Sie sind auf Seite 1von 8

II I

SPE 36584

The Auger Platform: Debottlenecking and Expansion Of Fluid Handling Facilities


T. R. Judd, Shell Offshore Inc.; C. B. Wallace, Shell E&P Technology Co.

commenced in 1994, SOI has 100/0 interest in the leases


Ccfwwhf 1JW. Swa of Petroleum Engineers Irw
which were acquired in 1984 and 1985. The field, located
?Ws paper was prepared fw p+esenfabon at Ihe 19W SPE Annual T.chnmd Cmnfecon- in the central Gulf of Mexico in Garden Banks Blocks
and ExhMmn held m Oenver, Colorado, U.S A E9 October 19W
426, 427, 470, and 471, is approximately 214 miles
TM paper was selected W presentation by an SPE Prdgram Commmw fol!ewmg
mwew d infcmnation confanmd in an abstract submrfted by the author(s) Gmtents cd @w southwest of New Orleans and 255 miles southeast of
paper, as pm8entd, have not been rewvwed by the Sdciety of Patroleum Englneem and
am wbjod tm correction by the mdhor(s} The mateoat, as presented d- nd
Houston. Field reserves are estimated at 220 million
nocessady refleci any posdkm of the %cIefy of Petroleum Enguwers b office-, or barrels of oil equivalent. Total project cost for Auger is
members Papers presented at SPE meetmgs are subpxf b pubkcattcm r- by
Eddonal Commiifeea of fhe Smety of Pefroleum Engmears Perrmwon to copy IS approximately $1.2 billion including drilling.
restricted to an abstract of ml more than 303 words Iilustratons may not be copmd The
abstmc+ should ccotain conspicuous acknwiedgment of where and by whom the paper
was presented Wrde Librarian, SPE, P O @ax 833&6 Richardson, TX 7YMX3836 The Auger project represents Shells first application of a
U S A fax 01-214-652-8435
TLP. Until Shells Mars TLP was installed in May 1996,
Auger held the producing water depth record of 2860 tl.
Abstract for the Gulf of Mexico, and for a TLP. These records will
AUGER Shells first Tension Leg Platfom~ (TLP), was
be eclipsed during the next several years as other SOI
installed in 1994 in 2860 feet of water in the Gulf of
deepwater developments including Mensa, Rwn/Powell
Mexico. The platform was designed to process 40 MBPD
and Ursa come onstream.
of oil, 100 MMSCFD of gas, and 25 MBPD of water. For
most of its operation, the surface fluid handling facilities
Topsides Facilities
have proven to be the primary constraint limiting The Auger topsides include an integral drilling rig;
increased production.
32 well slots (24 oil/gas, 8 waterflood) around a 74 R by
Through innovative debottlenecking and expansion of the
194 R. rectangular well bay; a 140 bed quarters building;
surface facilities, Auger production rates have recently
and processing facilities for oil, gas, and produced water
increased to more than 72 MBOPD and 150 MMSCFD of
including separation, dehydration, treatment, compression
gas Further plans are underway to ultimately increase the
and utility and safety systems (e. g., flare, firewater, etc.).
total platform capacity to 100-140 MBOPD and 300-400
The original Auger design was based on production rates
MMSWD.
of 40,000 BBL/D of oil, 100 MMSCFD gas,
This paper will present the original platform design,
25,000 BBLiD produced water and planned for 60,000
describe the constraints on the facilities due to higher than
BPD of waterflood injection.
anticipated well flow rates and surface temperatures, and
The TLP is a floating structure and is subject to
discuss the steps taken to reduce the constraints and
considerably more movement than is the case with fixed
resolve most problems, These problems include: (I) poor
platforms, Critical process equipment having gas/liquid or
gadliquid separation etlciency in high pressure
Iiquidlliquid interfaces was therefore designed to
separators, (2) excessive natural gas liquid (NGL)
accommodate the effects of motion. Additionally, since
condensation in the gas export pipeline, (3) gas
the TLP is held in place by tendons, buoyancy must be
dehydration system limitation due to high rates and
provided. This places a premium on weight reduction for
surface temperatures and (4) other facilities engineering
topside facilities. Fortunately, alternative technologies
related problems,
exist which combine reduced weight and sensitivity to
motion when compared to process equipment commonly
Introduction
used on fixed platforms. Two examples include use of
Shell Offshore Inc. (SOI) completed the Auger discovery
hydrocyclone rather than induced gas flotation for
well in May 1987 and initial production from the field

