SAUDI ARAMCO ID/PID FORM REV 1 - 010109 March 2012 Rev 6 31-Mar-12

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
HVAC Metal Duct System SATIP-K-001-03 30-Apr-13 HVAC
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Duct Leakage Test and Duct Sealing See Procedures shall follow the outlines and classifications
1.1 See Remarks
Procedures Remarks in the SMACNA HVAC Duct Leakage Test Manual

2.0 MATERIAL RECEIVING

Duct Hangers and Supports


SAIC- SAIC- Saudi Aramco to be notified on receipt of initial
2.1 (including fasteners, etc.)
K-4008 K-4008 W W shipment by type or manufacturer
Receiving Inspection

Metal Ducts SAIC- SAIC- Saudi Aramco to be notified on receipt of initial


2.2
Receiving Inspection K-4008 K-4008 W W shipment by type or manufacturer

Saudi Aramco to be notified on receipt of initial


shipment by type or manufacturer.
Duct Insulation SAIC- SAIC-
2.3
Receiving Inspection K-4008 K-4008 W W
When requested by Saudi Aramco PID, provide one
(1) meter sample for review and approval prior to use

Duct Accessories SAIC- SAIC- Duct accessories consists of Duct Heaters, Volume
2.4
Receiving Inspection K-4009 K-4009 H W Dampers and other items listed in this check list.

Air Terminal Devices & Flexible SAIC- SAIC- Terminal Devices include Diffusers, Grills and
2.5
Connector Receiving Inspection K-4009 K-4009 H S Registers

Saudi Aramco shall be notified on every delivery of


SAIC- SAIC-
2.6 Fire Damper Receiving Inspection
K-4010 K-4010 H H Fire/Smoke/Fire-Smoke Damper and inspect each
one for compliances to the project requirements

SAIC- SAIC-
2.7 Storage, Handling and Preservation
K-4011 K-4011 W S Weekly inspection by Contractor QA/QC

3.0 INSTALLATION

Duct Hangers and Supports (including SAIC- SAIC- Saudi Aramco to be notified on start of this activity for
3.1
fasteners, etc.) K-4012 K-4012 W W each area or building.

Page 1 of 3
08/20/2017 13:21:32
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 March 2012 Rev 6 31-Mar-12
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
HVAC Metal Duct System SATIP-K-001-03 30-Apr-13 HVAC
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

SAIC- SAIC- Saudi Aramco to be notified on start of this activity for


3.2 Metal Duct Inspection
K-4013 K-4013 W W each area or building.

See As per Approved Duct Leakage Test and Duct Sealing


3.3 Duct Leakage Test and Duct Sealing See Remarks
Remarks W W Procedures in item 1.1

Grease Duct (Serving Type I hood or as SAIC- SAIC-


3.4
applicable) Inspection K-4014 K-4014 H W

SAIC- SAIC- Saudi Aramco to be notified on start of this activity for


3.5 Duct Insulation Inspection
K-4015 K-4015 H W each area or building.

SAIC- SAIC- Saudi Aramco to be notified on start of this activity for


3.6 Duct Accessories Inspection
K-4016 K-4016 W W each area or building.

Air Terminal Devices & Flexible SAIC- SAIC- Saudi Aramco to be notified on start of this activity for
3.7
connector Inspection K-4017 K-4017 H W each area or building.

SAIC- SAIC- Saudi Aramco shall be notified on start of this activity


3.8 Fire Damper Inspection
K-4018 K-4018 H H and shall inspect every installation

SATR- SATR-
3.9 Fire Damper Functional Test
K-4001 K-4001 H H

4.0 PRE-COMMISSIONING

4.1 Not Applicable

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1
adjust the levels of Saudi Aramco participation based upon the Contractors performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization

Page 2 of 3
08/20/2017 13:21:32
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 March 2012 Rev 6 31-Mar-12
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
HVAC Metal Duct System SATIP-K-001-03 30-Apr-13 HVAC
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3
representative is not present.

Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4
attendance.

5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H 100% Hold Point for QC Inspection or Test. R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 3 of 3