Sie sind auf Seite 1von 9

Invited Paper

Overhead line solutions


for a changing Industry
R. STEPHEN* - ESKOM (South Africa)

Synopsis wires to deliver the product. The


route can be commercially deter-
The challenges facing the Electric- mined and paid for in an open market
ity Supply Industry are changing rapidly, trading environment.
utility owners are no longer engineers
nor, in some cases, primarily in the elec- Each of these changes affects the
tricity distribution business. Engineer- ability of the industry to deliver
ing skills are depleted due to re-engi- power as well as affects the loading
neering and right sizing. Customers on the assets, in particular the over-
require an ever increasing level of reli- head lines. These changes and the
ability and weather conditions appear effects on the assets will be dealt with
to be altering, increasing the chances the in proceeding sections.
of wide spread storms. In addition to
this, environmental pressures forbid Effect of changes on over-
new construction in most cases. In head lines
order to operate in this environment, it
is critical that engineers understand the The effect of changes in the Industry
options available to solve issues and is experienced in a number of areas:
problems relating to power transmis- Business priorities focus on profit
sion. This paper describes the chang- rather than budget management.
ing environment as well as develop- Engineering skills outsourced
ments completed and underway in SC skills with a reduction of in house skills.
B2, Overhead Lines, which can assist Power flow requirements the
the engineer to meet these challenges. positioning of Independent Power
Producers and trading affects power
Introduction flow patterns on overhead lines.

Since the late 1980s the Electricity The impact on overhead lines is
Supply Industry has been undergoing more than that experienced on other
various types of de-regulation. This assets, the reason being that there is
normally implies the separation of no one Original Equipment Manufac-
Generation, Transmission and Distri- turer (OEM) for the line. The utility is
bution into independent companies, responsible for the design, construc-
as well as privatization of utilities. tion and maintenance of the line,
where other devices such as breakers
In addition customers can pur- etc, have experts on hand in the
chase directly from Generators who OEM to assist and advise on mainte-
use the Transmission and Distribution nance and loading practices... For

6 ELECTRA N 220 - Juin 2005


Invited Paper
overhead lines, this is not the case, The advent of storms extending
the utility needs to rely on experts in over large areas as experienced in
the field to provide this service. Canada and France in recent years has
led to a re evaluation of the design
The effect of trading and IPPs loads applied to lines.
on lines is that the line loading is
increased in ways never before envis- The Environmental constraints
aged. Lines built as radial lines with and permissions required has resulted
light conductors are required to carry in permission taking from 4 years
heavy loads in a meshed network. (developing countries) to 20 years
This is shown in the Figure 1 where (Europe). In addition legal costs can
the power flow changed from East to often prove to be the single largest
West to North to South. cost component of the project.

Fig. 1: Changes in Power flows in the UK as a result of deregulation


(Cigre Colloquium Scotland 2003)

generation
demand

The maintenance is being fur- Possible solutions


ther optimized thus requiring assets
to operate for longer than previous- Transmission line engineers need
ly between maintenance is carried to understand the nature of the prob-
out. lem facing them as well as where to
The ability to strengthen the obtain information. This applies to
existing network or to construct new consultants and utility engineers.
lines is limited due to the required
return on assets as well as the nor- In this regard SC B2 carried out a
mally lengthy and costly environmen- work relating to mechanical aspects
tal permission process. of overhead line conductors [1]. The
Trading implies that the cost of resulting brochure covers the work of
constraints to power flow is prohibitive. the past four decades in this field and
allows the reader to rapidly assess
These impacts are not the only the progress in this field as well as the
ones to be taken into account: references for the documents.

No. 220 - June 2005 ELECTRA 7


C O N T I N U E D
Invited Paper
Increasing power transfer the safety to the public as well as the
Due to the trading and inability to integrity of the conductor. The safety
construct new lines, it is imperative of the public is also a function of the
that the utility engineer understands presence of vehicles or activity in the
the various steps required to increase vicinity of the line. Using these factors
the power transfer of overhead lines. together, as well as voltage surges on
SC B2 spent the last 14 years studying the line and the load on the line, it is
various aspects of this topic. The first possible to determine the probability
task was to determine equations where- of an unsafe condition arising. Keeping
by the temperature of the conductor this probability constant, it is possible
could be determined in the steady state to determine the rating of the line for
[2]. This enabled more accurate deter- different load profiles or traffic pat-
mination of the steady state thermal terns. This enabled designers to
rating of conductors to be realized. This increase the thermal rating of lines
information could be used by network beyond that which was previously pos-
planners and designers in determining sible. This was described in [5] and [6].
optimum stages in which to increase
the thermal rating of lines. The study continued including
the Real time monitoring of the
The evaluation of conductor tem- transmission line thermal rating. This
perature was extended to include the allows for the system operators to
dynamic state [3] (used in real time utilize the thermal rating of the line
monitoring and probabilistic determi- to the maximum whilst ensuring the
nation of conductor current rating) as risk of exceeding the templating or
well as the adiabatic state [4] (for design temperature is minimized.
determining the conductor tempera- There are many different methods of
ture under fault conditions). Real time monitoring, these were
covered in [7].
The thermal rating of transmission
lines is a function of the position of the It was found that the changing
conductor in space (clearance above environment also required that new
ground) and is therefore a function of or more appropriate conductors

