We have already communicated our instructions vide different transmittals about following matters

but till date no reply / action was taken from your side.

1. Following sets of technical submittals is required.


a. Sdf
b. sds
2. Arrangement of laboratory samples of following approved material for testing.
a. Ssfsf
b. Sfsds
c.
3. Submittal of Welders qualification record along with welding test samples (vertical and
horizontal) for welders to be deployed for fire fighting works.
4. Daily man power and progress report is required for MEP works.
5. Provide Technical submittal of swimming pool and fountain for our review and comments.
6. Submit Technical submittal for Building Maintenance Unit (BMU) for review and approval.
7. Coordination drawing of basement MEP works is still not submitted.
8. Podium shop drawing for sleeves openings is still not submitted while the slab is already
poured.

You are therefore advised to take necessary action for reply of above mentioned items at your
earliest.