Sie sind auf Seite 1von 6

Our energy working for you.

TM

Power topic #5590 | Technical information from Cummins Power Generation

Reliability considerations in
simple paralleling applications
White Paper
By Rich Scroggins, Technical Specialist, Sales Application Engineering

Reliability in power generation Single Generators vs.


systems, defined as the probability Redundant Paralleled
that power will be available at any
Generators
point in time, is the primary reason
standby generator sets are purchased. The decision on whether to use a single generator
set or multiple paralleled generator sets will typically
Using paralleled redundant generator
be based on reliability and cost. When a decision
sets is one method commonly used is made to use paralleled generator sets there are
to enhance system reliability. many considerations that need to be addressed to
ensure a reliable system.
Redundancy traditionally has been a
requirement only in critical applications
such as data centers and hospitals
Reliability and Redundancy
where an extended loss of power The purpose of redundancy is to eliminate a single
could result in loss of life or a sub- point of failure from a system. It is well documented
that having redundant systems will make the overall
stantial financial loss, as these were system more reliable however this is always based
the only scenarios where the cost of a on the assumptions that single points of failure
redundant generator and the associ- are truly eliminated and not just moved to another
part of the system and that the controls enabling
ated paralleling switchgear could be redundancy dont introduce new failure modes
justified. The availability of lower cost which compromise reliability. Paralleled generator
power transfer devices and paralleling sets that rely on a single master control for signals to
start and to close to a paralleled bus actually replace
control systems have in recent years one failure point with two as the master control and
made redundant paralleled generators the communication link between the master and the
an attractive option in less critical generator sets each represent single points of failure.

standby power applications.


A standby generator set from a reputable
manufacturer that has been maintained properly
Paralleling Systems
and tested periodically according to manufacturers
When a decision has been made to parallel generator
recommendations is a very reliable solution. Adding a
sets there are several concerns that need to be
redundant generator with the inherent complexity of a
addressed to ensure that the system is as reliable as
paralleling system isnt necessarily going to make the
possible.
system more reliable. Investing in a reliable generator
set and a robust maintenance program so the
generator doesnt fail is often a better investment than Control System
installing a more complex system to compensate for a
failed generator set. A robust control system is critical to having a reliable
paralleling system. A control system needs to minimize
single points of failure and have fault tolerance
Total System Cost measures built in. Key factors in a paralleling control
include the following:
There are some instances where the cost of two small
generator sets will be less than the cost of one larger
Eliminate single points of failure where possible
generator set. The total installed cost of the system is
The most effective way to eliminate single points
often overlooked in basic standby applications. There
of failure in a control is to use distributed logic and
are many factors which need to be evaluated beyond
control rather than centralized control. Critical control
the cost of the generator sets.
functions such as generator starting, bus voltage
sensing, synchronizing and closing to the bus should
Foundation: A larger generator set may require
be executed by individual generator set controls rather
additional structural support as the weight of
the generator set will be concentrated on one than a master control. This way the system will have
spot, however smaller generator sets may require redundancy in critical control functions in addition to
pouring multiple concrete slabs. having redundant generators and the single point of
failure is eliminated.
Space requirements: Multiple generator sets
and their associated switchgear will take up more
Generator starting: In a simple standby isolated
space than a single larger generator set although
bus paralleling application the start signal is sent
the smaller generator sets offer greater flexibility as
directly from the transfer switches that sense the
individual generator sets can be maneuvered into
utility failure to the generator sets. Sending the
smaller spaces than a larger set.
signal through a master control adds no value and
Cabling: Smaller generator sets enable the use introduces an unnecessary failure mode.
of smaller cable and easier termination however
Paralleling bus voltage sensing: For reliable
paralleled generator sets will require additional
paralleling each generator must sense the bus
cable runs which will be labor intensive, particularly
voltage independently rather than rely on a signal
if cable is run underground.
from a separate control
Commissioning costs: Startup and testing costs
Closing to a dead bus: Generator controls should
of paralleled generator sets are substantially higher
determine when to close their paralleling breaker
than those costs for a single generator set.
to the bus. To provide the fastest and most reliable
Maintenance costs: Replacement parts for service to a dead bus generators must arbitrate
smaller generators will be less expensive than between each other so that only one generator
replacement parts for a larger generator however closes to the bus. Waiting for a permissive signal
that difference is more than offset by the labor from a master slows the system down and adds an
costs of maintaining two generators and switchgear unnecessary failure mode
rather than one single generator set.
Synchronizing and closing to a live bus:
Capital investment: When the power demanded Generator sets synchronize reliably and quickly
at a facility is expected to increase in the future when there is no other control in the loop. External
initial capital investment can be minimized in controls adjusting bias lines or otherwise interfering
some cases by installing a smaller generator with with the synchronizing algorithm introduce
02 | Power Topic #5590

