Beruflich Dokumente
Kultur Dokumente
2
necessary to introduce additional control functionalities in connected) was developed using a step by step procedure
the HVDC-VSC stations. It is important to mention that as follows:
the main objective of the additional control is to make Energize the bus of the generator that has black
possible that the offshore DC connected WF contributes start capability and that has adequate capacity to
to mainland primary frequency regulation. absorb reactive power generated by unloaded
In this research it was assumed that the solution described transmission lines following its energization;
in [11] was implemented, such that frequency changes in Energize the HV lines, while keeping control of
the mainland grid are proportionally converted into DC the voltage on the grid using the generators
voltage changes, through a droop control approach reactive power absorption capability;
implemented at the onshore HVDC station. Afterwards Connect some steps of load by energizing
these DC voltage changes are converted by the offshore feeders in substations already connected to the
HVDC station into frequency changes, exploiting another grid.
droop control approach. Then it is assumed that wind Keep on connecting other generators following
generators can be operated on a deloaded maximum the energization of their auxiliary services and
power extraction curve to be able to provide primary after a minimum time required to have the
frequency control following a similar approach to the one generators ready to be synchronized with the
described in [9-10]. grid.
The frequency droops for the onshore and offshore While developing this sequence the following operational
converters can be adjusted centrally in a coordinated way restrictions were kept under control:
by the system operators, according to the specificities of Frequency excursions in the range of [-0,5; +0,2]
the AC onshore system operating conditions. Hz
Regarding the provision of reactive power / voltage Maximum overvoltage 1,1 p.u. during 5 s.
control, the HVDC-VSC is assumed to be capable to
Minimal time between operations:
provide such functionality, behaving in a similar way to a
Start-up time thermal units: 20 minutes.
STATCOM, i.e. injecting reactive power proportionally
Start-up time hydraulic units: 5 minutes.
to the terminal voltage changes. For the case of the
Grid operations: 40 seconds.
offshore WF, the full reactive capacity of the HVDC VSC
converter was made available to support the PSR
These values can be adjusted case by case, according to
procedure (after being connected to the grid) providing an
the grid operational characteristics and protection
extremely fast and valuable control capability to the grid,
systems.
by absorbing the excess of reactive power that may exist
When including wind generation in the PSR, identifying
in the first steps of the restoration scheme, namely due to the timings and step volumes of wind power connection
the energization of unloaded transmission lines. The
becomes one of the major concerns of all this procedure.
macroblock scheme used to model the dynamic behaviour
Simultaneously, the need of having specific requirements
of this offshore WF and its HVDC interconnection is
over existing wind turbines, namely the capability of
described in the next figure.
deloading operation and provision of primary frequency
regulation needs to be addressed in detail. A typical
approach consists in exploiting WF below its maximum
power extraction capability, hence creating a spinning
reserve margin. Additionally, the use of a local control
loop at the wind turbine level, whose input variable is the
frequency deviation, allows the control of the turbine
power output for primary frequency regulation purposes.
3
First it is essential that the crank up power for the
generators is provided to those units that are not energized
and dont have backstart capability. By then, the first
action is to energize the bus1 providing crank-up power to
the generator Gen1. Since Genref cant absorb the extra
reactive power created by connecting a line, the
restoration process cant go further until Gen1 is online.