Case 1 - Final Sag vs Conductor Temperature

Graph. 1: Sag Variation with Temperature for Original Zebra ACSR and ACSS/TW,
TACIR, and GZTACSR Replacement Conductors [8]

8 ELECTRA N 220 - Juin 2005


C O N T I N U E D

Invited Paper
should be chosen. These conductors pared to the ACSR conductors but
had to ensure that the line power less than the other options. The
transfer capacity could be increased graph also indicates that each con-
without the towers or foundations ductor needs to be chosen on the
having to be altered. A brochure was particular case. Different conductors
prepared [8] which described the dif- will suit different sags and tempera-
ferent conductor technologies as well ture requirements.
as the application of these technolo- Due to the many types of uprating
gies regarding the uprating of lines. that can be used, a paper [9] was pre-
This was covered in various case stud- pared and published in 2004. This
ies. One of the examples is shown in included a table of the uprating meth-
Graph. 1. ods discussed.

Table 1: Table showing the comparison between the uprating methods


Method How to use When best to use Cost

Deterministic Increase height above ground Templating temperatures Medium


to increase templating below 80oC.
temperature.

Probabilistic Increase templating Templating temperatures Low to


temperature. below 80oC. Medium
Make use of load profiles. Peaky load profiles.
Make use of local weather data.
Assess and decide on
appropriate risk levels.

Real time Install real time monitoring Any templating temperature Medium low
monitoring systems. but more effective at high (Less than INVITED PAPERS
temperatures. re-tensioning)
In networks where trading of
power is undertaken. ELECTRA is the journal
of CIGRE Members.
Re-conductoring Replace existing conductor with When high level of up High
new conductor (preferably, rating is required. Nevertheless, a number of
without having to increase tower Short lines. columns under the section
height or strengthen towers). Any templating temperature
but more effective with higher
Invited Papers are now
temperatures. open to all contributors.
This we hope will enhance
exchanges between
all players in the area
The Graph 1 indicates the present The Table 1 shows the different
of electrical power.
capability of the line (400mm2 A1/S1 methods and the relative cost that
54/7 Zebra) shown by the dotted can be used in uprating of lines.
If in your country you have
line. Assuming that the line can allow information about signifi-
for a 2m increase to 13,5m (case 1) Lowering impedance of overhead cant events or innovation in
the temperature at which the con- lines the area of electricity,
ductor can operate and hence Another method to increase the please share this with us.
increase the power transfer is shown power transfer of lines is to increase Your contribution
for different types of conductors. The the Surge Impedance Loading or (2 500 words maximum)
green line indicates the most efficient lower the overall impedance of the should be sent directly to
in this case which is the gapped zir- the Central Office or to your
line. This can be achieved by varying
conium alloy high temperature alu- National Committee.
the conductor bundle configuration.
It will then be forwarded to
minium alloy conductor steel rein-
the Editing Committee.
forced (GZTACSR). However, a more In this regard, an ELECTRA article
cost effective conductor is likely to was prepared in 2004 (to be pub- We rely on your collabora-
be the aluminium conductor steel lished in 2005) [10]. This indicated the tion, for which we thank you
supported trapezoidal wire (ACSSTW) different bundle configurations possi- in advance.
which is slightly more costly com- ble as well as the benefits.

No. 220 - June 2005 ELECTRA 9


C O N T I N U E D
Invited Paper
Fig. 2: Expanded bundle on right hand phase under construction [10]

The Figure 2 gives an indication of The below work indicates the abili-
the existing and HSIL bundles. This ty to tailor make the line design to suit
configuration was used in Brazil. the needs of the network planners.
This enables the overall cost of the net-
The comparison of the different works to be reduced as it reduces the
types of towers to increase the trans- need for series compensation as well
fer capacity is shown in figure 3. as reduces system losses.

