C.E.1.1 INTRODUCTION:
C.E.1.1.2 INSTITUTION:
COLLEGE: Department of Mechanical Engineering,
District: Buldhana,
State: Maharashtra
India
It is widely accepted that fossil fuels will be exhausted due to its fast
continual usage. Therefore, advancement in green and clean energy is
initiated by many countries. Renewable energy sources, like solar, wind,
sea, geothermal, and biomass are the far better options. In this project,
solar and wind energy are considered as better available resources.
Also, both the energy sources are easily available in our surrounding
area. This project is most useful for rural areas where continuous
power supply is a big question for government authorities. That is why
we took this project as challenge.
C.E.1.2 PROJECT BACKGROUND
C.E.1.2.1 OBJECTIVE:
Project leader
C.E.1.3.1
Extensive research and Study were made for the design of windmill and
solar panels, material selection for windmill and its parts with the help
of Internet and various text books in library.
C.E.1.3.3
C.E.1.3.4
C.E.1.3.5
C.E.1.4.1
C.E.1.4.4 The photovoltaic cell was installed on another platform and its
output supply was connected with the windmill generator output.
C.E.1.4.5 The cell array output was about 17 volts and windmill output
was about 13- 16 volts, which was sufficient for battery charging.
Image 1.4.4: photovoltaic cell
1. Rotor
Diameter 1.62 meter
Swept area 2.62 m2
Direction of rotation Clockwise
Numbers of blades 3
2. Tower
Height 2.90 meter
3. Operational data
Cut in wind speed 3 kmph
Rated wind speed 7 kmph
Cut of wind speed 18 kmph
4. Voltage produced
At 50 rpm 12 volts
At 100 rpm 16 volts
Cut of wind speed 18 kmph
Water pumping sets for micro irrigation and drinking water supply
Community radio and television sets
Railway signaling equipment
Battery charging
Street lighting
C.E.1.7 Summary: