CONSTRUCTION SCHEDULE

BESAO 3 HEP
ID Task Name Duration Cost Start Finish Predecessors Resource Names ober 2013 November 2013
5 10 15 20 25 30 4 9 14 19
1 CONSTRUCTION SCHEDULE 445 days 0.00 Mon 11/4/13 Fri 7/17/15
2 ACQUISITION OF AFFECTED LANDS COMPLET 1 day 0.00 Mon 11/4/13 Mon 11/4/13 11/4
3 ORDER OF ELECTROMECHANICALS 1 day 0.00 Mon 11/4/13 Mon 11/4/13 11/4
4 BIDDING OF ALL WORKS COMPLETE 1 day 0.00 Mon 11/4/13 Mon 11/4/13 11/4
5 MOBILIZATION 1 day 0.00 Mon 11/4/13 Mon 11/4/13 11/4
6 Start purchase/delivery of const'n mat"ls at site 1 day 0.00 Mon 11/4/13 Mon 11/4/13 11/4
7 Order Electromechanical 1 day 0.00 Mon 11/4/13 Mon 11/4/13 11/4
8 Repair and opening of access roads 1 day 0.00 Mon 11/4/13 Mon 11/4/13 11/4
9 Skyline construction complete 1 day 0.00 Mon 11/4/13 Mon 11/4/13 11/4
10 Construction of site facilities 50 days 0.00 Tue 11/5/13 Mon 1/13/14
15 Junction box 155 days 0.00 Mon 1/6/14 Fri 8/8/14
21 Conveyance line (steel pipe) 212 days 0.00 Mon 1/6/14 Tue 10/28/14
28 Tunneling works 310 days 0.00 Mon 1/6/14 Fri 3/13/15
32 Surgetank 175 days 0.00 Mon 8/4/14 Fri 4/3/15
39 Penstock line 150 days 0.00 Mon 8/4/14 Fri 2/27/15
46 Power plant 310 days 0.00 Mon 1/6/14 Fri 3/13/15
47 Construct sub structure 170 days 0.00 Mon 1/6/14 Fri 8/29/14
48 Site preparation/earthworks 50 days 0.00 Mon 1/6/14 Fri 3/14/14 5SS
49 Construct retaining walls 70 days 0.00 Mon 2/17/14 Fri 5/23/14 48SS+30 days
50 Rebar/form works 90 days 0.00 Mon 2/17/14 Fri 6/20/14 48SS+30 days
51 Concreting of substructure 70 days 0.00 Mon 4/14/14 Fri 7/18/14 50SS+40 days
52 Construct sub-station 30 days 0.00 Mon 7/21/14 Fri 8/29/14 51
53 construct superstructure 140 days 0.00 Mon 9/1/14 Fri 3/13/15 51SS
54 Steelworks 60 days 0.00 Mon 9/1/14 Fri 11/21/14 52
55 Install sidings/roofings 50 days 0.00 Mon 11/24/14 Fri 1/30/15 54
56 Finishing/painting works 30 days 0.00 Mon 2/2/15 Fri 3/13/15 55FF+30 days
57 ELECTRO - MECHANICAL 144 days 0.00 Tue 12/30/14 Fri 7/17/15
58 Arrival of electro - mechanical 1 day 0.00 Tue 12/30/14 Tue 12/30/14
59 Installation of electromechanicals 50 days 0.00 Mon 3/16/15 Fri 5/22/15 56
60 Comissioning 40 days 0.00 Mon 5/25/15 Fri 7/17/15 59
CONSTRUCTION SCHEDULE
BESAO 3 HEP
December 2013 January 2014 February 2014 March 2014 April 2014 May 2014 June 2014
24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 4 9 14 19 24 29 3 8 13 18 23 28 3 8 13 18 23 28 2 7 12 17 22
CONSTRUCTION SCHEDULE
BESAO 3 HEP
July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015
27 2 7 12 17 22 27 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23

12/30
CONSTRUCTION SCHEDULE
BESAO 3 HEP
February 2015 March 2015 April 2015 May 2015 June 2015 July 2015 August 2015
28 2 7 12 17 22 27 4 9 14 19 24 29 3 8 13 18 23 28 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26