135
2 THE AUGER PLATFORM: DEBOTTLENECKING AND EXPANSION SPE 36564
OF FLUID HANDLING FACILITIES

removal of suspended oi 1from produced waler and the use of the surface facilities. Production from individurd oil
of structured packing rather than valve or bubble cap trays wells reached 12,000 BBL/D and 25 MMSCFD.
in the glycol contactor used for gas dehydration. Several critical problems surfaced shortly after first
Figure 1 is a very simplified schematic of the original production in April 1994. These mainly had to do with
Auger oil and gas processing facilities. Oil WC1lSproduce wells flowing at much higher flow rates than had been
a 37 API gravity oil and 0,68 gravity gas. Gas wells anticipated. There were to have been 24 producing wells
produce a 42 API gravity oil and 0.65 gravity gas. The with a design processing temperature of 90 degrees F.
original concept included separate high pressure Well temperatures were to be kept high by nitrogen in the
separators for oil and gas wells designed to operate at 1550 production tubing/casing annuhrs to insulate the fluids
psig. Liquid from the two high pressure vessels and a from the cooling effect of seawater, thus minimizing
parallel Icst separator (not shown) flow to an Intermediate paraftlr and hydrate problems.
Pressure (1P) separator which operates at 600-700 psig. By July 1994, the production from just three wells was
Oil from the [P separator next flows to a Free Water 27,000 BBL/D and 75 MMSCFD The surface
Knock Out (FWKO) at 125 psig (there is currently no temperature of the wells ranged from 120-140 degrees F.
produced water), then to a Bulk Oil Treater (BOT) Early problems experienced included: 1) poor separation
operating at 40 psig and finally to an oil tank from which efficiency in high pressure separators and filter separator
it is pumped to a 75 mile, 12 pipeline to Eugene Island (collapsed filter elements, no coalescing) resulting in
Block 331. Oil from the FWKO passes through two heat carryover of oil into the glycol system, 2) high gas
exchangers to pick up heat from oil exiting the BOT and temperature and related water carrying potential,
from the heat media system. 3) dehydration system problems including carryover of
Gas from the High Pressure Oil, Gas, and Test Separators glycol into the gas export line, 4) difficulty testing wells,
is commingled and flows to a filter separator and then to a 5) excessive condensation of liquid hydrocarbons in the
Tri-ethylene Glycol (TEG) contact tower where the gas is sales gas pipeline, and 6) inability to accurately prechct
dehydrated. Although the sales gas water specification is facility performance with process simulation model due to
7 lb/MMSCF, the gas must be dried to below 4 lb/MMSCF foaming in separators. The ultimate bottleneck during
to avoid hydrate formation at low Gulf bottom most of this period was the inability of the gas pipeline
temperatures in the deep water (approximately 40 degrees company to handle condensed liquids and oil carryover
F). Gas is then delivered into a 37 mile, 12 Sheli from the HP separators, which caused fouling and foaming
pipeline to a platform at Vermilion Block 397 where liquid of the glycol system.
and gas are separated, metered and then recombined and To minimize surges, flow from all oil wells has been split
delivered into the gas transportation companys pipeline between both W vessels. Gas wells have been
for transporl to shore. predominantly shut in since the oil wells have been
Gas from the 1P and all lower pressure separators is capable of keeping the facilities and pipelines full. Also,
compressed to pipeline pressure and combined with high due to the elevated production temperatures, the heat
pressure gas upstream of the filter separator and exchangers upstream of the BOT were bypassed.
dehydrator. The 2000 HP DC motordriven 4 stage The debottlenecking study primarily addressed facilities-
reciprocating Flash Gas Compressor (FGC) compresses related problems at Auger which limited production rates.
gas from the stock tank, BOT and FWKO, The final two This effort involved operations and engineering stalT
stages of compression are provided by a centrifugal assigned to the Auger Project, along with Shell Head
Booster Gas Compressor (BGC)driven by a 5000 HP gas Offke and Research engineers.
turbine. FGC discharge gas is routed to the first stage By August/September 1994, a short term debottlenecking
BGC suction with IP separator vapors feeding the BGC plan had been formulated. Gamma scan of high pressure
interstate. Liquids condensed in compressor discharge separators and fluid sample tests indicated that foaming
coolers and separated in interstage scrubbers are reeycled was likely oecurnng in the separation vessels and the
to the appropriate vessel in the oil separation train. vane-type demisters in these vessels were largely
Production during this phase peaked out at 55,000 BOPD ineffective on foam. Tests on the HP Gas Filter Separator
and 105 MMSCFD, located upstream of the TEG contactor indicated it was not
completely removing entrained oil carried over from high
Stage 1 Debottlenecking Activities - Late 1994, pressure separators, This resulted in contamination of,
Early 1995 (Figure 2) and resultant foaming in the glycol system.
Debottieneeking activities began in the summer of 1994 The original design dewpoint of 2#MMSCFD for sales
when it became apparent that the production potential of gas was to be achieved through reduced gas inlet
high rate Auger wells far exceeded the handling capability temperature of 90 degrees F. The high well flow rates
were producing higher temperatures in the process facility

