Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.

00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
1 PROGRAMME FOR SECTION CH. 45+000 TO CH.67+000 - 194
22 KM
days Sat 19-07-14 Thu 29-01-15
2 Highway Works 158 days Mon 04-08-14 Fri 09-01-15
3 CH. 45+000 TO 54+100 - 9.10 KM 96 days Mon 04-08-14 Sat 08-11-14
4 C&G 20 days Mon 04-08-14 Sun 24-08-14

5 EMBANKMENT CONSTRUCTION 66 days Thu 07-08-14 Sun 12-10-14

6 SG FILLING 75 days Thu 14-08-14 Tue 28-10-14

7 GSB 70 days Thu 21-08-14 Thu 30-10-14

8 WMM 70 days Mon 25-08-14 Mon 03-11-14

9 DBM 48 days Fri 19-09-14 Thu 06-11-14

10 BC 45 days Wed 24-09-14 Sat 08-11-14

11 CH. 54+100 TO 58+500 - MOHANA BYPASS - 4.40 104 days Mon 04-08-14 Sun 16-11-14
KM
12 C&G 10 days Mon 04-08-14 Thu 14-08-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

1 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
13 EMBANKMENT CONSTRUCTION 90 days Thu 07-08-14 Wed 05-11-14

14 SG FILLING 85 days Thu 14-08-14 Fri 07-11-14

15 GSB 80 days Thu 21-08-14 Sun 09-11-14

16 WMM 78 days Mon 25-08-14 Tue 11-11-14

17 DBM 50 days Wed 24-09-14 Thu 13-11-14

18 BC 48 days Mon 29-09-14 Sun 16-11-14

19 CH.58+500 TO 67+000 - 8.50 KM 89 days Mon 04-08-14 Sat 01-11-14


20 C&G 20 days Mon 04-08-14 Sun 24-08-14

21 EMBANKMENT CONSTRUCTION 60 days Thu 07-08-14 Mon 06-10-14

22 SG FILLING 70 days Thu 14-08-14 Thu 23-10-14

23 GSB 65 days Thu 21-08-14 Sat 25-10-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

2 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
24 WMM 63 days Mon 25-08-14 Mon 27-10-14

25 DBM 40 days Fri 19-09-14 Wed 29-10-14

26 BC 38 days Wed 24-09-14 Sat 01-11-14

27 OTHER WORKS 98 days Fri 03-10-14 Fri 09-01-15

28 DRAIN WORKS 60 days Fri 03-10-14 Tue 02-12-14

29 METALLIC CRASH BARRIER 60 days Thu 06-11-14 Mon 05-01-15

30 ROAD MARKINGS, SIGN BOARDS, KILOMETERS, 60 days Mon 10-11-14 Fri 09-01-15
TURFFING, EARTHEN DRAINS & STADS

31 STRUCTURES 194 days Sat 19-07-14 Thu 29-01-15


32 MAJOR BRIDGE - 61+785 194 days Sat 19-07-14 Thu 29-01-15

33 PIERS - 11 NOS 108 days Sat 19-07-14 Tue 04-11-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

3 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
34 EXCAVATION 12 days Sat 19-07-14 Thu 31-07-14

35 PCC 5 days Tue 05-08-14 Sun 10-08-14

36 REINFORCEMENT FOR FOOTING 28 days Thu 07-08-14 Thu 04-09-14

37 SHUTTERING FOR FOOTING 28 days Sat 09-08-14 Sat 06-09-14

38 CONCRETE FOR FOOTING 28 days Sun 10-08-14 Sun 07-09-14

39 REINFORCEMENT FOR PIERS 28 days Tue 12-08-14 Tue 09-09-14

40 STAGING FOR PIER WORKS 30 days Sat 16-08-14 Mon 15-09-14

41 FABRICATION OF PIER SHUTTERING 45 days Fri 08-08-14 Mon 22-09-14

42 ERRECTION OF PIER SHUTTERING 40 days Mon 18-08-14 Sat 27-09-14

43 CASTING OF PIERS 42 days Tue 19-08-14 Tue 30-09-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

4 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
44 DE SHUTTERING OF PIERS 7 days Thu 25-09-14 Thu 02-10-14