the intent of adding paralleled generators in the unnecessary complexity into the system.
future as demand increases rather than installing
a single larger generator that is oversized for the
load. This will need to be balanced against the
future investment required to add generators and
switchgear and other required facility modifications.
SIMPLE LOAD ADD SCHEME WITH TWO LEVELS

Transfer
Inhibit
Paralleling Paralleling
Breaker Breaker
Auxiliary Auxiliary Non-Emergency ATS
Contact Contact

Generator Set 1 Generator Set 2


Figure 1: Implementing a load add function.

Load add and load shed A load shed scheme is required so that when
Load add and load shed schemes are used to make generators are overloaded the non-critical loads can
sure that there is always sufficient capacity to serve be taken off line so that there will be sufficient capacity
the most critical loads. Two levels of load add (one to serve the critical loads. Most paralleling generator
level for emergency loads and one level for all other set controls have a load shed or load dump output
loads) and one level for load shed (emergency loads which can be connected to the load shed input of the
are never shed) is sufficient for most simple, isolated transfer switches that serve the non-emergency loads
bus paralleling applications. This can be implemented (Figure 2). This will take the non-emergency loads off
without the use of a master control. A master control line in the event that the generator sets are overloaded.
may be required for additional levels of load add/shed. Note that to properly shed load transfer switches must
Although a master control can present a single point of be three position switches with center-off positions.
failure the system can be designed so that failure of the
master will not impact the most critical loads. Isochronous vs. droop load sharing
Most load sharing systems today are isochronous,
A load add scheme is required in a paralleling system meaning that the voltage and frequency are held constant
when a single generator is not large enough to carry all however there are still controls being produced that use
of the loads in the system. A simple load add scheme droop load sharing, which allow voltage and frequency
with two levels can be implemented using the inhibit to vary with load. Droop load sharing controls were once
function of the non-emergency load transfer switches popular because they allowed generator sets to parallel
and the aux contacts of the genset paralleling breakers with each other without communicating with each other.
(Figure 1). Emergency load transfer switches should Due to the variation of frequency and voltage with a
not be inhibited and should close to the bus as soon droop paralleling system the quality of power provided
as it is live. Non-emergency transfer switches can be to the load typically is not very good and may not be
inhibited until all of the generator sets come on line. suitable for some electrical equipment. Isochronous
load sharing is the appropriate technology to use.

IMPLEMENTING A LOAD SHED FUNCTION

Load
Shed
Load Load
03 | Power Topic #5590

Dump Dump
Contact Contact Non-Emergency ATS

Generator Set 1 Generator Set 2

Figure 2: Most paralleling generator set controls have a load shed or load dump output which can be connected to the load shed input of the transfer
switches that serve the non-emergency loads.
Random access paralleling vs. exciter paralleling Contactors that are not listed to a standard for
Random access paralleling refers to a system in which paralleling equipment may not be suitable for a
the first generator at rated speed and voltage closes to paralleling application as they may not have been
the dead bus and then all the other generators actively evaluated for safety when subjected to the higher
synchronize and close to the bus. Random access levels of fault currents present in a system with
paralleling is the most reliable paralleling method and paralleled sources.
is most commonly used in critical applications. A
less expensive paralleling method known as exciter Contactors that are components in UL 1008 listed
paralleling is used in some paralleling applications. transfer switches may not be suitable as a power
In an exciter paralleling system all of the generators transfer device in a paralleling application. UL 1008
start with their paralleling breakers closed and their recognizes and lists the entire switch mechanism,
excitation circuits de-energized. When the generators not the individual contactor. The individual contactor
start they are connected to the bus but produce no has not been type-tested according to the UL
voltage. When all generators reach starter disconnect requirements and does not carry the UL listing
speed their excitation circuits are energized and the separate from the transfer switch mechanism. In
generator bus voltage ramps up with the generators addition, UL 1008 lists switches that transfer loads
forcing each other into sync. Because exciter paralleling between sources but does not test or recognize
systems will not work until all generators either reach devices that parallel between two live sources.
disconnect speed or are locked out they are not used Because of these two factors it is not appropriate to
in critical applications. Random access paralleling with apply the UL 1008 standard to contactors that are
active synchronization should always be used when used to parallel between two live sources.
paralleling gensets in critical applications.

