Beruflich Dokumente
Kultur Dokumente
++
COURT OF APPEAL
ANZ BANKING GROUP LTD (ACN 005 357 522) First Applicant
IAN MENZIES CARSON Second Applicant
DAVID LAURENCE MCEVOY Third Applicant
SIMON GUY THEOBOLD Fourth Applicant
________________________________________________________________________________
Court of Appeal
459 Lonsdale Street, Melbourne, Vic, 3000
4GVTKGXGFHTQO#WUV.++QP,WN[CV 8GTKH[XGTUKQP
5KIPGFD[#WUV.++
---
---
COSTS Civil Procedure Act 2010 Statutory regime Overarching obligations of parties and legal
practitioners Application for leave to appeal against refusal to order security for costs Whether
failure by legal practitioners to use reasonable endeavours to ensure that the costs incurred in the
proceeding were reasonable and proportionate Section 24 Whether parties over represented by
counsel Whether application books unnecessarily voluminous Whether Indemnity costs order
appropriate Sanctions for breach of obligations Nature of costs orders that may be made.
---
For ANZ Banking Group Ltd Mr A C Archibald QC and Herbert Smith Freehills
Mr M N Connock SC with
Dr M D Rush
For Ian Menzies Carson & Ors Mr A C Archibald QC and Herbert Smith Freehills
Mr M N Connock SC with
Dr M D Rush
________________________________________________________________________________
Court of Appeal
459 Lonsdale Street, Melbourne, Vic, 3000
4GVTKGXGFHTQO#WUV.++QP,WN[CV 8GTKH[XGTUKQP
5KIPGFD[#WUV.++
REDLICH JA
PRIEST JA
MACAULAY AJA:
appeal from orders of Whelan J in which he had set aside the order of an Associate
Justice for security for costs, we requested the parties to address the question
whether in the conduct of the leave application there had been a breach by any party
of their overarching obligation under the Civil Procedure Act 2010 (the Act) to use
reasonable endeavours to ensure that the costs incurred in the proceeding were
reasonable and proportionate to the complexity and importance of the issues and the
sums in dispute.1 These reasons are concerned with that question. It has been
necessary to consider the nature and extent of that obligation within the structure
and purposes of the Act and the sanctions available to the Court in the event of non-
whether the obligation was breached by any party or their legal practitioners. First,
whether there was any over representation of a party by counsel and second,
whether the material produced on the hearing of the application for leave to appe al
Background
2 The applicants sought leave to appeal, and if leave was granted, the
determination of the appeal, from the orders of Whelan J (as his Honour then was)
made 31 August 2012. His Honour had granted leave and allowed the appeal setting
aside the orders of Efthim AsJ that the respondents provide security for the costs of
the applicants in proceedings that had been commenced in the Commercial and
Equity Division of the Supreme Court. The application for leave to appeal was heard
in one day, there being five senior counsel, six junior counsel and five firms of
solicitors representing the parties. The applicants, ANZ and the receivers, were
represented by two senior counsel and one junior, Yara by two junior counsel,
Apache by senior and junior counsel, Mr Oswal by senior and junior counsel and
Mrs Oswal by senior counsel. Different firms of solicitors represented each party. 2
In addition to the notices of appeal and the parties written cases, the parties between
them filed six lever arch folders of material (the application books).
3 The applicants ANZ and the receivers had sought security for their costs in
the amount of $86,361.00; and the applicants Apache and Yara, security in the
amount of $31,808.20 from the first respondent. The receivers, who are also
4 Having regard to the nature of the application, the amount of security sought,
the volume of material filed on the application and the degree to which the parties
were represented, and in pursuance of the courts obligation to give effect to the
overarching purpose of the Act,3 the Court sought submissions from the parties
pursuant to s 29(2)(b) of the Act directed to the question whether any of them had
failed to meet their obligations under the Act to use reasonable endeavours to ensure
5 The statutory regime and the obligations that are imposed by the statute have
enforcement of the overarching obligations under the Act has been so little traversed,
there is presently little to guide judicial officers as to the extent of the Courts powers
and the means by which parties or their legal representatives can be pe nalised for
any contravention. We have thus addressed some of these issues at greater length
consideration.
2 At the hearings before Whelan J and Efthim AsJ there was a very similar, though not
identical, level of representation.