45 PIER CAP REINFORCEMENT 10 days Fri 03-10-14 Mon 13-10-14

46 PIER CAP SHUTTERING 7 days Tue 14-10-14 Tue 21-10-14

47 PIER CAP CONCRETE 7 days Wed 22-10-14 Wed 29-10-14

48 CASTING OF PEDSAL 7 days Thu 23-10-14 Thu 30-10-14

49 FIXING OF BEARING 4 days Fri 31-10-14 Tue 04-11-14

50 FINISHING WORKS 4 days Wed 29-10-14 Sun 02-11-14

51 ABUTMENTS - 2 NOS 42 days Mon 04-08-14 Mon 15-09-14

52 EXCAVATION 4 days Mon 04-08-14 Fri 08-08-14

53 PCC 4 days Tue 05-08-14 Sat 09-08-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

5 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
54 FOOTING 10 days Thu 07-08-14 Sun 17-08-14

55 I ST LIFT 9 days Sun 10-08-14 Tue 19-08-14

56 II ST LIFT 3 days Tue 19-08-14 Fri 22-08-14

57 III ST LIFT 3 days Fri 22-08-14 Mon 25-08-14

58 IV ST LIFT 3 days Mon 25-08-14 Thu 28-08-14

59 V ST LIFT 3 days Thu 28-08-14 Sun 31-08-14

60 ABUTMENT CAP 7 days Thu 04-09-14 Thu 11-09-14

61 CASTING OF PEDSAL 6 days Sun 07-09-14 Sat 13-09-14

62 FIXING OF BEARING 1 day Sat 13-09-14 Sun 14-09-14

63 FINISHING WORKS 4 days Thu 11-09-14 Mon 15-09-14

64 RETAINING WALL & RETURN WALL 32 days Thu 07-08-14 Mon 08-09-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

6 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
65 EXCAVATION 4 days Thu 07-08-14 Mon 11-08-14

66 PCC 3 days Sun 10-08-14 Wed 13-08-14

67 I ST LIFT 7 days Wed 13-08-14 Wed 20-08-14

68 II ST LIFT 3 days Wed 20-08-14 Sat 23-08-14

69 III ST LIFT 3 days Sat 23-08-14 Tue 26-08-14

70 IV ST LIFT 3 days Tue 26-08-14 Fri 29-08-14

71 V ST LIFT 3 days Fri 29-08-14 Mon 01-09-14

72 VI ST LIFT 3 days Mon 01-09-14 Thu 04-09-14

73 VII ST LIFT 3 days Thu 04-09-14 Sun 07-09-14

74 FINISHING WORKS 3 days Fri 05-09-14 Mon 08-09-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

7 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
75 GIRDERS 156 days Tue 05-08-14 Thu 08-01-15

76 PREPARATION OF YARD INCLUDING BEDS 60 days Tue 05-08-14 Sat 04-10-14

77 CASTING OF 48 GIRDERS 75 days Fri 19-09-14 Wed 03-12-14

78 PRESTRESSING OF GIRDERS 60 days Fri 10-10-14 Tue 09-12-14

79 GROUTING & SEALING 75 days Fri 17-10-14 Wed 31-12-14

80 TRANSPORTATION TO SITE 75 days Wed 22-10-14 Mon 05-01-15

81 ERECTION AT SITE 62 days Thu 06-11-14 Wed 07-01-15

82 CROSS GIRDERS 60 days Sun 09-11-14 Thu 08-01-15

83 SLAB 64 days Tue 11-11-14 Wed 14-01-15


84 SHUTTERING 60 days Tue 11-11-14 Sat 10-01-15

85 REINFORCEMENT 60 days Thu 13-11-14 Mon 12-01-15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

8 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
86 CONCRETE 60 days Sat 15-11-14 Wed 14-01-15

87 OTHER WORKS 149 days Tue 02-09-14 Thu 29-01-15

88 CRASH BARRIER 7 days Sat 17-01-15 Sat 24-01-15

89 BACKFILLING 52 days Tue 02-09-14 Fri 24-10-14

90 APPROCH SLAB 13 days Fri 16-01-15 Thu 29-01-15

91 WEARING COAT 6 days Sun 18-01-15 Sat 24-01-15

92 STONE PITCHING 60 days Sun 07-09-14 Thu 06-11-14

93 FINISHING AND OVERALL COMPLETION 3 days Sun 18-01-15 Wed 21-01-15

94 MAJOR BRIDGE - 57+875 162 days Sat 16-08-14 Sun 25-01-15


95 PIERS - 06 NOS 83 days Sat 16-08-14 Fri 07-11-14
96 EXCAVATION 12 days Sat 16-08-14 Thu 28-08-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

9 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
97 PCC 5 days Tue 02-09-14 Sun 07-09-14

