Sie sind auf Seite 1von 6

- - - - - ---------------- ~ - - - - - - - - - - - - -

PLANNING OPEN STOPES:


OPERATING CONSTRAINTS
By
J. E. ASKEW!

ABSTRACT problems which impinge on other


Mine planning for ore recovery by open underground mining techniques, so that mine
stoping and pillar recovery is becoming more planning needs to take account of the
sophisticated, but there are basic operating operational aspects of open stoping mining if
constraints which must be imposed if this the best design is to be achieved.
planning is to realise the production results
on which the mine is dependant. The production It is anticipated that open stoping will
reliability of an open stope is usually a high continue to dominate underground
priority and common design problems can be metalliferous mining, particularly as
identified. A range of practical environmental constraints and deeper orebodies
considerations which should be considered at inhibit the use of more efficient mass mining
the mine planning stage are reviewed including techniques such as sublevel caving or block
equipment performance, blasting technology, caving. In addition, better understanding of
ventilation requirements, development layouts, ground behaviour is leading to the introduction
lead time, ground conditions, support, of modified open stoping techniques such as
backfilling and ore recovery. cratering and open stope mass blasting followed
by drawdown under rock fill.
INTRODUCTION
Over the past two decades, open stoping It is difficult to generalise in the area
has evolved into a major underground mining of open stope design and issues raised in the
method in metalliferous mines and design following presentation are bound to require
techniques have improved dramatically in this varying emphasis with stope design at
period. Mine planning for open stoping is different operations. The comments are made
making increasing use of computer design based on observation of the majority of
techniques such as geological data bases for Australian open stoping operations and a
analyses of stope tonnes and grade and rock limited number of operations in Canada, U.S.A.,
mechanics studies for the optimisation of Sweden and Spain.
extraction and recovery. Nevertheless, the
actual operation of recovering ore from open OPERATIONS AND PLANNING OBJECTIVES
stopes is fraught with many of the same The overall objective common to all
underground operations is to maximise total ore
recovery at least cost, in conjunction with
I Principal safety of employees and maximised productivity.
Barrett, Askew, Fuller and Partners Most mines of moderate or larger (+250,000 tpa)

The Aus.I.M.M. West Coast Tasmania Branch, Underground Operators' Conference. October 1982.
246 J.E. ASKEW

size will have separate mine planning and design will include the above, but in addition
production personnel and while the above there is a responsibility to:
objective might be seen as their mutual goal, maximise the recovery of the ore
in practice the emphasis on ways of achieving resource,
this goal can be quite different. ensure long term continuity of
Management style and personality at the production by scheduling for
operations level will have a great influence tonnes and grade,
on the relative priorities by planning and minimise ground stability problems
operations staff. including stress and structure
effects which could lead to
Day to day operating objectives can be excessive dilution.
defined as the following
l. to meet production tonnage targets, Exploration, ventilation and rock
2. to mine with maximum safety (and mechanics aspects of planning are considered
meet safety targets), to fall within' the realm of mine planning
3. to achieve high productivity of the and as such, the incorporation of these
underground work force, principles into stope design is necessary to
4. to produce at a design head grade meet the above objectives. Similarly,
commensurate with milling awareness of equipment availability,
requirements, and performance, materials handling constraints
5. to ensure the mine operates and milling requirements for ore grade and
profitably. type are included in the sphere of mine
planning. These latter aspects require
These objectives can be ranked in ."
interaction with, and ~adback from,
different order but commonly the production operating personnel to provide the raw data
personnel would assume that, provided upon which open stope mine planning can best
production tonnage targets and head grade be done. The communication between operations
targets are being met, then the planned and planning is considered to be the basis
profitability will be satisfied. of better open stope planning and it is in
this area that shortcomings are often
Achievement of high productivity is an observed at different mine operations.
essential element of mining profitably.
However, unless an accurate reporting COMMON PRODUCTION PROBLEMS
technique for productivity is in use, then Most open stoping operations of medium or
tonnage targets may be achieved by lower larger size will have more than one producing
productivity through an excessive pool of stope at any time. The producing stopes will
labour. Mine safety is a fundamental often be scheduled to provide a consistent
operating objective and open stoping lends head grade and the production rate from each
itself to improved safety records through stope may be varied to comply with this
less exposure of men, less mat~rials amidst the constraints'which relate to the
handling and greater mechanisation. stage of extraction of each particular stope.

Mine planning objectives for open stope There are commonly observed problems which

The Aus.I.M.M. West Coast Tasmania Branch, Underground Operators' Conference. October 1982.
J.E. ASKEW 247

create shortfalls in bUdget production targets. production in the scheduled open stope.

