TRADITIONAL METHOD OF PROCUREMENT COMPETITIVE BIDDING-ALSO KNOWN AS SINGLE STAGE TENDERING: DESIGN COMPLETED SIGNIFICANTLY QUANTITY SURVEYOR PRODUCES BOQ PUT TO TENDER.SELECTIVE BIDDERS (WITH PRE REQUISITE EXPERIENCE) ON BEING AWARDED, MAIN CONTRACTOR PUTS OUT REQUESTS FOR SUB CONTRACTORS AND MATERIALS ALTERNATIVELY ARCHITECT MAY NOMINATE THEM IN ADVANCE. HELPS REDUCE DELAYS DUE LEAD TIME FOR SUPPLY OF EQPT ETC.. TENDER PREPARATION PROCESS PREPARATION OF SOUND TENDER DOCUMENTS PROCESS OF DEVELOPING TENDER DOCUMENT FOR DIFFERENT TYPES OF CONTRACTS TENDER CONTENT & LEGAL SANCTITY RIGHTS & OBLIGATIONS IN TENDERING PROCESS PREPARATION OF TENDER DOCUMENTS PRE BID CONFERENCE & SITE INVESTIGATIONS PREPARATION OF SOUND TENDER DOCUMENTS INSTRUCTIONS TO TENDERERS GENERAL CONDITIONS (GCC) SPECIAL CONDITIONS (SCC) BILLS OF QUANTITIES CONTRACT DRAWINGS SITE DATA & GEOTECHNICAL DATA INSTRUCTIONS TO TENDERERS (1) INTRODUCTION BID DEPOSIT/SECURITY AND ISSUING OF BID DOCUMENTS DOCUMENT & DETAILS TO ACCOMPANY BID MINIMUM VALIDITY PERIOD OF BID SCHEDULE OF PRICES CORRECTION OF ERRORS PERFORMANCE BOND/PAYMENT BONDS FORMS/CERTIFICATES-SAMPLES ARBITRATION INSTRUCTIONS TO TENDERERS (2) PROJECT DELIVERY & MODE OF PAYMENT PRE BID CONFERENCE SEALING MARKING AND CLOSING OF BID WHAT DATE AND TIME-RECEIPT OF BIDS? WHAT DATE, TIME AND PLACE-OPENING OF BIDS PERIOD-EVALUATION OF BIDS POWER TO ACCEPT OR REJECT OFFERS NOTICE OF ACCEPTANCE LETTER OF INTENT GENERAL CONDITIONS (GCC) ? STANDARD DOCUMENT-NOT SPECIFIC TO ANY CONTRACT. TRIED & TESTED. GOVT. DEPTS (CPWD, PWD, DMRC, DDA, IOCL, NHAI, INDIAN RAILWAYS) HAVE THEIR OWN GCCINSTRUCTIONS TO TENDERERS? GCC NORMALLY SPELLS OUT:- RESPONSIBILITY & OBLIGATIONS OF PARTIES TO CONTRACT SCOPE & PERFORMANCE OF CONTRACT, VALUATION AND PAYMENT TERMS LABOUR LAWS, STATUTORY REQUIREMENTS, ARBITRATION, SAFETY CODE, STANDARD FORMS, DEEDS ETC. MOST GOVT. DEPTS USE CPWD GCC. TREND INCREASING TO USE FIDIC SPECIAL CONDITIONS (SCC) ? SCC CONTAINS AMENDMENTS/ADDITIONS/CHANGES IN GCC SCC MAKES IT SUITABLE FOR PARTICULAR PROJECT. IN CASE OF AMBIGUITY/CONFLICT WITH GCC, SCC PREVAILS COMMONLY CONTAINS: MATERIALS PROVIDED BY OWNER MOBILISATION ADVANCE EQUIPMENT ADVANCE SECURED ADVANCE AGAINST MATERIALS RECEIVED AT SITE RETURN OF ADVANCE DATE OF COMMENCEMENT OF CONSTRUCTION REQUIREMENT OF VARIOUS DOCUMENTS/PROGRESS REPORTS BILLS OF QUANTITIES BOQ SHOWS DESCRIPTION AND NET QUANTITY TO BE EXECUTED IN EACH ITEM OF WORK ITEMS CLASSIFIED INTO: SITE