98 REINFORCEMENT FOR FOOTING 28 days Thu 04-09-14 Thu 02-10-14

99 SHUTTERING FOR FOOTING 28 days Sat 06-09-14 Sat 04-10-14

100 CONCRETE FOR FOOTING 28 days Sun 07-09-14 Sun 05-10-14

101 REINFORCEMENT FOR PIERS 28 days Tue 09-09-14 Tue 07-10-14

102 STAGING FOR PIER WORKS 25 days Sat 13-09-14 Wed 08-10-14

103 FABRICATION OF PIER SHUTTERING 15 days Sun 07-09-14 Mon 22-09-14

104 ERRECTION OF PIER SHUTTERING 25 days Wed 17-09-14 Sun 12-10-14

105 CASTING OF PIERS 25 days Thu 18-09-14 Mon 13-10-14

106 DE SHUTTERING OF PIERS 25 days Sat 20-09-14 Wed 15-10-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

10 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
107 PIER CAP REINFORCEMENT 10 days Mon 06-10-14 Thu 16-10-14

108 PIER CAP SHUTTERING 7 days Fri 17-10-14 Fri 24-10-14

109 PIER CAP CONCRETE 7 days Sat 25-10-14 Sat 01-11-14

110 CASTING OF PEDSAL 7 days Sun 26-10-14 Sun 02-11-14

111 FIXING OF BEARING 4 days Mon 03-11-14 Fri 07-11-14

112 FINISHING WORKS 4 days Sat 01-11-14 Wed 05-11-14

113 ABUTMENTS - 2 NOS 36 days Sat 16-08-14 Sun 21-09-14


114 EXCAVATION 4 days Sat 16-08-14 Wed 20-08-14

115 PCC 4 days Sun 17-08-14 Thu 21-08-14

116 FOOTING 10 days Tue 19-08-14 Fri 29-08-14

117 I ST LIFT 9 days Fri 22-08-14 Sun 31-08-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

11 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
118 II ST LIFT 3 days Sun 31-08-14 Wed 03-09-14

119 III ST LIFT 3 days Wed 03-09-14 Sat 06-09-14

120 ABUTMENT CAP 7 days Sun 07-09-14 Sun 14-09-14

121 CASTING OF PEDSAL 6 days Wed 10-09-14 Tue 16-09-14

122 FIXING OF BEARING 1 day Tue 16-09-14 Wed 17-09-14

123 FINISHING WORKS 4 days Wed 17-09-14 Sun 21-09-14

124 RETAINING WALL & RETURN WALL 26 days Mon 18-08-14 Sat 13-09-14
125 EXCAVATION 4 days Mon 18-08-14 Fri 22-08-14

126 PCC 3 days Thu 21-08-14 Sun 24-08-14

127 I ST LIFT 7 days Sun 24-08-14 Sun 31-08-14

128 II ST LIFT 3 days Sun 31-08-14 Wed 03-09-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

12 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
129 III ST LIFT 3 days Wed 03-09-14 Sat 06-09-14

130 IV ST LIFT 3 days Sat 06-09-14 Tue 09-09-14

131 V ST LIFT 3 days Tue 09-09-14 Fri 12-09-14

132 FINISHING WORKS 3 days Wed 10-09-14 Sat 13-09-14

133 GIRDERS 109 days Sat 04-10-14 Wed 21-01-15


134 CASTING OF 56 GIRDERS 75 days Sat 04-10-14 Thu 18-12-14

135 PRESTRESSING OF GIRDERS 56 days Sat 25-10-14 Sat 20-12-14

136 GROUTING & SEALING 68 days Fri 17-10-14 Wed 24-12-14

137 TRANSPORTATION TO SITE 65 days Wed 22-10-14 Fri 26-12-14

138 ERECTION AT SITE 65 days Sun 09-11-14 Tue 13-01-15

139 CROSS GIRDERS 69 days Thu 13-11-14 Wed 21-01-15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

13 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
140 SLAB 59 days Tue 18-11-14 Fri 16-01-15
141 SHUTTERING 52 days Tue 18-11-14 Fri 09-01-15

142 REINFORCEMENT 55 days Thu 20-11-14 Wed 14-01-15

143 CONCRETE 55 days Sat 22-11-14 Fri 16-01-15

144 OTHER WORKS 144 days Wed 03-09-14 Sun 25-01-15


145 CRASH BARRIER 50 days Sat 29-11-14 Sun 18-01-15

146 BACKFILLING 52 days Wed 03-09-14 Sat 25-10-14

147 APPROCH SLAB 14 days Mon 05-01-15 Mon 19-01-15

148 WEARING COAT 6 days Fri 16-01-15 Thu 22-01-15

149 STONE PITCHING 60 days Sun 07-09-14 Thu 06-11-14

150 FINISHING AND OVERALL COMPLETION 3 days Thu 22-01-15 Sun 25-01-15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

