Beruflich Dokumente
Kultur Dokumente
Fig. 82
6/42 Siemens Power Engineering Guide Transmission and Distribution 4th Edition
Power System Protection
Typical Protection Schemes
Fig. 84
Siemens Power Engineering Guide Transmission and Distribution 4th Edition 6/43
Power System Protection
Typical Protection Schemes
6 Fig. 85
General hints:
Infeed
7 This circuit is preferably used for the
52 interruption-free supply of important
consumers without significant backfeed.
52 I>, t IE>, t > I2>, t 52 The directional o/c protection 67/67N
trips instantaneously for faults on the
51 51N 49 46 7SJ60
8 protected line. This allows the saving
of one time-grading interval for the o/c-
O H line or Protection relays at the infeed.
O H line or
cable 1 cable 2 same as The o/c relay functions 51/51N have
line or cable 1 each to be time-graded against the
relays located upstream.
9 51 51N 7SJ62
67 67N
52
10 52
52
52 52
Load Load
Fig. 86
6/44 Siemens Power Engineering Guide Transmission and Distribution 4th Edition
Power System Protection
Typical Protection Schemes
Fig. 87
Notes:
52
1) Teleprotection logic 85 for transfer trip 52
or blocking schemes. Signal transmis- 7
sion via pilot wire, power-line carrier,
microwave or optical fiber (to be pro- 52 52
vided separately). The teleprotection
supplement is only necessary if fast 21/ 2)
67N
fault clearance on 100% line length is 21N
7SA511
required, i.e. second zone tripping 3) 8
(about 0.3 s delay) cannot be accepted 85 79 4) Same
for far end faults. Line or protection
2) Directional ground-fault protection 67N cable for parallel line,
1) if applicable
with inverse-time delay against high-
resistance faults
3) Single or multishot autoreclosure 79 85 79
3) 9
only with overhead lines 7SA511
2)
4) Reduced version 7SA510 may be used 21/
where no, or only 3-pole autoreclosure 21N 67N 4)
is required.
52 52 10
52
52 52 52 52
Load Backfeed
Fig. 88
Siemens Power Engineering Guide Transmission and Distribution 4th Edition 6/45
Power System Protection
Typical Protection Schemes
7. Subtransmission line
1 Note:
1) Connection to open delta winding if
available. Relays 7SA511 and 7SJ512
can, however, also be set to calculate
the zero-sequence voltage internally.
2 General hints:
Distance teleprotection is proposed as
main, and time graded directional O/C as
backup protection.
1) The 67N function of 7SA511 provides
3 additional high-resistance ground fault
protection. It can be used in a directional
comparison scheme in parallel with the
21 67 21/21N-function, but only in POTT mode.
25 79 21N 67N If the distance protection scheme ope-
4 rates in PUTT mode, 67N is only availa-
68 51 ble as time-delayed function.
78 67N 51N Recommended schemes:
PUTT on medium and long lines with
phase shift carrier or other secure com-
BF 7SJ62 munication channel.
5 POTT on short lines.
BLOCKING with On/Off carrier (all line
S lengths).
85 CH To remote
R line end
6 7SA511
Signal transmission
equipment
Fig. 89
7
10
6/46 Siemens Power Engineering Guide Transmission and Distribution 4th Edition
Power System Protection
Typical Protection Schemes
Line con- Normally used with Short lines in particu- All kinds of line EHV lines
figuration: medium and long lines lar when high fault re- (Preferred US
sistance coverage is practice)
required 4
(7SA511/513 relays al- Multi-terminal and
low use also with short tapped lines with in-
lines due to their inde- termediate infeed ef-
pendent X and R setting fects
of all distance zones).
5
Advantages: Simple method No distance zone
Tripping of underrea- overreaching pro-
ching zone does not blems, when applied
depend on the chan- with CCVTs on short
nel (release signal lines
from the remote line Applicable to extreme
6
end not necessary). short lines below the same as same as
No distance zone or minimum zone setting for POTT for POTT
time coordination be- limit
tween line ends ne- No problems with the
cessary, i.e. this mode impact of parallel line 7
can easily be used coupling.
with different relay
types.
