Beruflich Dokumente
Kultur Dokumente
Rev: 4
Concrete Facing
February 2014
CONTENTS
Page
PART I : INTRODUCTION 2
Components 2
Materials and Services supplied by Reinforced Earth Company 2
Equipments, tools and materials supplied by Contractor 3
Work to be performed by Contractor 3
Facing panels 4
Reinforcement strips, fasteners and joint materials 5
Page 1
PART I: INTRODUCTION
Reinforced Earth is a composite material formed Joint Materials
by the association of a frictional soil and Rubber bearing pad, 100mm x 85mm x 20mm
reinforcement strips. In concept, it is like thick for the horizontal joint.
reinforcing concrete; that is, it is an economical Filter cloth or polyester foam strips 40mm
means of improving the mechanical properties of square for vertical and horizontal joint.
a basic material, earth, by reinforcing that material
with another, steel.
Reinforcement Strips - The reinforcement strips
Stresses produced within the soil mass are are supplied in sizes and lengths determined by
resisted by the strips. The stresses are the design of the structure. The strips are
transferred to the strips by friction. generally hot dip galvanised and are designed to
be bolted to the tie strips embedded in the back of
A Reinforced Earth structure constructed using the facing panels.
this material is shown as the reinforced volume
in figure 1 below. Concrete facing panels are Galvanisation may not be required for temporary
used at the face of the reinforced volume to structures.
prevent erosion of the backfill and to provide an
attractive, finished appearance. Fasteners - Reinforcement strips are connected
to facing panels with Grade 8.8 bolts and nuts of
appropriate size.
COMPONENTS
Reinforced Earth structures consist of the Backfill - Backfill conforming to contract
following: specifications must be used within the reinforced
volume.
Concrete Levelling Pad
A 150mm deep by 350mm wide pad of MATERIALS AND SERVICES SUPPLIED
unreinforced concrete that serves as a flat starting BY REINFORCED EARTH
surface for placing panels.
Engineering and design of the structure
Precast Concrete Facing Panels All facing panels
Full size or A panels are used for the All reinforcement strips
majority of the wall. The subscript 4 in panel All nuts, bolts and washers
designations is the number of reinforcement Delivery of all construction materials to the
strip connections (tie strips) per panel. site
On site technical assistance
Alternating panels in the initial course are half One set of lifting device (on loan)
height or C panels. Two spacer bars (on loan)
Top course panels are designated B, D, E, Installation of panels and reinforcement strips.
F, 3, 4, 5, 6, 7, 8 panels. These panels
have a flat top and vary in height to provide a
smooth surface at the top of the structure.
Figure 1
Page 2
EQUIPMENT, TOOLS AND MATERIALS
SUPPLIED BY CONTRACTOR
Figure 2
Page 3
PART II: HANDLING REINFORCED EARTH MATERIALS
FACING PANELS
Figure 5
Panels can be stored by re-stacking on dunnage.
Place the panels face down in line with the
dunnage (figure 6). Panels should be stacked no
more than six (6) high on firm level ground.
Figure 3a
Figure 3b
Figure 6
Page 4
PART III: CONSTRUCTION PROCEDURES
SETTING AND POSITIONING PANELS
The finished appearance of a Reinforced Earth
structure depends largely on the care taken in
erecting and positioning facing panels. For this
reason, particular attention must be given to the
initial course of facing panels and to backfill
placement.
Figure 10
Figure 7
Page 5
Check horizontal levels. The horizontal level of
the panels should be checked and adjusted to
ensure uniform appearance and even joints
throughout the structure.
Figure 13
Figure 11
Page 6
A. SITE PREPARATION
Step A-1: For the length of the wall section to be Step A-5: Snap a chalk line on the surface of the
built, excavate to the depth and width specified on levelling pad to establish a control line for the wall.
the contract drawings, remove all unsuitable
material and replace it with compacted fill, where
necessary. B. CONSTRUCTING INITIAL COURSE
Step A-2: Proof roll the foundation in accordance Panel layout begins at the lowest levelling pad.
with project specifications.
Step B-1: Place the first C (half) panel (1) on the
Step A-3: Install drainage systems as required. levelling pad (figure 15). Align the face of the panel
along the control line. Use 1200 mm level to set
Step A-4: Pour concrete levelling pad. The pad vertical and horizontal levels.
should be cured for 12 hours, or longer if required
by the contract specifications, prior to use. The Step B-2: Place the second C panel (2) on the
concrete finish must be smooth and flat and must levelling pad. Align it with the control line, and set it
not vary from the design elevation by more than 5 the correct distance from panel (1) using the spacer
mm in any 3000 mm in length. bar. Leave the spacer bar in place. Check levels.
When a step-up is required at the wall, pour the Step B-3: Place a third C panel (3) aligning the
higher levelling pad to the required level and leave panel with the control line and using the spacer bar
a 230mm gap between the new pad and the to ensure spacing. Check levels.
centreline of the dowel of the last panel of the lower
course (figure 14).
Figure 15
Figure 14
Figure 16
Page 7
Step B-4: Remove the spacer bar and set the first the backfill side of the structure. Either of the
A panel (4) between the two half panels (1) and following materials is commonly used:
(2). Centre the panel to ensure equal vertical joints.
Check horizontal level and prop vertical. Clamp the * Polyester foam supplied in 40mm square strips
panel to panels (1) and (2) as shown in figure 16. 2000 mm long, is used for all applications. Push the
Tighten clamps sufficiently to hold the panel in foam into the running vertical joints (including the
position without movement. The panel shall remain short horizontal section) with a hardwood wedge or
attached to the crane until it has been adequately similar implement (figure 19 and 20). Twisting the
braced or clamped to adjacent panels. foam while pushing it into the joint can facilitate this
process. No gluing is required.