14 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
151 MAJOR BRIDGE - 53+725 115 days Wed 20-08-14 Sat 13-12-14

152 PIERS - 02 NOS 65 days Wed 20-08-14 Fri 24-10-14

153 EXCAVATION 4 days Wed 20-08-14 Sun 24-08-14

154 PCC 2 days Sat 23-08-14 Mon 25-08-14

155 REINFORCEMENT FOR FOOTING 7 days Sun 24-08-14 Sun 31-08-14

156 SHUTTERING FOR FOOTING 14 days Mon 25-08-14 Mon 08-09-14

157 CONCRETE FOR FOOTING 14 days Wed 27-08-14 Wed 10-09-14

158 REINFORCEMENT FOR PIERS 14 days Sat 30-08-14 Sat 13-09-14

159 STAGING FOR PIER WORKS 16 days Fri 29-08-14 Sun 14-09-14

160 FABRICATION OF PIER SHUTTERING 14 days Mon 25-08-14 Mon 08-09-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

15 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
161 ERRECTION OF PIER SHUTTERING 12 days Sun 14-09-14 Fri 26-09-14

162 CASTING OF PIERS 7 days Fri 26-09-14 Fri 03-10-14

163 DE SHUTTERING OF PIERS 7 days Fri 03-10-14 Fri 10-10-14

164 PIER CAP REINFORCEMENT 4 days Fri 10-10-14 Tue 14-10-14

165 PIER CAP SHUTTERING 2 days Tue 14-10-14 Thu 16-10-14

166 PIER CAP CONCRETE 2 days Thu 16-10-14 Sat 18-10-14

167 CASTING OF PEDSAL 2 days Sat 18-10-14 Mon 20-10-14

168 FIXING OF BEARING 2 days Mon 20-10-14 Wed 22-10-14

169 FINISHING WORKS 2 days Wed 22-10-14 Fri 24-10-14

170 ABUTMENTS - 2 NOS 28 days Thu 21-08-14 Thu 18-09-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

16 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
171 EXCAVATION 4 days Thu 21-08-14 Mon 25-08-14

172 PCC 4 days Sun 24-08-14 Thu 28-08-14

173 FOOTING 7 days Tue 26-08-14 Tue 02-09-14

174 I ST LIFT 7 days Thu 28-08-14 Thu 04-09-14

175 II ST LIFT 7 days Sat 30-08-14 Sat 06-09-14

176 III ST LIFT 7 days Mon 01-09-14 Mon 08-09-14

177 IV ST LIFT 7 days Wed 03-09-14 Wed 10-09-14

178 ABUTMENT CAP 7 days Fri 05-09-14 Fri 12-09-14

179 CASTING OF PEDSAL 7 days Sun 07-09-14 Sun 14-09-14

180 FIXING OF BEARING 7 days Tue 09-09-14 Tue 16-09-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

17 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
181 FINISHING WORKS 7 days Thu 11-09-14 Thu 18-09-14

182 RETAINING WALL & RETURN WALL 23 days Fri 22-08-14 Sun 14-09-14

183 EXCAVATION 4 days Fri 22-08-14 Tue 26-08-14

184 PCC 3 days Sun 24-08-14 Wed 27-08-14

185 I ST LIFT 7 days Tue 26-08-14 Tue 02-09-14

186 II ST LIFT 7 days Thu 28-08-14 Thu 04-09-14

187 III ST LIFT 7 days Sat 30-08-14 Sat 06-09-14

188 IV ST LIFT 7 days Mon 01-09-14 Mon 08-09-14

189 V ST LIFT 7 days Wed 03-09-14 Wed 10-09-14

190 VI ST LIFT 7 days Fri 05-09-14 Fri 12-09-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

18 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
191 FINISHING WORKS 7 days Sun 07-09-14 Sun 14-09-14

