Sie sind auf Seite 1von 28

Derin Ural

Foundation Engineering
2006 SPRING

INS332E
Derin N. Ural 1

Foundation Engineering
a structure is no stronger than its connections
Connections between individual structural members

Connections between structures & the ground that supports it

Example of foundation failure ;


Tower of Pisa , 6 inclination
Derin N. Ural 2
http://torre.duomo.pisa.it/

copyright 2006
Derin Ural

Foundation Engineering

Foundation engineering emerged in the late 1800s

- First , load bearing masonry walls were supported on


spread footings.
- Later , steel & reinforced concrete buildings started
being built.

Less rigid ; taller & heavier Birth of Modern


structures Foundation Engineering

Derin N. Ural 3

Foundation Engineering

Modern Analysis Design Construction

1. Geotechnical (soil info)


Foundations require
know how 2. Structural (member)
3. Construction (actual built)
Derin N. Ural 4

copyright 2006
Derin Ural

Foundation Engineering

Design of Foundation of Structures (Bridges, Buildings, Dams)


requires knowledge on factors including :

1. The load transmitted to the foundation system from the


superstructure.
2. The requirements of the local BUILDING CODE
3. Behavior & stress related deformability of soil that will
support the foundation system
4. Geological conditions of soil.

Derin N. Ural 5

Foundation Engineering

Building Codes :

-Uniform
Uniform Building Code

-Euro-
Euro-Building Code

-Turkish Building Code

Derin N. Ural 6

copyright 2006
Derin Ural

Foundation Engineering
FOUNDATIONS

SHALLOW DEEP

Spread Wall
Mat Piles Caisson
Footings Footings

Depth of embedment 3 to 4 * width of Top soil layers have poor load


the foundation Derin N. Ural bearing capacity 7

Foundation Engineering
SITE INVESTIGATION
PURPOSE :To obtain data and information to evaluate the following;
following;
1. To determine the type of foundation required (shallow or deep)
2. To recommend allowable load capacity of the foundation
3. Sufficient data and laboratory tests to make settlement predictions
predictions
4. Location of the ground water table (wh
(whether it is in the construction zone)
5. Information so that the identification and solution of specific construction
problems can be made ;
Bracing
Dewatering
Rock excavations
6. Identification of potential problems concerning the adjacent property.
property.
(settlements, existing damage)
7. Identification of environmental problems and their solution (sanitary
(sanitary land fill)

Derin N. Ural 8

copyright 2006
Derin Ural

Foundation Engineering
SITE INVESTIGATION

Relative cost : 0.1% to 2% of cost of the project

Soil Exploration Methods


1. Boring and sampling
2. Subsurface soundings ,field (in-
(in-situ) tests

SPT
penetration tests
CPT

Inspection shafts, test pits, tunnels


Geophysical methods
Load tests
Derin N. Ural 9

Foundation Engineering
SITE INVESTIGATION
MAJOR STEPS
Planning
Type of Boring Method
No and Depth of Borehole
Type and Frequency of Field Tests
Sampling Procedures
Execution
Boring
Sampling
Field Tests
Geotechnical Report

Derin N. Ural 10

copyright 2006
Derin Ural

Foundation Engineering
I - BORING and SAMPLING
Drilling a hole in the ground for sampling and observations.

Location : Depends on the layout plan of the structure and shape of the
structure

Spacing : Erratic soil profile 78m


Uniform soil up to 150 m
1 storey building 23 - 30 m
Multi-
Multi-storey building 15 23 m
Highways 230 305 m
Earth dams 23 - 46 m
Residential subdivision planning 61 92 m

Derin N. Ural 11

Foundation Engineering

Depth :

1. The borings must reach stable layer and penetrate all unsuitable layers.

2. If the structure is on deep soft soil deposit the borings must extend
extend to a
depth where consolidation affects are negligible.

3. Bedrock and boulders must be identified by approximately 3 m drilling


drilling in
rock.

4. Depth 1-2 times the least dimension of the loaded area/

5. Depth > 10 m

Derin N. Ural 12

copyright 2006
Derin Ural

Foundation Engineering

IA - Boring Methods
Hand tools : Obtaining a test hole using a Pick & Shovel. Most common
Hand Augers.

Auger Borings : Flight augers act as a screw conveyor to bring the soil to the
surface.