Fig. 3: SIL values for different configurations

10 ELECTRA N 220 - Juin 2005


C O N T I N U E D

Invited Paper
The compact self supported tower on the conductor and hence acceler-
can be replaced by a cross rope com- ate the deterioration of the conductor.
pact design as shown in Figure 4. This
allows for compaction with a lower The determination of the safe ten-
cost tower. sion for conductors is not a simple
matter and has taken the best part of
Fig. 4: Compact cross rope configura- 4 decades to resolve. This is due to
tion (note centre phase is slack in this the complex make of the conductors
case due to tap off (not shown)) and the determination of the energy
input from the wind and the self
damping characteristics of the con-
ductor. The parameters that deter-
mine the vibration as well as the lim-
its to set the parameters were deter-
mined theoretically and experimen-
tally involving many experts over a
number of years. These results have
been published in a 2 part document
with single conductor undamped [11]
and damped [12]. Graphs have been
produced indicating the safe tension
Retensioning vibration considera- for different terrains. An example of
tions the graphs for flat terrain is repro-
The increase of thermal rating can duced here. The tension parameter
be achieved by increasing the height H/w is the ratio of horizontal tension INVITED PAPERS
of the conductor above the ground. H in the span to conductor weight w
This can be done by increasing the per unit length, and LD/m, the ratio ELECTRA is the journal
conductor tension. The drawback is of actual span length times conductor of CIGRE Members.
that this could increase the vibration diameter D to conductor mass Nevertheless, a number of
columns under the section
Graph. 2: Tension limitations for damped conductors Invited Papers are now
open to all contributors.
This we hope will enhance
exchanges between
all players in the area
of electrical power.

If in your country you have


information about signifi-
cant events or innovation in
the area of electricity,
please share this with us.
Your contribution
(2 500 words maximum)
should be sent directly to
the Central Office or to your
National Committee.
It will then be forwarded to
the Editing Committee.

We rely on your collabora-


tion, for which we thank you
in advance.

No. 220 - June 2005 ELECTRA 11


C O N T I N U E D
Invited Paper
m per unit length. The tension H exposition of LCA methodology. All
refers to initial horizontal tension of this is drawn together in conclusion
before any significant wind and ice and recommendations set in the
loading and before creep, at the broader context of LCA as one of
average temperature of the coldest many tools to assess and reduce the
month on the site of the line. [12]. impact or interaction of overhead
More recent results indicate that the lines and the environment. The docu-
bundled conductors can be tensioned ment therefore assists utilities in com-
at higher H/w ratios than single con- plying to the LCA requirements with-
ductors. As most transmission lines con- out having to go to extensive cost of
sist of bundled conductors this implies first finding out and understanding
that it will be possible to increase the the requirements as well as perform
tension further thereby increasing the the LCA for a particular line.
thermal rating of the line.
The document is a follow up to
Foundations another document [13] detailing the
The uprating of lines affects all the work of SC B2.14 dealing with stan-
aspects of transmission lines including dard practices relating to obtaining
foundations. For this reason a docu- environmental permission for vari-
ment covering the refurbishment and ous activities relating to overhead
uprating of foundations was pro- lines.
duced [14]. The document describes
the best methods to review the con-
dition and upgrading of existing foun- Some other developments
dations. It also describes the deterio- underway
ration of foundations and the reasons
for the deterioration such as damage In addition to the above develop-
by frost. Testing methods are also ments, SC B2 is continually reviewing
described. the changing environment and devel-
oping solutions to problems faced by
Environmental requirements utilities, manufacturers and other
The limitations of the environmen- customer groups. Developments
tal regulations dictate that certain cover all the major components of
work has to be completed before lines.
lines are constructed or upgraded or
modified in any way. There is a maze Insulators: Work covers stress cor-
of information that is required to be rosion, effects of snow and ice, evalu-
complied with. One of the most oner- ation of old insulators and guides for
ous of these is the compliance to ISO naturally polluted research stations. In
14040 Environmental Management addition the research relating to
Life Cycle Assessment (LCA) series. uprating is continuing with effects on
The brochure produced explains insulators of vibrations on hardware,
these requirements and it reports on high temperature operation of con-
Scandinavian LCA studies and com- ductors and use of corona rings for
pares a number of LCA software composite insulators.
packages. It presents an overview of
the interaction of overhead line com- Overall design: Work covers research
ponents with the environment. It con- into mid span clearances (to enable
tains the results of various LCA stud- more effective compaction), effect of
ies on overhead line components and large area storms (to determine lessons
overhead lines carried out by Working learnt) and comparison of probabilistic
Group members which give a good design methods (to use local weather