136
SPE 36S84 T. R JUDD AND C. B. WALLACE 3

and thus the polential for the gas stream to carry more success. Finally, fluid samples were obtained from several
water into the TEG Contactor. To reduce the temperature wells. The results from the laboratory analyses and PVT
of the gas entering the TEG system, an air cooler was studies were incor-pxated into the process simulation
installed in the high pressure gas stream. Also, the model which then provided satisfactory agreement with
production tubing Jcasing annulus nitrogen was displaced actual Auger operations.
with completion fluid, leading to a drop in temperature in As a result of the stage 1 debottlenecking work, Augers
the well fluids of approximately 10 degrees F. Several production rates were increased to 62,000 BBL/D and
options were considered to improve separation efficiency 125 MMSCFD. Production was limited by the amount of
in the high pressure vessels including a retrofit with vortex liquids in the gas pipeline, foaming in the HI? Separators,
tube inlet devices, installation of internal spray nozzles to and by TEG contactor capacity. Attempts to reduce liquid
al [eviate the foam problem and other modifications to the drop out in the gas pipeline by changing facility and
vessel internals and inlet piping. The option selected was pipeline operating conditions, varying pigging frequency,
to install a cyclone separator between the new air cooler and use of JT recycle from HP to 1P systems have achieved
and the filter separator. The cyclone would recover any only limited improvement.
liquids condensed from the gas by the air cooler plus
liquids entrained from the HP separators. This option was Stage 2 Debottlenecking Work - Late 1995
judged the optimum because of the minimal downtime (Figure 3)
required and the high cost of deferred production. In September 1995, the gas pipeline company had a
Major progress was accomplished during late 1994/early curtailment scheduled that precipitated a complete
1995. In addition to installation of the cyclone vessel and production shutdown on Auger, during which several new
HP gas coolers, the BGC and oil pipeline pumps were pieces of equipment were installed, A new vertical high
rewhecied to provide higher discharge pressures and flow pressure gas separator which incorporated a vane type
rates. The piping and heat exchanger of the final stage of inlet spreader, internal spray nozzles for foam abatement
compression of the BGC were revised for higher discharge and outlet gas vane type mist extractor, and a new
pressures. Spare pipeline and LACT charge pumps were coalescing filter vessel were installed. Other late 1995
ordered since standby pumps in these services had been debottlenecking work included a 20 pipeline tie-into the
pressed into continuous sewice, Aback pressure valve Auger oil pipeline to Eugene Island 331, a new manifold
was added on the HP separators, FGC Natural Gas header for the HP vertical separator and installation of a
Liquids (NGLs) were piped to the flare scrubber to vent boom and vent scrubber for the new separator PSVS.
minimize recycle load on this compressor. A new glycol contactor was installed and circulation
Another early problem involved higher than predicted capacity was increased from 750 to 1200 GPH with flow
flash gas generated in liquid dump lines. This two phase split between the two contractors, A larger glycol/glycol
flow through the piping reduced the available pressure heat exchanger was installed and higher capacity packing
drop for the dump valves. Also, where chokes were was installed in the glycol still and reboiler sparger
installed downstream of level control valves to minimize columns, A permanent Vapor Recovery Unit (VW) was
the pressure drop across the valve, the two phase flow was installed to supplement the existing FGC, but tie-ins were
limiting the flow across the choke. The chokes were not completed.
removed from the dump lines from HP and 1P separators By mid 1995, the resewoir engineers had determined that
to increase flow capacity. Larger dump valves were the Waterflood System would not be needed. If it could be
installed on the FWKO and BOT, Also. a second dump removed, it would provide the necessary weight savings to
line from the BOT to the dry oil tank allowed the Treater allow further expansion of the production facilities.
pressure to be lowered, thus reducing the amount of gas As a result of these equipment additions, flow rates
flashing off at the dry oil tank and reducing the back increased to 73,000 BOPD and 154 MMSCFD; but the HP
pressure on the level control valves. High flash gas rates Vertical Separator did not perform up to its design rate of
had greatly exceeded the capacity of the first stage FGC, 170 MMSCFD. The problem appeared to be inefllcient
Several operational changes also improved facility separation of oil and gas, which manifested itself as
performance, The most difficult well was diverted from increased gas rates at the 1P separator and carryover of oil
the HP to 1P separator. The operating pressure of the high into the outlet gas stream.
pressure ~stem was increased from approximately 1500 to
1800 psig. Flow from the wells was split between the HP Stage 3 Debottlenecking Work -1996 (Figure 4)
Oil Separator and the HP gas Separator, rather than being In April 1996, a major shutdown was executed by the gas
segregated into one vessel or the other. Trials of antifoam transportation company to increase their liquids handling
chemicals in the high pressure systems and friction capacity. During this shutdown, vortex tube inlet devices
reducing chemicals in the oil export pipeline had some were installed in the HP vertical separator and several gas

