GPU- STR-P-01 STR-P-02- NORTH/SOUTH EAST/WEST PIPE RACK FOUNDATION

Job Name: Denovo GPU-Piperack Foundation Work Description: STR-P-01 North-South Pipe Rack Foundation-Steel Reinforcement Fabrication
Job Number: OS-17-0101-37 Date: 25.07.17
No. of Weight of Steel Work
Total Bar Total Weight Weight/bar No. of No.of pieces pieces Work Conversion Rate Performed (kg) Total kg.
No. Item Bar Diam. (mm) Quantity (kg) (kg) pieces cut bent tied Cut Bend Tie Cut Bend Tied Performed per day
1 NS-01/03 25.4 200 2323.86 11.62 30 0 0 0.25 0.25 0.5 87.1448 0 0 87.14
2 NS-10 25.4 532 4506.04 8.47 42 0 0 0.25 0.25 0.5 88.935 0 0 88.94
3 NS-01/02/03/04 25.4 840 10507.27 12.51 126 0 0 0.25 0.25 0.5 394.023 0 0 394.02

TOTAL 570.10
LABOURER EQUIPMENT
Man- # NAME HOURS RATE SUMMARY
Name Skill hours Hourly Rate Total TOTAL
S.Heeralal Steel bender 10 $60.00 $600.00 FL2549 FORKLIFT 4 $140.00 $560.00 LABOUR $1,761.00
R.Ramroop Steel bender 10 $35.00 $350.00 FL4271 LULL 4 $140.00 $560.00 EQUIPMENT $1,520.00
K.Ramsamooj Operator 8 $35.00 $280.00 BAR CUTTER 10 $40.00 $400.00
N.Deo Operator 8 $32.00 $256.00 TOTAL $3,281.00
S.Jones Supervisor 5.5 $50.00 $275.00 Total $1,520.00
Total $1,761.00

RATE = $5.76 per kg.