December/ 2015
1. General 1 Pg.
9. Dewatering 6 Pg.
Newly installed pipe line shall be arranged the hydraulic pressure test to confirm the reliability for
The disinfection and cleaning for intra-pipe shall be arranged with using treated water from new water
treatment plant after its completion as a condition of commissioning for the pipe Laying Work.
Fig.-1
Pg.2
3. Testing Pressure
The Testing Pressure shall be arranged as Table -1 as below.
Dia.1200mm
0.000m
Transmission pipe CH 00 + 000KM 0.81 M pa 1.215 M pa
0.000m
Pg.3
Fig.-2
TARA GATE DN1(CH00+405)
4350
Concrete Brock
Concrete
2600
Heavy Sheet Pile
H-250250 Jack H-250 L=5.0m
Concrete Brock
Concrete
2000
PRESSURE METER
Pg4
5. Filling up with Water:
a.The water from the CWASA shall be used for hydraulic pressure test.
b. The water filling shall be carried out slowly with verifying of the releasing air
inside from air cook which mounted on the end plug. It is very important to make sure that
air is actually released during the water filling. Insufficient exhaust will lead to failed
result and compressed air by the water will be so dangerous.
c. In case of finding out the leakage during water filling we will fix it immediately.
d.The air venting facilities shall be installed on the high point of pipe line.
e. Being for the cement mortar lining of intra pipes the keeping enough time after water
filling is required for the absorption of water into cement mortar lining.
Fig.-3
Pg5
working pressure for a sufficient period of time for it to stabilize with respect to line movement
of at least 1 hour. Then disconnect the pump and allow no further water to enter the test section for a
period of at least.
table-2 below.
Dia.1200mm
(-10% / 30 min)
0.000m
9. Dewatering:
After completion of the hydraulic pressure testing we will arrange dewatering the water of intra pipe