Beruflich Dokumente
Kultur Dokumente
Key Qualifications
Have 34 years of versatile Engineering experience in power wing of Pakistan
WAPDA , MEW Kuwait, GCC Interconnection Authority and Saudi Electric
Company (SEC-WOA) Saudi Arabia as Electrical Maintenance Engineer of high
voltage GIS Substations, Senior Project Engineer ,Section Head E&DD Saudi
Electric Company, Manager Design EHV projects Pakistan NTDC respectively.
Worked as Senior Electrical Engineer Grade- 1 with Ministry of Electricity and
Water (MEW) Kuwait for 10 years as maintenance and operation engineer of high
voltage GIS and AIS Substations.
Senior Project Engineer with Gulf Cooperation Council Interconnection Authority
interconnecting SIX Gulf States (GCCIA) construction Project for 3 years. The
project involves review of engineering, design, review of technical specifications,
bidding documents, contract documents and evaluation reports for procurement of
works, materials and goods particularly for HV & EHV transmission projects and
consultancy services contract and Construction Supervision and Monitoring of
the project activities.
Section Head of Engineering and Design department of EHV projects for Saudi
Electric company western operating area (WOA) Jeddah for approximately 2
years for review and approval of Drawings submitted by different contractors, for
EPC Construction Projects.
Manager Design EHV Projects from 2009- Oct 2011with NTDCL Wapda Lahore
worked for all the under Construction and forthcoming EHV Projects all over
Pakistan.
Project / Construction Manager Barqaab Consulting Services Lahore for
Construction Supervision of 220 / 132kV Gas insulated Switchgear( GIS )
Substation Shalimar Lahore and 220/132KV AIS Substation Kassowal and Allied
transmission lines EPC Projects financed by JICA and World Bank for Client
NTDC from Nov 2011 till October 2014
Education:
N.E.D Engineering and Technology College/ Karachi University
. 1972- 1977 B.E. Electrical
EMPLOYMENT RECORD:
Activities
Activities
Manage working relationships with Employer NTDC, Contractors and different
concerned authorities involved in substation construction activities.
Coordinate with site Project Organizations for Construction activities to ensure the
implementation of Owner's requirements in to the Project.
Managing and Coordinating different Contractors and DISCOs for Project
Performance.
Managing and coordinating Project Interfaces with different utilities, contractors
and suppliers to ensure that all contract activities in full Compliance with Company
requirements with respect to health, safety, environment and quality.
Managing and Communicating Project Progress to all concerned authorities
including International Financing agencies like JICA, IBRD etc.
Processing and verification of Contractor's Claims in the light of Contract
Agreements, FIDIC guidelines and approved drawings.
Assisting and submitting proposal for recovery plans to Project Authority for timely
Completion of the Project.
Activities
Responsible for Engineering Design of substation projects
Preparation of standards and NTDC specifications
Evaluation of engineering consultancy bids, EPC projects and procurement of
different substation equipment and hardware and placing orders to the prospective
bidders, Allocation of material as per requirement of respective scope of work to
project authorities for execution of site activities.
Consultancy Engineering services for NTDC own projects
Selection and approval of different substation sites.
Witnessed Proto-Type and Factory Acceptance Testing of 220KV and 132KV
circuit breakers at Chinese Lab nominated by WAPDA in 2010.
Witnessed Proto-Type and Factory Acceptance Testing of 500KV disconnectors in
KEMA Czech-Republic Lab and Xian Lab China nominated by WAPDA in 2011.
Activities
Activities
Activities
Activities
Lead a team of Engineers and Technical Staff for Construction Projects of Extra
high voltage Substations and Transmission lines under International financing of
IBRD, Asian Development Bank, Islamic Development Bank, K.F.W. etc., Under
the Supervision of International Consultants, Suppliers and Contractors.
Project Management and Supervision of 220KV GIS and 500KVAIS Substation
extensions and Transmission lines for Power Dispersal of 1450MW Power of Ghazi
Barotha Hydro Power Project.
Project Coordination meetings and Site visits, Presentation of Work and
disbursement Progress to International Agencies.
Witnessed Proto-Type Testing of double Circuit 500KV Transmission lines towers
at Tower Testing Station Liang- Xiang, Beijing China nominated by NTDCL-
WAPDA in 2002.
6. July 1990-March 1995:
Activities
Inspection and Testing of Substation 11KV Local Control Cubicles and Other
Substation Equipments at manufacturers works. Issuing inspection Certificates
for delivery.
Review and update Substation Standards of WAPDA as and when required.
Activities
Supervision, Operation and Maintenance of High Voltage Substations up to
300kV.
In possession of MEW T.E.N department Operation Authority, Mandatory to
operate High voltage Substation Switchgears of different types and makes.
Supervision, Erection, Maintenance, routine checking and testing of different Fire
alarm detection and Extinguishing Systems installed at high voltage Substation
buildings, Power Transformers, Switchgears and Cable Sealing ends.
Worked as Network Contract and Material Engineer of T.E.N Department.
Timely arrangement of Substation materials from different equipment
manufacturers and Suppliers for maintenance Contracts.
Activities
Operation and Maintenance of 220 and132KV Grid Station.
Managing different job requirements like substation materials, arranging shut
downs with national power control center and implementing health, Safety
requirements etc.
________________________________________________________________________
Driving License:
Kuwait; Pakistan; Saudi Arabia
Languages: