1. Introduction
1.1. Purpose of the Document

This Request for Proposal (RFP) is in response to <Company Name>s needs and
contains specific requirements to be met by the vendors proposed solution. The
objective of this project is to select and implement a new information system to address
<Company Name>s current and future financial, trading and distribution operations
needs.

This system will provide <Company Name> personnel with the necessary information to
support the daily operations and management of the business and meet their information
requirements for the future.

Time-scales for vendor selection are very aggressive, with the objective of completion of
implementation in the <place> by <date>. There will be a roll out to the other <Company
Name> companies in <list location> during <dates>.

The solution should support the business processes of <Company Name> <place> and
(later) the remaining countries either directly or through the vendors use of a third-party
solution. In addition, the system will need to interface with the newly installed Warehouse
Management System (WMS) in a real time mode.

Vendors have to respond to the price component of this RFP to the following:

Software Acquisition and Installation


Server Hardware Acquisition and Installation
Implementation Services
The vendors are required to review this document and submit their response as per the
schedule included in this document.

1.2. Confidentiality

This RFP, plus any other documents released, information provided, discussions, etc.,
as part of the selection process, are strictly confidential and should not be divulged to
anyone who is not directly involved in preparation of the response. Additionally, all
information within this proposal or gained during the RFP or other processes will remain
confidential by the vendor. No information or publicity will be allowed to any third party
unless specific written authorization is obtained from <Company Name> <place>.

It is a condition of this RFP that the information provided herein is for the purpose of
allowing vendors to submit proposals to <Company Name>. It may not be used in any
other context nor revealed to any other party not directly involved in the submission of a
proposal in accordance with the terms of the specification.

1.3. Terms and Conditions of the Proposal

1.3.1. RFP Responses

The closing date for receipt of proposals is: <date and time>

2007 gantthead.com 3
Information Systems Replacement
gantthead.com Proposal Request for Proposal

Response to the RFP shall be delivered to: <contact>

The proposal should be clearly labeled:

Proposal to <Company Name> for the Supply and Implementation of a New


Information System

A Vendor Submission Form will be submitted together with the RFP. An electronic
copy of this document called <NAMEOFTHIS.doc> (Microsoft Word Version
98) is included as part of the RFP pack for this purpose.

<Company Name> management reserves the right to accept or decline late


proposals at its absolute discretion.

The proposal should include the name of the person to whom <Company Name>
may address any questions relating to the proposal.

Respondents should provide four complete copies of the proposal. Only two
copies of any accompanying documentation are required. One electronic version
of the proposal in Microsoft Word (Version 98) is required, plus one electronic
version of the Microsoft Excel (Version 98) cost worksheet.

<Contact> should be contacted for supplementary information relating to this


RFP via the above contact details. All requests should be written. E-mail is
acceptable.

<Company Name> reserves the right to distribute any questions with <Company
Name>s reply to any vendor if it deems appropriate.

1.3.2. Preparation of Responses

The preparation and submission of the proposal shall be made without obligation
to acquire any items included in the proposal, or to discuss the reason why the
proposal is accepted or rejected. <Company Name> will notify acceptance or
rejection in writing to the vendor.

The requirements specified in this RFP reflect those presently known. <Company
Name> reserves the right to vary, in detail, the final requirements.

<Company Name> will not be responsible for or pay any expense incurred in the
preparation of any proposal or in <Company Name>s evaluation of it.

<Company Name> may require that all or part of the successful proposal be
included in the contracts.

All prices shall be consistently in US dollars and all unit prices, charges and
totals should be inclusive of tax.

Respondents should provide a clause by clause response to the RFP as


specified.

General information, which is not specifically requested, should be attached


separately and clearly labeled "Supporting Material".
2007 gantthead.com 4
Information Systems Replacement
gantthead.com Proposal Request for Proposal

1.3.3. Contract

This document does not constitute an offer to sell, or a solicitation of an offer to


purchase.

<Company Name> reserves the right to accept all or part of the proposal.

<Company Name> requires that contracts covering the provision of services and
equipment requested in this RFP be negotiated to the satisfaction of <Company
Name>.

All vendors are required to acknowledge that they agree to the conditions set out
in this section.

2. Business Background
2.1. <Company Name>

<Company Description>

2.2. <Company Name> Operations

<Company Description>

3. Current Systems
The following is sample language to show you how to describe each of your current
systems, what it does, what it covers, where it is and what it consists of.

New Branch Operations System (NBOS) This is the current Trading and Distribution
system. It uses Informix 5.1 and running under a HP 9000 Unix operating system for
metro operations and individual PC Server based SCO Unix for suburban sites.

The Trading and Distribution system covers the following:

Sales Order Management

Inventory Management

Purchasing

Accounts Receivable

Replenishment

FAMAS System 21 (Financial System/General Ledger) This is the current financial


system. It runs under an AS/400 model 600 located in <Company Name> Corporations
data center in <place>. Users are connected to the machine via leased line.

Nationwide Consolidation System This is a <Company Name> internally developed


system used for consolidating all NBOS transactions and provides nationwide
consolidated reports. In addition, it also serves as the interface between the NBOS

2007 gantthead.com 5
Information Systems Replacement
gantthead.com Proposal Request for Proposal

transactions and System 21. Currently, <Company Name> is building a similar system in
Informix to replace this system so as to be independent from <Company Name>. This is
expected to be up and running by <date>.

The functionalities of the Nationwide Consolidation System are the following:

Consolidation of Sales and Accounts Receivables

Automatic email of report to principals

G/L Interface

Warehouse Management System (WMS) This is the current system being used to run
the warehouse. It is running on a Windows NT and using SQL Server 7.0. The WMS was
just recently implemented and covered the warehousing functions formerly handled by
NBOS. Now it interfaces with NBOS through flat file (with fix data field length) upload to
synchronize and maintain data integrity on both systems.

The Warehouse Management System covers the following:

Pre-advice

Goods Receipt

Put-away

Stock Allocation

Replenishment

Loading, Dispatch, and Proof Of Delivery

Returns

Transfer Orders

Housekeeping/Maintenance

Reporting

Third Party Distribution System (TDIS) This is the system used to capture and report
sales from sub-distributors. This system is built using Visual Foxpro and runs on
Windows NT/95. Data files from Quickbooks coming from <Company Name>s sub-
distributor are uploaded to TDIS and sales reports are generated and given to
corresponding principals.

Assorted stand-alone systems created in Visual Foxpro running on Windows NT. These
systems support the various financial and human resources aspects of the business.
These systems are as follows:

Expense Reimbursement Monitoring

2007 gantthead.com 6
Information Systems Replacement
gantthead.com Proposal Request for Proposal

Head Office Expense Reimbursement Monitoring

Medical Reimbursement Monitoring

Branch Company Policies & Operating Procedure System

Company Policies & Operation Procedure System

Branch Cash Receipts & Deposits Monitoring System

Value Added Tax Monitoring System

Expanded Withholding Tax Monitoring System

File Indexing & Locator System

Human Resources Information System

On a regional perspective, the trading and distribution system being used in seven
different countries where <Company Name> is present are the following:

Application Platform
<place> GDS AS400
<place> MXP HP/Unix
<place> MXP HP/Unix
<place> MXP HP/Unix
<place> ILS AS400
<place> NBOS HP/Unix
<place> FITSin4/99 WindowsNT

3.1. System Interfaces

List all systems to be impacted and/or replaced. Detail interfacing requirements. See our
sample wording below.

The objective of this Information Systems Replacement is to select an appropriate


application package to replace the NBOS that is the Trading and Distribution system.
Apart from this, other systems will also be impacted or replaced depending on the
capability of the package. These systems are the (1) JBS FAMAS System 21 (Financial
System/General Ledger), (2) Nationwide Consolidation System, and various stand alone
financial systems.

The NBOS system interfaces with the WMS. These interfaces should be handled by the
new information system. Currently, the information passed to and from NBOS and WMS
consists of the following:

NBOS to WMS:

2007 gantthead.com 7
Information Systems Replacement
gantthead.com Proposal Request for Proposal

Shipment Orders

Purchase Orders

Item Master Updates

Invoices

Stock Transfer to Principal

Transfer Order

WMS to NBOS:

Receipt File

o Receipt from Principal


o Receipt from Branch
o Returns
Adjustments

o Internal Adjustments
o Returned Receipts Adjustments
o Stock Transfer to Principal Adjustment
o Transfer Order Adjustment
o Inter-Warehouse Transfer
Quantity Management

The NBOS system currently has interfaces with the Nationwide Consolidation System
and with the FAMAS System 21 (Financial System/General Ledger). It is required that
the new information system replace the FAMAS System 21 (Financial System/ General
Ledger) and Nationwide Consolidation.

Currently, the information passed from NBOS to Nationwide Consolidation System to


FAMAS System 21 (Financial System/ General Ledger) consists of the following:

NBOS to Nationwide Consolidation System:

Inventory

Sales

Accounts Receivable

Cash Receipts

Nationwide Consolidation System to FAMAS System 21 (Financial System /General


Ledger):
2007 gantthead.com 8
Information Systems Replacement
gantthead.com Proposal Request for Proposal

General Ledger Interface

Inventory

Sales

All the files being uploaded are in flat files with fixed data length format. It is also
possible that TDIS might be replaced by the new information system. Therefore, an
interface has to be developed to upload Quickbooks data file to the system. Another
possible interface in the future is General Ledger (G/L) consolidation from different
countries. This allows the ability of the system to remotely upload G/L data from different
countries, consolidate it at one location and generate company-wide financial
statements.

3.2. Hardware Environment

Describe your current hardware environment, including servers, networks, platforms,


etc. Note our sample wording for ideas.

The current hardware environment is comprised of a number of PCs, Unix servers,


Windows NT file servers, a Local Area Network (LAN) and a Wide Area Network (WAN).

The standard PC configuration used by <Company Name> is a 32 MB RAM with an Intel


Pentium processor. The existing PCs are a mix of Compaqs and Packard Bells.
Windows NT and Unix File Servers are running on IBM, Compaq and/or HP.

All LANs use Windows NT 4.0 as the Network Operating System and are based on
Ethernet/UTP cabling. The WAN was implemented by connecting all the LANs using
high speed (64 KB) leased lines, backed up by ISDN (128 KB) connections. The Hubs,
switches and routers are all standard equipment from Bay Networks, Cisco and Xyplex.

3.3. Office Automation

The standard office automation product of <Company Name> is Microsoft Office.


Therefore, the new information system needs to interface with the Microsoft Office suite.

<Company Name> uses Microsoft Outlook for messaging. This is currently connected to
the companys frame relay network.

3.4. Transaction Volumes

<Company Name> <Headquarters>:

AverageNo.ofInvoicesperDay 280
AverageNo.ofLinesperInvoice 12
AverageNo.ofPurchaseOrdersperDay 54
AverageNo.ofCheckVouchersGeneratedperDay 41

<Company Name> <Remote location>:

2007 gantthead.com 9
Information Systems Replacement
gantthead.com Proposal Request for Proposal

AverageNo.ofInvoicesperDay 1000
AverageNo.ofLinesperInvoice 4
AverageNo.ofFinancialTransactionsperDay 2750
4. System Scope
The system functionalities that <Company Name> is looking for is categorized into the
following:

Front Office

Sales Force Automation


Customer Inquiry
Customer Relation
Marketing and Promotions
Reporting and Analysis

Distribution

Order Management
o Order Entry (Web-Enabled)
o Order Processing (Discount, Promotion)
o Credit Limit Evaluation
o Order Tracking (Web-Enabled)
o Reporting and Analysis
Invoicing
o Debit Invoice
o Credit Invoice (Customer Return)
o Reporting and Analysis
Purchasing
o Purchase Plan
o Purchase Order
o Consignment
o EDI Support
o Reporting and Analysis
Inventory Management
Requisition
Inventory Transaction
2007 gantthead.com 10
Information Systems Replacement
gantthead.com Proposal Request for Proposal

Item Maintenance
Inventory Control (Stock Management)
Reporting and Analysis

Financial Management

Accounts Receivable
Accounts Payable
General Ledger
Fixed Asset
Pricing and Costing
Budgeting
Cash Management
Multi-Currency Management
Reporting and Analysis

Human Resource Management

Payroll Administration
Recruitment
Employee Development
Skills and Qualification

2007 gantthead.com 11
Information Systems Replacement
gantthead.com Proposal Request for Proposal

5. Statement Of Business Requirements


5.1. Sales

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

No. RequirementDescription SD MC SC Comments


General
1. Eachsalesman(oragroupofsalesmen)hasa
specificcodeassignedtoaspecificcustomer,
specificregion/areaandspecificproduct.A
product(orcategoryofproduct)isassignedto
morethanonesalesmananddistributedto
morethanonecustomer.
2. SalesmanClassificationtoatleastthreelevels
SalesForceAutomation/CustomerRelation
3. Customers/salesmencanplaceordersbyusing
acommonwebbrowser(thesystemhasan
orderentryscreenonaninternetbasedformat)
4. Thesystemshouldbeabletosuggestdelivery
dateontheorderentryscreen.Theestimate
dateofdeliverycanbeoverride(Thesystem
hasfacilitytosetupacustomer,linkuptopre
specifiedleadtimes.)

2007 gantthead.com 12
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


5. Aseparatefunctionwhereasuggestedorder
quantitywillbecalculatedbasedonthe
historicalsalesofacustomer.Thisfacilitywill
beavailabletoboththesalesmenand
customersuse.
6. Customers/salesmencankeeptracktheorder
statusbyusingacommonwebbrowser,asit
goesintoprocessing,pickinganddelivery
7. Thesystemhasfacilityoforder
acknowledgment
8. Thesystemshouldhaveabilityinwhicha
salesmancanaccessspecificinformationthat
onlyapplicabletohisorherassignment
(dedicatedcustomer),alsoremotelyusinga
webbrowser.Thisonlinequeryshouldbeable
toprovideinformationsuchas:
Historicalpurchasesofthecustomer

Accountreceivableperformanceofthe
customer
Creditstatuspercustomer

Complaint,inquiryandrequest

Historicalsalesofthecustomer

CustomerInquiry
9. Thesystemhasfunctionalitytologany
customersinquiryandassignownershipto
theirdedicatedsalesmen
10. EachInquiryhaseachstatus(e.g.solved,
unsolved)
11. Thesystemshouldbeabletoseparateeach
inquiryas:

2007 gantthead.com 13
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


Inquiry

Complaint

Request(e.g.requestforreturnspickup)

SalesTargetMaintenance
12. SalesTarget/ForecastMaintenancebasedon
thefollowing:
SalesGroup

Salesman

Principal

ProductClassification

Product

CustomerClass

Customer

ReportingandAnalysis
Sales
13. SalesReports(MonthtoDate,YeartoDate,
Daily)
inunits

intons

indollars

intonsanddollarsnationwide

intonsanddollarsregionally

BySalesman(bothindollarsandtonsper
line)
ByArea(bothindollarsandtonsperline)

ByRegion(bothindollarsandtonsperline)

BySKU

2007 gantthead.com 14
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


ByTotalProductCategory

ByPrincipal

NationalTotal

14. Salesorderhistorycanbekeptforuserdefined
period
15. Dailyitemreviewupdate
16. Salesvs.Targets(weeklyupdatepersalesman
perline)
17. Reviseinvoiceregisterbycustomershowing
theoutofstocks
18. SalesbyChannelbySalesmanbySKUby
Region
forInstitutionalAccounts

forBigKeyAccounts

forSupermarket

forGrocery

forDrugstores

forWholesalers

forConvenientStore

forRegionalDistributor

19. BranchFinalSummary
20. No.ofAccountsbuyingaspecificSKU
21. No.ofSKUscarriedbyaspecificaccount
22. Abletocaptureindividualcustomersaleseven
forCODaccountcustomers.
23. Providecustomersalestrendforanalysis
24. Salestrendanalysiscanbepresentedin
graphicalformat.
2007 gantthead.com 15
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


25. Providecustomerprofitandlossanalysis,
promotionandinvestmentrationbasedonuser
definedmethod.
26. Abilitytomonitorsalesperformanceduring
presetpromotionperiod
27. Supportmonitoringofcustomerinventory(e.g.
expirationdate,stocklevelandmovements)
andreplenishmentinsystem.
Merchandising
28. SecondaryDisplaycostsalesratio
byoutlet

byprincipal/product

29. PromotionResults(PostPromoAnalysis)
Salescostratiobyprincipal/product

SalescostratiobySKU

Capabilitytododailyanalysis

SalesForecasting
30. ForecastingModuleby:
Customer

Principal

CustomerInquiry
31. Reportofcustomercomplaints,inquiryand
request
perSalesman

perCustomer

BusinessReviewwithPrincipals/TradePartner

2007 gantthead.com 16
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


32. ProformaTemplateforReportsPresentedto
Principals
Graphs/Charts
CollectionandReconciliation
33. DailyCollectionandReconciliationReport
perSalesman

perPrincipal

perDistrict

5.2. Marketing

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

No. RequirementDescription SD MC SC Comments


Forecasting
1. Abilitytogenerateaprofitandlossanalysisper
principalbasedondifferentsalesforecast
figureswithpredefinedparameters
2. Abilitytoforecastproductsdowntothetrade
partnerlevel
MarketingPromotion
3. Abilitytokeeptrackpromotionaleffectiveness

2007 gantthead.com 17
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


Costtosalesratio(includesdeals,display
allowanceandotherpromotionexpenses)
DailySalesReportduringpromotionperiod

OnlineInquiry
4. Onscreenanalysistoolstohelpuseridentify
andtargetmarketsegmentsbasedonanyuser
definedcriteria
ReportingRequirements
MarketingandPromotionalExpenses
Bytypeofexpense(deals,posters,display
allowance,promogirls,etc.)
byproductline

bytradepartner

byprincipal

bypromotion

5. FreeGoodsRegister
6. ProfitandLossStatementPerProduct

5.3. Order Processing

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Asignificantcustomization(beyond2days)isneededtosatisfytherequirement.

2007 gantthead.com 18
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


OrderEntry
1. Eachsalesorderhasuniquesalesordernumber
2. Receivesorderquantityatamaximumof6
digits
3. Allowdifferentsourcesoforderinputsuchas
manualentry,EDI,POS,handheldcomputer,
MSAccessformat,MSExcelformatandWeb
enabledformat(fromsalesrequirements)
4. Abilitytoprovidedifferentsalesorderformor
screentofacilitateorderclassifications(e.g.,
regularorder,initialstockingorder,indent
order,officeorder,consignmentorder,
guaranteedbysupplierorder,creditoverride
orderorcustomerdefineorderformat,etc.)
5. Noteverysalesorderneedstobeinvoiced
6. Abilitytocanceltheorderbeforeinvoiceis
generated(withauthorization)
7. Salesmancodefieldasmandatoryontheorder
entryscreen.
Duringthesalesorderentry,thesystemshould
onlyviewthededicatedsalesmantobeplaced
(eachinvoicewillbecreditedtoproper
salesmanonly)
8. FacilityofCustomerShiptoAddressencoding
(multipleaddresscodeforonecustomeris
allowed)
9. Everyaddresscodehasitsdeliverygroupcode
anddeliveryremark

2007 gantthead.com 19
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


10. Optiontoprintoutinforeigncharacter/language
address
11. Abilityofmultiplecrossreferencetoanorder
(e.g.,ordernumber,invoicenumber,customer
purchaseordernumber,thirdpartyorder
number,thirdpartyinvoicenumber
12. Abilitytohaveuserdefinedorderstatuscycle.
(e.g.,completed,suspended,shipped,cancelled,
onhold).Eachorderstatusshouldhaveatime
stamplogforperformancetracing.
13. Abilitytoalerttheuserofoutofstockduring
orderentry
14. Facilitytohandleconsignmentsales
transactions
15. AlloworderinmultipleUnitofMeasures
(UOMs)peritem
16. Allowmultipleorderlineswiththesameitem
codeandUOM
17. AlloworderinEAN/Barcodeorotheritemcode
reference
18. Theorderentryscreenhasorderinstruction
field.(Atleast10ordercommentlines)
19. SupportcustomerPOnumberonorderentry
andwillbeincludedoninvoiceforreference
purpose.
20. Stockisreservedimmediatelyasthe
order/invoicelineenteredevenbeforethewhole
orderisconfirmed.
21. Minimumordervalueisdefinedat
company/divisionlevel

2007 gantthead.com 20
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


22. ForEDISupport,allowconvertingEDIPOto
S.O.withpredefinedvalues.ThePOwillbe
separatedbycompany/division/agency
23. ForEDISupport,duringconvertingEDIPO,
predefinedcustomergrouppricewillbeused;
ifnotfound,thenpricefromcustomerwillbe
used.
24. Handlenonproductsalesorders(e.g.,charges)
25. Allowuserspecificationofitemshelflifeat
orderentry.
26. Nostockdeductionforindent/damageorder.
Allowcostentryforindentorderatorderline
level.
27. Ordercanbedefinedfordiscretestockpicking
andconsolidatestockpicking.
28. Providesalesamountadjustmententrytoaffect
thestockledgersalesamountonly.
29. Providestockledgerquantityadjustmententry
toaffectthestockledgerquantitybalance
withoutaffectingwarehousestockbalance.
30. Providecostofsalesadjustmententrytoaffect
thestockledgercostofsalesamount.
31. Providestockvalueadjustmententrytoadjust
thestockvalueoftheitemwithoutaffecting
stockquantity.
32. Systemcanoptionallyconsolidateordersofa
customerwithmultiplesalesmenintoone
invoicedefinedatcustomerlevel.
33. Multiplewarehousescanbechosenforasales
order.
34. Providetouchscreenfeatureinorderentry.
2007 gantthead.com 21
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


35. Supportelectronicapprovalofsignatureon
system.
Invoicing
36. FacilitiestohandleMultiPrincipalInvoicing.
(ThesystemshouldbeabletohandleA/Rper
principal.)
37. Facilitytocancelaninvoice(withauthorization)
beforedelivery.
38. FacilitiesofOrderNotes/ShippingInstructions
onInvoice.
39. OptionalTaxCalculation(VAT)/TaxExempt
foreachInvoice
TaggingofcustomersanditemsasVATor
NonVAT
40. FacilitytoAddChargesonInvoice(e.g.,Freight
Charges,etc.)
Taggingofcustomershavingfreightcharges,
etc.
41. InvoiceSkewingFeature(abilitytohold
printingofinvoiceuntilactualdeliverydate)
42. Includeexpecteddeliverydateoninvoice.
43. SupportDeliverynote/Blanketorderhandling
44. Abilitytopromptpendinginvoicefordelivery
45. Optionformultipledeliverieswithoneinvoice
46. Printbarcodeofinvoicenumberandorder
numberoninvoiceandsalesorder.
47. Supportmultiplecurrenciesoninvoice.
48. Includeforensicclassificationofitemateach
invoiceline.
49. Allowsizeoforderquantityinfivedigits.
2007 gantthead.com 22
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


50. Facilitytodoapositive/negativeadjustmenton
aninvoiceandcreditmemo.(Adjustmentwill
affectsalesbutwillnotaffectinventory
quantities)
51. Allowuserdefinedcontrolforparticular
customerorcustomertypespurchasing
particularSKUorSKUtype.
52. Printremarksoninvoice(e.g.earlypayment
discount).
53. IncludeLetterofCredit(L/C)andcontract
numberoninvoice.
54. Supportprintingofdeliveryaddressinspecified
foreignlanguagesandcharacters.
55. Provideinvoicediscountvalueanddistribution
allowancesummarybyagencybyproductby
customerinformationmonthly.
56. Abilitytoinformcustomersofnearexpiration
productsbasedonrecordsofdelivery.
CreditEvaluation
57. Allowparameterized(userdefined)credit
blockingfacility(e.g.,percreditlimit,per
overdueaccount,percustomer,etc.)
58. Whenasalesorderisconfirmed,customer
credit/overduestatusandminimumordervalue
ischecked.Theorderwillbesuspendedifover
credit,overdueandunderminimumordervalue
(automaticcreditchecking/overdueaccount).
59. Abilitytocategorizecustomeronpredefine
valuesuchasgood/doubtful/badasaresultof
theaccountreceivableperformance.Systemto
maintainacreditwatch.
2007 gantthead.com 23
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


60. Customercreditavailabilityisautomatically
deductedonorderconfirmation.
61. Customersoverduestatuswillbeupdated
online.Providesamassupdatefunctionforuser
torecheckeverysuspendedorder.
62. Orderscanbereleasedautomaticallyifthe
customerisnotoverdue.(SeparateFullinvoices
andHangingBalance)
63. Abilitytoincludecustomersordersnotyet
deliveredandactivequotationsincreditlimit
checking.Abilitytoinquirewhatmakesuptotal
creditoutstanding.
64. Creditholdsalesordercanbedividedinto
reviewedorwaitingforcreditreleaseand
acceptinputofreasonforholding.
65. Allowmaintenanceonsuspendedordersand
updateimmediatelyafteranychangesmade.
66. Usercanmanuallysuspendanorder(i.e.,user
holdorder).Stockwillbeallocated.Butno
creditavailableisdeductedfromcustomer.
67. Allowuserdefinedminimumordervalue
checkingbycustomerorcustomergrouporby
customerorcustomergroupbyagency.
68. Optiontoviewonlytransactionsthatneedtobe
evaluated.
DealsandDiscounts

2007 gantthead.com 24
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


69. Supportsuserdefinedmultileveldiscounting
(atleastfivelevels)withitscode,description
andformula(basedonspecificagreementper
customer).For<CompanyName>,typesof
dealsareasfollows:freegoods(allowdifferent
itemasfreegoods),specialprice,itemdiscount
(linediscount)andInvoicetotaldiscount
(financialdiscount).
70. Abilitytoapplystandardprice/discountmatrix
percustomer/customergroupagainstitem/item
group/agencyonsalesordering.
71. Supportsautomaticgrantingofdealsaswellas
manualentryofdiscount.
72. Discountcanalsobedefinedbyamountper
quantityinsteadofpercentage.
73. Allowatleastfourdiscountinputfieldsateach
invoiceline,andeachfieldallowsinputofboth
percentageoramount.
74. Itempricecanbeexpressedasitemunitpriceor
priceperquantities.
75. Abilitytohavethedealsnumberprompts
automaticallyduringorderentryofspecific
productandcustomer,asaresultofpresetting
ofpromotionperiod.
76. Abilitytodefinethepricesandthediscountsas
pricelistsfordifferentgroupsofcustomers,as
generalpricesoraccordingtoindividual
customeragreements(userdefinedformulafor
eachcustomeranddiscounts).
77. Allowdifferentpricefordifferentitemunits.

2007 gantthead.com 25
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


78. Itempriceisretrievedfrompricetable
automatically.
79. Providesupervisoroverrideforpresetpriceand
discount.
80. Paymenttermscanbeoverriddenineachorder.
Paymenttermsinsalesordercannotexceedthe
customer'smaximumpaymentterm.
81. Displayfeeperagencyhandling.Multiple
displayfeeorderlineisallowed.
82. Grossdiscountcalculationcanbedefinedat
customerlevel.Usercanselecteithergrossor
reducingbalancediscountcalculation.
83. Threenexteffectivedatesareprovidedforitem
listprice,customergrouppriceanddiscount.
Theprice/discountwillrollupautomaticallyon
effectivedate.
Returns/CreditMemos
84. AutoRecallofInvoicesforCreditMemos
(userdefined,threeyearretentionperiod).
85. ThesystemhastoautomaticallygenerateCredit
Memosandupdateinventorylevelupon
confirmationofreturnonWMSExceed
86. Hasmaintenanceforreferencereasoncodeof
returntransaction,customizereasoncode
(interfacewithWMS).
87. Hasmaintenanceofsubreasoncodeforeach
reasoncode.
88. CreditNotecanbegeneratedtoeitherreferto
aninvoiceornot.

2007 gantthead.com 26
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


89. ForCreditNotereferredtoaninvoice,itemand
quantityreturnedmustcheckagainstthe
originalinvoiceautomatically.
90. MorethanoneReturn/CreditNotecanbeissued
againstthesameinvoice,andtheitemand
quantityreturnedbytheseReturn/CreditNote
shallbecheckedagainsttheoriginalinvoice.
91. AllowreturnindifferentUOMintheCredit
Noteagainsttheoriginalinvoiceforthesame
item.
92. Creditnotecancellationisallowed.
93. CreditNotecanbecancelledbeforeitis
applied/settledagainstinvoice.
DeliveryPerformanceMonitoring
94. Deliveryleadtimeisdefinedat
company/divisionlevel.Deliverydatewillbe
calculatedautomaticallywhichwillexclude
Saturday,Sundayandholidays.Allowuserto
specifywhetherthedateisexpectedorpending
persalesorder.
95. Abilitytomonitorsalesorderlifecyclefrom
salesorderdateuptodeliverydate.
96. Deliveryleadtimeisdefinedat
company/divisionlevel.Deliverydatewillbe
calculatedautomaticallywhichwillexclude
Sundayandholidays.Allowusertospecify
whetherthedateisexpectedorpendingper
salesorder.
97. RelateTimelinessofDeliverytoCompleteness
ofDelivery(OrdersDelivered,Complete,&
OnTimeODCOT)
2007 gantthead.com 27
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


ConsignmentProcess
98. Normalconsignmentdeliverytransactionscan
beprocessedwithConsignmentDeliveryNotes
printed.
99. Normalconsignmentsalestransactionscanbe
processedwithConsignmentSalesInvoices
printed.
100. Consignmentreturn(fromindividualcustomer
deliverylocationbacktomainwarehouse).
101. Autoconsolidationofallconsignmentstock.
102. Foranydamagegoodsreturn,systemautomatic
transfer/writeoffgoodstodamagewarehouse.
103. Supportinterconsignmentlocationgoods
transfer.
104. Maintainindividualcustomerinventoryper
delivery
105. Consignmentinventorycanbecapturedvia
handheldterminalsothatopeningstockcanbe
checkeddaily.
106. Allowusingscanningdevicetocapturestock
in/outandincludeincreaseofstockatitem
return.
107. Providedownloadofdailyclosingstockand
consolidationforidentificationofconsignment
salesvolume.
OfficialReceipt
108. AbilitytofacilitateentryofOfficialReceipt
whichcontainsBankAccount,BankNameand
Amount,linktoCR/DR(CashManagement)
109. AbilitytofacilitateDisbursementVoucher

