Project Number: 6548 Superintendent:

Tank Number: 2151 Client: VOPAK


Field Inspection Checklist
API 650 / 653 - Tank Construction Revision#: 0 Date: 7/26/2017
Form
QF-120 Rev: 06 API-650 / 653 12th / 5th Edition Add 2 / none
Where RT shown - AUT (PAUT) may be used. Location:
650/653
IN SCOPE See Applicable Procedures at the end of the FIP. Superintendent: Test Operator: Client:
Ref.
(Modify as required for unique customer requirements) Initials Initials Initials Date
YES NO
INITIAL INSPECTION
X Tank gas free by others - TARSCO Check
X Check for flammable vapors under the existing tank bottom - Notify VOPAK if vapors found
X Gain Access to External Floating Roof (EFR) Through Manway - Cut Away Part of EFR

YES NO GENERAL SHELL REQUIREMENTS

X Cavities resulting from gouging or grinding operations to remove attachment welds to the shell shall be 653/
examined by magnetic particle or liquid penetrant methods. 12.1.2.2

X Completed welds attaching nozzle neck to shell, and reinforcing plate to shell and to nozzle neck, shall be 653/
examined by the magnetic particle or liquid penetrant methods. 12.1.2.3
The welds of permanent attachments (not including shell-to-bottom welds) and, areas where temporary 653/
X attachments are removed and the remaining weld projections have been removed, shall be examined 12.1.4.2
visually.

INSTALL 2nd RING SHELL PLATE


X Receive and Release shell plate Material.
X Remove Plate to be Replaced and prepare weld preps for new plate
X Install and Weld in accordance with the specified Drawing and WPS.
9.4 /
X Visually Inspect and RT/UT the weld seams. Record on Form TARSCO-QA-01VT and Vendor's RT/UT 7.3.3
Form. Record the welder on the Welder Map Drawing. Record RT/UT Locations on the NDE Map.

INSTALL 3rd RING SHELL PLATE


X Receive and Release shell plate Material.
X Remove Plate to be Replaced and prepare weld preps for new plate
X Install and Weld in accordance with the specified Drawing and WPS.
9.4 /
X Visually Inspect and RT/UT the weld seams. Record on Form TARSCO-QA-01VT and Vendor's RT/UT 7.3.3
Form. Record the welder on the Welder Map Drawing. Record RT/UT Locations on the NDE Map.

INSTALL 4th RING SHELL PLATEs


X Receive and Release shell plate Material.
X Remove Plates to be Replaced and prepare weld preps for new plates
X Install and Weld in accordance with the specified Drawing and WPS.

W:\06 Projects\6547 VOPAK TK D 2151\QC Documents\TO JOSE FOR SUBMIT\ITP Data\QF-120 Field Inspection checklist API-650-653 VOPAK D-2151 tk Page 1 of 6
Project Number: 6548 Superintendent:

Tank Number: 2151 Client: VOPAK


Field Inspection Checklist
API 650 / 653 - Tank Construction Revision#: 0 Date: 7/26/2017
Form
QF-120 Rev: 06 API-650 / 653 12th / 5th Edition Add 2 / none
Where RT shown - AUT (PAUT) may be used. Location:
650/653
IN SCOPE See Applicable Procedures at the end of the FIP. Superintendent: Test Operator: Client:
Ref.
(Modify as required for unique customer requirements) Initials Initials Initials Date
YES NO
9.4 /
X Visually Inspect and RT/UT the weld seams. Record on Form TARSCO-QA-01VT and Vendor's RT/UT 7.3.3
Form. Record the welder on the Welder Map Drawing. Record RT/UT Locations on the NDE Map.

REMOVE OLD 5th RING and INSTALL NEW 5th RING SHELL PLATEs and Wind Girder & its Support
Pads and Supports
X Receive and Release 5th Ring shell plate Material.
X Remove old 5th RING and Wind Girder and prepare weld preps for new plates
X Install and Weld in accordance with the specified Drawing and WPS.
Visually Inspect and RT/UT the weld seams. Record on Form TARSCO-QA-01VT and Vendor's RT/UT 9.4 /
X
Form. Record the welder on the Welder Map Drawing. Record RT/UT Locations on the NDE Map. 7.3.3
X Install the Wind Girder and Weld in accordance with the specified Drawing and WPS.
Visually Inspect the weld seams. Record on Form TARSCO-QA-01VT Form. Record the welder on the 9.4 /
X 7.3.3
Welder Map Drawing.

REMOVE OLD and INSTALL NEW FOAM SYSTEM


X Remove remains of the old Foam System
X Receive and Release Foam System Material.
X Install and Weld in accordance with the specified Drawing and WPS.