Drawbacks: Parallel, teed and Distance zone and Same as for POTT,
tapped lines may time coordination with same as however, loss of re- 8
cause underreach remote line end relays for POTT mote end signal
problems. Careful necessary does not completely
consideration of zero- Tripping depends on Except that a weak block the protection
sequence coupling receipt of remote end infeed supplement scheme. Tripping is
and intermediate in- signal (additional inde- is not necessary in this case released 9
feed effects is neces- pendent underrea- with a short time
sary. ching zone of 7SA511/ No continuous on- delay of about
Not applicable with 513 relays avoids this line supervision of 20 ms (unblocking
weak infeed termi- problem). the channel possi- logic).
nals. Weak infeed supple- ble!
ment necessary 10
Fig. 90
Siemens Power Engineering Guide Transmission and Distribution 4th Edition 6/47
Power System Protection
Typical Protection Schemes
8. Transmission line with reactor Operating time of the 7SA513 relay is in Both 7SA513 and 7SA511 can practise
the range of 15 to 25 ms dependent on selective single-pole and/or three-pole
1 Note: the particular fault condition, while the tripping and autoreclosure.
1) 51G only applicable with grounded reac- operating time of the 7SA511 is 25 to The ground current directional compari-
tor neutral. 35 ms respectively. son protection 67N of the 7SA513 relay
These tripping times are valid for faults uses phase selectors based on symmet-
2) If phase CTs at the low-voltage reactor in the underreaching distance zone rical components. Thus, single pole au-
side are not available, the high-voltage (80 to 85% of the line length). Remote toreclosure can also be practised with
2 phase CTs and the CT in the neutral can end faults must be cleared by the super- high-resistance faults.
be connected to a restricted ground fault imposed teleprotection scheme. Its The 67N function of the 7SA511 relay
protection using one 7VH80 high-imped- overall operating time depends on the should be used as time delayed direc-
ance relay. signal transmission time of the channel tional O/C backup in this case.
(typically 15 to 20 ms for frequency shift The 67N functions are provided as high-
3 General hints: audio-tone PLC or Microwave channels, impendance fault protection. 67N of the
and lower than 10 ms for ON/OFF PLC 7SA513 relay is normally used with an
Distance relays are proposed as main 1 or digital PCM signalling via optical additional channel as separate carrier
and main 2 protection. Duplicated 7SA513 fibres). scheme. Use of a common channel with
is recommended for long (>100 km) and
Teleprotection schemes based on distance protection is only possible in
heavily loaded lines or series-compensat-
7SA513 and 7SA511 have therefore ope- the POTT mode. The 67N function in the
4 ed lines and in all cases where extreme
rating times in the order of 40 ms and 7SA511 is blocked when function 21/
short operating times are required due
50 ms each. With state-of-the-art two- 21N picks up. It can therefore only be
to system stability problems.
cycle circuit breakers, fault clearing used in parallel with the distance direc-
7SA513 as main 1 and 7SA511 as main times well below 100 ms (4 to 5 cycles) tional comparison scheme POTT using
2 can be used in the normal case. can normally be achived. one common channel. Alternatively, it can
Dissimilar carrier schemes are recom- be used as time-delayed backup protec-
5 mended for main 1 and main 2 protec- tion.
tion, for example PUTT, and POTT or
Blocking/Unblocking
6
CC
52L
7SJ600
52R
TC1 TC2
7 CVT
50
50N
51
51N BF
79 67N 79 67N
9 51G 7SJ600
68 68 7SA522 or
BF 85 7SA511 BF
79 79 BF, 59
S Direct Trip
Trip
85 7SA513 R Channel
10 52L
S Channel To remote
R 2 line end
S Channel
R 3
Fig. 91
6/48 Siemens Power Engineering Guide Transmission and Distribution 4th Edition
Power System Protection
Typical Protection Schemes
Siemens Power Engineering Guide Transmission and Distribution 4th Edition 6/49
Power System Protection
Typical Protection Schemes
The location of the CTs on both sides of For the selection of the main 1 and main one breaker and the manual closure of
the circuit-breakers is typical for substa- 2 line protection schemes, the com- the other breaker, may be made selecta-
1 tions with dead-tank breakers. Live-tank ments of application examples 8 and 9 ble by a control switch.
breakers may have CTs only on one side apply. A coordinated scheme of control circuits
to reduce cost. A Fault between circuit Autoreclosure (79) and synchrocheck is necessary to ensure selective tripping,
breakers and CT (end fault) may then function (25) are each assigned directly interlocking and reclosing of the two
still be fed from one side even when the to the circuit breakers and controlled by breakers of one line (or transformer
breaker has opened. Consequently, final main 1 and 2 line protection in parallel. feeder).
2 fault clearing by cascaded tripping has to In case of a line fault, both adjacent The voltages for synchrochecking have
be accepted in this case. breakers have to be tripped by the line to be selected according to the breaker
The 7SV512 relay provides the neces- protection. The sequence of automatic and isolator positions by a voltage repli-
sary end fault protection function and reclosure of both breakers or, alterna- ca circuit.
trips the breakers of the remaining in- tively, the automatic reclosure of only
3 feeding circuits.
