Sie sind auf Seite 1von 8

lead slag pool D

INTERIM PAYMENT CERTIFICATE NO.3


MEASUREMENT SHEET

LEAD SLAG POOL (D) CIVIL WORKS


March 02 to March 31, 2016

Total Qty
Sr. No. Activity ID Activity Name B.O.Q Description No.s Length Widt Height Qty/Unit Unit Cement Bags Consumed
1.4 EARTH WORK
1.4.1 Excavation
1.4.1 as per drawingsand adding working space with 1 19000 17000 3000 969.00 M3 969.0
SUM 969.0
1.4.2 BACKFILL
1.4.2 as per drawings 1 M3 230.0
SUM
PC CONCRETE
3. Base Slab
1 18000 16000 10 28.80 M3 28.8
SUM 28.8 97.0
RC CONCRETE
4. Base Slab
2.4.1 (a) Slab asd per drawing and specifications 1 15800 17800 500 140.62 M3 140.6 875.0
SUM 140.6 875.0
5. Walls
2.4.1 (f) Short Wall 2 13650 350 3300 15.77 M3 31.5 196.0
2.4.1 (f) Long Wall 2 15650 350 3300 18.08 M3 36.2 225.0
2.4.1 (f) Chamfer 1 58600 450 450 6.00 M3 6.0 38.0
SUM 73.7 459.0
STEEL
6. Slab and Walls
2.2.1 (a) Slab & Walls asd per drawing and specifications 1 - - - - Ton 12.448
SUM Ton 12.448

363907055.xlsx Page 1 of 8 08/23/2017


bag house foundation 2 set

INTERIM PAYMENT CERTIFICATE NO.2


MEASUREMENT SHEET

BAG HOUSE FOUNDATION 2 SETS (A) CIVIL WORKS


March 02 to March 31, 2016

Total Qty
Sr. No. Activity ID Activity Name B.O.Q Description No.s Length Widt Height Qty/Unit Unit Cement Bags Consumed
EARTH WORK
1. Excavation

SUM
2. BACKFILL
1.4.2 as per drawingsand adding working space with 1 M3 234.2
SUM 234.2
GRANULAR FILL MATERIAL
3. Raft Foundation

SUM
PC CONCRETE
4. Raft Foundation

SUM
RC CONCRETE
5. Raft Foundation

SUM
6.Pedestal
6.1 P1 as per drawing and specifications 16 500 500 1200 0.30 M3 4.8
SUM 4.8 38.0
STEEL
7. Raft Foundation

8. Columns

SUM

363907055.xlsx Page 2 of 8 08/23/2017


bag house foundation 3 set

INTERIM PAYMENT CERTIFICATE NO.2


MEASUREMENT SHEET

BAG HOUSE FOUNDATION 3 SETS (A) CIVIL WORKS


March 02 to March 31, 2016

Sr. No. Activity ID Activity Name B.O.Q Description No.s Length Widt Height Qty/Unit Unit Total Qty Cement Bags Consumed
EARTH WORK
1. Excavation

SUM
2. BACKFILL
1.4.2 as per drawings 1 343.00 M3 343.0
SUM
GRANULAR FILL MATERIAL
3. Raft Foundation

SUM
PC CONCRETE
4. Raft Foundation

SUM
RC CONCRETE
5. Raft Foundation

SUM
6. Columns
6.1 as per drawings and specs 24 500 500 1200 0.30 M3 7.2
SUM 7.2 57.0
STEEL
7. Raft Foundation

8. Columns

SUM

363907055.xlsx Page 3 of 8 08/23/2017


lead slag pool c

INTERIM PAYMENT CERTIFICATE NO.3


MEASUREMENT SHEET

LEAD SLAG POOL (C) CIVIL WORKS


March 02 to March 31, 2016

Total Qty
Sr. No. Activity ID Activity Name B.O.Q Description No.s Length Widt Height Qty/Unit Unit Cement Bags Consumed
EARTH WORK
1.Excavation
1.4.1
SUM
2. BACKFILL
1.4.2 as per drawings 1 M3 230.0
SUM
PC CONCRETE
3. Base Slab

SUM
RC CONCRETE
4. Base Slab
2.4.1 (a)
SUM
5. Walls
2.4.1 (f)
2.4.1 (f)
2.4.1 (f)
SUM
STEEL
6. Slab and Walls
2.2.1 (a)
SUM

363907055.xlsx Page 4 of 8 08/23/2017


INTERIM PAYMENT CERTIFICATE NO.6
INTERIM PAYMENT CERTIFICATE NO.01
MEASUREMENT SHEET
CIVIL WORKS
KingKong Industries Pvt. Ltd
Dec 01 to Dec 18, 2016

