Beruflich Dokumente
Kultur Dokumente
QUA-008
ROUTINE MANAGEMENT
ROUTINE MANAGEMENT
CONTROL OF REVISIONS
QUALITY
QUA-008
ROUTINE MANAGEMENT
SUMMARY
Page
General Information.................................................... 4
Introduction.................................................................. 7
Process..................................................................... 9
Exercises.................................................................... 17
Exercises.................................................................... 24
Template.................................................................... 28
References.............................................................. 29
GENERAL INFORMATION
Target audience
Facilitator
Prerequisites
Length of Program
Theory: 8 hours
Practice: none
MODULE DESCRIPTION
Objective:
To present the manner in which the daily routine is managed using key performance
indicators.
Evaluation Process
After studying all the material presented and correctly carrying out all the proposed
exercises, you will perform a theoretical self-evaluation. Then you will undergo a
theoretical evaluation on which you must receive a score of 70%.
If you do not get 70% correct, you must review the training stages in which you had
the most difficulty. If necessary, get help from your immediate supervisor.
TRAINING SCHEDULE
Training Stage 1
Activities Resources
2. Study and reinforce the concept Module QUA- 008 Pages 9 and 10.
of process and the structure
responsible for guaranteeing
work team results.
Module QUA- 008 Pages 11 and 12.
3. Study the concepts of key
performance indicators: as they
are chosen and defined.
ROUTINE MANAGEMENT
Management using TQC (Total Quality Control) is based on two groups of distinct
actions: ROUTINE and IMPROVEMENT. We are going to present Routine
Management in this module.
The following figure and table show how everyone involved in Routine Management
interacts.
Together, these components ensure that the process accomplishes its objective.
The basis of Routine Management is involving the operators in two very important
activities: Following the Operating Standards and participating in the Failure Analysis
Process.
PROCESS
WHAT IS A PROCESS?
Any time we talk about a work team or a work post, we often talk about processes
that are performed in these locations.
But what does the word process really mean? Look at the figure below:
Looking at this figure, we can imagine all the steps that this person carried out to
reach this exact moment. For example:
Each of these steps is called an Activity, that is, a basic and simple operation
performed by the operator.
The set of Activities done sequentially by a person (or several people) is called a
Task.
A Process is a group of related tasks that together generate value for the
customer. Process is work. It is related to what is done!
Customers
The process must have a result that adds value for the customer, that is measurable,
and that has a person in charge who will strive to make sure that this result meets
customers needs.
The person responsible for the process must control results and continuously
improve them.
In Routine Management, process results are tracked and compared with expected
values using Key Performance Indicators KPI.
To measure and control the results of the business and its processes.
The person responsible for the business is accountable for its results, that is, the
goals established with the Stakeholders must be met!
The following table shows some examples of key performance indicators in the melt
shop business.
John Smith
John Smith
John Smith
John Smith
John Smith
John Smith
John Smith
John Smith
John Smith
Key Performance Indicators (KPIs) are tracked by the supervisor or routine facilitator
with the help of Improvement and Routine Management software called GMR.
This software is used to optimize the routine and improve management processes by
tracking:
Projects;
The following figure shows how key performance indicators are tracked in GMR.
If results are outside the normal range, their root cause should be minimized in order
to prevent undesired results from occurring again.
The FCA is a tool that is available in Improvement and Routine Management (GMR)
software.
Special Causes These are variations that do not occur by chance. They
stem from known or unknown sources, and are not associated with events
(facts) other than those that occur during the process routine.
Common Causes These are variations that occur by chance. They stem
from known or unknown sources that are part of a process, and whose
occurrence is lasting and continuous.
Fact (1st Event): This is the effect or undesired result in some process.
Action: Actions necessary to eliminate the root cause of the problem are
proposed in this field.
Who: This is the person accountable for the planned action. It must always be
one person.
When: Describes when the action will be carried out, with a starting date and
an end date.
TIPS
Find the true cause of the problem so that it is not just the symptoms that are
being treated through the use of quality tools (see Module QUA-030).
Control limits: use statistics and historical data to assess the limits in the
graphs (see Module QUA-016). If historical data is not available, start with the
limits/specifications established by the Stakeholders.
ROUTINE IMPLEMENTATION
Based on the Quality Airplane, all these steps are necessary to attain stable results.
EXERCISES
Mark the correct answer:
6. Mark the following alternatives that have all the steps of Routine Implementation.
a. ( ) Critical Training, Execution according to standards, Auditing of Standards,
and Failure Analysis.
b. ( ) Process Analysis, Standardization, Critical Training, Execution according to
Standards, Auditing of Standards, and Failure Analysis.
c. ( ) Standardization, Failure Analysis, Auditing of Standards, Stable Results.
d. ( ) Process Analysis, Standardization, Auditing of Standards and Stable
Results.
TRAINING SCHEDULE
Training Stage 2
Activities Resources
3. Carry out the theoretical self- Module QUA- 008 Page 26.
evaluation relative to all training
steps in this module.
