Sie sind auf Seite 1von 2

Universal Sealants

(UK) Limited

UNIFLEX Product Information

Expansion Joint Systems


The System
The Uniflex System uses a butyl rubber
membrane, bonded to the substrate with Uniflex
Epoxy Adhesive to provide an efficient and ROOFING UNIFLEX HOT POURED
permanent joint that is easily installed. The GRADE RUBBER
System will accommodate a variety of conditions ASPHALT BITUMEN
from those experienced on an asphalt-covered CLOSED PAVING CONCRETE
CELL GRADE
traffic-free roof, to bridge decks with sheet FOAM ASPHALT
membrane, spray on coating or asphalt
waterproofing, also it can be used with two layer
mastic asphalt or brick paving systems.
The Uniflex Membrane is prepared from specially
developed butyl rubber compound that is tough,
weatherproof, flexible and can withstand
up to 300% elongation.
The Uniflex Epoxy Adhesive has
been designed specifically for
bonding Uniflex to concrete,
asphalt, steel and other surfaces
to make the system so effective.

Components
The Uniflex Membrane is normally supplied in 20
metre rolls of any required width up to 1300mm,
adhesive, closed cell foam and steel plates if required
are all part of the different systems we can provide.

Performance
The Uniflex System is chemically inert and completely
impervious to water and water vapour. In buried joints
the membrane is completely protected by the wearing
surface. Uniflex Membrane will not rock or crack in
service and the combination of a simple design and
proven components makes the system naturally long-
lasting and well up to the requirements of modern
building and civil engineering practice.
FM 11022

SPECIALIST MANUFACTURERS, SUPPLIERS AND CONTRACTORS TO THE CONSTRUCTION INDUSTRY...WORLDWIDE


Universal Sealants
(UK) Limited

UNIFLEX Technical Data

Expansion Joint Systems Key


Uniflex surface joint on asphalt Paving Grade
Asphalt

Sitework Roofing Grade


Asphalt
Concrete surfaces must be finished to U3 standard,
Paving Blocks
abraded to remove laitence and providing good /Screed
bonding substrate. The concrete shoulders must be Uniflex buried joint: between asphalt
Screed
smooth and level with each other across the courses
expansion gap. if the concrete surface is not sound,
making good should be done with Polymer modified Concrete
concrete.
Uniflex
The concrete surface should be primed with Uniflex
adhesive diluted to make a primer. The area of mastic Uniflex buried joint: asphalt on concrete
asphalt to which the Uniflex membrane is to be bonded Closed Cell
Foam
must be well sand-rubbed when laying to remove excess
bitumen fat, and any nibs removed to give a clean flat Protection
Plate above
surface free from surplus sand and other materials. The Uniflex and
surface should be smooth and level across the joint. Paviours
Uniflex buried joint: asphalt over waterproof
membrane Waterproof
Membrane
The preferred method is to use asphalt straps 250mm wide and
Uniflex Design Services 25mm thick to link the Uniflex to the waterproofing membrane but
an alternative provides for the Uniflex to be bonded to the
concrete and the waterproof membrane taken across the Uniflex Galvanised
The Uniflex system is versatile and simple, internal and and bonded to it. Steel
external corners can be easily accommodated and made
Hot-poured
on site, also termination at the ends of the joints can be Rubber
formed by returning up the vertical from the horizontal, Bitumen

angle flashings are treated in a similar fashion at columns,


walls and kerbs giving continuity of the waterproofing seal.
However, our Technical Department will be pleased to Uniflex buried joint: beneath
screed/paviours and protected
assist in detail design in order to suit site requirements.

l
Applications
The Uniflex system is adaptable and the following
illustrations show how it is used and the most frequently
specified.

ll

HEAD OFFICE
Kingston House, 3 Walton Road , Pattinson North
Washington, Tyne & Wear NE38 8QA,
United Kingdom Uniflex buried joint:
T: +44 (0) 191 416 1530 F: +44 (0) 191 415 4377 asphalt over waterproof membrane
The design can be used with mastic asphalt waterproofing (Figure l),
W: www.usluk.com E: info@usluk.com or with spray/sheet waterproofing membranes (Figure ll).
Galvanised steel plates are only required should the structural gap exceed 35mm.
Colours are for illustration purposes only.

Das könnte Ihnen auch gefallen