Total Qty
Sr. No. Activity ID Activity Name B.O.Q Description No.s Length Widt/Dia. Height Qty/Unit Unit Rate Amount % Payment
SITE CLEARANCE
Cleaning site up to outside foundations,
1 S.T Site Clearance removing debris and any organic matter and ready for 1 107000 32000 - 3424.00 M2 3424.000 70 239,680
excavation, plus cleaning debris for temporary track

SUM 3424.0 PKR 239,680


EXCAVATION
1 E.W Excavation Structural excavation in soil below sub soil water level for as 1 5000 5000 2000 50.00 M3 50.000 300 15,000
directed by Engineer In-charge (Mr. William) including test pits
2 E.W Excavation 5 4000 4000 2000 32.00 M3 160.000 300 48,000
3 E.W Excavation 9 3000 3000 2000 18.00 M3 162.000 300 48,600
4 E.W Excavation 1 3000 5000 2000 30.00 M3 30.000 300 9,000
5 E.W Excavation 1 4000 3000 2000 24.00 M3 24.000 300 7,200
SUM 426.0 PKR 127,800
TEMPORARY TRACK
1 E.W Filling Providing and spreading loose fill as per approval of Engineer 1 12191.4 33526.36 914 373.58 M3 373.582 229.6 85,767
In-Charge and area specified
2 E.W Filling 1 6705.22 32002.43 1097.22 235.45 M3 235.445 229.6 54,053
3 E.W Filling 1 13715.33 3047.85 914 38.21 M3 38.207 229.6 8,772
SUM 647.2 PKR 148,592
SPECIAL ITEMS
WATER PUMP
Suppply of red color water pump including
1 SERIVCES Pump 1 - - - 1.00 Nos 1.000 15000.00 15,000
boring, fitting, assembling and water pipe
SUM 1.0 PKR 15,000
DEWATERING
1 SERIVCES D-Watering services for d-watering 1 - - - 4.00 Day 4.000 800.00 3,200
SUM 4.0 PKR 3,200
TOTAL PAYABLE PKR 534,272
INTERIM PAYMENT CERTIFICATE NO.6
INTERIM PAYMENT CERTIFICATE NO.01
MEASUREMENT SHEET
CIVIL WORKS
KingKong Industries Pvt. Ltd
Dec 19, 2016 to 1 Jan,2017

Total Qty
Sr. No. Activity ID Activity Name B.O.Q Description No.s Length Widt/Dia. Height Qty/Unit Unit Rate Amount % Payment
SAND GRAVEL FILLING
1 C.F E-1 Providing and compacting with approved Chenab sand and 1 2388 3048 950 6.91 M3 6.915 2660 18,393
2 C.F E-2 Gravel (30:70) under column footing including dressing, 1 2769 3099 950 8.15 M3 8.152 2660 21,685
watering, compacting mechanically in layers not excluding
3 C.F E-3 150mm thick in depth to 95%, modification proctor dry 1 2540 2895 950 6.99 M3 6.986 2660 18,582
4 C.F E-4 density (MPD) brought from outside the project limits, any 1 2387.5 3048 950 6.91 M3 6.913 2660 18,389
lead and any lift compacted as per specifications and as per
5 C.F E-9 approval of the Contractor. 1 3353 3048 950 9.71 M3 9.709 2660 25,826
6 C.F E-10 Average Height taken as 95CM 1 2057.3 2743 950 5.36 M3 5.361 2660 14,260
7 C.F E-11 1 2133.5 2616.07 950 5.30 M3 5.302 2660 14,104
8 C.F C-1 1 2387.5 3556 950 8.07 M3 8.065 2660 21,454
9 C.F C-2 1 3099 3962.2 950 11.66 M3 11.665 2660 31,029
10 C.F C-3 1 2388 3505 950 7.95 M3 7.951 2660 21,151
11 C.F C-4 1 4700 3300 950 14.73 M3 14.735 2660 39,194
12 C.F C-16 1 1981 3048 950 5.74 M3 5.736 2660 15,258
13 C.F A-5 1 3556 3505 950 11.84 M3 11.841 2660 31,496
14 C.F A-6 1 2591 2946 950 7.25 M3 7.251 2660 19,289
15 C.F A-7 1 3277 3200.3 950 9.96 M3 9.963 2660 26,502
16 C.F A-8 1 2896 3097 950 8.52 M3 8.520 2660 22,664
17 C.F A-9 1 3048 2438 950 7.06 M3 7.059 2660 18,778
18 C.F E-16 1 4530 4100 950 17.64 M3 17.644 2660 46,934
19 C.F E-15 1 3400 4300 950 13.89 M3 13.889 2660 36,945
20 C.F E-14 1 4800 4100 950 18.70 M3 18.696 2660 49,731
21 C.F E-13 1 4200 5000 950 19.95 M3 19.950 2660 53,067
22 C.F E-12 1 4900 3300 950 15.36 M3 15.362 2660 40,862
23 C.F C-15 1 3900 3900 950 14.45 M3 14.450 2660 38,436
24 C.F C-14 1 4200 3900 950 15.56 M3 15.561 2660 41,392
25 C.F C-13 1 4000 4300 950 16.34 M3 16.340 2660 43,464
26 C.F C-12 1 4000 4100 950 15.58 M3 15.580 2660 41,443
27 C.F C-11 1 4200 4200 950 16.76 M3 16.758 2660 44,576
28 C.F C-10 1 4400 4000 950 16.72 M3 16.720 2660 44,475
29 C.F C-9 1 3800 4100 950 14.80 M3 14.801 2660 39,371
30 C.F C-8 1 3800 3900 950 14.08 M3 14.079 2660 37,450
31 C.F C-7 1 3900 4200 950 15.56 M3 15.561 2660 41,392
33 C.F C-5 1 3700 4200 950 14.76 M3 14.763 2660 39,270
SUM 382.3 2660.0 PKR 1,016,861
INTERIM PAYMENT CERTIFICATE NO.6
INTERIM PAYMENT CERTIFICATE NO.01
MEASUREMENT SHEET
CIVIL WORKS
KingKong Industries Pvt. Ltd
Dec 19, 2016 to 1 Jan,2017

