METHOD STATEMENT
692-C03R
Flushing of Storm Drainage system
Issued by:
TABLE OF CONTENTS
1. TITLE.
2. SCOPE OF WORK
General description.
Plant and equipment.
Materials.
Site planning & preparation
Work methodology.
Organization, Responsibilities & Supervision.
Work Force.
Risk assessments
Jubail ES & H Contractor Requirements
Protective & Safety Equipment.
Contractual Requirements.
Information to personnel.
Emergency Procedures.
Permit Requirements.
4. ENVIRONMENTAL ISSUES
5. QUALITY ASSURANCE
Contractual Requirements.
Critical works.
Inspection & Testing.
Follow up & Evaluation.
6. APPENDICES
1.0 TITLE
General Description
This method statement is covering the installation work at Royall Commission Project
development of Jalmuda Shoreline for Storm Drainage lines.
To execute the job, below listed plant & equipment shall be used but not limited to the
following:
Lifting Equipments
Long bed Trailer
Dewatering Equipments
Hand Tools
Crane
Sling/Belt
Shackle
Chain Block or Come along
Sling/Belt
Shackle
Chain Block or Come along
Material
The material used shall be in accordance with the specification and contract
drawings such as RPM pipe, Lubricant, and gasket.
Pipes shall be stored on a plain ground either in the wooden timbers or on sand
mounds with adequate chokes to prevent from movements.
From the lay- down area to the trench site, it shall be transported through trailers.
Prior to unloading of pipes from trailers, all items shall be inspected for any visual /
transportation damages.
Care shall be taken to prevent pipes from rolling or falling from flat bed trailer and
this shall be attained by using proper supports, chocks.
Spigot end has to be properly secured for not to have any damage and direct
contact with moisture.
Special care has to be taken to prevent any damage on liner of the pipe.
The rubber gaskets received along the pipes and fittings shall be stored in shelter
with original packing until it is used at site.
The supplied lubricant is special vegetable soap (free from grease and petroleum
products). Only the supplied lubricant shall be used.
Extra care shall be taken to ensure that all materials are not damaged during
transport.
Site Planning
Trench Excavation:
Position the crane (If it is needed) near the trench (safe distance).
Unload the pipe and lower into the trench.
Ensure no sand/debris go inside the pipes.
Make sure that the bedding is mechanically compacted and tested prior to pipe
laying as per the requirements.(RC Hold Point)
After placing the first pipe, bring the second pipe near the pipe earlier placed and
install it with clamps, chain blocks/pullers.
Once the pipe is fixed in the coupling, check the alignment and move to other joint.
Keep continue this way and ensure for the entire line.
Release the pipe from the crane, remove the slings and clamps.
Work Methodology :
(Manufacturer recommended procedure attached, and shall be followed.)
After the pipe joint Gravity test, the pipes can be backfilled and compacted in
lifts of 150mm upto warning tape and thereafter in lifts of 300mm upto FGL.
The backfilling should be compacted to 90% max dry density as per RC spec.
No. -02315 and contract drawing 692-320-20TR-CE-211.
Sand shall be used for backfilling free of any contamination.
QA/QC Engineer is responsible for the proper carrying out of the inspection and
Testing details as per Specification and Procedure.
Field Engineer and Piping Superintendent responsibilities are to manage all the
everyday activities as per plan and schedule. They Coordinate with the HSE
Department to ensure that Proper Safety Implementation respective to
Personnel, Equipments and Environment are strictly adhered. Piping Supervisor
responsibility is to monitor everyday field activities, assuring that implementation
is as per this Method statement.
Work Force
Field Engineers
QC Inspectors
Surveyor
Safety Officer
Equipment Operators
Rev 1, May 2015 Page 8
Document Type
Foremen
Pipefitters
Helpers
Wear at all the time suitable protective clothing, gloves and eye protection, dust
masks should be used all the time; the wet adhesive may cause irritation by skin
contact.
All Environmental and Health shall be taken care
Execute periodic cleaning to keep site.
Adjacent properties free of accumulations of waste materials, debris, rubbish, and
windblown debris resulting from construction operations.
Store volatile wastes in covered metal container remove from premises daily.
Prevent accumulation of waste which creates hazardous condition.
Conduct cleaning and disposal operation to comply with local environmental laws.
Provide plastic cover over electrical and electronic components to reduce dust
accumulation in interior parts.
Protective and Safety Equipment
All person at all time when on the site have to wear a protective helmet.
Safety shoes/boots shall be issued to all personnel on the site.
Appropriate glasses and eye protection to be issued to workman as required.
In places where high slopes workers shall be equipped with a safety full body
harness with retrieval line securely anchored to the structure.
Rubber boots to be provided during concrete woks. These boots should be in
good condition in order to prevent any contact of concrete with workers foot.
All workers as a requirement will use protective hand gloves to protect against
sharp or rough edges, chemicals, and hot or cold surface accordingly..
Lifting equipment and carriers shall not use its full capacity to handle a load
Contractual Requirements
All safety and health which are required to fulfill by the contractor will be taken
care in accordance with the International EH & S Standards in conjunction with
clients Specification, Standards, and Instructions.
Information to Personnel
Safety and Environmental education and information to be disseminated to all
the employees in shape of seminars, safety tool box meetings and safety
refresher courses.
Emergency Procedure
First aid clinic is available at site in the hour of need. Emergency Telephone
numbers are posted and displayed on site on appropriate locations.
Rescue aids will be in place such as retrieval lines, safety harness, etc.
In the event of heat stress and strokes a fully equipped ambulance is available to
transport the victim to the nearest hospital for treatment.
Contractual Requirements
Please see the Section 3.4 above
Emergency Procedure
Please see the Section 3.6 above
Critical Works
Inspection and testing to be carried out in accordance with the approved ITP
and RC Specification (Attached ITP).
*****************************
Acknowledgement Signatures
The personnel listed below confirm receipt of the method statement and have had the contents explained to them, understand
it and are aware of the site ES&H requirements.
Name Employer Date Signature
Note to FE, CS & FCS Any significant change from this method statement requires it to be revised and resubmitted to RC
before work can commence.