SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

SAIC NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO INSPECTION CHECKLIST
Final Alignment of Pump & Driver SAIC-G-2022 1-Dec-06 MECH-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A. General Requirements

Soft foot check is done with piping disconnected on each equipment


API 686, Ch 7,
A1 foot. Note: Maximum permissible movement is 0.05 millimeter (2 mils) at
Para. 5.4.4.1
each foot, or as specified by Manufacturer.

API 686, Ch 7,
A2 Fixed and movable equipment shall be free to turn.
Par 5.4.4.1
Data of alignment are recorded in SATR-G-2004 or approved equivalent
A3 Contractor QP
alignment form.

Provisions are made for doweling the pump and drive components to the
31-SAMMS-004,
A4 baseplate. Note: Dowels are furnished by the Vendor, but installed in the
Para. 3.3.21
field at the time of final alignment.

For all pumps, 3 mm (1/8 in) thick stainless steel shim packs shall be 31-SAMMS-004,
A5
furnished. Para. 3.3.4

The maximum allowable number of shims under any equipment support API 686, Ch 7,
A6
foot is five. Para. 5.4.2.1

Alignment is within the Manufacturer's tolerances Before Piping


and conduit are attached. Pipe strain checks are per the API 686, Ch 7,
A7
manufacturer's procedures. Alignment is within the Manufacturer's Para. 5.4.5
tolerances After pipe & conduit attached.

Final Alignment was performed AFTER Hydrotest of piping and


completion & acceptance of piping supports. NO COLD SPRING!
See Note 1 & Attachments 1 & 2.
Complete Checklists. Note: After final piping bolt- API 686, Ch 7,
A8
up, final shaft alignment shall be verified and all machinery shall be hand Para. 5.4.9
rotated to ensure that neither binding nor case distortion has occurred
during piping installation. Piping spring hanger & spring support stops
shall be installed during final shaft alignment checks.

REMARKS:
NOTES: Complete the associated checklists of API 686 Chapter 7 & Chapter 6 & attach to this checklist.
ATTACHMENTS: ATTACHMENT 1 - API RP 686 FINAL ALIGNMENT CHAPTER 7
ATTACHMENT 1 - API RP 686 FINAL ALIGNMENT (PIPING CONCERNS) CHAPTER 6
REFERENCE DOCUMENTS:
1. 31-SAMSS-004, Centrifugal Pumps, (30 September, 2003)
2. API 686, Recommended Practice for Machinery Installation and Installation Design, (First Edition, April 1996)

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

Page 1 of 25
Quality Record Approved:
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Page 2 of 25
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 2 (Standards Cutoff - December 2005) REV 2 31-Dec-05
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Final Alignment of Pump & Driver SAIC-G-2022 1-Dec-06 MECH-
ATTACHMENT 1 - API RP 686 FINAL ALIGNMENT CHAPTER 7
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 2 (Standards Cutoff - December 2005) REV 2 31-Dec-05
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Final Alignment of Pump & Driver SAIC-G-2022 1-Dec-06 MECH-
ATTACHMENT 1 - API RP 686 FINAL ALIGNMENT (PIPING CONCERNS) CHAPTER 6