WAP/GNR/EIA-PTN/NWDA-Valsad/2017/
Date: 08.08.2017
To,
The Superintending Engineer
National Water Development Agency (NWDA),
Investigation Circle, 3rd Floor, Om Plaza Building,
Abrama, Dharampur road,
Valsad 396002, Gujarat
Sub: Additional cost for the Comprehensive Environment Impact Assessment (CEIA) study for
the proposed Par-Tapi-Narmada Link Project.
With reference to your letter under Ref. (ii) and our earlier submitted letter vide under Ref. (iii), we are
hereby submitting the revise quote of Rs. 49.00 Lakhs (Rupees Forty Nine Lakhs only) + Taxes (GST
etc.) as per applicable rates. The detailed break up for cost are given as under:
Activity Cost (Rs. Lakhs)
Remuneration of Experts 8.0
TA/DA 3.0
Local Transportation 2.0
Office Expenses 3.0
Ecological Survey 15.0
Ambient Air Quality Monitoring 7.0
Water Quality Monitoring 3.0
Soil Quality Monitoring 3.0
Satellite data collection, ground truth studies interpretation and analysis 5.0
Total 49.0 Lakhs
The above revised cost is for one additional season of sampling. We kindly request you to issue the work
order to start the sampling work.
Thanking you & assuring you our best services at all times.
(S.K.Srivastava)
General Manager & Regional Manager (W.R.)