Beruflich Dokumente
Kultur Dokumente
Since the late 1980s the Electricity The impact on overhead lines is
Supply Industry has been undergoing more than that experienced on other
various types of de-regulation. This assets, the reason being that there is
normally implies the separation of no one Original Equipment Manufac-
Generation, Transmission and Distri- turer (OEM) for the line. The utility is
bution into independent companies, responsible for the design, construc-
as well as privatization of utilities. tion and maintenance of the line,
where other devices such as breakers
In addition customers can pur- etc, have experts on hand in the
chase directly from Generators who OEM to assist and advise on mainte-
use the Transmission and Distribution nance and loading practices... For
generation
demand
Graph. 1: Sag Variation with Temperature for Original Zebra ACSR and ACSS/TW,
TACIR, and GZTACSR Replacement Conductors [8]
Invited Paper
should be chosen. These conductors pared to the ACSR conductors but
had to ensure that the line power less than the other options. The
transfer capacity could be increased graph also indicates that each con-
without the towers or foundations ductor needs to be chosen on the
having to be altered. A brochure was particular case. Different conductors
prepared [8] which described the dif- will suit different sags and tempera-
ferent conductor technologies as well ture requirements.
as the application of these technolo- Due to the many types of uprating
gies regarding the uprating of lines. that can be used, a paper [9] was pre-
This was covered in various case stud- pared and published in 2004. This
ies. One of the examples is shown in included a table of the uprating meth-
Graph. 1. ods discussed.
Real time Install real time monitoring Any templating temperature Medium low
monitoring systems. but more effective at high (Less than INVITED PAPERS
temperatures. re-tensioning)
In networks where trading of
power is undertaken. ELECTRA is the journal
of CIGRE Members.
Re-conductoring Replace existing conductor with When high level of up High
new conductor (preferably, rating is required. Nevertheless, a number of
without having to increase tower Short lines. columns under the section
height or strengthen towers). Any templating temperature
but more effective with higher
Invited Papers are now
temperatures. open to all contributors.
This we hope will enhance
exchanges between
all players in the area
The Graph 1 indicates the present The Table 1 shows the different
of electrical power.
capability of the line (400mm2 A1/S1 methods and the relative cost that
54/7 Zebra) shown by the dotted can be used in uprating of lines.
If in your country you have
line. Assuming that the line can allow information about signifi-
for a 2m increase to 13,5m (case 1) Lowering impedance of overhead cant events or innovation in
the temperature at which the con- lines the area of electricity,
ductor can operate and hence Another method to increase the please share this with us.
increase the power transfer is shown power transfer of lines is to increase Your contribution
for different types of conductors. The the Surge Impedance Loading or (2 500 words maximum)
green line indicates the most efficient lower the overall impedance of the should be sent directly to
in this case which is the gapped zir- the Central Office or to your
line. This can be achieved by varying
conium alloy high temperature alu- National Committee.
the conductor bundle configuration.
It will then be forwarded to
minium alloy conductor steel rein-
the Editing Committee.
forced (GZTACSR). However, a more In this regard, an ELECTRA article
cost effective conductor is likely to was prepared in 2004 (to be pub- We rely on your collabora-
be the aluminium conductor steel lished in 2005) [10]. This indicated the tion, for which we thank you
supported trapezoidal wire (ACSSTW) different bundle configurations possi- in advance.
which is slightly more costly com- ble as well as the benefits.
The Figure 2 gives an indication of The below work indicates the abili-
the existing and HSIL bundles. This ty to tailor make the line design to suit
configuration was used in Brazil. the needs of the network planners.
This enables the overall cost of the net-
The comparison of the different works to be reduced as it reduces the
types of towers to increase the trans- need for series compensation as well
fer capacity is shown in figure 3. as reduces system losses.
