Daily Report

Project Name: Myanmar Aquarium Project

Project Code: 4YG - 04700 Report Date : 1-Aug-2017 Tuesday No. of Day Report No. DPR- 692

Proj Start Date 2014 Contract Period 1 Year Calendar Day AM PM Fine
Weather
Estimate Completion Date 14-Nov-2017 Remain Period 106 Calendar Day 6~8 8~10 10 ~12 12~2 2~4 4~6 Rain
Work Force
Office
Trades PM PE SSE Site Engr QA/QC QS Admin Safety Security Site Store Driver Surveyer Geotech Workers Mason Carpenter Smith Welder
Staff
Today 1 2 1 3 2 1 2 3 25 64 41 4
Steel Roofing D&W Ceiling Water
Trades Scaffolder Painter Aluminium Total
Erector worker Installer worker Proofing
Today 4 2 155

Machine & Equipments On Site

Description previous Today Cum. Remarks Description previous Today Cum. Remarks Description previous Today Cum. Remarks
Excavator 60 Ton Crane Car Crane
Dozer 50 Ton Crane 13 tons Back Hole
1.5 Ton Roller 25 Ton Crane Rummer 1
Boom Lift Generator Truck
Material Delivery On Site
Quantity Quantity Quantity
Description Unit Description Unit Description Unit Remarks
Today Total Today Total Today Total
Sand (river) suds 5.56 Thinner gls 5
18mm Plywood (8'x4') shts 100 3" x 2" Jungle wood tons 5.287
Red Oxide (5gl) tins 2

FO-OP-01 REV-00 Page: 1/3


Daily Report

Project Name: Myanmar Aquarium Project

QC Test Sampling
Project Code: 4YG - 04700 Report Date : 1-Aug-2017 Tuesday No. of Day Report No.
Test Item Remarks
Sampl
e
LTI Free Day UA,UC Near Miss FAI MTC LTA Daily TBT Conducted
HSE
0 0 0 0 0 By Safety Officer

Works Carried out Details


Trades Of Work Location Remark
I Block(A) F&B Building
1 Kalzip Wall Flashing installation In Progress

II Block(B) Aquarium Building


1 Rebar Fixing & Formwork installation For 2nd Floor Beam & Slab (GL: B-4 to B-9) In Progress
2 Plastering Work at Quarantine Plattform Wall In Progress
3 Sand Filling Work For Ground Floor Topping In Progress
4 Formwork installation For Exhibit 7.1c & 9.1 In Progress
5 Rebar Fixing Work For Skimmer Tank Of Exhibit 9.1 In Progress
6 Rebar Fixing For Exhibit 3.1 (Top Rebate) In Progress

III Block(C) Service Building

Special Events

Visitors Site
Purpose
on Site Instruction
Project Manager Project Engineer Prepare By: Site Engineer
Name Name Sai Thing Nun Name Kaung Htet Zaw

Signature Signature Signature


FO-OP-01 REV-00 Page: 2/3
Daily Report

Project Name: Myanmar Aquarium Project

Project Code: 4YG - 04700 Report Date : 1-Aug-2017 Tuesday No. of Day Report No.

Rebar Fixing &Formwork installation For 2nd Floor Beam & Slab (Gl: B-
Formwork installation For Exhibit 9.1 Formwork installation For Exhibit 7.1 a,b,c
4 to B-9

Formwork installation For Exhibit 1.4

FO-OP-01 REV-00 Page: 3/3