192 GIRDERS 100 days Thu 04-09-14 Sat 13-12-14

193 CASTING OF 12 GIRDERS 75 days Thu 04-09-14 Tue 18-11-14

194 PRESTRESSING OF GIRDERS 60 days Fri 10-10-14 Tue 09-12-14

195 GROUTING & SEALING 55 days Fri 17-10-14 Thu 11-12-14

196 TRANSPORTATION TO SITE 52 days Wed 22-10-14 Sat 13-12-14

197 ERECTION AT SITE 45 days Thu 18-09-14 Sun 02-11-14

198 CROSS GIRDERS 45 days Mon 22-09-14 Thu 06-11-14

199 SLAB 64 days Thu 25-09-14 Fri 28-11-14

200 SHUTTERING 60 days Thu 25-09-14 Mon 24-11-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

19 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
201 REINFORCEMENT 60 days Sat 27-09-14 Wed 26-11-14

202 CONCRETE 60 days Mon 29-09-14 Fri 28-11-14

203 OTHER WORKS 93 days Wed 03-09-14 Fri 05-12-14


204 CRASH BARRIER 7 days Fri 28-11-14 Fri 05-12-14

205 BACKFILLING 52 days Wed 03-09-14 Sat 25-10-14

206 APPROCH SLAB 14 days Mon 17-11-14 Mon 01-12-14

207 WEARING COAT 6 days Thu 27-11-14 Wed 03-12-14

208 STONE PITCHING 60 days Wed 10-09-14 Sun 09-11-14

209 FINISHING AND OVERALL COMPLETION 3 days Sun 09-11-14 Wed 12-11-14

210 BOX CULVERTS - 10 Nos 73 days Wed 20-08-14 Sat 01-11-14


211 EXCAVATION & PCC LAYING 20 days Wed 20-08-14 Tue 09-09-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

20 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
212 FOUNDATION 45 days Fri 22-08-14 Mon 06-10-14

213 SUBSTRUCTURE 60 days Sun 24-08-14 Thu 23-10-14

214 SUPERSTRUCTURE 60 days Wed 27-08-14 Sun 26-10-14

215 RETURN WALLS 60 days Sun 24-08-14 Thu 23-10-14

216 CRASH BARRIER 14 days Wed 15-10-14 Wed 29-10-14

217 FINISHING WORKS 14 days Sat 18-10-14 Sat 01-11-14

218 PIPE CULVERTS - 12 Nos 28 days Sat 19-07-14 Sat 16-08-14


219 EXCAVATION & PCC LAYING 14 days Sat 19-07-14 Sat 02-08-14

220 HEAD WALL FIRST LIFT 14 days Mon 21-07-14 Mon 04-08-14

221 GRANULAR BED LAYING 7 days Thu 31-07-14 Thu 07-08-14

222 LAYING OF NP4 PIPES 10 days Sat 02-08-14 Tue 12-08-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

21 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
223 HEAD WALL II LIFT 14 days Thu 31-07-14 Thu 14-08-14

224 FINSHING WORKS 3 days Wed 13-08-14 Sat 16-08-14

225 MINOR BRIDGE - 10 Nos 72 days Thu 14-08-14 Sat 25-10-14


226 EXCAVATION & PCC LAYING 20 days Thu 14-08-14 Wed 03-09-14

227 FOUNDATION 45 days Sat 16-08-14 Tue 30-09-14

228 SUBSTRUCTURE 60 days Mon 18-08-14 Fri 17-10-14

229 SUPERSTRUCTURE 60 days Wed 20-08-14 Sun 19-10-14

230 RETURN WALLS 60 days Fri 22-08-14 Tue 21-10-14

231 CRASHBARRIER 14 days Thu 09-10-14 Thu 23-10-14

232 FINISHING WORKS 14 days Sat 11-10-14 Sat 25-10-14

233 PUP'S - 2 Nos 55 days Sat 19-07-14 Fri 12-09-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

22 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

ID Task Task Name Duration Start Finish


Mode 31 Mar '14 12 May '14
234 EXCAVATION & PCC LAYING 7 days Sat 19-07-14 Sat 26-07-14

235 PUP FOUNDATION 14 days Mon 21-07-14 Mon 04-08-14

236 PUP SUBSTRUCTURE 45 days Wed 23-07-14 Sat 06-09-14

237 PUP SUPERSTRUCTURE 45 days Fri 25-07-14 Mon 08-09-14

238 CRASHBARRIER 7 days Wed 03-09-14 Wed 10-09-14

239 FINISHING WORKS 3 days Tue 09-09-14 Fri 12-09-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

23 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

24 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

25 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

26 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

27 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

28 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

29 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

30 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

31 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

32 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

33 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

34 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

35 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

36 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

37 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

38 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

39 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

40 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

41 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

42 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

43 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

44 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

45 of 46
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14 23 Jun '14 04 Aug '14 15 Sep '14 27 Oct '14 08 Dec '14 19 Jan '15 02 Mar '15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only