DEVELOPMENT & EARTHWORK FOUNDATION & SUB STRUCTURE SUPERSTRUCTURE, BRICKWORK/MASONARY WORK FLOORING & STONEWORK JOINERY PAINTING AND FINISHING STRUCTURAL STEEL AND ALUMINIUM WORK SEWAGE, SANITARY, DRAINAGE,WATER SUPPLY ELECTRIFICATION MISCELLANEOUS CONTRACT DRAWINGS? MOST IMPORTANT DOCUMENT-PHYSICALLY, QUANTITATIVELY AND VISUALLY COMMUNICATES TO CONTRACTOR PROJECT DESCRIPTION DRAWINGS ARE CLASSIFIED INTO: SITE DRAWINGS ARCHITECTURAL DRAWINGS COORDINATED STRUCTURAL DRAWINGS HVAC & OTHER SERVICES DRAWINGS (FIRE FIGHTING, BUILDING AUTOMATION) ELECTRICAL DRAWINGS SPECIFIC DETAILS GENERAL ARRANGEMENT DRAWING ARE IMPORTANT BEFORE GOOD FOR CONSTRUCTION (GFC) DRAWINGS ARE PREPARED AND ISSUED BY THE ARCHITECT. GFC DRAWINGS ARE A PRE REQUISITE FOR LUMP SUM BIDS. SITE DATA SITE SPECIFIC DETAILS TO ENABLE CLEAR VISUALISATION OF CHALLENGES AND OPPORTUNITIES: OVERHEAD, AT SURFACE & UNDERGROUND SERVICES ACCESS/LAND ISSUES ENVIRONMENTAL PROBLEMS OR RESTRUCTIONS PHYSICAL/OPERATIONAL CONSTRAINTS POLITICAL/DISTURBING ELEMENTS SPECIAL WEATHER CONDITIONS/WORKING SEASON SPECIAL TERRAIN ISSUES GEOTECHNICAL DATA GEOTECHNICAL INVESTIGATIONS ARE PERFORMED BY GEOTECHNICAL ENGINEERS OR ENGINEERING GEOLOGISTS TO OBTAIN INFORMATION ON THE PHYSICAL PROPERTIES OF SOIL AND ROCK AROUND A SITE FOR: DESIGN EARTHWORKS AND FOUNDATIONS FOR PROPOSED STRUCTURES AND FOR REPAIR OF DISTRESS TO EARTHWORKS AND STRUCTURES CAUSED BY SUBSURFACE CONDITIONS. GEOTECHNICAL INVESTIGATIONS ARE ALSO USED TO MEASURE THE THERMAL RESISTIVITY OF SOILS OR BACKFILL MATERIALS REQUIRED FOR UNDERGROUND TRANSMISSION LINES, OIL AND GAS PIPELINES, RADIOACTIVE WASTE DISPOSAL, AND SOLAR THERMAL STORAGE FACILITIES. GEOTECHNICAL DATA A GEOTECHNICAL INVESTIGATION WILL INCLUDE SURFACE EXPLORATION AND SUBSURFACE EXPLORATION OF A SITE. SOMETIMES, GEOPHYSICAL METHODS ARE USED TO OBTAIN DATA ABOUT SITES. SUBSURFACE EXPLORATION USUALLY INVOLVES SOIL SAMPLING AND LABORATORY TESTS OF THE SOIL SAMPLES RETRIEVED. TO OBTAIN INFORMATION ABOUT THE SOIL CONDITIONS BELOW THE SURFACE, SOME FORM OF SUBSURFACE EXPLORATION IS REQUIRED. METHODS OF OBSERVING THE SOILS BELOW THE SURFACE, OBTAINING SAMPLES, AND DETERMINING PHYSICAL PROPERTIES OF THE SOILS AND ROCKS INCLUDE TEST PITS, TRENCHING (PARTICULARLY FOR LOCATING FAULTS AND SLIDE PLANES), BORING, AND IN SITU TESTS. OBLIGATIONS OF CONTRACTOR NON RELEASE OF DRAWINGS, SPECS AND OTHER DOCUMENTS TO THIRD PARTY THE CONTRACTOR WITHOUT THE CONSENT OF EMLOYER OR HIS REPRESENTATIVE. ONE COPY