Beruflich Dokumente
Kultur Dokumente
1. PURPOSE:
To establish the system for the maintenance of electrical equipments and to ensure
that the equipments are available continuously for preventive maintenance.
2. SCOPE:
3. DEFINITIONS:
4. RESPONSIBILITY:
4.1 Head of department is over all responsible for implementing this procedure.
4.2 Personal performing breakdown maintenance shall not carry out preventive
maintenance.
4.3 Individual responsibilities of specific activities are described here after.
5. PROCESS INPUT:
Approved By:
Issued By: Edition No. 01
Sr.
Activity Responsibility Ref. Doc.
No.
All the equipments requiring periodic
1 maintenance will be identified and a list will Asst.Manager FQMNT02F01
be prepared.
2 A unique I.D.No. Will be given to them. Asst.Manager FQMNT02F01
The frequency of maintenance will be Operation &
decided on the basis of Maintenance
3 Asst.Manager
Manufacture recommendation Manual
Decided by maintenance Department FQMNT02F06
The P.M. schedule/P.M.Schedule cum check
4 sheet will be made as per the identified Asst.Manager FQMNT02F06
frequency above. FQMNT02F18
FQMNT02F07,
The equipment will be spared and the FQMNT02W03,
Asst.Manager/PMI/
preventive maintenance will be carried out FQMNT02W10,
5 Sr.Formen/ FQMNT02W12
as per P.M check list/ P.M.Schedule cum
Foreman FQMNT02F18,
check sheet & relevant work instruction. FQMNT02W05
The P.M. checklist / P.M.Schedule cum
FQMNT02F07,
6 check sheet will be filled up after PMI FQMNT02F18
completing maintenance.
In case of any schedule getting delayed due
to any reasons or preventive action if not
7 PMI FQMNT02F08
carried out, should be recorded in the P.M
slippage record.
Review the P.M. schedule at least Six
FQMNT02F03,
8 monthly for types of checks & frequency on Asst.Manager/PMI FQMNT02F04
the basis of its effectiveness.
Approved By:
Issued By: Edition No. 01
Sr.
Activity Responsibility Ref. Doc.
No.
Receiving work order from user department
1 Shift Incharge
regarding breakdown of any equipment.
Review the problem and allocate the job to Asst.Manager/
2
concern person. Shift Incharge
Carry out the breakdown maintenance. As Sr.Forman/ Shift
3 FQMNT02W06
per work instruction. Incharge/Foreman
Prepare daily breakdown report and sent Sr.Forman
4 FQMNT02F03
copy to Dy.GM (Mech) & GM (F&A). /Foreman
Prepare monthly breakdown report and sent
Sr.Forman
5 copy to V.P. (foils), all Deptt. Heads, MIS & FQMNT02F04
/Foreman
PPC.
7. PROCESS OUT PUTS:
7.1. Continue availability of machine.
7.2. Relevant reports & records of equipments.
7.3 P.M.Slippage Record.
Approved By:
Issued By: Edition No. 01
8. PROCESS MONITORING:
Sr.
Description Frequency Responsibility
No.
1 Review of P.M. schedule. Six monthly Asst.Manager
9. RECORDS:
Retention Disposal
Sr.No. Record No. Record Title Location
period authority
Till the Dy.
COMPREHENSIV ELECTRICAL
1 FQMNT02F01 equipment General
E EQUIPMENT SHOP FLOOR
Last Manager
LIST
EQUIPMENT Till the ELECTRICAL Dy.
2 FQMNT02F02 HISTORY equipme SHOP FLOOR, General
RECORD nt Last MSDS&ERS Manager
DAILY Dy.
Six ELECTRICAL
3 FQMNT02F03 BREAKDOWN General
Months SHOP FLOOR
REPORT Manager
MONTHLY Dy.
ELECTRICAL
4 FQMNT02F04 BREAKDOWN 1Year General
SHOP FLOOR
REPORT Manager
MAJOR
Dy.
BREAKDOWN ELECTRICAL
5 FQMNT02F05 1Year General
ANALYSIS SHOP FLOOR
Manager
REPORT
ELECTRICAL Dy.
6 FQMNT02F06 PM SCHEDULE 1Year SHOP General
FLOOR/MSDS Manager
Approved By:
Issued By: Edition No. 01
DAILY ENERGY
GENERATION Six Dy. General
13 FQMNT02F13 MSDS
/CONSUMPTION Months Manager
REPORT
CONSUMPTION OF
DIESEL
Dy. General
15 FQMNT02F15 DG LOG BOOK 1Year MSDS Manager
ELECTRICAL
POWER ELECTRICAL Dy. General
17 FQMNT02F17 1Year
CONSUMPTION SHOP FLOOR Manager
REPORT
18 FQMNT02F18 PM SCHEDULE CUM
CHECK SHEET: -
FQMNT02F18/ 01 LT air circuit breaker
FQMNT02F18/ 02 66 kv CT, PT, CVT & LA
FQMNT02F18/ 03 LT APFC panel, HT
capacitor bank & reactor
FQMNT02F18/ 04 Battery bank & battery
charger
FQMNT02F18/ 05 11 kv & 132 kv MOCB Dy. General
1Year MSDS
FQMNT02F18/ 06 11 kv T.M.G. ACB Manager
FQMNT02F18/ 07 11 kv ABB (indoor &
outdoor) & Siemens VCB
FQMNT02F18/ 08 66 kv Sf6 circuit breaker
FQMNT02F18/ 09 22 kv Sf6 circuit breaker
FQMNT02F18/ 10 11 kv, 22 kv & 66 kv
isolators
FQMNT02F18/ 11 11 kv, 1500 kva DG set
Approved By:
Issued By: Edition No. 01
10. REFERENCE :
Approved By:
Issued By: Edition No. 01