Ore fragmentation has a major bearing on MINE PLANNING FOR PRODUCTION


the productivity of mucking units, secondary These production problems can be greatly
breaking requirements, problems within ore alleviated by due consideration at the mine
passes, crushing and maximum availability of planning stage. More detailed comments on
drawpoints. Also related to the blasting the general aspects of these problems as they
phase of extraction, misfires and "benches" might be applied at the mine planning stage
on stope faces can cause very serious delays are discussed below.
in mine production due to delays in blasting.
LEAD TIME
Equipment availability under average The objective of maximising profitability
operating conditions (where these statistics demands that exploration and development are
are available) can vary greatly, as operating only sufficiently far ahead of production to
conditions in particular stoping situations ensure that production targets can still be
vary. Usually, performance statistics met. Very often at the feasibility stage,
provided from mine record~ do not provide mine planning exercises will adopt standard
sensitivity factors for different operating performance criteria such as mine development
conditions such as operator skill, spares at 100 m per period, exploration development
availability, ventilation constraints and of no more than two year's production and
congestion. stope development of no more than one year of
future production. These development
Ground instability, both of development parameters all relate back to an assumed rate
and within the open stope can have very major of mine development. A common problem is
effects on production, in the extreme, leading that ground conditions or equipment
to stope abandonment. availability are misjUdged and development
rates fall significantly below the period
The lead time for commencing production development target.
from a particular stope can be readily
misjudged due to a variety of factors. These Superimposed on the above development
include: lead time is the need for exploration
1. development scheduled under drilling to block out proven stope tonnages
differing ground conditions with and grade. The diamond drilling density
different development dimensions necessary to provide sufficiently accurate
and lack of skilled labour, information is often widely variable between
2. exploration requirements, deposits (and within a deposit where there is
3. time taken in drilling the stope gross variability in the nature of the ore).
and creating the stope slot, Time must a~so be allowed for geological
4. ground support requirements, both interpretation of exploration results.
in development and for the stope
(e.g. cable bolting), and ROCK MECHANICS
5. completion of backfilling and curing Rock mechanics input to open stope design
of fill in adjacent stopes, prior to is best scheduled at the exploration and

The Aus.I.M.M. West Coast Tasmania Branch, Underground Operators' Conference. October 1982.
248 J.E. ASKEW

initial planning stage. very often rock the significance of joints, shear
mechanics input to open stope planning is made zones, faults, etc, are understood.
far too late, when design problems have The ability of numerical modelling
already reached the production phase. This to take account of rock
is partly due to the evolution of rock structure, blasting and gravity
mechanics to be identified as a separate effects are yet to be resolved.
facet of mining engineering. There is a Rock structure also influences
recent encouraging trend for rock mechanics fragmentation. The exploitation
to be absorbed back into mine planning of structure to improve
departments and losing its distinct identity. fragmentation is yet to be
When this integration is complete then there recognised to the degree achieved
will be fewer occurrences of belated rock in some surface mines.
mechanics input. 3. Instrumentation: Use of simple,
reliable instruments which monitor
Applied rock mechanics has greatest stress and rock movement can be
value in mine planning aspects which alleviate invaluable aids to operations
production problems in the following areas: management. Detection of the
1. Prediction of Stress Related onset of failure and the response
Instability: Long range planning time of rock movement to extraction
must sequence extraction to meet and stress build up is realised at
production requirements whilst some mines. Data from monitoring
ensuring that related becomes the basis for back
instability does not jeopardise analysing stability performance.
recovery. Input of pragmatic As such, it is the single most
rock mechanics advice is a useful useful tool in validating
aid. Where sufficient knowledge numerical models.
of regional stability has been 4. Dilution: Stope overbreak occurring
developed, numerical modelling during the blasting phase of open
of stope and pillar recovery will stope mining will displace ore from
provide supporting evidence to mine production. Knowledge of
investigation of alternative likely limits of overbreak and
stope dimensions and extraction the overbreak grade provides
sequence strategies. confidence in mining to budget
2. Rock Structure: Structure very production requirements and can
often is the major control of be the basis for examining
stope stability, yet stress alternative blasting sequences.
analysis commonly is the rock
mechanics tool mine planners FRAGMENTATION
and operators seek in the first The efficiency of open stoping is
instance. Copious quantities of sensitive to ore fragmentation. A reduction
numerical modelling computer in drillhole density will reduce stope
printout do not, unfortunately, breaking costs (for the same explosive costs)
provide useful design data unless but poorer fragmentation will usually result

