Beruflich Dokumente
Kultur Dokumente
April 2010
POWER April 2010
Contents
Advantage India
Market overview
Investments
Opportunities
Industry associations
2
ADVANTAGE INDIA
Power April 2010
Advantage India
Nine projects are being targetted by the government at a total estimated investment of US$ 3.3 billion (INR
160 billion), with the size of each project being 4,000 MW.
Advantage
India
Significant additions to Capacity
generation capacity addition High potential Targeted per capita
planned under the consumption at the end of
Eleventh Plan (2007–2012). Eleventh Five Year Plan
Enabling regulation (2007–2012) 1,000 kWh.
and policy
India’s power market has evolved into a competitive structure that has
minimal regulatory micro-management.
3
POWER April 2010
Contents
Advantage India
Market overview
Investments
Opportunities
Industry associations
4
MARKET OVERVIEW
Power April 2010
Captive
Source
19509
Hydro 36863
Thermal 102454
Source: Central Electricity Authority (CEA)
Total 159398
5
MARKET OVERVIEW
Power April 2010
2009–2010P 611.7
2008–09 723.6
2007–08 704.5
2006–07 662.5
2005–06 617.5
2004–05 587.4
2003–04 558.3
2002–03 531.4
2001–02 515.3
2000–01 499.5
1990–91 264.3
6
MARKET OVERVIEW
Power April 2010
• The states contributed 79,391.85 MW to the total installed capacity, while the Central and private
sectors contributed 50,992.63 MW and 29,014.01 MW, respectively, as of March 2010.
• The average plant load factor (PLF) of thermal plants, achieved in 2009–2010, has been estimated at 77.48
per cent.
Installed capacity — sector-wise share PLF achievement (2009–2010)
7
MARKET OVERVIEW
Power April 2010
Sources of power
Sources: Ministry of Petroleum and Natural Gas, Ministry of Atomic Energy, ‘Renewable Energy in India — the evolving dynamics’, Ernst & Young, 2009
8
MARKET OVERVIEW
Power April 2010
Demand-supply gap
• India’s energy requirement during the year 2008– Demand-supply gap (billion units)
09 was 774,324 million units (MU), while its 1000
energy availability was 689,021 MU. 774.3
800
559.4 620.9
• An energy shortage of 11 per cent was recorded 600 447.3 689.0
in 2008–09, as compared to 9.9 per cent in 2007– 559.4
400 266.4 517.4
08. 168.1 395.9
200
245.4
• The peak demand for energy in 2008–09 was 0
156.8
109,809 MW, while the peak demand met was VI VII VIII IX X XI*
96,685 MW.
Demand Availability
• The consequent peak shortage in 2008–09 was Source: CEA
12 per cent, as compared to 16.6 per cent in
*In 2008–09
2007–08.
9
MARKET OVERVIEW
Power April 2010
In MW
• Significant additions to generation capacity Capacity addition during Eleventh Plan Period
have been planned under the Eleventh Plan
Period. Central State Private Total
Hydro 8,654 3,482 3,491 15,627
• The capacity addition target for 2009–2010 is Thermal 24,840 23,301 11,552 59,693
14,507 MW. Against this, a capacity of 9,585
MW has already been commissioned as on Nuclear 3,380 0 0 3,380
March 31, 2010.
Total 36,874 26,783 15,043 78,700
10
MARKET OVERVIEW
Power April 2010
Transmission network
• The number of power transmission lines in India Major transmission networks in India (400 kv and above):
has increased from 3,708 circuit kilometres existing, approved and planned – upto 2011-12
(ckm) in 1950 to about 220,794 ckm in 2009.
They are estimated to reach 2,93,372 ckm by
2012.
11
MARKET OVERVIEW
Power April 2010
Contents
Advantage India
Market overview
Investments
Opportunities
Industry associations
13
INVESTMENTS
Power April 2010
Investments — FDI
• The power sector received FDI worth US$ 1,320 FDI equity inflows in power sector
million between April 2009 and January
2010, bringing the cumulative inflow from April 2000
to January 2010 to US$ 4,510.45 million. 2008-09 985
14
POWER April 2010
Contents
Advantage India
Market overview
Investments
Opportunities
Industry associations
15
POLICY AND REGULATORY FRAMEWORK
Power April 2010
CERC: Central Electricity Regulatory Commission SERC: State Electricity Regulatory Commission STU: State transmission utility
CTU: Central transmission utility GENCOs: Generation companies SLDC: State Load Despatch Centre
NRLDC: Northern Regional Load Despatch Centre IPPs: Independent power producers
RLDC: Regional Load Despatch Centre RLDC: Regional Load Despatch Centre
16
POLICY AND REGULATORY FRAMEWORK
Power April 2010
• India’s power sector outlay for the Tenth Plan Period • Distribution has been privatised in
was US$ 56.31 billion (INR 2,703 billion) and estimated Mumbai, Orissa and Delhi.
expenditure was US$ 37.37 billion (INR 1,794 billion).