After 20minutes the thermal unit Gen1 is operational and
the system restoration can now resume, the lines 3-9 and
9-13 breakers are closed leading power to the buses 10
and 14 where the hydraulic unit Gen2 and thermal unit
Gen3 are installed. The crank-up power is given to these
Figure 2 Single line diagram of the test system units and they can now begin the start-up process. During
the time it takes for these units to become operational, the
Table I -Main characteristics of the generators
Synchronous machines
loads in the energized area of the grid are picked up in
Connection S Voltage Speed
Under- small increments, avoiding frequency deviation below
Name Unit type excitation
node (MW) regulator Governor
limiter 49.5Hz. As soon as Gen2 is online, the lines 3-4 and 13-
Genref Hydraulic REF 158 DC1A
[11]
GovHyd
[12]
UEL2 multi-
segment [11]
17 breakers are closed and a new sequence of load pick
Gen1 Thermal 1 192 DC1A Gover UEL2 multi- up is established, then the lines 13-19 and 19-21 are
[11] [13] segment [11]
Gen2 Hydraulic 10 231.6 DC1A GovHyd UEL2 multi- closed and another sequence of load pick up is done until
[11] [12] segment [11] Gen3 is operational. With this unit online that has the
Gen3 Thermal 14 384 DC1A Gover UEL2 multi-
[11] [13] segment [11] highest rated power in the system, the rest of the power
grid can be energized, the line 9-11 (that is the longest
Detailed data about the characteristics of the lines, and consequently the one that creates most reactive
transformers and load can be obtained upon request. The power) can now be closed, followed after by the line 13-
main characteristics of the conventional generators 15. The final step is this restoration plan is the final load
(nominal power, unit type, type of voltage and speed pick up and with this providing power to the rest of the
regulators) are described in the previous table. consumers and finalising the power system restoration
It was considered that the all substation load is fully re- sequence.
established when we reach 90 MW and 30Mvar at each
bus load. The PSR sequence of events that was identified for case
The line connecting to the off-shore HVDC VSC is a) is described in a synthetic manner in the table II.
considered to be long. After energizing the HVDC grid,
the wind power generation pick-up was incremented by Table II PSR sequence for case a)
Time Time Time
steps, connecting clusters of wind generators every 30 (s)
Event
(s)
Event
(s)
Event
4
Figure 4 Behaviour of bus voltages during the PSR for case a)
Case b)
5
made, connecting a total 16 wind turbines, with a rated
power of 2MW each, providing more 32MW to the
system. This value is achieved in two distinct power
clusters, in order to respect the frequency increase limit.
After this, more load is picked up until Gen3 is
operational. Finally, line 13-15 is closed and the
remaining loads are full energized.
The PSR sequence of events that was identified for case
b) is described in a synthetic manner in the next table.
6
1800 seconds. In this period, there are three load pickups,
decreasing significantly the systems frequency, and the
maximum power available in the WF is 40 MW.
When the frequency is at 50Hz, and considering the
defined deloading, the WF will inject 36 MW. The
decrease in the frequency leads the WF to inject the
power reserve, hence the rapid variations seen. As the
frequency is restored the WF injected power will
decrease, not reaching the minimum value because the
frequency will not reach its nominal value in time for the
next load pickup.
Figure 8 Reactive power generation from the WF converter Figure 9 WF active power response to the system frequency
The total system restoration time (for 720 MW) was, for
Figure 9, shows in detail the response of the WF to this case, 43.8 minutes. The not served energy to the
frequency variations in the time frame between 1720 and
7
consumers during the PSR procedure was in the amount References
of 140.75 MW/h.
Next figure allows comparing the way how the two PSR [1] Directive 2009/28/EC of the European Parliament and of the
procedures evolved in time. Council of 23 April 2009 on the promotion of the use of energy
from renewable sources and amending and subsequently repealing
Directives 2001/77/EC and 2003/30/ EC
[2] http://teeic.anl.gov/er/wind/restech/scale/index.cfm
800 [3] Andersson, G., et al. "Causes of the 2003 major grid blackouts in
Without wind generation
700
North America and Europe, and recommended means to improve
With off-shore wind generation system dynamic performance." Power Systems, IEEE Transactions
600 on 20.4 (2005): 1922-1928.
[4] Moreira, C. L.; Resende, F. O.; Lopes, J. A. P.; , "Using Low
Power (MW)
500
Voltage MicroGrids for Service Restoration," Power Systems,
400 IEEE Transactions on , vol.22, no.1, pp.395-403, Feb. 2007.
300 [5] Fernanda Resende, Nuno Gil, Peas Lopes, Service restoration on
distribution systems using Multi-MicroGrids , European
200 Transactions on Electrical Power, vol.21, no.2, pp.1327-1342,
March, 2011
100
[6] M. M. Adibi and L. H. Fink, "Special considerations in power
0 system restoration." IEEE Transactions on Power Systems, vol. 7,
no. 4, pp. 1419-1427, November 1992
21
22
25
27
30
31
34
35
38
42
45
23,5
28,5
32,5
36,5