3 Section 8 of the Act.
6 The reforms introduced by the Act are described in Williams Civil Procedure as
breaking new ground in Australia and putting Victoria at the forefront of civil
justice reform throughout the common law world.4 The Acts purpose was to
reform and modernise the laws, practice, procedure and processes relating to civil
proceedings in Victorian courts. The need to ensure that costs were reasonable and
proportionate was a core objective of these civil procedure reforms. In respect of the
overarching obligation provisions discussed below, the Act largely adopted the
recommendations of the Victorian Law Reform Commission in its Civil Justice Report,
published in May 2008.5 That Report was itself heavily influenced by Lord Woolfs
review of the civil justice system in England and Wales, in which he concluded that
7 In the second reading speech to the Act, the Attorney-General stated that the
purpose of the reforms was to make the essential goals of the civil justice system
quickly and easily ... once again more achievable.7 The Attorney-General went on to
say:
I note recent judicial statements criticising the costs charged by some lawyers
as being disproportionately high in comparison to the amounts in dispute, as
well as urging lawyers to focus on resolving disputes, rather than attempting
to win at all costs. Under the civil procedure reforms, these kinds of
behaviours will need to change.
4 LexisNexis Butterworths, Civil Procedure: Victoria, vol 2 (at Service 273) [C 1.01.0].
5 Victorian Law Reform Commission, Civil Justice Review, Report No 14 (2008).
6 Lord Woolf, Access to Justice: Interim Report to the Lord Chancellor on the Civil Justice System in
England and Wales (1995), 13.
7 Victoria, Parliamentary Debates, Legislative Assembly, 24 June 2010, 2607 (Attorney-General
Rob Hulls).
When the courts are used by litigants and lawyers in this way, the public
loses faith in the justice system and the courts are unavailable to hear
meritorious claims. This package of reforms will require all participants in
the civil justice system to lift the standards of conduct in civil litigation and to
work together to achieve a positive change in the civil justice system.8
8 One of the main purposes of the Act is to provide for an overarching purpose
in relation to the conduct of civil proceedings to facilitate the just, efficient, timely
and cost-effective resolution of the real issues in dispute.9 The Act provides for
conduct in litigation, and expanding the powers of the courts in relation to costs in
9 The court is obliged to give effect to the overarching purpose of the Act to
facilitate the just, efficient, timely and cost effective resolution of the real issues in
dispute.11 The court is directed to further the overarching purpose by having regard
to the objects and matters articulated in s 9 of the Act which include the efficient use
manner proportionate to the complexity and importance of the issues and amount in
dispute.
10 The overarching obligations apply to any person who is a party, any legal
practitioner arising under common law or statute to the extent that such duties and
obligations and the overarching obligations can operate consistently. 13 But a legal
civil proceeding must comply with the overarching obligations despite any
8 Ibid.
9 Section 1(1)(c).
10 Section 1(2)(a) and (b).
11 Section 7.
12 Section 10.
13 Section 13(1).
A legal practitioner is not required to comply with any instruction or wish of a client
which is inconsistent with the overarching obligations,15 and must not cause the
11 Part 2.3 outlines the overarching obligations. The duty stated in s 16 is that
each person to whom the overarching obligations apply has a paramount duty to
12 The overarching obligation in issue is the obligation of the parties and their
practitioners to ensure that legal costs are reasonable and proportionate. Section 24
imposes a positive obligation to take steps to ensure that costs are not excessive and
provides:
14 Section 13(2).
15 Section 13(3)(b).
16 Section 14.
17 Section 13(3).
18 Section 19.
that can be applied in determining whether the parties have met their obligations.
Rather, the court must weigh the legal costs expended against the complexity and
importance of the issues and the amount in dispute, in order to determine whether
the parties used reasonable endeavours to ensure those costs were proportionate.
14 Each party and their solicitor and counsel have an obligation to comply with
the overarching obligation. Whether any of them have breached that overarching
regard to the issues and the amount in dispute in the proceeding. The legal
practitioners duty is non-delegable. The obligation will override their duty to their
client where the discharge of that duty would be inconsistent with the overarching
with the overarching obligation. Both solicitor and counsel also have an overarching
responsibility with respect to the extent and level of their clients representation.