• Recovery from SEBs has been regularised
• The outlay for the sector is US$ 115.56 billion (INR after securitisation.
5,547 billion), according to the Eleventh Plan.
• The principles of a multi-year-tariff (MYT)
• Regulatory commissions have been constituted in 22 regime have been proposed for tariff
states. rationalisation.
17
POLICY AND REGULATORY FRAMEWORK
Power April 2010
Open
access, Section Possible wholesale/
Evolving market with competitive structure Electricity
63/ Section 79 retail competition
and minimal regulatory micro-management Act, 2003
(2)/Section 60
18
POLICY AND REGULATORY FRAMEWORK
Power April 2010
19
POLICY AND REGULATORY FRAMEWORK
Power April 2010
• Inter-state thermal power plants with a capacity of 1000 MW or more, located in states other
than those specified above.
• Inter-state hydel power plants with a capacity of 350 MW or more, located in the states of
Jammu and Kashmir, Sikkim, Arunachal
Pradesh, Assam, Meghalaya, Manipur, Mizoram, Nagaland and Tripura.
• Inter-state hydel power plants with a capacity of 500 MW or more, located in states other than
those specified above.
20
POLICY AND REGULATORY FRAMEWORK
Power April 2010
21
POLICY AND REGULATORY FRAMEWORK
Power April 2010
• The government have launched an initiative for the • Projects to use supercritical technology
development of coal-based UMPPs, each with a based on pithead (captive block) or
capacity of about 4000 MW. imported coal (coastal).
22
POLICY AND REGULATORY FRAMEWORK
Power April 2010
• Of the four pithead sites identified, Sasan in Madhya • PFC is responsible for facilitating the bidding
Pradesh and Tilaiya in Jharkhand were awarded to process, land acquisition, clearances and
Reliance Energy. approvals, securing coal blocks, etc.
• More sites are being identified to expand the • The first UMPP is expected to be
number of UMPPs. commissioned in Mundra by 2012.
23
POWER April 2010
Contents
Advantage India
Market overview
Investments
Opportunities
Industry associations
24
OPPORTUNITIES
Power April 2010
Opportunities … (1/2)
25
OPPORTUNITIES
Power April 2010
Opportunities … (2/2)
26
POWER April 2010
Contents
Advantage India
Market overview
Investments
Opportunities
Industry associations
27
INDUSTRY ASSOCIATIONS
Power April 2010
Industry associations
Year of
Organisation Core expertise
establishment
Damodar Valley Corporation (DVC) 1948 Generation, transmission and distribution in specified regions
Bhakra Beas Management Board (BBMB) 1967 Administration, operation and maintenance of projects
Rural Electrification Corporation (REC) 1969 Financing and implemention of rural electrification schemes
North Eastern Electric Power Corporation Development of power projects in the country’s North-eastern
1976
(NEEPCO) region
Power Finance Corporation (PFC) 1986 Financing of power development schemes
Tehri Hydro Development Corporation
1988 Development of hydro potential in specific rivers/valleys
(THDC)
Satluj Jal Vidyut Nigam (SJVN) 1988 Development of hydro potential in a specific basin
Transmission system for evacuation of Central sector power and
PGCIL 1989 establishment/operation of inter-regional grids and load dispatch
centres
CERC/SERCs 1998 Regulatory bodies to deal with Central and state-level issues
Power Trading Corporation (PTC) 2001 Trading of power
Bureau of Energy Efficiency (BEE) 2002 Responsibility for spearheading improvement of energy efficiency
28
NOTE
Power April 2010
Note
Wherever applicable, numbers in the report have been rounded off to the nearest whole number.
Conversion rate used: US$ 1= INR 48
29
POWER April 2010
DISCLAIMER
India Brand Equity Foundation (“IBEF”) engaged Ernst & presentation to ensure that the information is accurate to
Young Pvt Ltd to prepare this presentation and the same the best of Ernst & Young and IBEF’s knowledge and
has been prepared by Ernst & Young in consultation with belief, the content is not to be construed in any manner
IBEF. whatsoever as a substitute for professional advice.
All rights reserved. All copyright in this presentation and Ernst & Young and IBEF neither recommend nor endorse
related works is solely and exclusively owned by IBEF. The any specific products or services that may have been
same may not be reproduced, wholly or in part in any mentioned in this presentation and nor do they assume
material form (including photocopying or storing it in any any liability or responsibility for the outcome of decisions
medium by electronic means and whether or not taken as a result of any reliance placed on this
transiently or incidentally to some other use of this presentation.
presentation), modified or in any manner communicated
to any third party except with the written approval of Neither Ernst & Young nor IBEF shall be liable for any
IBEF. direct or indirect damages that may arise due to any act
or omission on the part of the user due to any reliance
This presentation is for information purposes only. While placed or guidance taken from any portion of this
due care has been taken during the compilation of this presentation.
30