X Visually Inspect the weld seams. Record on Form TARSCO-QA-01VT Form. Record the welder on the
Install Drawing.

INSTALL FIRE FIGHTING PIPING SUPPORTS


X Receive and Release Foam Support Material.
X Install and Weld in accordance with the specified Drawing and WPS.

X Visually Inspect the weld seams. Record on Form TARSCO-QA-01VT Form. Record the welder on the
Install Drawing.

FOAM CHAMBERS
X Receive and Release Foam Chamber Material.
X Install and Weld and Bolt, as specified, in accordance with the specified Drawing and WPS.

X Visually Inspect the weld seams. Record on Form TARSCO-QA-01VT Form. Record the welder on the
Install Drawing.

W:\06 Projects\6547 VOPAK TK D 2151\QC Documents\TO JOSE FOR SUBMIT\ITP Data\QF-120 Field Inspection checklist API-650-653 VOPAK D-2151 tk Page 2 of 6
Project Number: 6548 Superintendent:

Tank Number: 2151 Client: VOPAK


Field Inspection Checklist
API 650 / 653 - Tank Construction Revision#: 0 Date: 7/26/2017
Form
QF-120 Rev: 06 API-650 / 653 12th / 5th Edition Add 2 / none
Where RT shown - AUT (PAUT) may be used. Location:
650/653
IN SCOPE See Applicable Procedures at the end of the FIP. Superintendent: Test Operator: Client:
Ref.
(Modify as required for unique customer requirements) Initials Initials Initials Date
YES NO

DIFFUSERS
X Receive and Release Diffusers Material.
X Provide and install diffusers to replace the existing one in accordance with the specified Drawing and WPS.
X Visually Inspect and Record on Form TARSCO-QA-01VT. Record the welder on the Install Drawing.

HANDRAIL
X Receive and Release Handrail Material.
X Install handrail in accordance with the specified Drawing and WPS.
X Visually Inspect and Record on Form TARSCO-QA-01VT. Record the welder on the Install Drawing.

GROUND LUGS (SS)


X Receive and Release Groundlug Material.
X Install Lug in accordance with the specified Drawing and WPS.
X Visually Inspect and Record on Form TARSCO-QA-01VT. Record the welder on the Install Drawing.

PAD PLATES TO SHELL AND BOTTOM and for STAIRS


X Receive and Release Pad Plate Material.
X Install Pads in accordance with the specified Drawing and WPS.
X Visually Inspect and Record on Form TARSCO-QA-01VT. Record the welder on the Install Drawing.

REMOVE NOZZLES M and N - INSTALL INSERTS


X Remove NOZZLES M and N
X Prepare weld preps for new plates
X Receive and Release Plate Material.
X Install Inserts in accordance with the specified Drawing and WPS.
Visually and RT/UT Inspect and Record on Form TARSCO-QA-01VT and Vendor's RT/UT Form. Record
X
the welder on the Install Drawing.

INSTALL PADS AND BRACKETS for AUTOMATIC TAPE GAUGE


X Receive and Release Pad & Bracket Material.
X Install Pads and Brackets in accordance with the specified Drawing and WPS.

W:\06 Projects\6547 VOPAK TK D 2151\QC Documents\TO JOSE FOR SUBMIT\ITP Data\QF-120 Field Inspection checklist API-650-653 VOPAK D-2151 tk Page 3 of 6
Project Number: 6548 Superintendent:

Tank Number: 2151 Client: VOPAK


Field Inspection Checklist
API 650 / 653 - Tank Construction Revision#: 0 Date: 7/26/2017
Form
QF-120 Rev: 06 API-650 / 653 12th / 5th Edition Add 2 / none
Where RT shown - AUT (PAUT) may be used. Location:
650/653
IN SCOPE See Applicable Procedures at the end of the FIP. Superintendent: Test Operator: Client:
Ref.
(Modify as required for unique customer requirements) Initials Initials Initials Date
YES NO
X Visually Inspect and Record on Form TARSCO-QA-01VT. Record the welder on the Install Drawing.

PAD PLATES TO BOTTOM - GAUGING BENCH SUPPORTS


X Receive and Release Pad Material.
X Install Pads in accordance with the specified Drawing and WPS.
X Visually Inspect and Record on Form TARSCO-QA-01VT. Record the welder on the Install Drawing.

REMOVE DECK PLATES AND INSTALL REPLACEMENT PLATES


X Remove Deck Plates
X Prepare and clean plates for new plates
X Receive and Release Deck Plate Material.
X Install Plates in accordance with the specified Drawing and WPS.
Visually and VB Inspect and Record on Form TARSCO-QA-01VT and -04VB. Record the welder on the
X
Deck Plate Welder Map Drawing.