2007 gantthead.com 28
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


110. Abilitytoacceptpostdatedchecksfor
succeedingmonths
BackOrder
111. Providesfacilityinwhichanyunservedorders
(specificallyforpriceprotectionanddeals)will
haveagraceperiod(setupasaparameter)fora
chancetobeservedbeforethesearecancelled
forrebooking(rePO).
112. Abilitytoprioritizebackorderstobeserved
basedonafirstcomefirstservedbasisorany
otheruserdefinedcriteria.
113. Providesfacilitytocancelunservedorder(not
fullyservedPOwillbecancelled).
114. Facilityofbackordermonitoringtodifferentiate
doublebookingusingauserdefinedperiodof
timetobecovered.
115. Backorderhandlingcanbedefinedat
company/divisionlevel.(Insufficientstock
frequencycanbecapturedforanalysis.)
ReportingRequirements
116. RegistersforSales,CM&InvoiceAdjustment
Transactions
117. Backorder/ServiceLevelReport(double
bookingnottobeincluded)
118. CreditHeld/BlockedSalesOrderReport
119. Orderstatusreportwithorderstatusselection
120. Suspendedorderreport
121. Gross&NetSalesReports(w/salesforecast)

2007 gantthead.com 29
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


122. AllOrderEntryReportsshouldbeflexible
enoughtobeproducedbasedoneachora
combinationofthefollowingcriteria:
ByDateRange/DateDefinition
(MTD/YTD/Comparative)
ByCompany

ByTerritory/Branch/Distribution
Center/ZoneDeliveries
BySalesGroup

ByCustomer

ByCustomerClassification

ByPrincipal

ByProductClassification(atleastfour
levels)
ByProduct

BySalesman

ByReasonCode(ForReturnsTransactions
Only)
134. DailyScheduledSODiscrepancyReport
135. Invoicepricevariationreport
136. Monthlystockmovementreport/datadownload
invariousrecordselectioncriteria.
137. BackOrderReport
138. ServiceLevelReport
OrderFillRate(DollarsandUnits)
LineItemOrderFillRate(DollarsandUnits)
DeliveryTurnaroundTime(toincludepartial
deliveriesforasingleorder)

2007 gantthead.com 30
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


142. Salesorderenquiry/reportbyseveralexternal
principals'referencenumbersshouldbe
provided.

5.4. Purchasing

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

No. RequirementDescription SD MC SC Comments


General
1. EachPOhasitsuniquePOnumberby
company/division.
2. Providevendor,item,POnumber,ETA
information,paymentterms,freighttype,
deliveryaddress,specialinstruction,PO#,date,
remark.
3. ProvideinquiryofPOstatus.
4. AbilitytomaintainPOPaymentTerms.
5. AbilitytoprocessaPOformultiplewarehouse
deliveriesandmultiPOforonewarehouse.
6. Abilitytolocateprincipalbyaccountnumber,
invoice,address,nameandtelephonenumber.
7. UsercanalsocreateaPOwithoutwarehouse.
8. SupportMultiWarehousePO.

2007 gantthead.com 31
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


9. HandlemultiplecurrencyPO.
10. WarehousecanbespecifiedwithinaPO.
11. SupportraisePObyitemwithbarcode,
customeritemcode,MOQ,CBM,weight,pallet
factorandvalue.
12. MOQcanbedefinedatagencyoritemlevelby
quantityandvalue.
13. AllowcreationofPObycustomeritemcode
withoutcreationofitemmaster.
14. IndentPOcanbeoffsetbyindentsalesinvoice
aftercreditapproval.
15. ProvidependingoroutofstockPOquantity
info,CBM&weight(includingdetailsofeach
outofstockPO)
16. Rollingforecastbasedonsaleshistoryforuser
maintainedperiodand/orsalesforecastforuser
nominatedperiod.
17. IndentPOcanbeoffsetbyindentsalesinvoice
aftercreditapproval.
18. Providesummaryreportbycompany/division,
agencyonoutstandingshipmentsandPOvalue
difference.
19. ProvidePOshortship&overshipinfoper
completedPO
20. Abilitytomonitorshipmentleadtime.
21. Purchaseitemshallassociatewith
vendor/vendors.Itemcannotbepurchasedfrom
nonassociatedvendor.
22. AllowovershippedquantityentryinPO
receipts.

2007 gantthead.com 32
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


23. Onorderquantityoftheitemisupdated
immediately
24. Vendoritempricecanbepresetby
item/vendor/currency/UOM.Forthcoming
purchasingpricecanbesetwithdifferent
effectivedates.
25. Systemshouldretrievetheitemlineand
remainingPOquantityautomaticallyuponPO
itemreceipt.
26. CancellationofshortshippedPOisprovided.
Theonorderquantityoftheitemsshouldbe
released.
27. POquantityinputcanbeselectedfromdifferent
UOMsofsameSKU.
28. AllowoverrideofPOunitcost.
29. Sameitemcanhavedifferentpurchasingprice
fromdifferentvendors.
30. Provideupdateofshippingcostatshipment
schedule.
31. POquantityuptofivedigits
32. UsercanpresetthedefaultFOB,shipviaand
carriercodeatcompany/divisionorvendor
accountlevel.
33. UnconfirmedPOitemreceiptisnotallowed.
34. UsercanselectdifferentPOitemtypes(e.g.
sellablestock,packingmaterials,POS)interface
toAccountsPayable.
35. Allowuserdefinedpurchasequota.

2007 gantthead.com 33
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


PurchasePlanandPOPreparation
36. FacilitytodevelopaPurchasePlanwithpre
definedparametersonproductandsaleshistory.
37. Allowusertodefineandmonitortarget/quota.
38. FacilityonsystemgeneratedPObasedon
TheoreticalStockLevelwitheditfacility.
39. FacilityformanualPOPreparation.
40. AbilitytocreateBlanketPurchaseOrder.
41. UsercanpresetthedefaultFOB,shipviaand
carriercodeatcompany/divisionorvendor
accountlevel.
POEntryandGeneration
42. Systemshouldprompttheuserforimmediate
POconfirmationandPOprintingjustafter
completionofPOentry.
43. Usercansetnottoprintthesystemitemcode,
priceandamountonthePO.
44. ThereshouldbeadefaultETA/ETDinthePO
header.
45. ShouldhaveaneditlistoncePOisprinted.
46. UsercanupdatetheETA/ETDonallitemlines
atonetimeinthePOmaintenanceprogram.
47. Thereshouldhavearelationbetween
vendor/divisionanditemsothatthesystemcan
searchvendorsforitemsduringPOentry.In
addition,theusershouldnotpurchaseitemfrom
vendor/division,whichhavenorelationwith
item.
48. Handlevendor'sitemcode.Itshouldbeprinted
onthePO.
2007 gantthead.com 34
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


Handlevendor'sitemUOM/conversionfactor
49. HandlenochargePOitemlineseparately
50. Onorderquantityoftheitemisupdated
immediately
51. Vendoritempricecanbepresetby
item/vendor/currency/UOM.Itshouldhandle
multipleeffectivedates.
52. HandlepartialshipmentwithinaPOdetailline.
53. Systemshouldretrievetheitemlineand
remainingPOquantityautomaticallyafter
receiptofPOitem.
54. POcanberevisedandthenreprintedevenits
statusispartialreceipt.A"REVISED"message
shouldbeshownontheprintedPOwithrevised
dateandcancellationofpreviousPO.
55. POstatusandlinestatusshouldbe
automaticallyupdatedafteritemreceipt.Handle
partialreceiptstatusatlinelevel.
56. CancellationofshortshippedPOisprovided.
Theonorderquantityoftheitemsshouldbe
released.
57. ProvideacopyPOfunctionforcreatingnew
similarPO.
58. Calculationmethodoffreightchargesportionin
itemunitcostcanbespecifiedduringPOentry.
Wecanspecifywhetherfreightandother
costingchargesaredividedbyCBMorvalue
foritemcostcalculationduringPOentry.
59. POpurgingautomaticallyshoulddeleteaging
POswithuserdefinedcriteria.

2007 gantthead.com 35
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


60. SystemRecallofPO'sforReceiving.
61. Discountsperpurchaseorderandpurchase
orderline.
62. Partialreceiptswithoptiontocancelpending
orderorwaitforfurtherreceipts.
Replenishment
63. Provideenquiryofcurrentandhistoricalsales
(minimumoneyear).
64. Providehistoricaldataasperuserdefined
periodorrange.
65. Provideaveragemonthlysalesdata.
66. Providestockmonthdataasperuserdefined
criteria.
67. Provideopeningstockbyitem.
68. Allowinputofforecasting/estimatedsalesin
comingmonths.
69. Providelinkagewithallshipmentstatus.
70. Provideautoreplenishmentsystem(i.e.,allow
setuppriorityonminimumstocklevelin
quantity/monthsandminimumMOQsothat
purchaseordercanbeautogeneratedwith
overridefunction).
71. Provideareplenishmentplanforatleast6
monthsbasedoncurrentinventoryleveland
estimatedsales.
EDISupport
72. Support13and14digititemEANwithcheck
digitvalidation.
73. Support13digitcustomerEAN.

2007 gantthead.com 36
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


74. SupportmultipleitemEANtooneitemcode
relationship.
75. Definecustomergrouppricebycustomergroup
byitemwithineffectivedaterange.
76. Defineproductdiscountbycustomergroupby
itemwithineffectivedaterange.
77. Defineorderparameters(e.g.salesman,order
type,etc.)asdefaultvaluesbycustomergroup
andagency.
78. InterpretEDImessageswithEANCOM
standard.
79. Extractdatafromhostandsendoutwardsin
EDIEANCOMformat(e.g.,invoices).
80. ConvertEDIPOtoSOwithpredefinedvalues.
ThePOwillbeseparatedby
company/division/agency.
81. DuringconvertingEDIPO,predefined
customergrouppricewillbeused;ifnotfound,
thenpricefromcustomerwillbeused.
82. AllowuserstocancelEDIPOwithreasoncode.
83. AllowuserstopurgeobsoleteoutstandingEDI
PObasedonuserdefinedperiod.
84. Predefineddefaultvalueswillberolledupat
daybeginprocess.
85. DuringconvertingEDIPO,predefined
<CompanyName>pricewillbeused.Ifnot
foundthenpricefromprincipalwillbeused
86. Fordifferentcustomers,samepieceof
informationwillbeextractedfromdifferent
positionsinadataelement.

2007 gantthead.com 37
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


87. Byusingcontrolparameterper
co/div/customer/timeperiod,theEDIPOwill
eitherundergosalesorderprocessautomatically
orbesuspendedforapproval.
88. Allowtodefineextradiscountby
company/division/customer/branch/timeperiod.
ReportingRequirements
89. Daily/MonthlyROICreportshowingitem
receipttransactionanditscost.
90. Onorderreportbycurrency/POnumber/vendor.
91. POreceiptsbyitemreport.
92. POinformationcanbedownloadtoPCfiles.
93. OutstandingPOreport.
94. POvs.ReceiptReport(inunitsandcost).
95. ServiceLevelReportperSupplier.
96. ExceptionreportsforinvalidPOs.
97. Customergrouppricelistbycustomergroupby
item.
98. Productdiscountlistbycustomergroupbyitem.
99. O/SEDIPOenquirybyEDIreferenceno.
100. EDIcustomerPOlistingforvalidPOs.
101. ReprintEDIcustomerPOlistbyspecifying
rangeofEDIreferenceno.
102. Statisticalreports
103. Providesummaryreportbycompany/division,
agencyonoutstandingshipmentsandPOvalue
difference.

2007 gantthead.com 38
Information Systems Replacement
gantthead.com Proposal Request for Proposal

5.5. Inventory Management

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

No. RequirementDescription SD MC SC Comments


ItemMaintenance
1. Thesystemhastosupportalphanumericitem
codes.
2. Itemcodehasatleast22charactersandits
descriptionhasatleast35characters.
3. Aflexibleandcomprehensiveitemhierarchyto
handlethemanytomanyrelationshipwithfull
abilitytotrace(e.g.,warehouse,agency,group,
UOM,principal,countryoforigin,shipment,
lot/batch,expirydate,costetc.).
4. Supportslot/expirydatetrackingfacility.
5. CaptureUOM,parentandsonrelationship,
dimensions,weight,palletpattern,lotcontrol,
serialcontrol,expirydate,etc.
6. Asingleitempossessesmultiple(atleastfive)
sellingUOMs(i.e.packsize).
7. SupportstheoreticalstocklevelperSKU,re
orderlevelperSKU(basedonhistoricalsales).
8. ThesystemhasSKUClassification(atleastfive
levels)withreferenceclassificationmaintenance.

2007 gantthead.com 39
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


9. ProvidesmaintenanceofSKUphysical
dimensions(length,width,height,weightand
volume).
10. UserdefinedFEFOorFIFOforeachSKU.
11. ProvidesUnitOfMeasurementmaintenance(per
SKU).
12. SupportsmultiplelogicalwarehousesperSKU.
13. Supportsitemtypes,categoriesandclasses(e.g.,
consumerproducts,foods,poison,drugs,etc.).
14. Includemultiplecrossreferencesandaccesstoa
productdowntoSKU/batch/costlevel(e.g.,
barcode,EAN,customer/vendorcode).
15. Supportsitemtaggingasfollows:
Suspended

Itemnotavailableforselectedorall
transactions
ItemsuspensionforallDistributionCentersor
selected
Onesonly
Restricted(itemavailableforsellingto
selectedcustomersOnly)
16. SupportsKitProductCapability
17. SupportsBarcodeReadyInventoryMaster(Case
BarCode,UnitBarCode).
18. Providestrackingofitemmaintenancehistory.
19. Handlealotofstockthathasthesamelot
number,butwithdifferentexpirydates.
20. Purgeobsoleteitemcodesatregulartimeperiod
basedonuserdefinedperiod.
21. Capturecustomerandsupplieriteminformation.
2007 gantthead.com 40
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


22. Supportsitemsearchingbydescription.
23. Allowcopyinitemmaintenance.
24. Inactivationallowedifnoinventorybalanceand
salesovertwoyears.
25. Onelineofpackinginformationforspecific
countriesortomeetotherregionrequirements.
26. Itemmastermaintenancetieupwithprereceipt
costs.
27. Itemmastercanbeuploadedfrom
Excel/databases.
28. SupportsmultiplecostsundereachSKU.(Stock
withdifferentcostshavetheirindividualstock
balance.)
29. Specialclassificationandhandlingfor
poison/dangerousdrugs.
30. Stockadjustmentcanbedoneinlocatable
warehousewherethestockbalanceiszero.
31. Optionallyallownegativestock.
32. Supportbothstockitemandindentitem.
33. ItemmastercanbedefinedbySKUwith
minimum/maximumstockingperiod.
34. Customermastercanincludedefinitionof:
Tradingterms,promotionfunds,flatrebate,
etc.
Majorornonmajorcustomers.
Address,creditterms,multicurrencies.
35. SupportVendormaster.
36. Providemasterfilesdataforreporting.
37. Securitysetonagencylevel.