Each must ensure that, having regard to the issues, the extent and level of
given or received by legal practitioners, and instructions given by the client may
inform but will not be determinative of the question whether, viewed objectively,
16 Part 2.4 of the Act governs the Courts power to issue sanctions for
19 Section 13(1).
20 Section 13(2) and (3).
(a) an order that the person pay some or all of the legal
costs or other costs or expenses of any person arising
from the contravention of the overarching obligation;
(d) an order that the person take any steps specified in the
order which are reasonably necessary to remedy any
contravention of the overarching obligations by the
person;
those in any other jurisdiction in Australia, to sanction legal practitioners and parties
who fail to meet their overarching obligations. For example, the Civil Procedure Act
2005 (NSW) provides that the overriding purpose of the Act is to facilitate the just,
quick and cheap resolution of the real issues in the proceedings.21 Although there
are also provisions relating to more specific obligations such as effective case
management, delay and proportionality of costs,22 the NSW provisions remain more
aspirational than obligatory. The Courts powers as to costs are still governed by the
Rules of the Court. There are no broad powers to issue sanctions for contravention
of the obligations. Similarly, the Federal Court provisions merely empower the
Court to take into account a failure to comply with the duty to act consistently with
18 Section 29 of the Act provides the Court with broader and more flexible
powers than under the Supreme Court (General Civil Procedure) Rules 2005 (the Rules)
or under its inherent jurisdiction. Rule 63.23(1) enables the Court to make orders for
costs against a legal practitioner who has caused costs to be incurred improperly by
a failure to act with reasonable competence and expedition. However, the primary
The primary object of the Rule is not to punish the solicitor, but to protect the client
who has suffered and to indemnify the party who has been injured. 25 Rule 63.23(1)
obligations of this kind set out in the Act did not only arise upon its commencement,
21 Section 56(1).
22 See ss 57, 59 and 60.
23 Section 37N(4) of the Federal Court of Australia Act 1976 (Cth).
24 White Industries (Qld) Pty Ltd v Flower & Hart (a firm) (1998) 156 ALR 169, 229.
25 Myers v Ellman [1940] AC 282, 289 (Viscount Maugham).
26 [2011] VSC 239.
but in fact have always existed. 27 His Honour referred to the joint judgment of
Redlich JA and Beach AJA (as he then was) in A Team Diamond Headquarters Pty Ltd v
Main Road Property Group Pty Ltd & Ors,28 in which their Honours said:
20 The Courts powers under s 29 of the Act include the power to sanction legal
Part 2.4 indicates.30 In our view, these powers are intended to make all those
the just, efficient, timely and cost effective resolution of disputes. Through them,
Parliament has given the courts flexible means of distributing the cost burden upon
and across those who fail to comply with their overarching obligations. A sanction
which redistributes that burden may have the effect of compensating a party. It may
take the form of a costs order against a practitioner, an order that requires the
practitioner to share the burden of a costs order made against their client or an order
which deprives the practitioner of costs to which they would otherwise be entitled.
The Act is clearly designed to influence the culture of litigation through the
27 Ibid [22].
28 (2009) 25 VR 189.
29 Ibid 193-4 [15] (citations omitted).
30 As per s 36(1)(a) of the Interpretation of Legislation Act 1984, s 36(1)(a), headings form part of
the Act. Any heading must give way to clear and unambiguous words in the provision, but it
nonetheless forms part of the interpretative process. See Silk Bros Pty Ltd v State Electricity
Commission (Vic) (1943) 67 CLR 1, 16.
obligations, it will be no answer that the practitioner acted upon the explicit and
s 13(3)(b), the legal practitioner acts on the instruction of his or her client in breach of
21 Section 28(2) enables a court, in exercising its discretion as to costs, to take into
enactment of s 29 together with s 28(2) imbues the Court with broad disciplinary
powers that may be reflected in the costs orders that are made. The Court is given a
powerful mechanism to exert greater control over the conduct of parties and their
legal representatives, and thus over the process of civil litigation and the use of its
22 The Act does not merely reaffirm the existing inherent powers of the court but
provides a powerful indication of the will of the Parliament about the values sought
to be achieved by the way in which cases are managed in the courts and the balances
23 It is therefore somewhat surprising that despite the length of time the Act has
been in force, the scope of the sanction provisions in the Act for a failure to comply
Consultancy Services (No 4),32 His Honour concluding that the jurisdiction has both
31 Chief Justice Black (as his Honour then was), The role of the judge in attacking endemic
delays: Some lessons from Fast Track (2009) 19 Journal of Judicial Administration 88, 923 .