137
4 THE AUGERPLATFORM:DEBOTTLENECKINGAND EXPANSION SPE 36S84
OF FLUID HANDLING FACILITIES

pipeline control valves were re-trimmed. Also during the Ievel hydrocarbons, (c4, c5, c6, etc.), in the gas stream can
shutdown, miscellaneous tie-ins were made in preparation give huge differences in the volumes of liquids generated
for fhrther expansion and to finalize the VRU installation. in the gas pipeline. Some sensitivity analysis might have
After these changes were made, Auger rates climbed to dictated a more flexible design for the liquids handling
over 73,000 BBL/D and 163 MMSCFD. Effectiveness of system going toward shore.
the VRU, however, was hampered by recycling of Another learning woutd be to allow for design engineers
compressor generated NGLs. to plan for facility expansion from the start. This would
Atler installation of the vortex tubes, the need for include flanged break out spool piping to minimize on-site
injection of defoamer chemicals decreased significantly welding and downtime. Also, if in the original design,
and the separator etliciency improved, specifically in when staff time and resources were more available, higher
reducing the amount of gas carry-under in the oil fedng rates were anticipated, accounted for and documented,
1P system. then the job of the debottlenecking engineer would be
Conversion of the existing filter separator to a coalescer made greatly easier. Various contingencies could be
vessel and revision of tower internals in the original TEG documented and preliminary expansion designs
contactor are planned for later in 1996. An upgrade to the completed. This would mean that debotttenecklng efforts
produced water handling system will also be required since could begin directly in execution, rather than with design.
water production is anticipated by the end of 1996. Many facility project engineers have developed their
A continuing problem that has not yet been resolved is skills by working major projects and facility designs. In
the excessive condensation of hydrocarbon liquids in these designs of new production facilities, several key
compressor interstate coolers. Condensed liquids are parameters are understood and fixed. Generally a design
dumped to lower pressure vessels where they re-flash and basis is developed, leading to a cost estimate and finally a
the vapors are then recompressed. Considerable schedule is developed. All three of these components are
compressor capacity is required to handle the recycle then largely fixed and the engineers can execute the
vapors, project with these basic boundary conditions unchanged,
Peak rates are expected to reach 75,000 BOPD and An engineers job is to hold the cost, meet the schedule,
165 MMSCFD. and build the agreed design.
In the case of debottlenecking an operating facility, all of
Future Expansion Plans (Figure 5) the normat constraints are turned upside down. The
Work has begun to firther increase the capacity of schedule is usually ASAP, and may change based upon
Auger, possibly to 100,000 BBL/D of dry oil or plant turnarounds and shutdowns dictated by outside