2007 gantthead.com 41
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


38. Authoritycheckingofcostinginformationon
displayandreporting.
39. Multiplelevelitemgroup.
40. Multiplelevelcustomergroup.
41. Productdescriptioninspecifiedforeign
languages.
42. Productphotocanbestoredintheitemmaster.
InventoryTransactions
43. Inregardswithstockreturnsfromcustomer,the
systemhastosupportStockTransferto
Principals(STP)withSTPreasoncode.
44. Supportautostocktransfertoprincipals,
triggeredbyCreditMemotransactionwhose
reasoncodeisanAutoSTPreasoncode.
45. SupportsTransferOrder(transferoutto
branch/distributioncenter).
46. SupportsTransferIns(ReceiptfromBranch
Transfers).
47. SupportsInventoryAdjustmentTransaction
(withinventoryreasoncode).
48. SupportsInterwarehousetransfer(transfer
betweenlogicalwarehouse).
49. SupportinventoryadjustmentandSTPreason
codemaintenancewithfacilityforsub
classification.
50. SupportsStockWithdrawalwithreasoncodes.
51. Providereservedquantitybyitembysalesman.
52. Providereservedquantityenquirybyreference
number.

2007 gantthead.com 42
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


53. Uponstockallocation,systemcanautodeductby
lotlevelandavailablequantity.
54. Displaystockstatuswithstockingmonth.
55. Allowenquiryofstockintransit.
56. Salesorderstockallocationcanbedowntoitem
level,batchlevelandexpirydatelevel.
57. UserdefinedstockingpolicyperSKUas
FEFO/FIFO.
58. Stockaginginformationwithreferencetoarrival
dateasperbatchperexpirydateandperreceipt.
59. Stockbalancesarekeptasperitem,UOM,batch,
expirydateandperreceipt.
60. Acceptdifferentcostfordifferent
customer/customertypeonsameSKU.
61. Multiplewarehousestransferfunction.
62. AutoconversionofUOMinPOreceipts.
63. Incorporatebarcodescanningsystemonshelf
level.
64. Allowstockreservationbycustomer/customer
type.
65. Issuerepackingrequest,quotationofpackaging
cost,stocktransferandconfirmation
electronicallyw/opaperdoc.
66. Providestockreservationinformationper
customertype/customerperSKUperUOM.
67. Providedummystockhandling.
ReportingRequirements
68. Inventoryregisterscontainingquantityanddollar
(costandselling)valuesofall.

2007 gantthead.com 43
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


69. Inventorytransactiontypesbasedonthe
followingcriteria:
ByDateRange

ByReferenceNumber

ByCompany

ByTerritory/Branch/DistributionCenter

ByPrincipal

ByProductClassification(atleastfour
levels)
ByProduct

70. StockMovementReport(inUnitsandinCost)
Showsbeginningbalancefortheperiodand
thepeso/quantitysummaryofeachinventory
movementtypeofeachSKU.Thelastcolumn
showstheendingbalancefortheparticular
SKUandlogicalwarehouse.
Thereshouldbeanoptiontoshowthisreport
bylotnumber
71. StockCardReport
ShowsthedetailedtransactionofeachSKU
perwarehouse.Theendingbalancereflected
shouldtallywiththeStockMovementReport.
72. InTransitsReport
73. InventoryOrderAnalysisReport(containing
unitsandcost).Relevantinformationforthis
reportwouldbeasfollows:
Sixmonthshistoricalsales(average&per
month)
TheoreticalStockLevel

2007 gantthead.com 44
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


QuantitytoOrder(asrecommendedbythe
system)
InTransit

Over/UnderStockQuantity

74. StockStatusReport(InventoryReportwithTotal
InventoryCost&CostofSalesFigures)with
columnforPOBalances,TIL,DaysCovered:
ByDistributionCenter

NationwideFigures

75. Itemavailabilityenquiryandreportshowingon
hand,available,allocated,onorder,backorder
andintransitquantities.Showbyitemby
warehouse,orbyitembylot.
76. Inventorytransactionenquirybywarehouseby
item.
77. Dailyandmonthlyinventorytransactionreports.
78. Dailyandmonthlyoccupancyreport,breakby
warehouse/agency/itemlevel.
79. Stockagingreportby
co/div/agency/item/warehouse.
80. Expirydatereportby
company/division/agency/item/warehouse.
81. Stockagingreportbyperiodwithstockvalue,by
co/div/agency/item.
82. Lotmovementcanbetrackedusingbatchcontrol
recallreportbyitembylot.
83. DailyandmonthlyROICreport.
84. Controlreportsformonitoringstockbalance
discrepancy.
85. Weeklyreceiptsummaryreport.
2007 gantthead.com 45
Information Systems Replacement
gantthead.com Proposal Request for Proposal

5.6. General Ledger

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

No. RequirementDescription SD MC SC Comments


General
1. Abilitytocreatememoaccountsfornon
financialtransactions.
2. Preventpostingsametransactiontwice.
3. Abilitytocompareactualyeartodateandmonth
againstbudgetedandprioryearfigures.
4. Abilitytomaintainmultipleexchangerateswith
predefineddates.
5. Abilitytomaintainforwardrates.
6. Abilitytoautomaticallypostexchangevariances
toavarianceaccount.
7. Abilitytoconvertcurrencyduringtransaction
input.
8. Abilitytosupportforwardexchangecontracts.
9. Electronicinterfacewithbankingsystem.
10. Abilitytohandleforeigncurrencytransactions.
11. Abilitytohandlemultiplebankaccountsin
multiplecurrencies.
12. Simulatefinancialplanningscenariosasitrelates
topredicting.

2007 gantthead.com 46
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


13. Inventoryinvestmentbylocation.
14. Allocatetransportationcoststothedistribution
centers.
15. Warehousespacerequirements.
16. Laborrequirementsandequipmentneedfor
distributioncenters.
GeneralLedger
17. Abilitytohavechartofaccountscovering
multiplelegalentitiesorseparatechartsatusers
discretion.
18. Chartofaccountscodemusthaveatleasteight
charactersforaccountname.
19. Threecharactersforagencycode.
20. Threecharactersforareacode.
21. GLaccountcodemusthaveatleastthree
charactersforcompanycode.
22. Threecharactersfordivisioncode.
23. Pluschartofaccountscode.
24. Systemshouldbefullyintegratedandrealtime
onlineupdate.
25. Abilitytokeeponlyoneaccountingperiodopen
fortransactionposting.
26. Userscompany/divisionsecurity.(morethan
100divisions).
27. Allowmergingandswappingofdivisionsand
companies.
28. Accountingcalendarmaintenancewithpassword
control.

2007 gantthead.com 47
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


29. Periodforfiscalyearisatleast12to99ina
calendar.
30. Changeofaccountperiodtobecontrolled
manuallyorautomatedinmonthendprocess.
31. Aclosedperiodcannotbereopened.
32. Shouldnotallowbackwardand/orforward
periodposting.
33. Acrossledgerpostingfunctionforeach
transactiontype(JV,PU,PV,RV,PC,DN,CN)
withautomaticallyverification,withthescreen
formatjustlikeanelectronicdocument.
JV=Journalvoucher
PU=Purchasevoucher
PV=Paymentvoucher
RV=Receiptvoucher
PC=Pettycashvoucher
DN=Debitnote
CN=Creditnote
34. Automaticassignmentofvouchernumberwith
optionsformanualchanges(withauthorization).
35. Printvouchersheetforeachtransactiontypeand
posttoaccountafteruserfillsinallinformation
totheelectronicdocumentandconfirmationby
authorizeduser.
36. PrintoptionforcreditnoteforCNentryinthe
electronicdocument.
37. PrintoptionfordebitnoteforPVandDNentry
intheelectronicdocument.
38. Allowuserinputareasoncodewithtwodigits
andkeepintransactionrecord,whenfillinginthe
PVelectronicdocument.
2007 gantthead.com 48
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


39. InPUelectronicdocument,allowuserpressa
functionkeytodisplayallROICrecordsofaGL
dummyaccountforusertoselect,then
consolidatewithotherentriesandposttoAP
vendoraccount,thenprintPurchasevoucher
sheetafterconfirmedbyauthorizeduser.
40. AbilitytoextracttransactionfromGLandAP
systems,thenoutputtoafileintext/excelformat
underuser'scriteriasetting.
41. AgoodreportwriterinGLfortheaccountstaff
toproducetheirownfinancialreportsandwith
summaryfiledownloading.
42. Thesystemshouldnotpostunbalancedjournal
entries.Screenpromptswhenjournaldoesnot
balance.
43. Allowrejectedjournalstobeheldinsuspense
accountforcorrection,deletionorretry.
44. Capabilityofreversingallpostedjournals.
45. Allocationofrecurringexpensestodifferent
accounts.
46. AfunctionCrossLedgerJournalEntryforuser
toposttransactionstoGL,APandAR(non
trade)atsametimewithsamejournalnumber.
47. AfunctionCrossLedgerPaymentEntryfor
usertoinputpaymenttoGL,APandAR(non
trade)atsametimewithsamejournalnumber.
48. AllowcopyfunctionforGLaccountmasterin
companyand/ordivisionlevel.
49. Consolidationaccountmaintenance.
50. Bankreconciliation.

2007 gantthead.com 49
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


51. Endofyearprocess:
Prioryearendclosingadjustmententry.

Postyearendclosingadjustmententry.

Yearendclosingresettrialrunsandfinal
run
OnlineInquiry
52. Accountbalance,budgetvs.actualforcurrent
yearinquiry.
53. Transactioninquiry.
54. Generalledgerreport.
55. Trialbalance.
56. Dailytransactionlist.
57. Generalledgerreportwithselectionfor6digit
accountsand12digitaccounts.
58. Dailyreconciliationcontroltotal.
59. Consolidatedaccountstructureinquiry.
60. Consolidatedbalancesinquiry.
61. CheckInquiry.
62. CancelledCheckInquiry.
63. Abilitytorecognizeintergrouptradingand
interfacewithappropriategeneralledger
accounts.
64. Automaticpostingofbankchargestogeneral
ledger.
65. Generalledgerinterfacestorecognizecostatthe
differentstandardcostlevelsorthedifference
betweenthem.

2007 gantthead.com 50
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


66. Abilitytoautomaticallylinkinternalcustomers
torelevantGeneralLedgeraccountsamples,
staffsales,etc.
67. Abilityforautomaticpostingofsubledger
balancestothecontrolaccountintheGeneral
Ledger.
68. Abilityforamultiplehierarchyofgeneralledger
toexist(atleasteight)andtoallowreportingand
analysisacrossthoseledgers.
69. Abilitytouploadfromspreadsheetsintorelevant
ledgersbothGLandsubsidiary,ifrequired,to
ensureadequatelydefinedsecurity.
70. SummarylevelinformationtobekeptinGL,
withabilitytodrilldownfromtheGeneral
Ledgerthroughtothesubsidiaryledgerstothe
originalentrysourcewithouthavingto
physicallymovefromonemoduletoanother.
71. Automaticupdatewithrealtimeprocessingof
journals.
72. Abilitytoautomatethereconciliationprocess
withthesubsidiaryledgers.
Budget
73. Abilitytocreatebudgetswithdifferentlevelsof
detaildependingonrequirement(e.g.,company,
division,departmentetc.).
74. Abilitytocreatebudgetsatuserdefinedlevels.
Somelevelsshouldbememobudgetsthatdonot
feedthroughtomainbudget.
75. Abilitytocreatemultiplebudgetsforsamecost
centers(forbudgetreviews).

2007 gantthead.com 51
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


76. UploadbudgetfiguresfromPCtohostcomputer
andalsokeeprevisionhistory.
77. Abilitytoautomaticallygenerateadraftbudget
frompreviousyearsactualorbudgetsusing
userdefinedparameters.
78. Abilitytomaintainlastyear,currentyearand
nextyearsbudgetinthesystem.
79. Automatedbudgetprofilingbasedonpast
performanceanduserparameters.
80. ProvidewithinGeneralLedgerBudgeting
Module
thefollowing:
Facilitytocopyonespecificbudget(cost
center)toanother.
Facilitytodeleteonespecificcostcenter
budget.
81. Permitmultiplebudgetsforsamecost/profit
centers.

5.7. Accounts Payable

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

No. RequirementDescription SD MC SC Comments


General
2007 gantthead.com 52
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


3. AlphanumericPrincipal/SupplierCodewithat
least:
4. Onecharacterfordivision

5. Onecharacterfornature

6. Threecharactersforagency

7. Twocharactersforcurrency

8. Onecharacterforaccounttype

9. MaintenanceofPrincipal/SupplierPayment
Terms.
10. Principal/SupplierClassificationasto
ConsignmentorDirect.
11. MonitorPrincipal/SupplierInvoicesvs.RR.
12. AgingofPrincipal/SupplierInvoices.
13. AutogenerateanAPrecordfromPOaftergoods
receiving(integratewithWMS).
14. Allowmultiplecurrencytransactions.
15. Autoprintcheckswithremittanceadviceand
securitysettings.
16. Allowmanualinputofcheckentries.
17. Abilitytoconsolidatepayments.
18. DailypostingofAPtoGLbatchorinteractively.
19. Allowdifferenttypesofdebitnotes(fortrading
accountandnontradingaccounts).
20. Abilitytogenerateduelisttoissuepayment
(eitherautoormanualcheckprinting)and
integratetosystem.
21. Generatetransactionsforserviceaccounts(e.g.,
recurringandmiscellaneousexpenditure).

2007 gantthead.com 53
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


22. Masscash/checkpaymententry.
23. Whencheckisvoided,theabilityto
automaticallyreversetransactionposting.
24. Cancelpaymentrun.
25. Promptpaymentstocreditorswithdebitbalance.
26. Allowspaymenttocreditorswithdebitbalance.
27. Allowsonlyauthorizedpersonneltoapprove
invoiceamountshigherthanthecontractprice.
28. Creditnote/creditadjustmententrywithonline
applicationoption.
29. Carryopenitemstonextperiodifstillopened.
30. Allowusertochangethevendorreferenceand
duedateofaninvoice.
31. Promptuserofexistingsimilaritiesininvoice
numbers.
32. Supportselectronicfundtransferwiththeability
toemailorfaxpaymentdetailsautomatically.
33. Matchapplication/matchtooutstandingitems.
34. Canceltransaction/journal.
35. Purgehistoryrecordsbasedonuserdefined
period.
36. Cashforecastupdate.
37. Processexternaljournals.
38. Interfacewithbankreconciliationmodule.
39. Providesalesmancommissionratecalculation
basedonitemsales/agencysalesbysalesman.
40. Processaccrualsjournal.
41. Processfixedexpenses.

2007 gantthead.com 54
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


42. Printmonthlyreports:
43. Ageddetailreport.

44. Agedsummaryreport.

45. APledger.

46. APstatement.

47. APsummaryreport.

48. Recalculateagingmonthly.
49. Movesettled.
50. Purgetransactionsfromproductionsystembut
shouldbeabletoretrievetransactionsonauser
definedperiod.
51. Automaticcomputationofwithholdingtax.
52. Generatewithholdingtaxcertificateper
supplier/principal.
53. Alphalistingoftaxwithheldfromdifferent
companies.
54. AutomaticcomputationofValueAddedTax
(VAT).
55. Closedperiodcannotbereopened.
Onlineinquiry/Reports
56. AgoodreportwriterinAPfortheaccountstaff
toproducetheiranalysisofreports.
57. Vendortransactioninquiry.
58. Vendorbalanceinquiry.
59. Cashforecast.
60. DatabasesearchforvendormasterandAP
transactionrecordsbyseveralsearchingcriteria.
61. Dailytransactionlistwithreconciliationcontrol.
2007 gantthead.com 55
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


62. Ageddetailreport.
63. Agedsummaryreport.
64. Matchreferencereport.
65. APledger.
66. APstatement.
67. APanalysisreport.
68. Vendormasterlist.
69. TotalDisbursementperBank.
70. TotalCancelledChecks.
71. PaymentHistoryperSupplier.
72. OutstandingPayments.
73. StockStatusReport.
74. StockMovementReport.
75. StockInterfaceReport.
76. InventoryInterfaceReport.
77. ReceivingReportRegister.
78. TotalInventoryCost.
79. Summaryofpostableaccountbyprincipal.