Hollow Stem

Augers
Solid stem

Derin N. Ural 13

Foundation Engineering
water + soil out water in

Wash Borings :

Water jet, mechanical energy


Jetting action of water

casing

Chopping bit , replaced by Wash pipe


sampler during sampling

Derin N. Ural 14

copyright 2006
Derin Ural

Foundation Engineering

Rotary Drilling : Percussion Drilling :


A heavy bit (200 to 1000 kg) is
Common in rock formations, alternately raised and dropped to
crush and grind soil.

Derin N. Ural 15

Foundation Engineering

IB - Sampling
Boring operations are stopped frequently (at 1,5 or 2,0 m intervals) for sampling.

SAMPLES

Disturbed Undisturbed
(For soil classification) (For strength and deformation)

Derin N. Ural 16

copyright 2006
Derin Ural

Foundation Engineering
COMMON METHODS FOR SAMPLING - (SPT)

1) Sampling by Standard Split Spoon :

Once the borehole is advanced to a desired depth, the drilling tools are removed.
The split spoon sampler is attached to the drill rod & lowered to the bottom of
the borehole. The sampler is driven into the soil with hammer blows.

Drill rod

5'' Coupling or Head

24'' Split Barrel

Driving Shoe
3''
2''
Derin N. Ural 17

Foundation Engineering

The number of blows


Hammer required for the driving
(623 N) 30'=76 cm the sampler through
Anvil three 66 intervals is
recorded . The sum of
the number of blows for
the last two 6'
6' intervals
is referred as the
standard penetration
number, (N). After
driving is completed, the
6''=15cm soil sample inside split
tube is collected &
Total 18=45cm transported to the
laboratory. Split spoon
samples are usually
taken at 1,5 m intervals.
Derin N. Ural 18

copyright 2006
Derin Ural

Foundation Engineering

2) Sampling by Thin Wall Tube :

Unlike the standard split


Drill rod spoon, the thin wall
tube is attached to the
end of the drill rod, once
1.875 the desired depth is
Thin walled tube
attained and lowered
hydraulically. The
sampler with soil is then
sealed & taken to the
2' or 3 most common lab.

Derin N. Ural 19

Foundation Engineering

2) Sampling by Piston Sampler :


Piston samplers are used when "Highly
undisturbed" soil samples are needed.
The cost is higher than the first two
methods. The piston is lowered
hydraulically

Derin N. Ural 20

copyright 2006
Derin Ural

Foundation Engineering
SAMPLE DISTURBANCE

The degree of disturbance of the soil sample collected can be expressed


by the Area Ratio (Ar) :

D02 Di2
Ar (0 0 ) = 100
Di2

Where :
D0 :outside diameter of sampler
Di :inside diameter of sampler

A soil sample can be considered `undisturbed` if Ar10%.

Derin N. Ural 21

Foundation Engineering
SAMPLE DISTURBANCE

Disturbed sample from standard split spoon can be used for laboratory
tests including :

Grain size distribution


Liquid limit Soil classification
Plastic limit
Shrinkage limit

Undisturbed samples are required for the following tests :

Consolidation
Triaxial compression Strength & Deformation

Unconfined compression

Derin N. Ural 22

copyright 2006
Derin Ural

Foundation Engineering
The standard penetration test may be stopped if :
50 blows are required for any 6
6 penetration,
Total 100 blows are obtained,
10 successive blows produce no tip advancement.

Derin N. Ural 23

Foundation Engineering
Correction of N for overburden pressure
One must incorporate the effect of the soil in overlying layers of the
soil of interest . Therefore the following correction procedure is used :

20
N = C N N F = 0,77 N F log ( for 0,25 ton / ft 2 )

Where :
N: corrected SPT #
NF: field SPT #
CN: correction factor

20
For SI Units N = 0,77 N F log ( for 23,9 kN / m 2 )
0, 0105
Unit of overburden pressure` : kN/
kN/m2. Example!
Example!
Derin N. Ural 24

copyright 2006
Derin Ural

Foundation Engineering
Correlations for Standard Penetration Resistances ( N,N
N,N)

Compressive
N Consistency
strength , qu (kPa)
02 Very soft 0 - 25
For cohesive soils

24 Soft 25 50
48 Medium 50 100
8 16 Stiff 100 200
16 32 Very stiff 200 400
>32 hard >400
Derin N. Ural 25

Foundation Engineering
Correlations for Standard Penetration Resistances ( N,N
N,N)