4 87 7SS5. or
BB1 7VH83
BB1
7SV512 or
7VK512 7SV600
BF 85
5 UBB1 7SA522 or
1) 1) 2) 7SA511
79 21 50 51
21N 67N 50N 51N 59
52
UBB1
25
6 UL1 or UL2
or UBB2 UL1
Line 1
79
52
UL1 or UBB1
8 25
UL2 or UBB2
BF
7SV512 or
7SV600
Line 2
9 7VK512 UL2
79
Main 1
UL2 or 52 Protection of Line 2
UL1 or UBB1 (or transformer,
10 25
Main 2 if applicable)
UBB2
UBB2
BF
7SV512 or
7SV600
BB2
87 7SS5. or
BB2 7VH83
Fig. 93
6/50 Siemens Power Engineering Guide Transmission and Distribution 4th Edition
Power System Protection
Typical Protection Schemes
52
o/c- Fuse
relay
Load Load
5
Fig. 94
51 51N
52 7SJ60
10
Load bus, e.g. 13.8 kV
52 52
Load Load
Fig. 95
Siemens Power Engineering Guide Transmission and Distribution 4th Edition 6/51
Power System Protection
Typical Protection Schemes
4 7SJ60 51G
I>> IE>
7SJ60
51 51N
5 52
Load
bus
52 52 52
Load
6
Fig. 96
same as
63 infeed 1
7SJ62
9 51G IE>, t I>, t IE>, t I> IE>
51 51N 67 67N
7SJ60
10 1)
52 52
Load
bus
52 52 52
Fig. 97
6/52 Siemens Power Engineering Guide Transmission and Distribution 4th Edition
Power System Protection
Typical Protection Schemes
7SJ60 7SJ60
Siemens Power Engineering Guide Transmission and Distribution 4th Edition 6/53
Power System Protection
Typical Protection Schemes
17. Autotransformer
7SJ60 or
1 7SJ61 52
Notes:
1) 87N high-impedance protection requires
51N 50 46 50 87N 7VH80 special class X current transformer cores
BF 51 2)
with equal transmission ratio.
2) The 7SJ60 relay can alternatively be
1)
2 connected in series with the 7UT513 re-
lay to save this CT core.
General hint:
7UT513 87T 49
63 Two different protection schemes are
provided:
3 87T is chosen as low-impedance three-
52 52 winding version (7UT513). 87N is a sin-
1) gle-phase high-impedance relay (7VH80)
50
51 connected as restricted ground fault pro-
51 tection. (In this example, it is assumed
4 46 that the phaseends of the transformer
winding are not accessible on the neu-
50 tral side, i.e. there exists a CT only in the
59N BF 1) 50
BF neutral grounding connection.)
7RW60 7SJ60
51N
5
7SJ60
Fig. 100
6
18. Large autotransformer bank
68
21 21N 78 7SA513 General hints:
7SV600 7SV600
The transformer bank is connected in a
7 50 50 11/2 breaker arrangement.
BF BF Duplicated differential protection is pro-
EHV 52 52 posed:
Main 1: Low-impedance differential pro-
tection 87TL (7UT513) connected to the
transformer bushing CTs.
8 HV
Main 2: High-impedance overall differen-
tial protection 87TH (7VH83). Separate
87 50 class X cores and equal CT ratios are re-
7VH83 TH BF 7SV600 quired for this type of protection.
52 Back-up protection is provided by dis-
9 tance relays (7SA513 and 7SA511), each
7SA511 looking with an instantaneous first
7UT513 87 49 zone about 80% into the transformer
TL 21 and with a time-delayed zone beyond
63 the transformer.
The tertiary winding is assumed to feed
10 21N a small station supply network with iso-
52 lated neutral.
68
78
51
52
50
BF 50
BF 7SV600
59N 51G
6/54 Siemens Power Engineering Guide Transmission and Distribution 4th Edition
Power System Protection
Typical Protection Schemes
3
b) With high-resistance grounded infeed
(IE IN Motor)
Notes: 52 I>> > Locked I 2> I<
rotor
1) Window-type zero sequence CT. 49 7SJ62 or
2) Sensitive directional ground-fault protec-
50 49
CR 46 37
7SJ551 4
tion 67N only applicable with infeed 3)
from isolated or Peterson-coil-grounded I E> 2)
network. 7XR96
(For dimensioning of the sensitive direc- 1) 51G 67G
tional ground fault protection, see also 60/1A
application circuit No. 24)
5
3) If 67G ist not applicable, relay 7SJ602
can be applied.