140,000 BBL/D of wet oil and 300-400 MMSCFD of gas. forces. Schedules, therefore, are always changing, trying
New facilities on Auger will include a 14 riser, a new dry to take advantage of every opportunity for acceleration.
oil train, a fourth pipeline pump and LACT train, a new The capital cost, while not unlimited, is usually minor
parallel BGC, some flare train work, and additional glycol compared to the profit potential provided by either
system capacity. These expansions are made possible by minimizing shut in time or maximizing production rates
the weight savings from demolition of the Waterflood for a major production facility. Finally, the design basis is
System. Some type of condensate weathering or not fixed because new data and production information
stabilization may be provided to reduce compressor NGL continues to come to light. Your debottlenecking design
recycle. The existing 12 oil pipeline will be converted to must be flexible to account for changes in production and
gas service and a new 16 oil pipeline will be installed new information, It also must be flexible to take
from Auger to transportation infrastructure in shallower advantage of other opportunities for installation during
water, unexpected shutdowns.
Jn short, everything you learned building the project the
Case History For Future Improvements first time is out the window for the debottlenecking effort.
When undertaking a new facility design, the best fluid All your normal constraints are backwards.
characterization is usually used, but relying on that to be Finally, when working with an operating facility, it is
exact can give too tight of a design for the facilities. Some vitally important to communicate with the field operations
flexibility should be considered if actual production data staff. The differences in location and rotating schedules of
does not exactly match the design conditions. Also, for the field people make this a huge time burden, but a
specific component designs, some sort of sensitivity necessary one. Any change or addition that the engineer
analysis may be beneficial. A case in point is the Auger wants to make will have to be operated by the field
gas pipeline. The gas rates have been somewhat higher, personnel. If they are not on board with the designs from
but the real surprise has been the liquids generated in the the beginning, your odds of success are limited. Atso,
pipeline. Small differences in the concentration of mid- most engineers dont want to admit this, but the operations

138
SPE 36594 T. R, JUDD AND C. B. WALLACE 5

folks can have some very good ideas for process


improvements. These ticld generated ideas should be
seriously considered along }vith those generated from the
ivory towers.
Tables

Table 1- Auger TLP Production Facility - Production


Rates

Production Facility Oil Rate Gas Rate


Conllguration MMBOPD MMSCFD 1
Original Design 40 100
Initial Configuration 55 105
Stage 1 Debottlenecking 62 125
I Stage 2 Debottlenecking I 73 I 154 1
Stage 3 Debottlenecking I 75 ) 165
Auger Expansion 100 I 300