2007 gantthead.com 56
Information Systems Replacement
gantthead.com Proposal Request for Proposal

5.8. Accounts Receivable

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

No. RequirementDescription SD MC SC Comments


Classification
1. Alphanumericcustomercode(atleastnine
characters)
2. FiveforCustomerCode

3. Fourforbranch/division/subsidiary

4. Referencefileforcustomerclassificationin
termsofthefollowing:
customerbusinesstypesupermarkets,drug
stores,topkeyaccounts
customeraccounttypeactive,inactive

7. Shiptoaddressmaintenanceforeachcustomer

8. Automaticmonthlyupdateofcreditlimitbased
onsalesvolumeandpayinghabits.Basicformula
forcreditlimitissixmonthsaveragesales
multipliedbypayingfactor.Payingfactoris
determinedbyhowquickcustomersettleshis
account.
BouncedChecks

2007 gantthead.com 57
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


9. BouncedChecksEntryinReferencetoOR
Number
10. BouncedCheckReasonCode(e.g.,Insufficient
Funds,StopPayment)ReferenceFile
11. AutoDebitNoteGenerationforeverybounced
checkentered.
A/RAdjustments
12. Handlebouncedcheck.(Donotreverseinvoice
entry,butgenerateabouncedcheckdebitand
offsetbyabouncedcheckpaymentlater).Ifthe
invoicewasalreadypurged,itshouldberevived.
13. A/RAdjustmentEntryinreferencetoOpenAR
Itemwithrestrictions.
14. A/RGovernment,PrincipalCertificate
TransactionsinreferencetoOpenA/RItem.
15. Allowcreditnoteentrythatwillaffectsalesentry
forSAadjustment,andallowonlinematchto
debittransaction(i.e.,invoice,debitnote,debit
adjustment)
16. Allowdebitmemoentry,thatwillaffectcash
entryforSAadjustment
17. Allowcreditanddebitadjustment/journalentry,
nonsalesrelatedandallowonlinematchtodebit
transaction(i.e.invoice,debitnote,debit
adjustment)
18. Matchapplicationforusertoassigntheopen
credittransactiontodebittransaction.
19. Printingofdebitandcreditmemo.

2007 gantthead.com 58
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


20. Onceaninvoiceisgeneratedforasalesorder,an
ARrecordhastobecreatedonlineandthe
customermastersbalancehastobeupdated,as
well.
21. ReturnsshouldhaveareferenceInvoiceNumber
sosystemshouldbeabletoautomaticallytrace
fordiscountsgivenforthereturns.
TransactionRegisters
22. TransactionRegistersforallA/RTransactions
indicatedabovetogetherwithSalesandReturns
Transactionstobeproducedusinganyora
combinationofthefollowingcriteria:
A/RTransactionType
ByDateRange/DateDefinition(MTD/YTD)

ByCompany

BySalesGroup

ByTerritory/Branch/DistributionCenter

ByPrincipal

BySalesman

ByReasonCode

ByCustomerClassification

OfficialReceipt
23. OR/DVEntryWithReferencetoInvoice
Amount(oneormultipleinvoiceapplications)
24. ReferencefileforDeductionVoucherReason
Codes

2007 gantthead.com 59
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


25. Inputpaymentbybatchandacheckagainsttotal.
Ascreentodisplaytheinvoicesandallowthe
usertoselectwhichinvoicetosettle.
Needtohandlepartialpaymentandunallocated
credit/cash/deposit.
26. Paymentreentryfunction.

27. Asuspensecustomerforeachnormaltrade
customerissetupfortemporarycontainsthe
disputeorunallocatedtransactions.
28. Extrastatementsforsomecustomersareprinted
atmonthend,uponcustomersrequestfor
reconciliationandreference.
29. Asubmoduletohandlepostdatedcheckwith
longmaturityperiod.
30. Printreceiptwithdetailsofcheck/cashpayment.

31. Cashierautomationmonthlypaymenthistory
extractionanddownload.
32. Cashierautomationmonthlyobsoleterecord
deletion.
33. OR/DVRegister
BySalesman

ByPrincipal

ByInvoiceTransaction

ByOutlet

StatementofAccount
34. Aseparateaccountcanbecreatedforallaccount
indisputetogetatruepictureoftheAccount
Receivablebalance.
2007 gantthead.com 60
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


35. Statementsforthesecustomersareprintedat
monthend,butnotsendtocustomer,andkeep
forreconciliationandreference.
36. AllowARtransactiontobetransferredfrom
customertocustomerorfrombranchtobranch
withoutchangeoftransactiondate,duedateand
transactionreference(withrestrictionofuse).
37. Autoprintcollection/reminderletteronoverdue
accountpredefinedbytheuser.
38. Abilitytohavedifferentthemeofletter
dependingontheagingofreceivables(e.g.,30
daysletter,60daysletter,90daysletteretc.)
39. Acontrolfunctiontoinputcollectionmemoand
reminder.
40. Abilitytoprintstatementofmultiplecurrency
withaging.
41. Separateconsignmenttransactionfromregular
transaction.
CreditReview
42. Overduebypassflagmaintenance.

43. Onlinereagewithsinglecustomerorall
customers;resetoverdueflagwithgraceperiod.
44. Extendedcreditlimitfortemporarycredit
allocation.
45. Postdatedcheckregistermodulewithintegration
toinvoicessettlement.
46. Aflexibleanduserfriendlyreportgenerator
programforadhocoronetimeinformation
manipulation(togetherwithagooddata
warehouse).
2007 gantthead.com 61
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


47. PaymentdatawithcustomerPOnumberfrom
bank/customer,andmatchtotheirordernumber
andourinvoicenumber.
48. Creditreleasebasedoncustomerscreditterms
andgracedaysadded.Thisshouldbemaintained
incustomermasterrecord.
49. Agingreporttheagingcolumnsdayssetting
canbechangedandaddtwomorecolumns.
50. Onlinereagewithsinglecustomerorall,reset
overdueflagwithgraceperiodwithrestrictions.
51. Paymenthistoryforpaymentanalysis,e.g.,
invoiceduedatetopaymentdateanalysis,
paymenttermsanalysis.
52. OpenitemsinARsystemarepreferred.Balance
broughtforwardwithoptionfordetail
breakdownalsoaccepted.
53. Customermasterrecordsmaintenancehistory
anddetailforinquiryandaudittrial.
54. Onreceiptofapaymentfromacustomeranearly
discountmayhavebeentaken.Thesystemneeds
tobeabletocalculate/capturetheearlydiscount
andidentifythebranchandthecustomerto
whomtheearlydiscountbelongssothatprofitby
branchandcustomercanbecalculated
incorporatingtheearlydiscount.
55. Collectionperformanceanalysisbasedon
collectiondateandcustomerinformation.
EndofDay,Month,YearProcessing
56. Endofdayprocess

2007 gantthead.com 62
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


57. DailyinterfacetoGL

58. SOtransactioninterfacetoAR

59. Massreaging

60. Resetoverdueflagwithhandlingofgrace

daysbasedonuserdefinedformula
61. EndofmonthNormalmonthendReset
MTDfigures
62. Changeperiod/year

63. ClosedtransactionnormalEOMpurging

64. Printnormalmonthendreports

65. Datafilesdownload

66. Purgehistoricaltransactionbasedonauser
definedperiod
67. EndofmonthCalendarmonthendPrint
statements
68. Printcalendarmonthendreports

69. Closedtransactioncalendarendofmonth

purging
70. EndofyearResetYTDfigures.

OnlineQuery
71. Customerrecordcanbesearchedbycustomer
number,fullandshortname.
2007 gantthead.com 63
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


72. Recordscanshowforeignlanguagecharacters.

73. Showagingofoutstandingdebts,openorder
valueandunallocatedcash/credit.
74. Displayinvoicesandrelatedpayment(s),debit,
creditandbalance.Abletobrowseattheinvoice
lineorpaymentlinetolookatthedetailed
invoiceandpaymentrecord.
75. DatabasesearchforcustomermasterandAR
transactionrecordsbyseveralsearchingcriteria.
76. Customerperiodbalancewithcomparison
inquiry.
77. Customersummaryinquiry.

78. ARtransactiondetailsinquiry.

79. AbilityofcustomertoaccessA/Rthroughthe
Internet.
80. Optiontoprintallqueries.

ReportingRequirements
81. Allowtheusertodefinetheagingcolumnsinthe
agingreport(i.e.,030days,3160days,etc.,
preferablyuptoover360days).Allowbothdays
andmonth(e.g.,allinvoicesissuedinMay,June,
July,witho/sbalance).
82. Overduereportbysalesperson.

83. DailyARtransactionlistforcheckinganddaily
debtorcontrolsummaryreport.

2007 gantthead.com 64
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


84. Unallocatedcash/creditreport

85. Maturepostdatedcheckreport

86. SalesandCollectionRegister.Reportshowing
BeginningA/Rforthemonthtogetherwithall
A/RTransactionsfortheMonthtoarriveatthe
EndingA/R.
87. AgingReportsinSummary&Detailformat
basedonanyoracombinationofthefollowing
criteria:
ByCompany
ByTerritory/Branch/DistributionCenter
BySalesGroup
ByCustomer
ByCustomerClassification
ByPrincipal
BySalesman
ByReasonCode(ForDVs&BouncedChecks
Only)
ByPrincipal,TradePartner,Government
ByPrincipalGuaranteedAccounts
ByProductClassification
99. SegregateAgingDetailsastoHangingBalance
orFullInvoice.TobeavailableMTDandYTD.

2007 gantthead.com 65
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


100. DaySalesOutstanding(DSO)Report.This
reflectstheaveragenumberofdaysbeforean
outstandinginvoiceiscollected.Componentsof
thisreportareasfollows:
MonthlyHistoricalSalesPerPrincipalandPer
Outlet
OutstandingA/Rasofaspecifiedperiod
Computationoftheabovefigurestocomeup
withtheactualDSO
101. CollectionReport
102. Principal
103. Customer/Group
104. Subdistributor
105. Pricedifferenceregister
106. Freegoodsregister
107. STP(StockTransfertoPrincipal)
108. SalesrecapbyPrincipal/Customer
109. CreditMemoRegister:
SKU

Outlet

Salesman

Line/Category

AccountsReceivable(NonTrade)
114. Customercodeisatleastfivecharactersand
subsidiary/branch/divisioncodeisatleastfour
characters(A/REmployeeCashAdvance,
RevolvingFund,CarLoanandOther).

2007 gantthead.com 66
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


115. Providecopyfunctiononcustomercreation.
116. Provideanindividualsubsidiaryledgerforeach
employee.
117. ARinformationBRnumber,bankaccountand
address,postalcode.
118. Putaccountonholdwithreasoncodeanddisable
fromanymovemententryexceptinquiry.
119. Handlesmultiplecurrencyaccountsforone
customer.
120. Customeragingcodesshouldagebymonthorby
days.
121. Allowcreditnoteentryandonlinematchtodebit
transaction.
122. InvoiceandDebitmemoentry.
123. Creditadjustment/journalvoucherentry,allow
onlinematchtodebittransaction.
124. Debitadjustment/journalvoucherentry.
125. Matchapplicationforusertoassigntheopen
credittransactiontodebittransaction.
126. OnceanentryispostedtoARsubledger,the
customermastersbalancehastobeupdated,as
well.
127. Inputpaymentbybatchandacheckagainsttotal.
Ascreentodisplaytheinvoicesandallowthe
usertoselectwhichinvoicetosettle.
128. Needtohandlepartialpaymentandunallocated
credit/cash/deposit.

2007 gantthead.com 67
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


129. AllowARtransactiontobetransferredfrom
customertocustomerorfrombranchtobranch
withoutchangeoftransactiondate,duedateand
transactionreference.
130. Autoprintcollection/reminderletteronoverdue
accountpredefinedbytheuser.
131. Statementtoshowmultiplecurrencies.Also
showaging.
132. Onlinereagewithsinglecustomerorall
customers.
OnlineInquiry
133. Customerrecordcanbesearchedbycustomer
number,fullnameandnickname.
134. Showagingofoutstandingdebts,open/openand
closedtransactions.
135. Displayinvoicesandrelatedpayment(s),debit,
creditandbalance.
136. Displaytransactionleveldetails,matching
referenceandexchangerate.
137. DatabasesearchforcustomermasterandAR
transactionrecordsbyseveralsearchingcriteria.
138. Customerperiodbalancewithcomparison
inquiry.
139. Customersummaryinquiry.
140. ARtransactiondetailsinquiry.
141. Optiontoprintallqueries

2007 gantthead.com 68
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


ReportingRequirements
142. Allowtheusertodefinetheagingcolumnsinthe
agingreport(i.e.,030days,3160days,etc).
Allowbothdaysandmonth(e.g.,allinvoices
issuedinMay,June,July,witho/sbalance).
143. DailyARtransactionlistforcheckinganddaily
debtorcontrolsummaryreport.
144. Unallocatedcash/creditreport

5.9. Fixed Assets

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

No. RequirementDescription SD MC SC Comments


FixedAsset
1. Alphanumericassetcodewithatleasttendigits.
2. Handlesthefollowingevents:
3. Systemcanhandlethefollowingevents
applicabletoindividualorselectedgroup
assets
4. Acquisitionofnewasset

5. Acquisitionofpartiallydepreciatedasset

6. Transferofassetwithinacompany

2007 gantthead.com 69
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


7. Transferofassetbetweencompanies

8. Partialdisposalofanasset

9. Fulldisposalofanasset

10. Automaticallycalculatedepreciationofan
asset
11. Manuallycalculatedepreciationofanasset

12. Abilitytorevalueassets.

13. Defaultapplicationofassetdepreciation
methodologiesandratesbasedonasset
categoriesanddatesofacquisitionwithdifferent
treatmentbetweentaxandbookvalue.
14. Abletoforecastdepreciationcostsbasedon
capitalapprovals,currentassetlevelsandcurrent
expenditure.
15. Abilitytotrackcapitalexpenditureapprovals.
16. Abilitytotrackcapitalcommitments.
17. Generateandprintassetlabelwithbarcode.
18. Identifyassetbyphysicallocationinfourlevels
(i.e.,company,businessunitdivision,andcost
center)andindividualassignments
19. Provideassetmanagementreports(e.g.,asset
movementreport,assetstatusreport,asset
depreciationreport,etc.).
20. Provideexportandimportfunctions.Thefile
formatmaybetextorExcelformat.
21. Theassetcodemaybeautomaticallygenerated
fordifferentcompanies,divisions,asset
categoriesandyear.

