Primavera P6 is the latest software package that is used for comprehensive enterprise project portfolio
management (EPPM) solutions. Primavera was founded by Primavera Systems Inc. in 1983 which is
then acquired by Oracle Corporation in 2008.
Installation of Primavera is a bit tricky but not very di cult at all. In this post I am going to share the
procedure that how one can install Primavera P6. Installation procedure is similar for Windows 7 and
Windows 8. Dont worry if you are using windows XP and other related operating systems. This
installation guide will work for each and every of famous operating systems.
First Download both the les from the link below i.e. both ths PS.iso le and MagicISO Virtual CD/DVD
manager
Run the ISO MagicDisk ISO Virtual CD/DVD Manager (Click to enlarge)
2) Wait for a while until the disk is mounted and a new window is displayed as shown below containing
all the les in the P6.iso le;
1) Double click the setup.exe le to run the Primavera P6 setup as shown; (Click Yes if systems prompts
for security assurance)
https://www.iamcivilengineer.com/2014/08/how-to-install-primavera-p6-project.html 3/13
8/1/2017 How to install Primavera P6 Project Management? | Civil Engineering Blog
2) Click Next
3) Enter EC-C01 as Product Code in the setup as shown;
https://www.iamcivilengineer.com/2014/08/how-to-install-primavera-p6-project.html 4/13
8/1/2017 How to install Primavera P6 Project Management? | Civil Engineering Blog
https://www.iamcivilengineer.com/2014/08/how-to-install-primavera-p6-project.html 5/13
8/1/2017 How to install Primavera P6 Project Management? | Civil Engineering Blog
Trending Now - 300+ Civil Engineering Interview Questions You must Prepare for
Get Prepared Now
18) If you get an error while launching Primavera P6 about Error: Couldnt Locate the language le and
a Runtime Error dont worry proceed as follows;
19) In the Login and Password enter admin in both, and hit OK
https://www.iamcivilengineer.com/2014/08/how-to-install-primavera-p6-project.html 6/13
8/1/2017 How to install Primavera P6 Project Management? | Civil Engineering Blog
20) If you get an error Licensed named users is less than con gured Named user ignore it and Hit Ok
21) You will be taken to the Primavera Home Screen as shown;
22) Go the Admin Menu at the top menu bar and click Users as shown;
https://www.iamcivilengineer.com/2014/08/how-to-install-primavera-p6-project.html 7/13
8/1/2017 How to install Primavera P6 Project Management? | Civil Engineering Blog
24) Uncheck all the checkboxes in the Named User Column and Just Check the Project Management in
the concurrent User column as shown;
I hope this installation guide for Primavera P6 will help you in installation and don't forget to share it with
your friends and give us feedback. If you have any other problem during installation comment below.
https://www.iamcivilengineer.com/2014/08/how-to-install-primavera-p6-project.html 8/13
8/1/2017 How to install Primavera P6 Project Management? | Civil Engineering Blog
Free Project Management Civil Engineering Blog: Free Gantt Chart Template Civil Engineering Blog:
Download Primavera P6 Download MS Project Fu
Civil Engineering Softwares Project Management...
Ad bitrix24.in iamcivilengineer.com Ad Gantt Excel iamcivilengineer.com
Civil Engineering Blog: Civil Engineering Blog: Civil Engineering Blog: Civil Engineering Blog:
Primavera P6 Project Unable to Connect to Performing CPM Softwares
Management Reference... Database Connection,... Calculations and...
iamcivilengineer.com iamcivilengineer.com iamcivilengineer.com iamcivilengineer.com
Civil Engineering Blog: Civil Engineering Blog: Civil Engineering Blog: Civil Engineering Blog:
Practical Civil Engineering 300+ Civil Engineering Download Engineering Download Construction
Works Questions and... Interview Questions You... Project Management by... Project Management...
iamcivilengineer.com iamcivilengineer.com iamcivilengineer.com iamcivilengineer.com
Hurry Up !!! - Just join the 10k+ fans of ours on Facebook and get real updates
Iamcivilengineer
https://www.iamcivilengineer.com/2014/08/how-to-install-primavera-p6-project.html 9/13
8/1/2017 How to install Primavera P6 Project Management? | Civil Engineering Blog
Saad Iqbal
Hi there, My name is Saad Iqbal, I am a civil engineer by profession from Pakistan. I am passionate
about structures, and blogging on the web....
Next Previous
Download Uniform Building Code (UBC) 97 full 10+ Reasons not to marry Civil Engineer
[pdf] - Civil Engineering Codes (http://www.iamcivilengineer.com/2014/08/10-
(http://www.iamcivilengineer.com/2014/08/dow reasons-not-to-marry-civil-engineer.html)
nload-uniform-building-code-ubc-97.html)
POST A COMMENT
Reply Thanks sammy actually you haven't followed step # 24, you have to uncheck all check boxes
in the rst column and check only rst check box in concurent user columns as shown in the
picture...
Reply please remove all users at Step 24 except admin. after that only check one box as
mentioned above. now it should be closed.
Reply
https://www.iamcivilengineer.com/2014/08/how-to-install-primavera-p6-project.html 10/13
8/1/2017 How to install Primavera P6 Project Management? | Civil Engineering Blog
Unable to connect to the database. Would you like to con gure the database connection now?
Reply
Kindly help me about this! This happen to popped out every time I log in. I cant proceed to step#20.
Every time I con gure the database, it always fails. Don't know what to do next.
Hello Saad,
Reply
I am so much grateful for your very helpful post. This has helped me so much in overcoming a
delay.
Hey Saad. I did what you say. but I still recieve the message "Project management - Total named
Reply
users exceed licensed maximum users." what am I going t do?
Thanks.
Reply
https://www.iamcivilengineer.com/2014/08/how-to-install-primavera-p6-project.html 11/13
8/1/2017 How to install Primavera P6 Project Management? | Civil Engineering Blog
Dear Saad
I m getting error: license le is not valid for current version,Please contact supervisor.
Regards
Muhammad Rohan
hello,
Reply
followed the above procedure step by step.
after installation when launch the program it gives license error but i ignored the error it loaded the
database and a falsh of p6 console appeard for a sec and then disappeared.
and happens everytime i run the p6.
pleasse advice me any possible solution.
regards
very helpful tips for me to launch P6, i was getting language error but now solved it. thanks buddy
Reply
Unable to connect to the database.would you like to con gure the database connection now?
Reply
Friends plz help me.. how to solve this database problem
Unable to connect to the database. Would you like to con gure the database connection now?
Reply
Kindly help me about this! This happen to popped out every time I log in. I cant proceed to step#20.
Every time I con gure the database, it always fails. Don't know what to do next.
Thanks for sharing this informative post to our vision. Its really informative.
Reply
Primavera Training in Chennai | Big Data Training in Chennai
https://www.iamcivilengineer.com/2014/08/how-to-install-primavera-p6-project.html 12/13
8/1/2017 How to install Primavera P6 Project Management? | Civil Engineering Blog
After step 20 primavera home screen pops up for a second but then crashes again.
Reply
I'm using windows 10, if that has anything to do with it. can you help?
Reply Greetings Aalam, if you are using Windows 10 than try to use the compatibility feature of
windows 10, right click the PM.exe le in the directory where you have installed primavera
after this click the properties and go to compatibility option, then try to run it as windows 7
or even Xp after this use the "Run as administrator" option to run Primavera, Hope its solves.