Step B-5: Place a fourth C panel (5) aligning the
panel within the control line and using the spacer * Filter cloth is normally used in marine and other
bar to ensure spacing. Check levels. structures subject to flooding.
Step B-6: Remove the spacer bar and set the Step B-9: Begin backfilling. Place approved backfill
second A panel (6) between the two half panels up to the bottom row of panels tie strips (figure 21a)
(2) and (3), using the spacer bar to ensure the at 375mm per layer.
correct distance between the new A panel the
previous A panel. Check horizontal level and prop Backfilling can be compacted to within 1500mm of
vertical. Clamp the panel to the two adjacent half the panels by a large vibratory roller. A small hand
panels (2) and (3). operated compactor must be used within 1500mm
of the panels to avoid undue panel movement
Step B-7: Continue along the wall alternating
between placing half panels and full panels. Always
remember to use the spacer bars to place panels Check wall alignment visually and with a level:
and to always check that the panels are level. adjust panels as necessary.
Bracing of the panels shall be as shown in Figures
17 and 18.
Figure 17
Figure 19
Figure 18
Figure 23
Figure 21
Figure 24
Page 9
C. CONSTRUCTING SECOND AND
SUBSEQUENT COURSES
Only after backfill has reached the top of the C Set the batter of the panel by driving kiln dried
(half) panels can construction of the second course hardwood wedges into the short horizontal panel
begin. joints at the face of the wall. A batter of 10mm in
1500mm is generally used as a starting point.
Throughout construction always set panels at
grade; never set a panel onto one that has not Clamp the new A panel (101) to the initial course
been completely backfilled. Begin the second and panels (4) and (6) before detaching the panel from
subsequent courses of panels at the end of the wall the lifting device.
where construction began (figure 25).
Step C-3: Remove the next pair of clamps ; place
Step C-1: Remove the two clamps holding A the rubber pad onto the half panel (3) and set A
panels (4) and (6) to C panel (2). (As each course panel (102) onto it.
proceed, remove only two clamps at a time to allow
for setting a new panel). To prevent concrete to Check the horizontal level and adjust if necessary.
concrete contact at horizontal joints, place 100mm Use the spacer bar to obtain the correct spacing
x 85mm x 20mm thick rubber pad onto the top edge between A panels (101) and (102). Leave the bar
of the half panel (2) (figure 26). in place. Match the face of the panel just placed to
that of the panel below and set its batter. Clamp the
Step C-2: Set A panel (101) onto C panels (2) panel (102) to adjacent panels (6) and (8).
(Figure 25) centering the panel to ensure equal
vertical joints and matching panels front face to
that of panel (2). Check the horizontal level and
adjust if necessary.
Figure 25
Figure 27
Figure 26
Page 10
Step C-4: Remove the next pair of clamps; place Reinforced Earth structures with a levelling pad at
the 100mm x 85mm x 20mm thick rubber pad onto or above grade require placement of an earth berm
the half panel (5) and set A panel (103) onto it. as toe protection along the face. Structures with a
levelling pad below grade require the backfilling of
Check the horizontal level and adjust if necessary. an embedment in front of the wall.
Use the spacer bar to obtain the correct spacing The height of the berm or the depth of the
between A panels (102) and (103). Leave the bar embedment depends on the design height of the
in place. Match the face of the panel just placed to structure and is shown on the contract drawings.
that of the panel below and set its batter. The berm or embedment must be placed either
Clamp the panel (103) to adjacent panels (8) and before the wall reaches 50% of its height or when it
(10). Continue to set A panels in the same has reached a height of 5000mm whichever is less.
sequence using all three spacer bars supplied in a
leap-frogging pattern. Step C-8: When backfill reaches the tops of the
As the work proceeds, check the walls alignment initial course of full panels (halfway up the second
frequently. Install vertical joint material, as in step course), begin construction of the next course of full
B-8. panels. Repeat steps C-1 through C-8, placing
panels, spreading and compacting backfill and
Step C-5: When the course of panels is complete connecting reinforcement strips, for each additional
and vertical joint material installed, backfill up to the course until the wall is ready to be topped off.
tie strip level. Figure 27 shows the sequence for
backfilling the second and subsequent courses. Note : When backfilling has reached the level of the
top of the second row of A panel, check that the
Step C-6: After backfilling re-check the batter and panels have become almost vertical.
alignment of the wall, then place and connect the If they have not adjust the amount of batter so that
next layer of reinforcement strips, as in Step B-10. the third row will be vertical after backfilling.
Figure 28 Figure 29
Page 11
PART IV: SUMMARY OF CONSTRUCTION PROCEDURES
A. PREPARE SITE
Step A-1 : Excavate site to depth and width specified on contract drawings
Step A-2 : Proof roll foundation
Step A-3 : Install drainage systems, as required
Step A-4 : Pour levelling pad
Step A-5 : Establish wall control line on levelling pad
Step A-6 : Place safety barrier or tape or safety cone near excavation site where
appropriate
D. COMPLETE WALL
Step D-1 : Construct top course
Step D-2 : Remove all clamps and wedges from wall
Step D-3 : Install capping units, if necessary
E. APPENDIX 1
Machine, labour and equipment required
15T 20T Vibratory roller
Plate compactor 1 baby roller for compacting strips zone within 1500 mm from the rear face
of the panel.
2 general works for trimming granular backfill around the rear face of the RE panel.
Page 12