2007 gantthead.com 70
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


22. Abilitytoallocatedepreciationandcostbythat
assetlocationorprofitcenter.
23. Abilityforthesystemtogenerateandinterface
depreciationjournalswithGeneralLedger.
24. Accountingperiodsareuserdefinable.
25. Provideauserfriendlyreportwriter.
26. Provideaccesssecurity,bothintermsofaccess
toenquiry,reportingandfunctions,andinterms
oflimitingaccesstocompanies,divisionsand
certaingroupsofassets.
27. Allowtaxcalculationforaselectedassetpool.
28. Provideaudittrail.
29. Abilitytotrackandmanageleaseholdassetsand
controlleasepayments.

5.10. Price and Costing

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

2007 gantthead.com 71
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


PricingandCosting
1. Standardcostsaretobecalculatedbyreference
toabasecostinputbytheuser.Uptotenuser
definedfactorsexpressedasapercentageofbase
orawholedollarfigurethatwillbecontrolled
throughusermaintainedtables.Factorswillbe
positiveandnegativeandwillbedatedriven.
2. Standardorcostmustrecognizeaforeign
currencyelementandbeabletobeadjustedby
changesinaglobalexchangerateforeach
currency
3. Basecosttobechangedgloballybyreferenceto
userdefinedorsystemfieldsonadatedriven
basisorindividuallyentered.
4. Abilitytosetspecialcostsattimeoforderingby
usingaSpecialTypePurchaseOrderwhich
overridesstandardcostforthespecificstock
unitsreceivedagainstthatorder.Abilitytolink
suchstocktoacustomerorderandchargecostof
saleswithspecialcostswhenassociated
customersorderisdelivered.Thismaybe
handledbyaspecialvariance.(Seecommentson
variancesbelow.)Variancestoberecognized
whengoodsarereceived.
5. Accesstoalevelofstandardcosttobecontrolled
bysystemsecurity.
6. Anychangesinstandardcosttoautomatically
createarevaluationvariance.

2007 gantthead.com 72
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


7. PurchasePriceVariancetoberecognizedwhen
thegoodsarereceivedotherthanonaSpecial
TypePurchaseOrder)intostock,andthe
PurchaseOrdervalueismoreorlessthanthe
BaseCost.Theimpactofthisdifferenceonall
standardcostlevelsmustberecognizedas
variancestoeachlevel.
8. AnInvoiceVariancewillberecognizedwhenthe
principal/suppliersinvoiceisprocessedanditis
moreorlessthanthepurchaseordervalueandan
authorizeduseracceptssaiddifferentvalue.This
variancemustbetracedbackdowntothe
individualstockitemscoveredbytheinvoice.If
theyhavealreadybeensoldthenthevariance
willbereleasedtoprofitintheprofitcenterthat
soldthestock.
9. Alltheabovecostingvarianceswillbecalculated
foreachstandardcostlevel,mustbeassociated
withspecificstockunits,andmustmovewith
theseunitsastheyaretransferredtoother
locationsorsold.
10. Costingsystemshouldbeabletoprovide
computeraidedcalculationoflandedcostand
theirtransfertoBaseCost.
11. Systemtocomputediscountsusingstandard
terms.Manualoverridefacilitytodiscountrateto
beavailable(controlled).
12. Systemcomputeddiscountstobeallocatedto
individualprofitcentersbasedonstock
receipting.
13. Abilitytoapplydiscounts:

2007 gantthead.com 73
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


particularitem

totallineitems

particularoutlet

alloutlets

VATandnonVATitems

14. Abilitytoinputandsubsequentlyedit(subjectto
usersecurity)sundrysurchargesanddiscountson
salesorders,including:
cuttingcharges

freightcharges

surchargesanddiscountsintheformof
percentage
absolutevalueorordervalue

advertising

rebates

15. Abilitytomaintainquantitybreaks(forboth
purchasesandsales).Inadditiontopricesand
discountsappliedtotheitem,thesystemshould
supporttheapplicationofadditionaldiscounts
andpricesbasedonthequantityofproduct
bought/sold.Quantitybaseddiscountsmayvary
fromcustomertocustomer.
16. Abilitytosetupandmaintainpromotionsplan,
eitherbyfixedpricesordiscounts,bydate
ranges,inadditiontonormalpricesforthe
following:
customer

customertype

2007 gantthead.com 74
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


itempricebandsforallcustomers

groupsofcustomer(buyinggroups)

individualitem

groupsofitems(includingitemnature,
manufacturer,etc)
combinationsoftheabove

17. Inaddition,promotionsmustbeabletobe
maintainedonanational,regionalorlocalbasis.
Forexample,itshouldbepossibletodefinea
promotionthatappliestosalesofanitematone
branchonly.
18. Systemshouldbecapableofnotpermittingsales
tobemadebelowminimumsalespricesorbelow
aminimumsalesmargin.
19. Abilitytosetdifferentmarginsat
national/state/branchlevel.
20. Marginabovecostpricetobedisplayedattime
ofsalesorderentrybylineitemandintotal.It
shouldbepossibletodisplaydifferentcostprices
dependentonorganizationalhierarchy.
21. Onlinemargin/profitabilitycalculationsfor
inquiriesandsalesofsingleproductsandtotal
ordersdependentonorganizationhierarchy.
22. Abilitytodefineusersecurityforinquiriesand
maintenanceofdiscountstructures(i.e.,master
data)byorganizationhierarchy.

2007 gantthead.com 75
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


23. Inadditiontothediscountstructurepreviously
described,andtopreservelocalflexibility,the
systemshouldsupporttheabilitytooverridethe
systemcalculatedprice,through:
Entryofafixedorabsolutepriceforanitem,
and/or
Theentryofadiscount(either%orabsolute
value)againstthewholeorder.
However,theabilitytoperformtheaboveshould
becontrolledbyusersecurityordelegated
authoritylevelsbybranch.
24. Abilitytogenerateoffinvoicerebatesforcertain
productsalesfordefinedtradepartnersbasedon
annual/monthlyvolumesorvalue.
25. Abilitytodefineforspecifictradepartnerhow
pricesaredisplayedoncustomerinvoices,i.e.,
whetheradditionalpriceinformationisshownor
suppressed.
26. Branchloadingtheabilitytoaddauserdefined
percentagetotherecommendedtradepriceto
items,bymanufacturerandproduct(discount)
grouptobecontrolledthroughusersecurity.
27. Automatedprofilingoftradepartnerbuying
habitsandsuggestionofoptimaldiscount
structures.
28. Thisshouldatleastbeareportshowingcurrent
andpreviousyearsalesandassociatedmargins
byitem/productgroup.
29. Abilitytoholdprocesscostsfortradepartners,
principals,andproductsbasedondistribution
channels.

2007 gantthead.com 76
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


30. Maintainmultiplecostsstructuresandselectthe
correctonebasedonthefollowingperSKU:
Distributioncenter

Contracts

Warehouselocation

Effectivedate

Quantitybreaks

31. Abilitytodefineandmaintainavarietyof
discountandrebatestructureswhichmayormay
notbevolumedependent,andwhichmayapply
toindividualorrangesofproductsand/orwhich
mayapplyonanational,regionalorbranch
basis.Aswithtradepartnerpricing,principal
discountsandrebatesarebasedontheTrade
PriceList.

2007 gantthead.com 77
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


32. Abilitytoholddifferentcostsforaspecific
product,basedonprincipaldiscountsand
rebates,andtocontrolhowcostsareviewedor
usedinmargincalculations,andcontrolhowand
towhomthesearemaintained,displayedand
reported.

Whilethetradepricelistisusedasthebasisfora
productscostandthereforethesalesprice
calculations,eachbasepricecanthenbesubject
toavarietyoftypesofsupplierdiscountsand
rebates.Thisresultsintherebeinganumberof
costlevels.Whilethetruenet
margin/profitabilitymustbeavailableatalltimes
foraspecificproduct,theabilitytomaintainand
inquireondifferentlevelsandhencethereported
margincalculationisdifferentdependingonthe
usersroleintheorganization.Theaccesstothis
margininformationmustbecontrolledthrough
security.
33. Abilitytocreateandmaintainspecialrebatesand
costsstructuresrelatedtospecifictradepartner
promotionprojects.Inadditiontonormalrebate
anddiscountstructuresofferedbysuppliers,
specialpricesarealsonegotiatedforoneoff
contractsorprojectswithtradepartner.In
returnfortheadditionalvolume,thesupplier
providesadditionaldiscountsorrebates,which
mayormaynotbeincludedinnormalsupplier
rebates.
34. Abilitytoautomaticallygenerateprincipalrebate
claimsonauserdeterminedfrequency.
2007 gantthead.com 78
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


35. Abilitytoapportionprincipalrebatesand
discountstoindividualstockitemsandtothe
branchmakingthesale.
36. Abilitytoreconcilerebatepaymentsreceived
fromprincipalswiththoserebatefactorsusedin
costingcalculations.
37. Abilitytopurchasenonstandardproductsfrom
principals.Standarditemsarethosewhichare
regularlypurchasedfromsuppliersandexistin
theproductmasterfile.Onoccasion,ata
customersrequest,special,ornonstandard
productsmaybepurchasedfromsuppliersto
completeacustomerorder.Insuchcases,the
pointofsalemusthavetheabilitytocreatean
orderforanonstandardproductandderivea
priceforthattransactiononly,without
necessarilydirectlymaintainingtheproduct
masterfile.Thepracticeofpurchasingnon
standarditemsisnotencouragedbutisregarded
asnecessary.Thesolutionmustprovideforstrict
controlsonhow,andbywhom.Thereshouldbe
sufficientdetailedreportingtoidentify
specificallywhatwaspurchased,andtoenable
thecreationofamasterfilerecordiftheproduct
islaterrequiredtobeastandardproduct.
38. Abilitytorevalueproductsbasedonchangesto
anylevelofcostandcalculatesvariancesfor
eachlevel.
39. Abilitytocalculatepurchasepricevariances
wherethepurchaseordervalueisdifferentfrom
thestandardcostandtheitemisnotaspecialor
nonstandardproduct.
2007 gantthead.com 79
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


40. Abilitytoreportoncomparisonsofrebate
structuresacrossprincipals,tradepartners,and
products.
41. Abilitytoprompt/forceoptimalbuyingprogram
basedonprincipaldiscountsforordersizes,
promotions,etc.
42. Abilitytoholdallprincipalandtradepartner
contractsdataonline.
43. Abilitytolinkprincipalsandtradepartners
throughasinglecontract(projects).

Differentpurchasepricesarenegotiatedfora
certainitem/manufacturercombinationfora
specificcontract.Forexample,asalescontract
mightbenegotiatedwithSM.Priceswillbe
negotiatedwith<CompanyName>sprincipal
specificallyforthatcontract.Thetwocontracts
thatarethusrelatedshouldbelinkedwithinthe
system.
44. Abilitytoproduce,holdandgeneratecontracts
onlineusingstandardtextsandmasterfiledata
45. Abilitytomaintainpricesforeachindividual
sellingunitofmeasure(i.e.,PalletPrice,Carton
Price,andUnitPrice).

2007 gantthead.com 80
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


46. Thesystemshouldallowfornetpricestobe
createdbyapplyingdiscountsofftradeprice
basedonthefollowing:
tradepartner
outlettype
itempricebandsforallcustomers
groupsofcustomer(buyinggroups)
individualitem
groupsofitems(includingitemnature,
manufacturer,etc.)
combinationsoftheabove
Thesystemshouldsupporttheuseofone,some
orallofthepotentialdiscountsaboveandforthe
definitionoftherulesandorderinwhichtheyare
applied.
47. Abilitytomanagepercentagebasedandabsolute
pricingconcurrently.
48. Discountsandpricescanalsobeappliedto
specificcontractswithcustomers,andinsome
casesthesamecustomermayhaveseveral
contracts(e.g.,foreachdivision)wheretheprice
ordiscountforthesameitemmaydiffer.The
systemmustsupporttheuseofcontractpricing
inadditiontonormalpricingstructuresforthe
samecustomer.

2007 gantthead.com 81
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


49. Inadditiontothepricingstructuresand
flexibilitydescribedpreviously,pricingand
discountscanvaryfromregiontoregionand
frombranchtobranchwithineachregion,and
hencethesystemmustsupporttheapplicationof
theaboveflexibilitybasedondifferentbranches,
locationsorregions.Hencethesamecustomer
mayhavemultiplepricelists.
50. Abilitytomaintainseparatepricesforpurchase
andsalesofitemsperprojectorcontract

5.11. Human Resource

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

No. RequirementDescription SD MC SC Comments


EmployeeDemographics
1. Fulldemographic/addressinformationin
employeeprofiles.
2. Sophisticatedsearch/inquirycapabilities.
3. Userdefinedemployeegroupings/classifications,
levelsandpositions.
4. Onlineselection/querybyanyfieldinemployee
screen.

2007 gantthead.com 82
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


5. Abilitytotracksposition(s)currentlyand
previouslyheld,wageandbenefitsinformation,
educationalbackgroundandskillsdata,previous
employment,payrolldata,relations(dependents,
beneficiaries),equipmentandpropertyissues,
applicationsfortransfer,andmanymorefields
includingspecialuserdefinedfields.
6. Abilitytokeeptrackofemployeerecordsaseach
employeebeinghired,promoted,demoted,
transferredbetweendepartment,transferredfrom
affiliatecompanyandresigned.
7. Historyofchangestoemployeerecords,
compensationandpositions.
8. 'Tickler'dates/reports(nextreview,probationary
expiry,lasthire,etc.).
Recruitment
9. Userdefinedrecruitmentmethods,actionplans
andselectionprocess.
10. Personnelrequisitioncanbegenerated
automaticallyfromtherecruitmentplanor
enteredmanually.
11. Fullapplicantprofileinformation,including
demographicdata,skills,education,notes,equity
details(EEO).(Shouldbeabletoregisterapplied
position,expectedsalary,workexperience,
familybackground,areasofinterest,references
education,employmenthistory,traininghistory,
compensationhistory,medicalhistory,
performanceevaluation,skillsandmiscellaneous
personalinformationsuchasphoto,address,etc.)