32 [2013] VSC 14.
an obligation.33 A number of judges at first instance have emphasised that the Act
requires the Court to be proactive and innovative in its approach to achieve its
objects.34 This approach led Derham AsJ to justify the exercise of the Courts power
to order the production of documents in Matthews v SPI Electricity Pty Ltd & Anor
(No 3).35 A failure to act promptly and minimise delay in contravention of s 25 of the
Act was relied upon to support the striking out of proceedings by Digby J in Chan &
Ors v Chen & Ors.36 J Forrest J in Matthews v SPI Electricity Pty Ltd & Anor (No 2)37
accepted that s 29 authorises the Court to order a person who the Court is satisfied
costs of any other person arising from the contravention of the overarching
obligation but refused to make the order sought. In Bare v Small,38 Hansen and
Tate JJA recently gave effect to the Courts discretionary power to fix or cap a partys
the just, efficient, timely and cost-effective resolution of the real issues in dispute. In
Sunland Waterfront (BVI) Ltd & Anor v Prudentia Investments Pty Ltd & Ors,39
Warren CJ, Osborn JA and Macaulay AJA approved the approach of Croft J in taking
the nature and extent of contraventions of the overarching obligations of the Act into
25 The explanation for the under-utilisation of the provisions of the Act lies in
part in a false perception that these provisions and the overarching obligations do
33 Ibid [5][7].
34 Hodgson v Amcor Ltd; Amcor Ltd & Ors v Barnes & Ors (2011) 32 VR 495, 504 [26]; Thomas v
Powercor Australia Ltd [2010] VSC 489, [41] (Forrest J); Crowe v Trevor Roller Shutter Services
Pty Ltd [2010] VSC 536, [19][20] (Beach J).
35 [2013] VSC 116.
36 [2013] VSC 538.
37 [2013] VSC 86.
38 [2013] VSCA 204.
39 [2013] VSCA 237.
40 Ibid [553][554].
not effect any material change to the Rules and the inherent jurisdiction of the
specific legislative intervention is unnecessary, since the rules or the inherent powers
of the court confer ample authority on the judges to manage litigation in a manner
that minimises delays and ensures that costs are proportionate to the matters in
The Act creates obligations which extend beyond those in the Rules and confers
26 The Act prescribes that parties to a civil proceeding are under a strict,
positive duty to ensure that they comply with each of the overarching obligations
and the court is obliged to enforce these duties. The statutory sanctions provide a
valuable tool for improving case management, reducing waste and delay and
provisions have been a rarity at first instance. When no party invites the court to
determine whether there has been a breach of the Act, there may be a judicial
disinclination to embark upon such an own-motion inquiry for fear that inquiry as to
a potential breach may be time consuming and may require the introduction of
material that was not before the court as part of the proceeding. Such fears cannot
relieve judges of their responsibilities. But we would not wish it to be thought that a
considering whether there has been a contravention of the Act. As the sanction for a
breach will usually lie in an appropriate costs order, a judge may at the conclusion of
the reasons for judgment immediately invite oral submissions as to why there should
41 See for example Octagon Inc v Hewitt & Anor (No 2) [2011] VSC 373, [48]. See also r 63.23 of the
Rules and s 24 of the Supreme Court Act 1986 (Vic). As to the Courts inherent jurisdiction, see
White Industries (Qld) Pty Ltd v Flower & Hart (a firm) (1998) 156 ALR 169; Myers v Elman [1940
AC 282; and Knight v FP Special Assets (1992) 174 CLR 178.
42 Justice Sackville, The future of case management in litigation, (2009) 18 Journal of Judicial
Administration 211, 217.
not be a finding that the Act was contravened. The judge may in a relatively brief
way deal with that issue in providing succinct reasons for a finding that there has
been a breach of the Act and how that finding affects the orders for costs that are to
be pronounced.