Total Qty
Sr. No. Activity ID Activity Name B.O.Q Description No.s Length Widt/Dia. Height Qty/Unit Unit Rate Amount % Payment
LEAN CONCRETE
1 C.F E-1 lay lean concrete under footings inclusing supply of machinery, 1 2388 3048 - 7.28 M2 7.279 280 2,038
2 C.F E-2 tools and labor in wet ground conditions as per satisfaction of 1 2769 3099 - 8.58 M2 8.581 280 2,403
the contractor's representative.
3 C.F E-3 1 2540 2895 - 7.35 M2 7.353 280 2,059
4 C.F E-4 1 2387.5 3048 - 7.28 M2 7.277 280 2,038
5 C.F E-9 1 3353 3048 - 10.22 M2 10.220 280 2,862
6 C.F E-10 1 2057.3 2743 - 5.64 M2 5.643 280 1,580
7 C.F E-11 1 2133.5 2616.07 - 5.58 M2 5.581 280 1,563
8 C.F C-1 1 2387.5 3556 - 8.49 M2 8.490 280 2,377
9 C.F C-2 1 3099 3962.2 - 12.28 M2 12.279 280 3,438
10 C.F C-3 1 2388 3505 - 8.37 M2 8.370 280 2,344
11 C.F C-4 1 4700 3300 - 15.51 M2 15.510 280 4,343
12 C.F C-16 1 1981 3048 - 6.04 M2 6.038 280 1,691
13 C.F A-5 1 3556 3505 - 12.46 M2 12.464 280 3,490
14 C.F A-6 1 2591 2946 - 7.63 M2 7.633 280 2,137
15 C.F A-7 1 3277 3200.3 - 10.49 M2 10.487 280 2,936
16 C.F A-8 1 2896 3097 - 8.97 M2 8.969 280 2,511
17 C.F A-9 1 3048 2438 - 7.43 M2 7.431 280 2,081
18 C.F E-16 1 4530 4100 - 18.57 M2 18.573 280 5,200
19 C.F E-15 1 3400 4300 - 14.62 M2 14.620 280 4,094
20 C.F E-14 1 4800 4100 - 19.68 M2 19.680 280 5,510
21 C.F E-13 1 4200 5000 - 21.00 M2 21.000 280 5,880
22 C.F E-12 1 4900 3300 - 16.17 M2 16.170 280 4,528
23 C.F C-15 1 3900 3900 - 15.21 M2 15.210 280 4,259
24 C.F C-14 1 4200 3900 - 16.38 M2 16.380 280 4,586
25 C.F C-13 1 4000 4300 - 17.20 M2 17.200 280 4,816
26 C.F C-12 1 4000 4100 - 16.40 M2 16.400 280 4,592
27 C.F C-11 1 4200 4200 - 17.64 M2 17.640 280 4,939
28 C.F C-10 1 4400 4000 - 17.60 M2 17.600 280 4,928
29 C.F C-9 1 3800 4100 - 15.58 M2 15.580 280 4,362
30 C.F C-8 1 3800 3900 - 14.82 M2 14.820 280 4,150
31 C.F C-7 1 3900 4200 - 16.38 M2 16.380 280 4,586
33 C.F C-5 1 3700 4200 - 15.54 M2 15.540 280 4,351
SUM 149.6 PKR 112,672
INTERIM PAYMENT CERTIFICATE NO.6
INTERIM PAYMENT CERTIFICATE NO.01
MEASUREMENT SHEET
CIVIL WORKS
KingKong Industries Pvt. Ltd
Dec 19, 2016 to 1 Jan,2017

Total Qty
Sr. No. Activity ID Activity Name B.O.Q Description No.s Length Widt/Dia. Height Qty/Unit Unit Rate Amount % Payment
TOTAL PAYABLE PKR 1,129,533