Beruflich Dokumente
Kultur Dokumente
Construction Projects
Construction cost estimates is the forecast of cost of construction of a
project. Estimating cost of construction projects is the first step for any
project management. In any construction activity, two basic things are
involved, namely, the quantity aspect and the quality aspect.
An estimate of a project is a forecast of its probable cost for the due fulfillment of the
project objectives, to the prescribed workmanship covered by specifications for various
items of works and to the stipulated time schedule. For a given project fully described
by drawings and specifications, estimating involves quantity take off for various items
of work, rate analysis and costing.
Preliminary and Detailed Construction Cost Estimates
In general, construction cost estimates can be broadly divided into two
categories- detailed and approximate or preliminary. Strictly speaking, all
estimates are more or less approximate as the very name implies, and
the actual cost of construction would only be known when a work has
been completed in all respects and all costs allocated.
Thus, a detailed cost estimate gives a realistic estimate of final cost and is
generally required for obtaining sanction/approval of sponsor of the
project or competent authority in respect of public bodies like govt.
organizations. It is also used in the course of the execution of the work to
control progress and costs.
In such cases, the cost involved in preparing a detailed estimate may not
be justified or the time involved would be substantial or data may not be
available or preparation of a detailed estimate may not be otherwise
justified.
The approximate costs are prepared based on unit costs of major sub-
works established by a survey of costs of similar completed sub-works.
The unit costs are updated using cost indices published by govt. bodies or
reputed bureaus. For instance, the Central Public Works Department have
prescribed cost indices for various cities based on 100 for a particular
base year for buildings. The actual costs are known for a particular year
from records, then the current costs would be determined using the
appropriate indices.
Example 2:
Cost of one furnished room in a 3-star hotel- Rs. 3 Lakhs
The takeoff and grouping are carried out on the quantity sheet. The
measurements are recorded item wise and the items are arranged in the
sequence of execution.
(ii) Thin, surface oriented items with large superficial areas measured in
terms of area
(iii) Items which are long, narrow and thin, having dimensions in other
perpendicular directions difficult of measurement, measured in linear
units (i.e. per unit length)
(iv) Items which are difficult of measurement and which are distinct units,
measured in units (i.e. per number)
(v) Items which are heavy and are generally difficult of measurement in
terms of linear dimensions, measured by weight.
Example: Steelwork
(iii) The measurement for the same item of works under differing
conditions should be entered separately, bringing out clearly the
differences in the descriptions.
Degree of Accuracy
The degree of accuracy of measurements would depend on the unit of
measurement and rate for a particular item.