Fi~res

Fig. 1- Auger Production Fat. - Original Installation


Fig. 2- Auger Production Fat. - Stage 1 Debottlenecking
Fig. 3- Auger Production Fat. - Stage 2 Debottlenecking
Fig. 4- Auger Production Fat, - Stage 3 Debottlenecking
Fig. 5- Auger Production Fat. - Facility Expansion
Fig, 6- Auger Production His[ory

Nomenclature

B(X - Booster Gas Compressor


BOT - Bulk Oil Treater
FGC - Flash Gas Compressor
FWKO - Free Water Knock Out
HP - High Pressure
1P - Intermediate Pressure
NGL - Natural Gas Liquid
TEG - Tri-ethylene Glycol
VRU - Vapor Recovc~ Unit

139
THE AUGER PIATFORM: DEBOTTLENECKING AND EXPANSION SPE 365S4
OF FLUID HANDLING FACILITIES

Figure 1
AugerProductionFacilities
Oripinal Installation
Design Oil Rate = 40 MBOPD Max Oil Rate =
Design Gas Rate . 100 MMSCFD Max Gas Rate = us

44 + HPGas
Filter
TEG
Contactor
GAS

GAS
WELLS
f
HP Gas r
Sep ~ EXPORT

4
I A
+ ~ BGC2 Dry Oil
4b .

b
OIL t A
WELLS
HP Oil
%

v IPSep

I
BGC = Booster Gas Compressor Bulk Oil
FGC = Flash Gas Compressor Treater

+ D

Figure 2

AugerProductionFacilities
StagelDebottlenecking Max Oil Rate = Q
Max Gas Rate m
Cyclone
Fin-Fan GAS
TEG
Contactor
EXPORT

HP Gas
Sep

+ Dry Oil

4+

* FGC
I 4
A
t
HP oil
Sep
Most
Oil ~
Wells 4 IP Sep

as Wells Sh ut-m 1
~] m
BGC = Booster Gas Compressor
FGC = Flash Gas Compressor Dry Oil Tank]
I
I and Export 1
140
SPE 3s5s4 T. R. JUDD AND C. B. WALLACE

Figure 3

AugerProductionFacilities
Stape2Debottlenecking Max Oil Rate = 73
Max Gas Rate = m

Dry Oil

FGC
I
b

,
+ + W Sep I I
[
CGas Wells Shut-in>

BGC = Booster Gas Compressor


FGC = Flash Gas Compressor Dry Oil Tank
I and Export
Fimre 4
AugerProductionFacilities Max Oil Rate = U
StaA3Debottlenecking Max Gas Rate = -l&5

7
~GAS
EXPORT

n Dry Oil
Tank
Vapors

BGC = Booster Gas Compressor


FGC = Flash Gas Compressor Dry Oil Tank
and Export
141
THE AUGER PIATFORM: DEBOTTLENECKING AND EXPANSION SPE 365W
OF FLUID HANDLING FACILITIES

Figure 5

AugerProductionFacilities Max Oil Rate. ~


Max Gas Rate = ~
fhwefixDansion
TEG GAS

r-if
HP Contactor - EXPORT
Cyclone
- vat No. 2
,% HP Gas TEG
Contactor GAS
%m - EXr--
ruKl

I.!RJf-p+-
as 5
10 *
I~-%
II ~1-1- - ---- t 14
t ].e..,wol;
A RegenSys I
, . BGC1
.
VRL[J b n.
ury WI
nll 1

Tank
mm. 7 &--
Vapors
lwelk~ I---HI I J-J
I
c-ii
l-l
pwlk I
n 4--IFT
HP Dry
OiLSep
I
1P Dry
OiBep
t

1
i D~OilTank
New Lact & and Export
I BGC = Booster Gas Compressor
[ P/Ilunlps I FGC = Flash Gas Compressor

Figure 6

AugerProductionHistory
180
1
Stage 3 ~
160
1

Debottlenecking Stage 2 ~
l+- stage 1 +
140

120

100

80

60

40

20

1995 1996-
142

Das könnte Ihnen auch gefallen