2007 gantthead.com 83
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


12. Crossreferencelinksbetweenapplicantand
applications(postings/requisitions).
13. Automatictransferofapplicationinformationto
employeefiles.
TrainingandDevelopment
14. Abilitytosetupatraininganddevelopmentplan
programforeachlevelandposition.
15. Abilitytofileeachtraininganddevelopment
program.Thefilesuchastrainingcodeand
description,subject,duration,date,trainer,
profileofparticipants.
16. Abilitytofacilitateemployeeperformance
reviewandlinkupwithemployeeprofile.
SkillsandQualifications
17. Supportuserdefinedskill,taskandabilityof
eachpositionorlevel.
18. Supportuserdefinedpositionorlevel.
19. Supportuserdefinedcompetencyprofile.
PayrollAdministration
20. Userdefinedearningcodes,summarization
classesforearnings,benefitsanddeductions,
payrolltypes.
21. Multiplepayrollfrequencies(weekly,biweekly,
semimonthly,monthly,quarterly).
22. Maintenanceoffulldetailedtransactionsforas
longasrequired.
23. Fullsummaryhistory:lifetodate,yeartodate,
quartertodate,monthtodateandpayperiodfor
alltransactions.
ReportingandAnalysis
2007 gantthead.com 84
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


PersonnelInformationSystem
Abilitytogenerateindividualemployment
historyreflectingthefollowingdetails:
FamilyBackground
DependentsData
Education
OrganizationalAffiliation
TrainingAttended
EmploymentHistory
CompensationHistory
PerformanceEvaluation
AwardsandMerits
DisciplinaryActions
MedicalHistory
CorporatePersonalProfile
24. Graphicalpresentationofreportreflecting
percentageofthefollowingpersonneldata:
Education
CivilStatus
Age
Numberofdependents
Gender
ResidentialLocation
Source
JobLevel
Position

2007 gantthead.com 85
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


Personnelperdepartment
Personnelperbranch
25. Abilitytogeneratecorporatemanpowersorted:
ByDepartment
ByPosition
ByJobLevel
ByBranch
26. Abilitytogeneratelistofbirthdaycelebrantsper
monthandlistofemploymentanniversary
celebrantspermonth.
PersonnelMovements
27. Reportsonpersonnelmovements:
Listofnewhires
Listofseparatedemployees
Listoftransfereesfromoneaffiliatecompanyto
another
Listofpromotedemployees
Listofdemotedemployees
Percentageofhiringrates
Percentageofturnoverrates
CompensationManagement
28. Listofsalariesthatcanbesortedout:
ByDepartment
ByPosition
ByJobLevel
29. Comparisonratioofcurrentsalariesvs.external
andinternaldata.
2007 gantthead.com 86
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


MedicalData
30. Listofemployeespertypeofillness.
31. Healthcarebenefitsthatcanbesortedout:
Permonth
PerQuarter
PerYear
DisciplinaryAction
32. Summaryofalldisciplinarycaseshandledper
year.
33. IndividualDisciplinaryActionMemo.
Certifications
34. EmploymentCertificatew/ocompensationdata
35. EmploymentCertificatew/compensationdata
36. SSSCertificateofPremiumContributions
37. HDMFCertificateofPremiumContributions
38. HDMFCertificateofLoanEligibility
PayrollSystem
39. EmployeeLedger
40. PayrollRegister
41. EarningsRegister
Sortedbypayrolldate
Sortedbytransactioncode
42. DeductionsRegister
Sortedbypayrolldate
Sortedbytransactioncode
43. Payslip

2007 gantthead.com 87
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


44. Yeartodatetaxreconciliationregister
45. QuarterlySSS/MedicareReport
46. MonthlySSS/Medicare/ECCReport
47. MonthlySSSR1AEnrollment
48. MonthlySSSLoanCollection
SortedbyEmployee
SortedbyTypeofLoan
49. QuarterlySSSLoanCollection
50. Alphalist
51. W2
52. Loan/BenefitsTransactions
53. MonthlyPIF/HDMFRegister
54. MonthlyPIF/HDMFLoanCollection
55. PayrollSummary
56. AttendanceList
57. LeaveSummary

6. System Requirements
6.1. Technical Requirements

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

2007 gantthead.com 88
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


General
1. ApplicationIntegration
SameLookandFeel
SingleAdministration
SingleProgrammingLanguage
(Excellentintegrationmeansthattheuserfeels
liketheyareusingapplicationsfromasingle
environment.)
2. AutoDocumentation,FlexibleReportingand
WebPublishing
(Readabilityofoutput.Systemshouldhavea
veryflexibleandpowerfulGUIbasedreport
writerorafacilitytobeabletoexportoutputinto
otherreportingtools)
3. WebEnabledApplication
(ApplicationrunsonInternetenvironment.
ShouldhaveextensiveconnectivitythroughEDI
andshouldsupportpopularstandardslike
EDIFACT.)
4. EaseofUse
IntuitiveInterface
OnlineHelp
Nonmodalscreennavigation
(Userfriendly.Systemshouldusestandard
Windowsicons,layoutandmakeextensiveuse
ofshortcutfeatures.Itshouldhavecontext
sensitivehelp,andwizardlikenaturallanguage
query.)

2007 gantthead.com 89
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


5. ConnectivitytoOfficeAutomation
(AbilitytoprovideconnectivitytoPCbased
officeautomationproductslikeMSOffice,fax
modem,etc.)
6. Supportforcentralizedcomponentbased
environment
(singletierdeploymentenvironment).
7. RelationalDatabaseManagementSystem
(RDBMS)
(Theapplicationpackageshouldbebuiltaround
moderndayRelationalDatabaseManagement
System,preferablySQLServerorOracle.)
8. StandardDBMSconnectivitytoexternaldata
sources,SuchasODBC,OLEDB,JDBC.
(ODBCataminimum;othersarebonus.)
9. OperatingSystem
(Theapplicationpackageshouldrunonindustry
standardoperatingsystem,preferablyWindows
NTorUnix.)
10. HardwareCompatibility
(ShouldrunonthelatesthighendPCServer
technologyandbeportabletoanymidrange
businessserver.)
11. MultipleUserAccess
(Abilitytoprovideconcurrentsystemaccessto
multipleusersanditshouldnotcausefileor
recorddeadlock.Providefastresponsetimetoall
concurrentusers.)

2007 gantthead.com 90
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


12. Thesystemshouldbeabletocopewithorshould
be:
MultiSite
MultiCurrency
MultiWarehouse
Multilingual(e.g.,Chinese,German,Swahili)
Goods/ServiceTax
MultiCompany/Division
Abilitytoprocessintercompanytransactions
13. Periodicprocessing(e.g.,daybegin,dayend,
monthend)canbeperformedseparatelyby
environmentorbycompany.
14. Supportmulticurrencywithexchangerate
definedbyperiodandallowuseroverridein
transactionlevel.
15. Allrawdatacapturedcaneasilybetransferredto
areportviaareportwriter.
16. Formsandreportscanbeprintedtoaspecific
printeraccordingtouserID,company/divisionor
othercriteria.
17. Regional/countryconsolidationandanalysison
inventory,salesandaccountinginformation.
18. Transactionnumbersgeneratedper
company/divisionandwithalphaprefix(e.g.,
salesorder/invoicenumber,purchaseorder
number).
19. Allowremovalofallmastersandtransactionsof
selectedcompanies.
20. Allowhousekeepingwith
company/division/timeframeselectionforall
modules.

2007 gantthead.com 91
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


21. Allowmanytomanyrelationshipfordivisions
andagencies.
22. Providefaxoutfacilityfromthemainmachine.
23. Allowtransferofagency/divisionfromone
company/divisiontoanother.
24. Autoprintingofcompanylogo,businessstream
andcompanynamesonexternaldocuments
accordingtocompany/division/agency/customer.
25. Year2000Compliance
(ThesystemmustbeYear2000compliantinall
aspects.)
DBMS
26. ODBC/JDBCSupport
27. ReferentialIntegrity
28. BuiltinTrigger
29. StoredProcedure
30. RowLevelLocking
31. Journal,Commitment/Rollback
32. OnlineSave
33. AdministrationTool
34. OpenPlatform
(Couldrunonmorethanoneplatform,preferably
SQLServerorOracle.)
35. OnlineaccesstoSQLServer7.0

EndUserQueryTool
36. ExplorationFlexibility
(Drilldown)

2007 gantthead.com 92
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


37. Administration
38. ExportCapabilitytoOfficeAutomationSoftware
39. WebPublishingOutput
40. RowandColumnLevelSecurity
41. ChartingFacility
42. ReportingFacility
43. BrowserBasedUserInterface
44. PerformanceMonitoring/Tracking

6.2. Security and Control Requirements

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

No. RequirementDescription SD MC SC Comments


1. MultipleUserClasses
(Thesystemmustallowformultiplelevelsof
userclasses.Eachlowerlevelcorrespondsto
morelimitedaccess.)
2. AccessControl
(Accesscontrolshouldbebasedon
menus/options.)

2007 gantthead.com 93
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


3. ScreenLevelSecurity
(Entirescreensorselectivepartsofscreens
shouldbeaccessibleonlytodulydesignated
classesofusers.Hence,auserbelongingtoa
highlevelclasscanaccessmorescreensthana
userbelongingtoalowerlevelclass.)
4. File,RecordandFieldLevelSecurity
(Specificfiles,recordsandfieldsareonly
accessibletodulydesignatedclassesofusers.
Therearealsodifferentlevelsofaccessibility.
Usersbelongingtoaspecificclasscaneither
haveread,write,updateordeleterights.Users
belongingtohighestlevelofclassorthosein
systemadministrationgroupmayhaveallthe
accessrights.)
5. Accesslevelbaseon
companies/division/department/agencies
(i.e.,usersareclassifiedonwhichcompany,
division,departmentoragencyinformationthey
canaccess).
6. Accesslevelbasedonlocation(i.e.,usersare
classifiedonwhichwarehousedatabasethey
couldaccess).
7. AccessControltoClientData
(SincewewillbeprovidingourClientswith
accesstoinformationregardingtheirstocks,
theremustbeacontrolinplacesothattheClient
willhaveaccessonlytoinformationregarding
himandhimalone.)

2007 gantthead.com 94
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


8. Password
(Passwordshouldbereadilychangeablebythe
endusers.Thesystemshouldforceusersto
changepasswordatpredeterminedintervals.The
systemshouldbeintuitivetodetectandrejectif
passwordisusedmorethanonceduringspecified
duration.)
9. AccesstoOperatingSystemPrompt
(OnlytheSystemAdministratorsshouldhave
accesstotheoperatingsystemprompt.)
10. SystemHousekeeping/Maintenance
(Thesystemshouldprovidetheabilityfor
backupsandotherhousekeepingwithoutexiting
totheoperatingsystem.)

6.3. Audit Requirements

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

2007 gantthead.com 95
Information Systems Replacement
gantthead.com Proposal Request for Proposal

No. RequirementDescription SD MC SC Comments


1. FullTransactionTraceability
(Alltransactionswillneedtobeauditedtoshow
thesourceofinitiationofthetransaction,the
individualwhoworkedonthetransaction,and
thedate/timeofinitiationandcompletionofthe
transaction.)
2. AuditTrailforMaintenanceofConfidentialor
SensitiveMasterData(Example:Customer
CreditInformation,BusinessDeal,orContract
Information)
3. UserLogs
(Theremustbefullvisibilityofallsystems
activitiesofallusers.)
4. DataIntegrity
(Theremustbemechanismsthatverifythe
integrityofdata.Theremustalsobecontrol
mechanismsontheEDIfronttoensurethatany
datatransmittedisacknowledgedbacktothe
originator.Thisacknowledgmentmustbe
comparedtotheoriginaltransmissionandany
exceptionshighlighted.)
5. RollBack/RollForwardandMirroring
(ItshouldbepossiblefortheRDBMStoroll
back/rollforwardusingtransactionlogs.
Mirroringofthedatabaseattheremotelocation
willallowcontinuousoperations,eveniftelecom
linesconnectingtothecentralserverare
disrupted.)
6. Input/OutputInterfaceControls
(Theremustbefullcontrolsonallinputand
outputinterfaces.)

2007 gantthead.com 96
Information Systems Replacement
gantthead.com Proposal Request for Proposal

6.4. Target System Performance

Note:
SDStandard Requirementisstandardtoapplicationsoftwarenomodificationneeded.
MCModerateChange Applicationsoftwarewillsatisfythisrequirementwithmoderatemodification(tobe
accomplishedwithintwodays)
SCSignificantChange Significantcustomization(beyondtwodays)isneededtosatisfytherequirement.

No. RequirementDescription SD MC SC Comments


1. AbilitytoHandleVolumes
(Thesystemshouldbeablehandlethevolumes
asprojectedinSection3.4,TransactionVolumes,
withoutanydegradationinsystemspeed.)
2. 24HourAccess
(Thesystemshouldprovide24houraccess.Day
endactivitiesshouldnotinterferewithusers
accesstothesystem.Thesystemshouldallow
foronlinebackupsandotherhousekeeping
activities.)
3. Printers
(Thesystemshouldsupportawidevarietyon
laser,inkjetanddotmatrixprinters.)
4. PerformanceDegradation
(Thereshouldbenonoticeabledegradationin
systemperformanceforupto400users.)
5. HistoricalData
(Thesystemshouldbeabletomaintainarolling
12monthsofhistoricaldataonline.)

2007 gantthead.com 97
Information Systems Replacement
gantthead.com Proposal Request for Proposal

7. Vendor Requirements
7.1. Supplier Profile

All vendors must give a comprehensive profile of their organization in the following
format and order.

7.1.1. Organization

Organization concerns the structure and size of the company both in terms of its
head office and other worldwide regional locations.

Please provide information as to whether the organization is independent or


part of a larger conglomerate. If the latter, please provide details on the
holding company.
Please provide corporate mission statement and strategic direction of the
product. Also long term plan for addressing emerging technology
Please provide information as to whether the organization is the package
manufacturer, reseller or value-added resellers (VARs). If the latter two,
please also provide details of the company.
Please provide information of any company that merged with or purchased by
the organization.
Please provide information of any alliance or affiliation that with which the
organization partners (e.g., tool or equipment supplier, standard groups,
industry groups).
Please provide information of the organization statistics (e.g., geographic
distribution, market share, reputation, company highlights, etc.).
Please provide information of your organizations performance against others
in the industry.
Please provide information on how much the organization spent on research
and development as a percentage of revenue for the last two years.
7.1.2. Product

Product concerns some basic information on the products of the company:

All products being marketed


How long the products have been in the market
Compatibility of different products marketed
Who and where was the product developed
Platform the products are running
Connectivity strategy for product proposed
7.1.3. Location

Location concerns the location and size of operations at the head office and any
regional offices.
Information Systems Replacement
gantthead.com Proposal Request for Proposal

For each location please state:

Number of employees by function (technical and non-technical).


Whether the offices are wholly owned subsidiaries of the main head office or
if it is a third-party managed operation (VARs).
Also indicate the office from where an implementation would be managed.
7.1.4. Growth

Growth concerns the manner in which the company has progressed since its
inception. Please provide information:

The year when the company was first established.


The place where the company was first established.
The size of the company per year since its inception in terms of locations and
staff numbers and within this, the number of consultants.
If the company has been in operation for a number of years, please
summarize up until the last five years, then provide detailed information from
this period.
The history in sales and consulting revenue over the last five years: product
sales, personal growth (local, regional and global) and R&D expenditure
(money and man-hours).
7.1.5. Experience

Experience concerns the relative experience vendor has in terms of an


implementation of this size related to the business activity and distance from the
most local regional office. Please provide information as to the experience of
your consultants and retention rate of your key support people in the last two
years.

7.1.6. Reference Sites:

Reference sites concerns the location and relative suitability of sites where the
package is already implemented and is currently operational. Please provide:

Number of reference sites by geographic area


Other locations
For each reference sites, please provide the following:

Client company name


Client contact person
Client address (street, city, country, post code), email address, telephone and
fax number
Client number of employee
Client industry

2007 gantthead.com 99
Information Systems Replacement
gantthead.com Proposal Request for Proposal

The package or module that was delivered


The date of the delivery
For reference locations whose software applications most closely match
<Company Name> requirements, please outline the business activities carried
out at these sites and their use of your package. Please indicate the period of
time each site has been in operation with the designated package and the
degree of customization that was required.