M
Fig. 102b 6
20. Large HV motors > about 1 MW
Notes:
7SJ62 or
1) Window-type zero sequence CT. 7SJ551 7
2) Sensitive directional ground-fault protec-
tion 67N only applicable with infeed 52 I>> > Locked I2> U<
from isolated or Peterson-coil-grounded rotor
network. 50 49 49 46 27
3) This function is only needed for motors CR
where the runup time is longer than the
8
Optional
safe stall time tE. IE> 2) I< 37
According to IEC 79-7, the tE-time is the 7XR96
1) 51G 67G
time needed to heat up AC windings, 60/1A
when carrying the starting current IA,
from the temperature reached in rated Startup 9
service and at maximum ambient tem- super- 49T 87M 7UT512
perature to the limiting temperature. visior 3) 5) 6)
A separate speed switch is used to
supervise actual starting of the motor. 3)
The motor breaker is tripped if the motor Speed RTD's 4)
does not reach speed in the preset time. switch M 10
optional
The speed switch is part of the motor
delivery itself.
4) Pt100, Ni100, Ni120
5) 49T only available with relay type 7SJ5
6) High impedance relay 7VH83 may be
used instead of 7UT12 if separate
class x CTs. are provided at the terminal
and star-point side of the motor winding. Fig. 103
Siemens Power Engineering Guide Transmission and Distribution 4th Edition 6/55
Power System Protection
Typical Protection Schemes
Note:
MV 1) If a window-type zero-sequence CT is
4 provided for sensitive ground fault pro-
tection, relay 7SJ602 with separate
G1 I>, IE>, t I2> > ground current input can be used
(similar to Fig. 102b of application exam-
Generator 2 51
46 49 7SJ60 ple 19b).
51N
1)
5
VN
RN =
3 (0.5 to 1) Irated
6
Fig. 104b: With resistance grounded neutral
8
Field
9 G 64R
51 32 46 40 7UM511
10
IE>, t
51G
Fig. 105
6/56 Siemens Power Engineering Guide Transmission and Distribution 4th Edition
Power System Protection
Typical Protection Schemes
IE>, t 7UM511
5
51G
6
Fig. 106
Fig. 107
Siemens Power Engineering Guide Transmission and Distribution 4th Edition 6/57
Power System Protection
Typical Protection Schemes
6/58 Siemens Power Engineering Guide Transmission and Distribution 4th Edition
Power System Protection
Typical Protection Schemes
Notes: 1
1) 100% stator ground-fault protection
based on 20 Hz voltage injection
52 2) Sensitive field ground-fault protection
63 Transf. fault press based on 1 Hz voltage injection
Unit
trans.
3) Only used functions shown, further 2
71 Oil low integrated functions available in each re-
87 lay type (see Relay Selection Guide,
TU
Fig. 43).
51 3
TN
Transf. neut. OC Unit aux.
backup
87U
Unit diff.
51
Oil low
4
Transf.
fault press 71
63
5
Unit
Overvolt. 59 aux.
81N
51 6
Overfreq. TN
78
Trans.
Loss of 24 neut.
sync. OC
Volt/Hz
40 87T
Stator A 7
O.L. Loss of Trans.
field diff.
49S 32
E
Reverse 8
G 87G power Relay
type
Functions 3) Number
of relays
Gen. required
2) diff.
64
R2 64R
7UM511 40 46 59 81N 49 64R 1 9
Field Field 46 21
grd. grd. 59
Neg. Sys. 7UM516 32 21 78 1
seq. backup GN
1) 2)
7UM515 24 51 64
R2
1 10
59 GN
GN
2
Gen. 7UT512 87G 87T and optionally 87 optionally
neut. OV TU 3
51 1)
GN
7UT513 87U 1
7SJ60 51N 51 3
Fig. 109
Siemens Power Engineering Guide Transmission and Distribution 4th Edition 6/59
Power System Protection
Typical Protection Schemes
Reverse interlocking
3 I>, t0 I>, t
50 51 7SJ60
50N 51N
52
4 t0 = 50 ms
52 52 52
I> I>, t I> I>, t I> I>, t
6 50 51 50 51 50 51
50N 51N 50N 51N 50N 51N
8 Fig. 110
10
6/60 Siemens Power Engineering Guide Transmission and Distribution 4th Edition
Power System Protection
Typical Protection Schemes
Bus tie 87
protection BB 10
52 52
86
Feeder Feeder
protection protection
BF
Load Back-feed
Fig. 112
Siemens Power Engineering Guide Transmission and Distribution 4th Edition 6/61