INSTALL EFR PATCH PLATES


X Prepare and clean plates for new patch plates
X Receive and Release Patch Plate Material.
X Install Plates in accordance with the specified Drawing and WPS.

X Visually and VB Inspect and Record on Form TARSCO-QA-01VT and -04VB. Record the welder on the
Deck Plate Welder Map Drawing.

REMOVE AND REPLACE EFR NOZZLES H, L, and G


X Remove Nozzles H, L, G
X Prepare and clean plates for new nozzles
X Receive and Release Pipe Material.
X Install PIpes in accordance with the specified Drawing and WPS.
Visually and Diesel Leak Inspect and Record on Form TARSCO-QA-01VT and -12DT. Record the welder
X
on the Deck Plate Welder Map Drawing.

REMOVE AND INSTALL EFR PONTOON DECK, COVER RING and COVER PLATES
X Receive and Release Plate Material.
X Install Plates in accordance with the specified Drawing and WPS.
X Visually Inspect and Record on Form TARSCO-QA-01VT. Record the welder on the Install Drawing.

W:\06 Projects\6547 VOPAK TK D 2151\QC Documents\TO JOSE FOR SUBMIT\ITP Data\QF-120 Field Inspection checklist API-650-653 VOPAK D-2151 tk Page 4 of 6
Project Number: 6548 Superintendent:

Tank Number: 2151 Client: VOPAK


Field Inspection Checklist
API 650 / 653 - Tank Construction Revision#: 0 Date: 7/26/2017
Form
QF-120 Rev: 06 API-650 / 653 12th / 5th Edition Add 2 / none
Where RT shown - AUT (PAUT) may be used. Location:
650/653
IN SCOPE See Applicable Procedures at the end of the FIP. Superintendent: Test Operator: Client:
Ref.
(Modify as required for unique customer requirements) Initials Initials Initials Date
YES NO

INSTALL SPARE 8" NOZZLES


X Receive and Release Nozzle Material.
X Install Nozzles in accordance with the specified Drawing and WPS.
X Visually Inspect and Record on Form TARSCO-QA-01VT. Record the welder on the Install Drawing.

INSTALL EFR SEAL


X Receive and Release Seal Material.
X Install Seal in accordance with the specified Drawing and WPS, if applicable.
X Visually Inspect and Record on Form TARSCO-QA-01VT. Record the welder on the Install Drawing.

INTERNAL AND EXTERIOR BLAST AND PAINTING


X Blast and Paint in accordance the the vendors Paint Instructions, Checklist and ITP

DRAIN PIPE INSPECTION AND RE-INSTALLATION


X Disconnect Drain Pipe
X Inspect and Report Condition
X Based on Good Condition - Rinstall - IF NOT GOOD CONDITION - Notify Customer for Disposition

INSTALL FLOATING ROOF NOZZLE GASKETS


X Receive and Release Gasket Material.
X Install Gaskets in accordance with the specified Drawing and Manufacturer's Recommendation
X Visually Inspect and Record on Form TARSCO-QA-01VT.

INSTALL ALUMINUM DOME ROOF


X Receive and Release Dome Material.
X Install Dome in accordance with the specified Drawing and Manufacturer's Recommendation
X Visually Inspect and Record on Form TARSCO-QA-01VT.

INSTALL FOAM PIPING FLEXIBLE BOOTS


X Receive and Release Boot Material.

W:\06 Projects\6547 VOPAK TK D 2151\QC Documents\TO JOSE FOR SUBMIT\ITP Data\QF-120 Field Inspection checklist API-650-653 VOPAK D-2151 tk Page 5 of 6
Project Number: 6548 Superintendent:

Tank Number: 2151 Client: VOPAK


Field Inspection Checklist
API 650 / 653 - Tank Construction Revision#: 0 Date: 7/26/2017
Form
QF-120 Rev: 06 API-650 / 653 12th / 5th Edition Add 2 / none
Where RT shown - AUT (PAUT) may be used. Location:
650/653
IN SCOPE See Applicable Procedures at the end of the FIP. Superintendent: Test Operator: Client:
Ref.
(Modify as required for unique customer requirements) Initials Initials Initials Date
YES NO
X Install Boots in accordance with the specified Drawing and Manufacturer's Recommendation
X Visually Inspect and Record on Form TARSCO-QA-01VT.

W:\06 Projects\6547 VOPAK TK D 2151\QC Documents\TO JOSE FOR SUBMIT\ITP Data\QF-120 Field Inspection checklist API-650-653 VOPAK D-2151 tk Page 6 of 6