PROJECT TITLE : Mitsubihsi Storage Tank

[PT ]
[Prepare By Ranu Januar] 21-Aug-17

Weekly

21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15
Aug Aug Sep Sep Sep Sep Oct Oct Oct Oct Oct Nov Nov Nov Nov Dec Dec Dec Dec Jan Jan Jan
'17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '18 '18 '18

ASSIGNED PLAN PLAN PLAN


WBS TASK DESCRIPTION REMARKS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
TO START END DAYS

Contract Award
Detail Engineering
1000 Deliverable Submission 1st submission
Design calculation report and Data Sheet (PS-MK-S4438-I-01-01 & PS-MK-S4438-I-01-01
1000 Included 21-Aug-17 23-Aug-17 3 Basic Data form Client is Required
& PS-MK-S4438-I-01-01)
Calculation Anchor Bolt Sizing (including required No. and Length) (PS-MK-S4438-I-01-02 Client Specification for Anchor Bolt
1001 Included 21-Aug-17 23-Aug-17 3
& PS-MK-S4438-I-01-02 & PS-MK-S4438-I-01-02) STD Drawing Required
Only Preliminary drawing. Client
1002 General Arrangement drawing (PS-M4437-001 & PS-M4438-001 & PS-M4439-001) Included 21-Aug-17 24-Aug-17 4 information for nozzle oreintation is
required.

Loading data is informed in GA


1003 Foundation loading drawing (PS-M4437-002 & PS-M4438-002 & PS-M4439-002) Included 21-Aug-17 24-Aug-17 drawing. Combined. Civil drawing
by Others. Include in 1002

ISSUED FOR FABRICATION


Only Preliminary drawing. Client
1004 Nozzle orientation detail drawing (PS-M4437-003 & PS-M4438-003 & PS-M4439-003) Included 21-Aug-17 24-Aug-17 4 information for nozzle oreintation is

2 nd submission
1st submission
required.
Only Preliminary drawing. Client
Shell plate development detail drawing with Plate Cutting Plan (PS-M4437-004 & PS-
1005 Included 24-Aug-17 27-Aug-17 4 information for nozzle oreintation is
M4438-004 & PS-M4439-004)
required.
Only Preliminary drawing. Client
Roof plate development detail drawing with Plate Cutting Plan (PS-M4437-005 & PS-

ISSUED
1006 Included 24-Aug-17 30-Aug-17 7 information for nozzle oreintation is
M4438-005 & PS-M4439-005)

2 nd
required.

1st
Only Preliminary drawing. Client
Bottom plate development detail drawing with Plate Cutting Plan (PS-M4437-006 & PS-
1007 Included 24-Aug-17 30-Aug-17 7 information for nozzle oreintation is
M4438-006 & PS-M4439-006)
required.
1008 Shell & Roof Manhole Drawing (PS-M4437-007 & PS-M4438-007 & PS-M4439-007) Included 24-Aug-17 27-Aug-17 4
1009 Shell Nozzle detail drawing (1/3) (PS-M4437-008 & PS-M4438-008 & PS-M4439-008) Included 24-Aug-17 27-Aug-17 4
1010 Shell Nozzle detail drawing (2/3) ( & & ) Included 24-Aug-17 27-Aug-17 4 include in 1009
1011 Shell Nozzle detail drawing (3/3) ( & & ) Included 24-Aug-17 27-Aug-17 4 include in 1009
1012 Roof Nozzle detail drawing (1/2) (PS-M4437-009 & PS-M4438-009 & PS-M4439-009) Included 24-Aug-17 27-Aug-17 4
1013 Roof Nozzle detail drawing (2/2) ( & & ) Included 24-Aug-17 27-Aug-17 4 include in 1012

1014 Column and Rafter detail drawing (PS-M4437-010 & PS-M4438-010 & PS-M4439-010) Included 24-Aug-17 27-Aug-17 4

1019 Anchor chair detail drawing (PS-M4437-015 & PS-M4438-015 & PS-M4439-015) Included 28-Aug-17 30-Aug-17 3

1st submission
STD drawing for name plate is

ISSUED FOR FABRICATION


1022 Name plate detail drawing (PS-M4437-016 & PS-M4438-018 & PS-M4439-016) Included 28-Aug-17 28-Aug-17 1
required
1015 Spiral stairway arrangement (PS-M4437-011 & PS-M4438-011 & PS-M4439-011) Included 30-Aug-17 4-Sep-17 6

2 nd submission
1016 Spiral stairway detail drawing (PS-M4437-012 & PS-M4438-012 & PS-M4439-012) Included 30-Aug-17 4-Sep-17 6 include in 1015

2 nd submission
1st submission
1017 Top handrail detail drawing (PS-M4437-013 & PS-M4438-013 & PS-M4439-013) Included 30-Aug-17 4-Sep-17 6

ISSUED FOR
1018 Roof platform detail drawing (PS-M4437-014 & PS-M4438-014 & PS-M4439-014) Included 30-Aug-17 4-Sep-17 6
Paint procedure (PS-MK-S4438-B-03-01 & PS-MK-S4438-B-03-01 & PS-MK-S4438-B-03- Shall be from paint manufacture
1023 Included 5-Sep-17 5-Sep-17 1
01) and client specification
1020 Internal Floating deck arrangement drawing (None & PS-M4438-016 & None) Included 7-Sep-17 12-Sep-17 6 Only for Make up Water Tank

ISSU
2 nd
1st
Internal Floating deck detail drawing upon receiving IFR Vendor Print (None & PS-M4438-
1021 Included 7-Sep-17 12-Sep-17 6 Only for Make up Water Tank
017 & None)
Inspection and Test plan (PS-MK-S4438-B-02-01 & PS-MK-S4438-B-02-01 & PS-MK-
1024 Included 8-Sep-17 8-Sep-17 1
S4438-B-02-01)
Progress report (Engineering) (PS-MK-S4438-A-03-01 & PS-MK-S4438-A-03-01 & PS-MK-
1025 Included (just our scope) monthly
S4438-A-03-01)
1026 As Built drawings (PS-M4437-017 & PS-M4438-019 & PS-M4439-017) Included Before hand over to client

PIM FINAL

https://www.vertex42.com/ExcelTemplates/construction-schedule.html Construction Schedule Template 2017 by Vertex42.com


21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15
Aug Aug Sep Sep Sep Sep Oct Oct Oct Oct Oct Nov Nov Nov Nov Dec Dec Dec Dec Jan Jan Jan
'17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '17 '18 '18 '18

ASSIGNED PLAN PLAN PLAN


WBS TASK DESCRIPTION REMARKS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
TO START END DAYS

Insert new rows ABOVE this one

https://www.vertex42.com/ExcelTemplates/construction-schedule.html Construction Schedule Template 2017 by Vertex42.com