12 ELECTRA N 220 - Juin 2005


C O N T I N U E D

Invited Paper
conditions to maximize the mechanical Conclusion
loading on lines).
The changing environment implies
Foundations: The work includes that CIGRE must continually be aware
the investigation and publication of of needs of customers. This, in turn,
case studies in refurbishment and means that the work of the Study
upgrading. In addition probabilistic committee must adapt to meet these
design of foundations is being final- needs. In the case of SC B2, as
ized. described here, my feeling is that the
work of the SC has met and will con-
Towers: Work includes the assess- tinue to strive to meet the needs of
ment of variation of tower strengths, customers.
towers for new lines and new testing
methods. The solutions refered to in this
invited paperpaper should allow for
Electrical aspects: Work deals with utilities to readily find the required
the determination of AC resistance at solution to the most pressing of
high current densities (above 1A/mm2) issues, that is uprating and refurbish-
and the determination of sag tension ment of lines as well as dealing with
relationships. The determination of environmental issues.
weather parameters for determination
of current rating is also being devel- References
oped to guide utilities in the best
practice relating to determination of CIGR Working Group B2.11. The
current ratings and to prevent the mechanical behaviour of conductors INVITED PAPERS
practice in increasing wind speed and fittings. Brochure 251. August
without the determination of increased 2004. ELECTRA is the journal
risk. CIGR Working Group B2.12. The of CIGRE Members.
thermal behaviour of overhead con- Nevertheless, a number of
Mechanical Aspects: The work ductors. Sections 1 and 2. Electra 144. columns under the section
under consideration includes the October 1992. Invited Papers are now
fatigue endurance capability of the CIGR CE/SC 22. Publi/Published: open to all contributors.
conductor/clamp system. This infor- Electra 1997. Ref. No. 174. The thermal This we hope will enhance
exchanges between
mation is vital to uprating and refur- behaviour of overhead conductors.
all players in the area
bishment activities. Section 3: Mathematical model for
of electrical power.
evaluation of conductor temperature in
Management of lines: This work the unsteady state. If in your country you have
includes the development of manage- CIGR CE/SC 22. Publi/Published : information about signifi-
ment methods relating to the emer- Electra 1999. Ref. No. 185. The thermal cant events or innovation in
gency restoration of lines. This behaviour of overhead conductors. the area of electricity,
includes the management of spares Section 4 : Mathematical model for please share this with us.
and the organizational requirements evaluation of conductor temperature in Your contribution
of the utility relating to effective man- the adiabatic state. (2 500 words maximum)
agement of emergency systems. CIGR Working Group SC 22.12 should be sent directly to
Cigre (Chairman R. STEPHEN). Proba- the Central Office or to your
National Committee.
Weather parameters: This work bilistic Determination of Conductor
It will then be forwarded to
includes the determination of weath- Current Ratings. (Electra No. 164.
the Editing Committee.
er parameters to use in the calcula- February 1996, pages 103-119).
tion of loads on the towers, conduc- R. STEPHEN CIGR CE/SC 22. We rely on your collabora-
tors and foundation system. This Publi/Published: 1994. Session tion, for which we thank you
includes high intensity winds as well paper. Ref. No. 22-204. Extension of in advance.
as ice loading events. reliability based methodology

No. 220 - June 2005 ELECTRA 13


C O N T I N U E D
Invited Paper

RTE

(using simulation techniques and sta- Conductors/ Tension nominale scuri-


tistical signatures) for aspects of over- taire en regard des vibrations oli-
head line design. ennes. 1re partie: conducteurs simples
R. STEPHEN, CIGR CE/SC 22. sans protection, Electra No. 186,
Publi/Published: 2000. Session October 1999, pp. 52-67.
Paper. Ref. No. 22-304. Description of CIGR Study Committee 22,
state of the art methods todetermine Working Group 11, Task Force 04,
thermal rating of lines in real time and Published 2001. Electra No. 198.
application in optimising power flow. Safe Design Tension with Respect to
CIGR SC B2.12 Conductors for Aeolian Vibrations. Part 2: Damped
the uprating of overhead lines. single Conductors.
Brochure 244. February 2004. CE/SC 22. Publi/Published: 1999.
R. STEPHEN, CIGR SC B2. Technical Brochure. Ref. No. 147. High
Published 2004. Session paper. Ref. voltage overhead lines. Environmental
No. B2-201. Description and evalua- concerns. procedures. impacts and mit-
tion of options relating to uprating of igations.
overhead transmission lines. CE/SC 22. Publi/Published: 1999.
CIGR SC B2.06. High surge Technical Brochure. Ref. No. 141. Refur-
impedance loading transmission line bishment and upgrading of founda-
HSIL: A concept to increase the tions.
capacity of overhead lines to be
published 2005. * R. STEPHEN, former Chairman of
CIGR Study Committee 22, Work- SC B2. Corporate Consultant, Eskom
ing Group 11, Task Force 04, Safe Holdings, P.O. Box 66, New Germany,
Design Tension with Respect to Aeolian 3620.
Vibrations. Part 1: Single Unprotected Email: stepher
stepherg@eskom.co.za
g@eskom.co.za

14 ELECTRA N 220 - Juin 2005

Das könnte Ihnen auch gefallen