OF THE DRAWING TO BE KEPT BY THE CONTRACTOR ON THE SITE. SHALL MAKE IT AVAILABLE TO EMPLOYER OR HIS REPRESENTATIVES AT ALL REASONABLE TIME FOR INSPECTION. CONTRACTOR MUST CARRY OUT WORKS ACCORDING TO ANY SUPPLEMENTARY DRAWINGS OR SPECIFICATIONS ISSUED BY THE EMPLOYER OR ITS REPRESENTATIVE. ANY WORKS DESIGNED BY THE CONTRACTOR MUST BE SUBMITTED TO THE EMPLOYER AND GET APPROVED BEFORE EXECUTION. SUCH APPROVAL SHALL NOT RELIEVE THE CONTRACTOR OF ANY OF HIS RESPONSIBILITIES UNDER THE CONTRACT OBLIGATIONS OF CONTRACTOR THE O & M MANUAL & DRAWINGS OF COMPLETED PERMANENT WORKS MUST BE SUBMITTED TO THE EMPLOYER FOR THE LATTERS APPROVAL AND USE. CONTRACTOR SHALL CARRY OUT THE WORKS AND REMEDY ANY DEFECTS THEREOF WITH UTMOST CARE AND DILIGENCE. THE CONTRACTOR SHALL PROVIDE ALL MATERIALS, PLANTS AND WORKMANSHIP AS SPECIFIED IN THE CONTRACT AND IN ACCORDANCE WITH THE INSTRUCTION OF THE EMPLOYERS REPRESENTATIVE. THE CONTRACTOR SHALL SUPPLY NECESSARY ASSISTANCE, LABOR, ELECTRICITY, FUELS, APPARATUS AND INSTRUMENTS FOR THE PURPOSE OF TESTING AS REQUIRED BY THE EMPLOYER AT THE PLACE OF MANUFACTURE, FABRICATION OR PREPARATION, OR ON THE SITE OR AT SUCH OTHER PLACES AS SPECIFIED IN THE CONTRACT. COST OF SAMPLES AND COST OF TESTS CLEARLY INTENDED OR PROVIDED FOR IN THE CONTRACT SHALL BE BORNE BY THE CONTRACTOR. OBLIGATIONS OF CONTRACTOR THE CONTRACTOR SHALL AGREE TO TIMING AND PLACE OF TEST PROVIDED EMPLOYER HAS NOTIFIED AT LEAST 24 HOURS BEFORE SUCH TEST(S). ALSO THE CONTRACTOR SHALL OBTAIN NECESSARY PERMISSION FOR THE EMPLOYER OR ITS REPRESENTATIVES ACCESS TO PLACES OTHER THAN CONTRACTORS TO CARRY OUT SUCH TESTS. THE CONTRACTOR SHALL NOT COVER UP OR PUT OUT OF VIEW ANY WORKS WITHOUT GIVING NOTICE TO THE EMPLOYER FOR INSPECTION AND SUBSEQUENT APPROVAL OF THE EMPLOYERS REPRESENTATIVE. IN BREACH OF THIS RESPONSIBILITY, THE CONTRACTOR SHALL, AT HIS COST, OPEN UP THE WORKS AS DEMANDED BY THE EMPLOYER. CONTRACTORS RIGHTS TO OBTAIN 2 COPIES OF THE DRAWINGS AND SPECIFICATION. TO EXTENSION OF TIME OR PROVISION OF COST IF ANY DELAY IN DELIVERY OF DRAWING OR INSTRUCTION FROM THE EMPLOYER DUE TO EMPLOYERS NEGLIGENCE. IF THE EMPLOYER OR ITS REPRESENTATIVE INSTRUCTS THE CONTRACTOR TO CARRY OUT ANY TEST WITHOUT THEIR PRESENCE, THEN THE RESULTS OF SUCH TEST MUST BE ACCEPTED BY THE EMPLOYER. TO OBTAIN NOTICE OF ANY DELEGATION OF TESTING AND INSPECTION TO ANY THIRD PARTIES BY THE EMPLOYER. TO RECEIVE PAYMENT/ADVANCE FROM TIME TO TIME AS SPECIFIED CONTRACTORS RIGHTS ISSUE