provided by him

on the drawing, any cable


e like will be deemed to be

362490201.xlsx - Pricing preambles Page 109/ 111


rnational Airport - KSA

ems within this section.

the trench as necessary to

elected material to replace

material as directed by the

joints and any necessary

essary and for all cutting at

ssary additional couplings,

accordance with Clause 59


onstruction issued by
mended

rted as indicated. This


ds

ump sum figure shall be


e executed by a Sub-

isting/cranage plant,

362490201.xlsx - Pricing preambles Page 110/ 111


rnational Airport - KSA

out by the Sub-Contractor).

uired.

nnels, etc. and making good

ements (if necessary) and

oordinate all matters


minated Sub-Contractors
rdination should be allowed

to any change due to any

shall include in his rates


delivered to site. All other
llary works as detailed
be the subject to any

362490201.xlsx - Pricing preambles Page 111/ 111

Das könnte Ihnen auch gefallen