7.1.7. Other Information

Please also provide us with any other information which you see as relevant,
specifically any known weakness that the product has in terms of functionality or
implementation/training requirements.

7.2. Maintenance and Support

Vendors are required to provide the following information related to the support
and maintenance of the proposed solution.

Options available for support, names and addresses of Agents (if any) in the
region.
Software maintenance charges and the spectrum of activities covered under
such maintenance contracts (new release, bug fixes, etc.).
Software support availability (Help Desk, hotline, etc.) and duration for which
they are available.
Response time to support inquiries from <Company Name>.
Standard hours during which support will be provided and out of hours
support options and costs.
Uptime guarantees.
Number of staff in the software support team.
Frequency at which new versions of the software are released.
Release date for the first version of the software.
Release date for the current version of software.
Release date for the next version.
Product development plan for the proposed software solution and annual
R&D.
Implications of modifications on upgrade, maintaining modification and
potential costs.
8. Implementation Requirements
It is planned that a vendor will be selected by <date> and contract negotiation completed
<date>. It is <Company Name>s intention to commence operational use of the
proposed system no later than <date>. Please use indicative figures for this section.

2007 gantthead.com 100


Information Systems Replacement
gantthead.com Proposal Request for Proposal

<Company Name> proposed the following order of priority in implementing the


information system:

1. Financial

2. Distribution

3. Front Office

4. Human Resource

<Company Name> is open to an option on the priority order of implementing the system
if convinced with the alternative solution of vendor.

8.1. Implementation Plan

Vendors should include an implementation plan with a timetable for the implementation
of the system, showing the recommended modules to be included in each phase and
estimate effort required. The plan must indicate the specific tasks involved and the time
frames required (both elapsed and man days). Implementation plan must also indicate
the set-up, testing, parallel and live run phases, the checks to be made at the end of
each phase and the deliverables from each one.

Clearly state the standard acceptance and testing criteria that is usually employed.

Indicate what kind of performance bond the vendor is willing to provide to <Company
Name> ensuring a satisfactory performance of the system.

This implementation plan will be refined during initial scoping of the project.

8.2. Data Conversion

As part of the project, some data will need to be converted and loaded into the system.
Conversion programs may need to be written to handle this task. Vendors must indicate
how they propose to do this and the approximate effort and cost of this effort.

8.3. Project Organization

Provide details of the proposed project structure identifying key individuals, e.g., Project
Managers and their roles, including the number and location of proposed
analysis/development personnel. Due to the expected impact on the business
processes, it is extremely important <Company Name> obtain a thorough understanding
of the organizations and individuals proposed for the project and the roles <Company
Name> staff would be expected to play. Vendors should provide details of sub-
contractors likely to be involved. Indicate the number of full time equivalent staff that will
be required. Resumes or a personal profile should be provided for key personnel within
the project.

It is desired to provide estimates of the required number of <Company Name> staff and
identify the skills required. Provide details for the following:

Number of Full Time Equivalent (separate IT and Business) required throughout the
duration of the project
2007 gantthead.com 101
Information Systems Replacement
gantthead.com Proposal Request for Proposal

Key roles to be included from the business


Key roles to be included from IT
Provide details of governance roles including:

Steering committee
Project management
Number and frequency
Provide an estimate of the infrastructure required at <Company Name> for your
implementation team:

Number of work desks


Number of telephones
Number of computers
8.4. Training

As part of the implementation requirements, training needs must also be identified for up
to 20 operating staff and managers. This will have to be conducted in two or three
batches. The training needs of the IT staff for ongoing support must also be identified.
Please include a training plan, clearly indicating what type of training can be imparted at
what phase of the project and where, with due consideration for the remoteness and
travel costs. The vendors must also indicate the number of man-days of training and
support provided free of charge.

List the documentation (systems and user manuals) provided with the standard software
solutions. It will be necessary for <Company Name> to see samples of such
documentation during the selection process (not to be supplied along with the Proposal).

Implementation costs should cover all effort required from initiation to post-
implementation wrap-up.

9. Selection Process
9.1. Objective

The objective of the evaluation process is to select a reliable and experienced vendor,
capable of supplying and installing a computer system with the functions required by
<Company Name>, within the time frame identified in Section 6.2. In addition, the vendor
should be willing and capable of providing ongoing maintenance and support of the
solution.

9.2. Timetable

The key dates for the RFP issue, receipt, evaluation and implementation are currently as
follows:

2007 gantthead.com 102


Information Systems Replacement
gantthead.com Proposal Request for Proposal

CompletedBy: KeyMilestones Comments


<date> Distributionofthe
RFP
<date> PreBidQuestion AnAgendawasattached
andAnswer togetherwiththeRFP.Meeting
isat<location,time,date>.
<date> Submissionof
ResponsetoRFP
<date> VendorPackage Onlyqualifyingvendorswill
Solution beinvitedtocometo[place]
Presentation (attheirownexpense)to
demonstratetheproducttothe
projectteam
<date> VendorSiteVisits <CompanyName>reserves
therighttomakeatleastone
installedsitevisitand/or
contactreferencesitesby
telephone
<date> AnnouncedWinning
Vendor
<date> Contractnegotiation Selectedvendorentersintoa
scopingperiodduringwhich
timethefollowingwillbe
produced:proofofconcept,
finalcosting(including
infrastructure),final
implementationplanand
signedcontract.

<Company Name> retains the right to amend this schedule as it sees fit.

9.3. Contacts during the selection process

For vendors for all clarifications until completion of the selection process, the primary
point of contact will be: <contact>

In order to ensure that any clarification is promptly made available, a secondary point of
contact is: <contact>

For an organized process of answering queries from vendors, a Question/Inquiry Form


shall be accomplished addressed to the contact persons above. This can be done
through facsimile or e-mail. An electronic copy of this document called
QUESTIONS.DOC (Microsoft Word Version 97) is included as part of the RFP pack for
this purpose. Questions received not following the format above shall not be
entertained. All questions/inquiries shall be responded within 24 hours from receipt of
request.

2007 gantthead.com 103


Information Systems Replacement
gantthead.com Proposal Request for Proposal

9.4. Selection Criteria

Package selection will be based upon a number of criteria, as detailed below. The
vendors are therefore required to consider how their package fits in with the criteria
listed and clearly indicate this in their response document.

Selection criteria will be based upon:

Functional Fit

The functional fit between the package and the business needs, as documented
in the Statement of User Requirements and its availability for implementation.
This will also take into account the ease of use of the package, the quality of the
documentation, the extent of the modifications required and the readiness and
flexibility of the vendor to handle customization and adapt to any future changes
in the business.

Supplier Fit

The quality of management, technical staff, financial and organizational stability


of the company. Contractual arrangements, current customer base and the
quality of the vendors support (i.e., assistance/troubleshooting, training, and
consulting) will also be considered. Customization should be carried out by the
vendors in such a manner that it can be incorporated into future releases of the
software. Vendor presence in countries where <Company Name> is operating
will be a definite advantage.

Technical Fit

The package will be technically measured based on its seamless online


connectivity to the application systems identified in the System Interface section
and its flexibility and support on open architecture so that any future need to
interface with other system would not cause any problem. It will also be
evaluated on its stability of its platform (preferably Unix or Windows NT),
robustness of its database (preferably MS Sequel or Oracle), and adherence to
defined security and control requirements, audit requirements and target system
performance.

Cost

The overall costs of implementing the proposed solution for up to 400 concurrent
users. A cost-effective solution that seeks to minimize overall cost of ownership

Implementation Strategy and Risk

Solutions that can be implemented quickly, are flexible and are able to meet
present and future needs. A proposed implementation approach seeks to
minimize risk.

9.5. Contract Negotiation

For the preferred vendor, <Company Name> <place> will handle negotiations to agree
on a contract. The agreed contract will stipulate that the equipment and application
2007 gantthead.com 104
Information Systems Replacement
gantthead.com Proposal Request for Proposal

software specified will satisfy the functions as stated in this RFP, and will perform at a
speed appropriate to the retail/distribution industry. It will include final costing and a
complete implementation plan.

10. Proposal Response Format


This section outlines the format in which the suppliers are required to respond to this
invitation. All suppliers will be required to provide the information as specified. Any other
information that may be relevant to our decision making process must be supplied as
addenda.

10.1. Summary of Proposal

The RFP document must have a summary section containing the following information:

Name of the package(s) being offered, version number, etc.


Broad functional fit to the specifications in the Statement of User Requirements
Hardware platforms recommended and alternatives.
Application environment
Number of sites where package is implemented. Number of sites for the version
proposed.
Approximate cost of implementation broken down by:
o Software Acquisition and Installation
Application Software
Data Access Software
Database Software
System Management Software
Development/Testing Software
o Hardware Acquisition and Installation
Application/Database Server
Web Server
Backup Server
o Implementation Service
General Project Cost (Consulting, Travel Expense, etc.)
Installation
Customization
Maintenance and Support
o Other Costs

2007 gantthead.com 105


Information Systems Replacement
gantthead.com Proposal Request for Proposal

Summary of Strengths of the Recommended Solution

It is the vendors responsibility to highlight all costs related to the implementation


of their solution. Key components that are required but not quoted for will be the
responsibility of the supplier.

10.2. Supplier Profile

Vendor should detail in this section all details pertaining to the vendor requirements
summarized in Section 6.

10.3. Compliance to User Requirements

Vendors should set out clearly in their proposal all information requested. The proposal
should follow the same numbering system as this RFP. An electronic copy of this
document called USREQT.DOC (Microsoft Word Version 98) is included as part of the
RFP pack for this purpose. Vendors should respond to each requirement with a SD
(Standard), MC (Moderate Change), or SC (Significant Change) answer.

The definitions are as follows:

SD Requirement is standard to application software no modification needed.

MC Application software will satisfy this requirement with moderate modification (to
be accomplished within two days)

SC Significant customization (beyond two days) is needed to satisfy the requirement.

Where a specific requirement cannot be fully met, or an alternative solution is proposed,


comments should be included (e.g., the cost of basic tailoring, how much time is needed,
etc.).

The vendors are also required to provide printed report samples for those listed below:

1. Sales Reports

2. Sales-Cost Ratio

3. A/R Reports

4. A/R Aging Reports

5. Service Level Reports

6. Collection and Reconciliation Reports

7. Sales Order Reports

8. Purchase Order Reports

9. Stock Movement Reports

10. Stock Aging Reports


2007 gantthead.com 106
Information Systems Replacement
gantthead.com Proposal Request for Proposal

11. Transaction Registers

10.4. Compliance to Technical Requirements

An electronic copy of this document called TECHREQT.DOC (Microsoft Word Version


98) is included as part of the RFP pack for this purpose.

10.5. Compliance to Implementation Requirement

Vendor should detail in this section all details pertaining to the vendor requirements
summarized in Section 6.

10.6. Cost

To assist <Company Name> in the evaluation and analysis of the costs associated with
the proposal, vendors should present their pricing using the cost model provided. This
cost model is in the Excel spreadsheet, PRICE.XLS, on the diskette enclosed with the
RFP.

It is expected for the vendor to provide the application software (including third party
software wherever applicable), database integration services and consulting.

Each heading should be expanded as required to show each item and clearly identify
what is included within the associated charge. The charges should be separated into
capital cost, one-time costs and ongoing charges.

It is expected that all charges and costs applicable to this proposal will be included in
this section. Including, for example: handling, transportation, installation, training,
maintenance and support, software upgrade, tools, travel, accommodations, and any
other item that could be interpreted as the real cost of procurement and any on-going
expenses due to the vendor. Costs are to be provided in <type of currency>.

Software costs should highlight the difference between standard core licenses, modules,
and enhancement costs and third party software licenses. Wherever a vendor is
supplying items of a different manufacturer, the manufacturer and model numbers must
be indicated.

In this section, vendors are requested to provide details on the equipment required as a
platform for the proposed system. <Company Name> requires that vendors provide
estimates for the capacity and costs of all equipment for the proposed system.

Any charges applying to the proposal should be included with a full and itemized
description.

All costs and prices quoted in the proposal are assumed to be valid until implementation
is completed.

10.7. Contracts

The vendors must indicate nature of contracts and agreements they are willing to enter
into. The information to be provided includes:

Sample contracts
2007 gantthead.com 107
Information Systems Replacement
gantthead.com Proposal Request for Proposal

Payment terms - details of payment settlement options


Period for which the price quotes will hold
Guarantees against the system non-performance
Penalty clauses
Any other vendor constraints

2007 gantthead.com 108


Information Systems Replacement
gantthead.com Proposal Request for Proposal

11. Glossary
The following glossary defines certain terms that at times have been used in this RFP.
The terms Client, Customer, Principal, Supplier and Third Party, for example, can cause
considerable confusion. Depending on the activity and the relationship with the
organization and <Company Name> as a whole, a Principal can also be a Supplier.

Term Explanation
A/R AccountsReceivable
A/P AccountsPayable
Customer Canrefertoprincipalortradepartner
DBMS DataBaseManagementSystem
EDI ElectronicDataInterchange
EDIFACT ElectronicDataInterchangeforAdministration,Commerceand
Transportation
FOB FreightonBoard
GL GeneralLedger
GUI GraphicalUserInterface
Hubs Ahubisapieceofelectronicwhichallowsyoutojoincomputers
togetherinastararrangement
ISDN IntegratedServicesDigitalNetwork
LAN LocalAreaNetwork
L/C LetterofCredit
MTD MonthToDate
NBOS NewBranchOperationsSystem
ODBC OpenDataBaseConnectivity
PC PersonalComputer
POD ProofOfDelivery
Principal Anexternalpartywhosuppliesconsumerproductsto<Company
Name>tobesoldtothemarket.
RDBMS RelationalDataBaseManagementSystem
RDT RadioDataTerminal
Routers Ontheinternet,arouterisadeviceorinsomecases,softwareis
acomputer,thatdeterminesthenextnetworkpointtocollidea
packetshouldbeforwardtowarditsdestination.Therouteris
connectedtoatleasttwonetworksanddecideswhichwayto
sendeach
SalesService MeetingplaceandoperationheadquartersofSalesPeoplefor
Center consolidatingbookedorder
SO SalesOrder
SKU StockKeepingUnits
2007 gantthead.com 109
Information Systems Replacement
gantthead.com Proposal Request for Proposal

Term Explanation
StockCreditMemo CreditMemoforanystockitem
StockInvoice Invoiceforanystockitem
Subdistributor Authorizedresellerofproducttothesecondaryandtertiary
market
Supplier Anexternalpartyprovidinggoodsandservicesotherthan
consumerproducts
Switch Intelecommunication,aswitchisanetworkdevicethatselectsa
pathorcircuitforsendingaunitofdatatoitsnextdestination.A
switchmayalsoincludethefunctionoftherouter,adeviceor
programthatcandeterminetherouteandspecificallywhat
adjacentnetworkpointthedatashouldbesentto.Ingeneral,a
switchisasimpleandfastermechanismthanarouterwhich
requiresknowledgeaboutthenetworkandhowtodeterminethe
route
TradePartner Anexternalpartywhobuysconsumerproducts
TDIS ThirdPartyDistributionSystem
UOM UnitofMeasure
WAN WideAreaNetwork
WMS WarehouseManagementSystem
YTD YearToDate

2007 gantthead.com 110

Das könnte Ihnen auch gefallen