The Aus.I.M.M. West Coast Tasmania Branch, Underground Operators' Conference. October 1982.
J .E. ASKEW 249

in loss of stope productivity. Adoption of interval is carefully controlled. With


larger LHD's an~ development dimensions to quantitative proof of improved fragmentation
accommodate coarser ore requires higher by mass blasting, increased use of this method
capital and fixed costs respectively: should occur, particularly as confidence and
Crushing costs will also rise. Sensitivity experience in mass blasting grows. Exposed
studies which fully examine the dependance brows in an open stope which is fired in a
of productivity and costs on fragmentation are number of stages are often unstable,
potentially a valuable test for mine design. contributing to secondary breakage and
Applied research on the mechanics of drawpoint choking. Mass blasting can minimise
fragmentation is being undertaken at the these exposures . In addition, drawdown of a
University of Queensland. full stope will prevent ventilation short-
circuits through the drawpoints and may
BLASTHOLE DESIGN temporarily enhance wall stability.
The fundamental axiom for planning of
open stope blastholes is to incorporate an DRAWPOINT DESIGN, LOADING AND MATERIALS
element of conservatism which takes account HANDLING
of blasthole deviation, available explosives Drawpoint layout has become more flexible
and detonators, charging constraints, blast in recent years with the introduction of the
vibrations limits and variability of rock remote control LHD. Thus, the requirement
conditions. These will vary for different of drawpoints to be at 10 - 15 m centres to
mines. Acceptable blasthole design is best provide good coverage for drawdown is no
resolved by discussion between operations longer mandatory. Other constraints of
personnel, explosives suppliers and planning development such as ground conditions and cost
staff. Close supervision of blasthole can now have greater emphasis.
drilling and charging is essential. In most
mines of the size under discussion, LHD productivity and availability are
appointment of a drilling and blasting reduced by unfavourable grades in drawpoints
engineer is warranted to co-ordinate and skew loading. The drawpoint should allow
supervision and progressively refine a "straight-on" approach to the muckpile and
blasthole design. have a slight down grade to aid crowding.

Mass blasting of open stopes is It is quite common for ground instability


technically viable and difficulties and brow break-back of drawpoints to be
experienced by some Australian operations observed. Considering that a single drawpoint
with this method have lessened recently. might access high stope tonnages over
Fragmentation is postulated to improve with extended periods, adequate provision for
mass blasting, but quantitative evidence is support of the brow and general drawpoint
not yet available. At present, the primary area is worthwhile. Stope and secondary
application of mass blasting is in pillar blasting add to the general wear and tear
blasting against backfill. A total that. the drawpoint must withstand. Fully
expansion void of at least 25 per cent is bonded ground support is best suited to
necessary and blast vibration limits often drawpoint reinforcement.
require that the charge weight per delay

The Aus.I.M.M. West Coast Tasmania Branch, Underground Operators' Conference. October 1982.
250 J.E. ASKEW

The haul distance of LHD's to ore passes factor" requires experience and, most
will vary, according to mine layout and cost importantly, close interaction of. planning,
criteria. Ore pass storage volume should be operations and supervision personnel. It
adequate to ensure that it does not constrain behoves operations management to ensure open
the rate of stope recovery. Provision for communication between these groups occurs and
good drainage of the drawpoint level and a united approach to achieving both short and
maintenance of the roads will improve long term production goals.
productivity. Comparative cost and production
statistics are invaluable to assess the impact Avenues for establishing and maintaining
of these measures. Front line supervision, the co-operation required include:
as with most production activities, has an broadening the daily mine
over-riding influence on the effectiveness of production meetings to include
measures such as good housekeeping and planning, maintenance, rock
safety. mechanics and geological personnel,
informal access to mine planning
OVERVIEW department, etc, by front line
Operations management have an supervisors, whilst maintaining
expectation that the mine planning departments a structured decision-making
will present open stope designs which can be technique which requires that
implemented with confidence that production operations management approval
targets will be achieved. Performance is given to design changes,
statistics and geological data must be period production planning meetings
available and presented in a manner which is which include planning
readily assimilated and shows the potential representatives,
variability and/or confidence in the inclusion of an operations
information. A degree of latitude to representative(s) in the long
accommodate operating problems which could term planning team, and
cause loss of production must be incorporated engendering a team spirit in the
into design. Definition of this "contingency mine staff.

The Aus.I.M.M. West Coast Tasmania Branch, Underground Operators' Conference. October 1982.

Das könnte Ihnen auch gefallen