The submissions
28 ANZ and the receivers, Yara and Apache each filed submissions contending
that they had complied with their obligations under s 24. They submitted that the
legal and factual issues, including the questions as to whether the Holdback Amount
was an adequate security for costs, the right of indemnity of Apache and Yara to the
fund and a point of general principle about the test for leave when appealing from
the decision of an Associate Justice under r 77.06.2(1). The applicants noted that
costs was a matter of serious concern, seeking security for costs was important.
Although the sums at stake during the present application for security for costs were
not substantial, it was said that there was common ground between the parties that
huge costs were likely to be incurred in the remainder of the proceeding. Matters
such as discovery and the preparation of lay and expert evidence were likely to be
immensely expensive. Thus the applicants contended that the true issue was in fact
not the quantum of security presently sought, but their ongoing entitlement to seek
security for future costs arising in the litigation. Furthermore, the sums at stake in
the underlying litigation are said to be extraordinary. The applicants refer to the
substantial damages claims which, though not yet quantified, may run to hundreds
of millions of dollars.
29 As to the materials filed, the applicants submitted that the application books
comprising six lever arch volumes contained all the documents necessary for the
purposes of the application for leave to appeal and the appeal if leave was granted.
It was submitted that only a relatively small volume of material was filed in the
proceeding before Efthim AsJ, which was met by a large volume of material by
Mrs Oswal. The applicants then filed all relevant material that was available. They
noted that they had annotated the material and provided extensive footnote
each of the applicants, who had interests that were separate and distinct from each
other, should be separately represented. Given the nature of the application and the
significant sums of money at stake in the underlying litigation, they submit that it
was responsible, sensible and appropriate for the applicants to each be represented
by junior and senior counsel. 43 Thus the applicants submit that each of them at all
31 The orders sought on all of the applications for leave to appeal were
substantially the same. Each applicant sought security for costs and a stay of
proceedings until security was provided. Yara and Apache adopted the submissions
of ANZ and the Receivers. 44 The issues in this Court were confined. There were
that the Holdback Amount provided sufficient security for costs; and, third,
whether he was wrong to hold that Apaches and Yaras right of indemnity was
32 Both before Whelan J and in this court the applicants failed to make out their
primary claim that the Holdback Amount was insufficient to constitute adequate
security in the absence of any evidence of any claim that would deplete it. The other
issues were also decided adversely to the applicants, the Court refusing leave on
each ground.
43 Yara noted in its further submissions that it was represented only by senior counsel and the
instructing solicitor as second junior counsel.
44 [2013] VSCA 156, [80], [84].
ensure that parties are not over-represented. The applicants and their legal
practitioners had an obligation to use reasonable endeavours to ensure that the costs
34 The second reading speech to the Act identifies the practice of unnecessarily
briefing two barristers as a procedural issue that needs redress. The Attorney-
submissions that were to a large extent in the same terms. The appearance of seven
counsel for the applicants, three of them senior counsel, and two of them appearing
for the same party on an application for leave to appeal on a security for costs
compelled the Court to inquire as to whether there had been any contravention of
the Act.
36 In order to comply with the particular overarching obligation in s 24, the legal
practitioners solicitors and counsel who act for or on behalf of a party or who
are asked to so act, must always give careful consideration to the level and the extent
party provides informed instructions to their legal practitioners that they wish
particular counsel to be briefed, the legal practitioners who act on thei r behalf have
an overriding duty to consider whether, having regard to the matters set out in s 24
and any other relevant circumstances, the engagement of particular counsel will
importance of the issues and the amount in dispute will not justify the engagement
of counsel of particular seniority or will not justify the engagement of more than one
counsel.