Fault tolerance manual mode


Installation Considerations
A key consideration in assessing the reliability of a
Installing and commissioning paralleled generator
system is the ability of the system to operate when
sets is not a simple process. A qualified manufacturer
certain components have failed. Having a pre-defined
will have experience with protective relaying,
sequence of operations for a user to follow in a worst
system grounding, and other paralleling issues
case scenario to manually provide power to loads
beyond the generator set functionality. Working
is often a requirement in critical applications. A user
with a manufacturer who has substantial paralleling
should be able to manually start generators, initiate
experience over a wide range of applications and
synchronization and close paralleling breakers. Manual
will assume responsibility for a correct installation is
operation does not mean that the generator control
a key to a successful project even in the most basic
is not operating. It means only that functions are
paralleling application. There are several considerations
user initiated rather than system initiated. All system
that an experienced installer will address.
protection functions will still be active. The control will
not allow a paralleling breaker to close if the generator
Selective coordination
and the paralleling bus are not in phase with each other.
The National Electrical Code requires selective
coordination for emergency and legally required loads.
Product Standards Any downstream breakers must coordinate with
upstream overcurrent protection such as paralleling
Consulting engineers in the US consistently specify breakers or a genset mounted breaker. Coordinating
that paralleling switchgear must be rated to UL 891 with a generator set mounted Molded Case Circuit
or UL 1558. These standards ensure that industry Breaker (MCCB) with an instantaneous trip will be
safety guidelines are being followed and that the power very difficult and will require in most cases that the
transfer and protective devices and bussing have all downstream breakers are supplied from the same
been appropriately evaluated as a system for safety breaker manufacturer as the genset mounted MCCB.
under fault conditions. It is much easier to coordinate with a power breaker
as is most often used in paralleling switchgear as
Power transfer devices must also be rated they are typically equipped with programmable trip
04 | Power Topic #5590

appropriately for the paralleling application. UL 891 unit specifically for the purpose of coordination.
and UL 1558 specify circuit breakers listed to UL 489 When the generator control includes integral, UL
(in the case of UL 891) or UL 1066 (in the case of UL listed overcurrent protection, coordination between
1558) for overcurrent protection and the breakers the genset and the paralleling breaker is simplified
are typically used for power transfer as well as for because the overcurrent trip curve is optimized to
protection. Draw out breakers are specified in critical allow the maximum permissible time delay while still
applications such as hospitals and data centers, protecting the alternator.
allowing operators to isolate faults and facilitate
inspection and testing of breakers and easily replace
breakers if necessary.
Separation of circuits The contractor and consulting engineer must have
The National Electrical Code requires that Emergency, a clear definition of what is included in the scope of
Legally Required and Optional loads are separated supply for each part of the system. Dividing scope
from each other. With paralleled generator sets of supply wont be limited to equipment but will also
that means that the Emergency, Legally Required include assignment of responsibility for meeting code
and Optional loads must be fed from the generator requirements like selective coordination and separation
paralleling bus by separate breakers in separate of circuits, system testing and start up and ongoing
compartments or sections in the switchgear line up. maintenance and service. Having the same entity
responsible for supply, commissioning and maintenance
Isolation of generators from the paralleling bus helps promote an efficient maintenance program.
To enable maximum reliability and safety there must
be means to individually disconnect each generator
from the paralleling bus located at the paralleling
Service and Support
switchboard. Without this disconnecting means,
One of the first questions that should be asked when
typically an incoming breaker, a fault on one generator
choosing a supplier of a paralleling system is how will
can make all generators inoperable and all generators
the system be supported in the future? Paralleling
will have to be locked out to do maintenance work
systems include engines, alternators, controls,
on any generator in compliance with NFPA 70E Lock
switchgear and transfer switches and properly
out tag out requirements (Figure 3). Without this
supporting all of this equipment requires a diverse
disconnecting means much of the value of having a
skill set. Some suppliers only have experience with
redundant generator will be lost.
one component in a system and will need to involve
DISTRIBUTION PANEL NO INCOMING BREAKER other companies to troubleshoot problems that arise.
Working with a supplier that has a proven track record
of designing, installing and maintaining complete
paralleling systems is the best way to ensure reliable
G operation over the life of the system. Questions to ask
include