Applying the steps above into the PDCA method, steps 1 and 2 above are
concentrated on P (planning), steps 3 and 4 are part of D (doing) - actual routine
implementation.
Routine Implementation
Corrective
Actions Step 1
A P Step 2
Step 3
KPI Results
Check C D
Step 4
Standards Audits
The objective of Process Analysis is to learn about the business / process in order to
define its performance measures, as well as to identify what is critical to ensure
Safety, Quality, Cost, Environment and Delivery aspects of the results of the
business / process.
The main result of Process Analysis leads to Standardization, by defining what tasks
are critical and, therefore, should be standardized, such as preparing the PGT
Process Guarantee Table (See QUA-025).
STEP 2 STANDARDIZATION
2. Presenting the concepts, key points, and possible risks of the task.
1
Divide the process in small steps (tasks).
2
The
O especialista
expert showsdemonstra
to the trainee
para ohow
aprendiz
a certain
comotask
se is
done
faz, fazendo!
by performing it in front of him/her.
3
The
O trainee repeats
aprendiz repete the task,
a a o e and the expertacompanha
o especialista watches
the performance and takes notes
e anota os erros, sem interromper.of possible mistakes,
without interrupting.
4
OThe
especialista
expert repeats
faz novamente
the demonstration
o processoand
e mostra
presents the
os
mistakes
erros cometidos
made in the
pelo
previous
aprendiz
step,
na etapa
correcting
anterior,
them.
-os.
5
The trainee repeats the demonstration, trying to make
no mistakes. The process repeats itself as many times
as necessary until the trainee reaches the necessary
standard.
For this methodology to be successful, the facilitator must have some basic
knowledge:
Leadership Knowledge: Teaching skills, ease of relating with the team, and
knowing how to motivate the team for training.
These are the standards that contain all the information necessary for the operator to
perform his functions; therefore, they must be used intensively in operator training. All
training must have a plan that includes items that are organized according to a
5W1H, with requirements that must be followed.
Training needs for operators arise as a result of: implementing new products and
processes (machines, materials, techniques, etc.), blocking causes of failures, and
change of standards based on some improvement or elimination of the causes of
failures.
Tips
Before initiating the subject itself, assess the knowledge that the person being
trained already has.
Aspects of safety and the environment are a part of training and should be
included in any work.
All the prior steps help employees carry out tasks according to standards by seeking
to ensure the result of repetitive operations that are critical for meeting the needs of
Stakeholders!
STEP 5
Standard Audits
Standard Audits confirm that the standards that have been implemented as
part of the routine and are being complied with, which means they are useful
to the employees.
Failure Analysis
A failure is any undesired occurrence.
As was seen in the previous training stage, FCA is available in GMR, which is used
whenever a routine KPI has a value other than the projected value.
For more information on GMR software, use the resources below, or contact the
Technology Management Area of your Unit.
Help menu: provides information on the screen that the user is logged onto.
Service Desk (2001): Operating and performance problems with the GMR
Software should be directed here.
EXERCISES
4. FCA is the tool used when the results of a KPI in the routine show values outside
the normal range. The tool is available in GMR Software.
( ) True ( ) False
a. ( ) 1-2-1-1
b. ( ) 1-1-1-2
c. ( ) 2-1-2-2
d. ( ) 1-2-2-1
7. The following may be stated in regards to the method applied during the training
that operators receive:
a. ( ) It is a complex program that requires a great deal of dedication and
preparation by the facilitator so that training is conducted effectively.
b. ( ) It must be performed in a room with appropriate lighting and physical space
for the participants.
c. ( ) Using demonstrations, the facilitator trains the operators in how to execute
a certain task. Next, the operators try to reproduce this task.
d. ( ) The facilitator explains how a certain task should be carried out and then
the operator carries out the task according to what was explained.
THEORETICAL SELF-EVALUATION
Mark the correct answer with an X.
3. Match the items in the column on the left with the items in the column on the right:
(1) Manager (Q) Establishes standards and trains the team.
(2) Routine Facilitator (Q) Is responsible for process tasks.
(3) Operators (Q) Defines the key performance indicators in the
process.
a. ( ) 2-1-3
b. ( ) 1-2-3
a. ( ) 3-2-1
b. ( ) 2-3-1
4. The tool that makes it possible to track the key performance indicators of a work
team must use:
a. ( ) Fact-Cause-Action.
b. ( ) 5W1H.
c. ( ) GMR Software.
a. ( ) Only I and II
b. ( ) Only II and III
c. ( ) Only I and III
d. ( ) I, II and III
a. ( ) Only I
b. ( ) Only II and III
a. ( ) Only I and III
b. ( ) Only I, III and IV
TEMPLATE
EXERCISES
EXERCISES I - EXERCISES II
page 17 page 24
1A 1B
2B 2-A
3C 3-F
4A 4-V
5B 5-A
6B 6-A
7-C
SELF-EVALUATION
SELF-EVALUATION - page 26
1-B 5-A
2-A 6-B
3-D 7-A
4-C 8-C
REFERENCES