37 Despite the applicants submissions being substantially the same, ANZ and
the receivers, who were represented by two senior counsel and a junior counsel,
explained in their written submissions that because lead counsel overseeing the
litigation, and who had appeared before Efthim AsJ and Whelan J, was unavailable
for the preparation of the written submissions, other senior counsel was briefed to
draft the written submissions with junior counsel. As the availability of lead seni or
counsel and junior counsel for the hearing was also uncertain, senior counsel who
had prepared the submissions was briefed to appear. Lead counsel became available
shortly before the hearing. Having regard to the importance and complexity of the
issues, the likely costs of the proceedings, the amount in dispute and the fact that the
oral submissions of lead senior counsel succinctly narrowed the focus of the
application, it cannot be said that the engagement of three counsel, and the costs
38 Although counsel who appeared for Apache and Yara adopted the
submissions of ANZ and the receivers, their counsel also made discrete and brief but
39 Each of the applicants, whose interests were separate and distinct, was
party to forfeit that right. In the context of the broader litigation, which is li kely to be
represented at this application by the counsel that were engaged. It is not without
significance that neither respondent contends that there was any contravention of the
Act in this regard. As a result of the explanations proffered by the parties as to the
reasons for the unusual degree of legal representation in the proceedings , and
having regard to the issues and the manner in which the hearing was conducted, we
are satisfied that there was no breach of the overarching obligation in that regard.
40 The Act is designed to protect litigants from incurring excessive costs, but it is
also designed to protect against the inappropriate use of the courts as a public
resources of the Court and the time of judges themselves. Where a large volume of
prima facie case that the overriding obligation has been breached. The court was
transcript and authorities running to over 2700 pages. Two folders pertained to the
Mr Oswal application and four folders related to the application of Mrs Oswal. The
transcripts from related hearings in the Supreme Court of Victoria. Much of this
41 The application books in the Mrs Oswal application include all of the
evidence filed by the parties before Efthim AsJ, and all written submissions filed by
the parties before Efthim AsJ and Whelan J. Transcript and, in particular, written
42 The affidavit dated 4 May 2012, filed on behalf of ANZ and the receivers, ran
for 369 pages and contained a number of unnecessary documents, mostly concerning
related but not directly relevant proceedings in other courts and jurisdictions. This
included a writ and statement of claim dated 2 September 2011; Radhika Oswals
46 Contrary to the contents of the Supreme Court of Victorias Registrars Notes on the Preparation
of Appeal Books, October 2000, 4.
respect of that interlocutory injunction and the transcript of that hearing; bills of
costs in respect of that application; the judgment of the Western Australian Court of
Appeal in Oswal v Yara Australia Pty Ltd;47 the transcript of a hearing before
Ferguson J in the Supreme Court of Victoria in the matter No. S CI 2011 785; copies
of freezing orders made by the Western Australian District Court; and letters from
The proceedings in Western Australia and before Davies and Ferguson JJ in the
Supreme Court of Victoria were not referred to at all in the applicants submissions,
43 The affidavit dated 7 May 2012, filed on behalf of Yara, ran for 77 pages. It
respect of the statement of claim and the orders of Davies J that Mrs Oswal provide
further and better particulars. The Table to clauses 10 and 11 of the Legal Practitioners
(Supreme Court) (Contentious Business) Determination 2010 (WA) was also included in
the affidavit. None of this material was relevant to the application before this Court.
44 The affidavit dated 21 May 2012, filed on behalf of Apache, ran for 198 pages.
The affidavit contained correspondence seeking advice from a cost consultant on the
quantum of the security for costs application. The letter contains a copy of the
amended writ and statement of claim, dated 24 April 2012, which runs for 170 pages
45 The affidavit dated 29 May 2012, filed on behalf of Mrs Oswal, mostly
comprises material that was relevant and relied upon during the application,
including copies of the guarantees and indemnities between the parties; the Apache
and Yara Share Sale Deeds; and the Share Mortgage between Mrs Oswal and ANZ.
This affidavit runs for 391 pages. The only unnecessary document is the Report from
This report is duplicated in the affidavit of Margaret Vine from Grace Costs.
extraneous material. The application books again contained all of the submissions
and some transcript material from the hearings before Efthim AsJ and Whelan J. The
affidavit filed on behalf of ANZ and the Receivers ran for 139 pages and included
copies of judgments involving the parties from the Federal Court and the Supreme
Court of Western Australia. These decisions were not relevant to this application.
The only material of relevance to this application was the bundle of correspondence
between the parties regarding the security for costs application and the six page costs
report.