Have the service technicians been trained and


certified by the manufacturer on all components
G of the paralleling system? Claims that an engine
dealer technician can service a paralleling system
should be viewed with skepticism.
Distribution Panel Have the service technicians been certified with
Figure 3:
the make and model of engines being used in
the application? Suppliers that use engines from
Ten second start requirement different manufacturers may require different
The National Electrical Code requires that emergency service organizations to support systems within the
loads are served within ten seconds of a utility failure. same geographical region.
As ten seconds isnt enough time to start, synchronize
Does the service organization offer comprehensive
and close multiple generator sets this requirement
maintenance programs for the entire system?
means that each of the generator sets in the system
must be large enough to carry all of the emergency Does the service organization have a demonstrated
loads on its own. For example, a system of three history of supporting paralleling systems in many
paralleled 600 kW generator sets will not meet the different types of applications?
NEC requirement if the emergency load exceeds What is the availability of replacement parts? Power
600 kW. To meet this requirement the sequence of transfer devices will often need to be replaced after
operations should not require any interaction with faults. Replacing a proprietary contactor rather than
a master controller. All control functions should be a paralleling circuit breaker can result in a system
carried out independently by the generator and the being down for significant period of time. Replacing
a proprietary component with a standard one may
05 | Power Topic #5590

transfer switch controls with no communication


not be acceptable if the new device isnt listed for
required other than a genset start command.
use with the existing overcurrent protection.
Supplier of distribution switchboard Ifa control needs to be replaced is custom
Sourcing the generator and paralleling controls programming required for the replacement control
separately from the switchboard complicates a project. and who is authorized to do the programming?
What is the time frame for replacing the control?
About the author
Rich Scroggins is a Technical Specialist in the switches, switchgear controls and networking and remote
Application Engineering group at Cummins monitoring products and has developed and conducted
Power Generation. Rich has been with Cummins seminars and sales and service training internationally on
for 18 years in a variety of engineering and several products. Rich received his bachelors degree in
product management roles. Rich has led product electrical engineering from the University of Minnesota
development and application work with transfer and an MBA from the University of St. Thomas.

Scalability Conclusions
Paralleling systems are frequently expanded after The decision on whether to provide backup power
they are put into service to accommodate increasing with a single generator set or with redundant paralleled
power demands. The ability to add a generator set generator sets will be based on reliability and cost. The
and the associated switchgear in the future should key question is does the redundancy coupled with the
always be considered. The system should have the added complexity of a paralleling system increase the
flexibility to allow generator sets from a different system reliability enough to justify the additional cost?
manufacturer to be added in the future. Being locked When a decision has been made to parallel generator
in to a certain manufacturer limits flexibility for future sets there are several considerations that need to be
expansions. Additional question to ask concerning addressed to maximize the reliability of the system.
expansion include:
Thecontrol system should be designed with critical
Are the generators properly isolated so that functions distributed to the individual generator
new generators can be added without taking controls to minimize single points of failure
the facility off line?
Thecontrols should have fault tolerance provisions
What is involved in modifying the control for such as load shed and manual operating modes.
expansion?
The installation must meet code requirements for
Ifa different manufacturers generators are used coordination, separation of circuits and ten second
for the expansion what will be required for the service to emergency loads and must allow proper
generators to parallel properly? isolation of the generator sets.
Does the manufacturer have experience Thesystem must be supported by an organization
implementing field expansions, including with a proven track record for servicing complete
expansions that include generators from other paralleling systems.
manufacturers.
How can the system be modified to support For additional information about onsite power systems
utility paralleling if that is required in the future? or other energy solutions, visit power.cummins.com.

06 | Power Topic #5590

power.cummins.com

2013 Cummins Power Generation Inc.


All rights reserved. Cummins Power Generation
and Cummins are registered trademarks of
Cummins Inc. Our energy working for you.
is a trademark of Cummins Power Generation.
GLPT-5590-EN (09/13)

Das könnte Ihnen auch gefallen