NOTICE FOR MATERIAL BREACH OF CONTRACT BY EMPLOYER SUBMIT CLAIMS DUE TO CHANGE IN SCOPE OR INACTION BY EMPLOYER CAUSING LOSS OF TIME OR MONEY AFTER DUE NOTIFICATION SUSPEND WORK/DELAY WORK AFTER DUE NOTICE DUE TO NON FULFILMENT OF EMPLOYERS OBLIGATIONS OBTAIN EXTENSION OF TIME AND/OR COST FOR DELAY CAUSED BY EMPLOYER EMPLOYERS OBLIGATIONS SUPPLY COPIES OF THE DRAWINGS AND SPECIFICATION TO THE CONTRACTOR AS PROVIDED IN CONTRACT PROVIDE UNEMCUMBERED ACCESS TO LAND AS PER CONTRACT ISSUE MATERIALS OR EQUIPMENT AS PER CONTRACT, IF ANY. OBTAIN ENVIRONMENTAL/FOREST ANY OTHER APPROVAL/CLEARANCE FROM APPROPRIATE AUTHORITY AGREE TO TEST RESULTS IF INSTRUCTED THE CONTRACTOR TO CARRY OUT ANY TEST WITHOUT HIS PRESENCE. GIVE NOTICE OF ANY DELEGATION OF TESTING AND INSPECTION TO ANY THIRD PARTIES. EMPLOYERS OBLIGATIONS RESPOND TO NOTICES BY THE CONTRACTOR OF ANY DELAY OR DISRUPTION DUE TO SOME DRAWING OR INSTRUCTION FROM THE EMPLOYER. DETERMINE TIME EXTENSION OR COST PROVISION FOR ANY DELAY IN PROVIDING NECESSARY DRAWING OR INSTRUCTION. INSPECT AND MEASURE WORKS WITHOUT UNREASONABLE DELAY ONCE THE CONTRACTOR GIVES NOTICE OF READINESS OF THE WORK OR PART OF IT FOR INSPECTION AND MEASUREMENT. APPROVE RATES FOR EXTRA WORK ORDERED AS PER CONTRACT MAKE TIMELY PAYMENTS FOR WORK DONE SATISFACTORILY. ISSUE ADVANCES AS PROVIDED IN CONTRACT. EMPLOYERS RIGHTS RECEIVE NOTICE OF ANY DELAY OR DISRUPTION OF WORK. REJECT ANY WORK OR MATERIAL IF FOUND DEFECTIVE AFTER TESTING .(GIVE REASONS FOR SUCH REJECTION.) DELEGATE INSPECTION AND TESTING TO ANY THIRD PARTY. DECIDE ON ANY ADDITIONAL TESTS OTHER THAN THE ONES PROVIDED IN THE CONTRACT. DECIDE WHETHER SUCH TESTS WOULD WARRANT TIME EXTENSION OF COST PROVISION. ACCESS AND INSPECT WORKS ANY TIME WITH A 24- HOUR NOTICE TO THE CONTRACTOR. ISSUE INSTRUCTION TO REMOVE, REPLACE MATERIALS OR PLANTS OR WORKMANSHIP IF HE THINKS THEY ARE NOT IN ACCORDANCE WITH THE CONTRACT. EMPLOY AND PAY OTHER PERSONS TO CARRY OUT THE ABOVE IF THE CONTRACTOR IS IN DEFAULT TO OBEY THE INSTRUCTIONS. EMPLOYERS RIGHTS REJECT PAYMENT ON ACCOUNT OF WORK FOUND UNSATISFACTORY IMPOSE LIQUIDATED DAMAGES AS STIPULATED IF WORK NOT COMPLETED AS PER CONTRACTUAL TIME FRAME RECOVER PAYMENTS MADE EARLIER BY MISTAKE GET WORK COMPLETED AT RISK AND COST OF CONTRACTOR IF HE FAILS TO DO SO. TAKE OVER WORKS SUBSTANTIALLY COMPLETED BEFORE DATE OF COMPLETION STIPULATED IN CONTRACT TERMINATE THE CONTRACT IN CASE OF MATERIAL BREACH BY CONTRACTOR AS PROVIDED IN THE CONTRACT