47 The affidavit filed on behalf of Mr Oswal, ran for 492 pages. It contained
copies of the Share Mortgage between Mr Oswal and ANZ and the Share Sale Deed
between ANZ, Mrs Oswal and Yara. Superfluous material was also included, such
as the prospectus for Yara Pilbara Holdings, 20 pages of Reserve Bank data on the
daily price of the $US and judgment in the matter of Tap (Harriet) v Burrup Fertilisers
Pty Ltd.48
material. The Mr Oswal application books and the Mrs Oswal application books
both contain 81 pages of transcript from the proceedings before Efthim AsJ on
12 June 2012, and 118 pages of transcript from proceedings before Whelan J (as his
Honour was then) on 9 August 2012. The reasons of Whelan J are reproduced in
the material contained within the application books and which was produced by the
applicants was unnecessary to the resolution of the issues we have identified or any
other matter relevant to the applications. That contention is made out. The
respondents identified the evidence that was referred to in the parties written
material now contained in the application books. The application books contained
voluminous unnecessary material which increased the costs for all parties and the
burden on the court. Very little of it was the subject of any reference in oral
argument. In all, significantly more than half of the material in the application books
50 The first issue we have identified required analysis of the principles attending
the grant or refusal of leave from an Associate Justice. The second issue principally
involved construction of the relevant share sale deeds and the contingencies related
thereto. There was little need to have regard to any documents beyond the share
sale deeds themselves. The third issue also called for a consideration of principle
without the need to consider any evidentiary material. None of the issues required
production of the evidence filed by the parties before Efthim AsJ, the written
those hearings.
in respect of this applications must be seen in the context of the litigation as a whole,
which will require both parties to incur very substantial legal fees. Such expenditure
civil litigation. Parliament has intended that this reform can only be achieved by
holding parties to account for undesirable civil litigation practices that are
unfortunately too common. The court was burdened with excessive material. The
applicants and the respondents were burdened with the costs of that material. There
has been a breach of the overarching obligation to ensure the costs are reasonable
53 Mrs Oswal sought indemnity costs from Apache and Yara on the basis that
the very making of the applications was inconsistent with the overarching
obligation in s 24 of the Act. This argument rested upon the assertion that no
substantial injustice was shown to arise from the decision of Whelan J as the
applicants Apache and Yara would be able to recover costs from the Holdback
Amount being property owned by the respondents, and over which they had
54 The applications of Yara and Apache were not inconsistent with the
overarching obligation under s 24 of the Act. Had the applications been bound to
fail, the obligations under ss 18 and 19 of the Act may have been relevant. As Yara
submitted in reply, it had always maintained that the Holdback Amount was not
part of the respondents property and could not provide security for any costs. Had
55 Mr Oswal, in a more restrained submission, said that it was open to the court
to make an order for costs on a higher basis but relied only upon the inclusion of
order.
56 The breach of the overarching obligation under the Act is a matter that may be
taken into account in making an order for costs. There will be cases where a breach
of an obligation under the Act may support an order for indemnity costs. The breach
may well reflect an already well-recognised basis for the making of such a costs
order. We do not need to consider whether there may be contraventions which give
57 In this case the respondents have not demonstrated that any special costs
order should be made in their favour. The applicants have not engaged in
showing its disapproval and at the same time preventing the respondents being left
out of pocket.49 If it is appropriate that the usual costs orders following the outcome
of the proceeding are made in the respondents favour, any additional costs in the
preparation for hearing that they have incurred as a result of the breach of the
further submissions as to the nature of any order that we may make in the event that
we find a contravention of the Act to have been made out. One applicant has
59 An order that may be appropriate is that the solicitor-client costs which each
legal practitioner may seek to recover from their client not include a percentage of
the costs of the preparation of the application books. A further order that could also
be made is that the legal practitioners for the applicants pay a portion of the
respondents costs of the applications that are related to the preparation for the
hearing. We will hear from the parties as to what orders we should pronounce as to
60 We will direct that the solicitors for each of the applicants provide their clients
Orders
61 After hearing from the parties following the delivery of judgment the Court
49 Hazeldenes Chicken Farm Pty Ltd v Victorian Workcover Authority (No 2) (2005) 13 VR 435;
Aljade and Malaysian Kuwaiti Investment Co v Oversea-Chinese Banking Corp Ltd [2004] VSC 351.
(3) Each applicants solicitor indemnify the applicant for 50% of the
50% of the costs relating to the preparation of the application books, and
(5) For the purpose of determining the appropriate amounts that the
applicants.
(6) Each applicants solicitors provide the applicant with a copy of these
---