Invited Paper
The compact self supported tower on the conductor and hence acceler-
can be replaced by a cross rope com- ate the deterioration of the conductor.
pact design as shown in Figure 4. This
allows for compaction with a lower The determination of the safe ten-
cost tower. sion for conductors is not a simple
matter and has taken the best part of
Fig. 4: Compact cross rope configura- 4 decades to resolve. This is due to
tion (note centre phase is slack in this the complex make of the conductors
case due to tap off (not shown)) and the determination of the energy
input from the wind and the self
damping characteristics of the con-
ductor. The parameters that deter-
mine the vibration as well as the lim-
its to set the parameters were deter-
mined theoretically and experimen-
tally involving many experts over a
number of years. These results have
been published in a 2 part document
with single conductor undamped [11]
and damped [12]. Graphs have been
produced indicating the safe tension
Retensioning vibration considera- for different terrains. An example of
tions the graphs for flat terrain is repro-
The increase of thermal rating can duced here. The tension parameter
be achieved by increasing the height H/w is the ratio of horizontal tension INVITED PAPERS
of the conductor above the ground. H in the span to conductor weight w
This can be done by increasing the per unit length, and LD/m, the ratio ELECTRA is the journal
conductor tension. The drawback is of actual span length times conductor of CIGRE Members.
that this could increase the vibration diameter D to conductor mass Nevertheless, a number of
columns under the section
Graph. 2: Tension limitations for damped conductors Invited Papers are now
open to all contributors.
This we hope will enhance
exchanges between
all players in the area
of electrical power.
Invited Paper
conditions to maximize the mechanical Conclusion
loading on lines).
The changing environment implies
Foundations: The work includes that CIGRE must continually be aware
the investigation and publication of of needs of customers. This, in turn,
case studies in refurbishment and means that the work of the Study
upgrading. In addition probabilistic committee must adapt to meet these
design of foundations is being final- needs. In the case of SC B2, as
ized. described here, my feeling is that the
work of the SC has met and will con-
Towers: Work includes the assess- tinue to strive to meet the needs of
ment of variation of tower strengths, customers.
towers for new lines and new testing
methods. The solutions refered to in this
invited paperpaper should allow for
Electrical aspects: Work deals with utilities to readily find the required
the determination of AC resistance at solution to the most pressing of
high current densities (above 1A/mm2) issues, that is uprating and refurbish-
and the determination of sag tension ment of lines as well as dealing with
relationships. The determination of environmental issues.
weather parameters for determination
of current rating is also being devel- References
oped to guide utilities in the best
practice relating to determination of CIGR Working Group B2.11. The
current ratings and to prevent the mechanical behaviour of conductors INVITED PAPERS
practice in increasing wind speed and fittings. Brochure 251. August
without the determination of increased 2004. ELECTRA is the journal
risk. CIGR Working Group B2.12. The of CIGRE Members.
thermal behaviour of overhead con- Nevertheless, a number of
Mechanical Aspects: The work ductors. Sections 1 and 2. Electra 144. columns under the section
under consideration includes the October 1992. Invited Papers are now
fatigue endurance capability of the CIGR CE/SC 22. Publi/Published: open to all contributors.
conductor/clamp system. This infor- Electra 1997. Ref. No. 174. The thermal This we hope will enhance
exchanges between
mation is vital to uprating and refur- behaviour of overhead conductors.
all players in the area
bishment activities. Section 3: Mathematical model for
of electrical power.
evaluation of conductor temperature in
Management of lines: This work the unsteady state. If in your country you have
includes the development of manage- CIGR CE/SC 22. Publi/Published : information about signifi-
ment methods relating to the emer- Electra 1999. Ref. No. 185. The thermal cant events or innovation in
gency restoration of lines. This behaviour of overhead conductors. the area of electricity,
includes the management of spares Section 4 : Mathematical model for please share this with us.
and the organizational requirements evaluation of conductor temperature in Your contribution
of the utility relating to effective man- the adiabatic state. (2 500 words maximum)
agement of emergency systems. CIGR Working Group SC 22.12 should be sent directly to
Cigre (Chairman R. STEPHEN). Proba- the Central Office or to your
National Committee.
Weather parameters: This work bilistic Determination of Conductor
It will then be forwarded to
includes the determination of weath- Current Ratings. (Electra No. 164.
the Editing Committee.
er parameters to use in the calcula- February 1996, pages 103-119).
tion of loads on the towers, conduc- R. STEPHEN CIGR CE/SC 22. We rely on your collabora-
tors and foundation system. This Publi/Published: 1994. Session tion, for which we thank you
includes high intensity winds as well paper. Ref. No. 22-204. Extension of in advance.
as ice loading events. reliability based methodology
RTE