N Dr (%) Consistency
For cohesionless soils

04 0 15 Very loose
4 10 15 35 Loose
10 30 35 65 Medium
30 50 65 85 Dense
>50 85 - 100 Very dense

Derin N. Ural 26

copyright 2006
Derin Ural

Foundation Engineering
Correlations for Standard Penetration Resistances ( N,N)
N,N)

Friction Angle
For cohesionless soils

N'
()
05 26 - 30
5 10 28 35
10 30 35 42
30 50 38 46

Derin N. Ural 27

copyright 2006
Derin Ural

Soil Exploration
Methods

CONE PENETRATION TEST

The end resistance of the cone at any depth called the


cone penetration resistance is (qc) measured. qc is the
force required to advance the cone divided by the end area.
Unlike the SPT, soil samples cannot be recovered during
the CPT.

A pplicable N ot A pplicable
Soft clays Very stiff clays
Fine to medium course Hard clays
sands
gra vels

copyright 2006
Derin Ural

CONE PENETRATION TEST

Types of cones:
Mechanical Cone (Dutch Cone - reading every 200 mm)
Electrical Cone (constant readings)
Electrical Piezocone

Friction Ratio :
FR= qS/qc *100 (%)
FR< 1% :sands,
FR> 5% :clays

CONE PENETRATION TEST

Data collected during electrical CPT


qC qS FR u
(Mpa) (kPa) (%) (kPa)

Note: qC can be correlated to : ,Dr ,CU, N 4

copyright 2006
Derin Ural

THE PRESSUREMETER TEST

The Pressuremeter test is an in-situ test developed by


Menard in 1956. Applicable for : soft clay , fine to
medium sands. The device consists of three parts(top,
cell and bottom) as shown below:

copyright 2006
Derin Ural

THE PRESSUREMETER TEST

The Pressuremeter is inserted into the borehole and the top


and bottom guard cells are expanded into the soil. The middle
cell is used to obtain the volume versus cell pressure.
Measuring
Cell
Zone 2
Volume (V)
Pseudo Zone 1: Soil pushed back to
Elastic
Zone 1
zone Zone 3
initial state
Reloading
V Plastic Zone Zone 2: Pseudo elastic, V vs P
V0 is linear
P Zone3: Plastic Zone

p0 Measuring
Cell Pressure (p) 7

THE PRESSUREMETER TEST

For Zone 2 :
E=2(1+)V0 p/V

where E : Youngs Modulus of soil


: Poissons ratio
V0: volume corresponding to beginning
of zone 2 at p0

p/ V = 1 / (slope of line in zone 2)

copyright 2006
Derin Ural

THE PRESSUREMETER TEST

Also, the relationship between E and G is given by

E=2(1+)G G=V0 p/ V

Pressuremeter test results can also be used to determine the at


rest earth pressure coefficient:
K0=p0/
Note:In France, shallow and deep foundation design is all based
on pressuremeter tests.

FIELD VANE TEST

This in-situ test is used to determine the undrained shear


strength of soft, fine grained clays (similar to lab vane test).
This test is performed every 0.75 to 1 m of depth.

T = CU ( D2 H/2 + a D3/4)

where H/D = 2

2/3 : uniform end shear


a= 3/5 : parabolic end shear
1/2 : triangular end shear
10
T : N-m

copyright 2006
Derin Ural

11

FIELD VANE TEST


When ; H/D= 2 & a=2/3

CU = 0.2728 T/D3

Also; (Cu)design= (Cu)field

1,2

1,0

0,8

0,6

0,4
0 120 12
PI %

copyright 2006
Derin Ural

PLATE LOAD TEST

Most reliable way to obtain the ultimate bearing capacity


at a site is to perform a load test.

13

PLATE LOAD TEST


Procedure

1) Piles should be driven first, to avoid excess vibration &


loosening of soil in excavation area.

2) Excavate hole to depth the test is to be performed.


Test hole depth > 4B

3) A load is placed on the plate (usually steel) and settlements


are recorded from a gauge. Load increments 1/5 bearing
capacity of soil or 1/10 estimated failure load. Time of
loading 1 hr & should be same duration for all increments.

4) Test should continue until settlement = 25 mm or,


until capacity of testing apparatus is reached. 14

copyright 2006
Derin Ural

PLATE LOAD TEST


Load (ksf) Load
0 5 10
0

lim Hard/dense
1 soils

Settlement
(in.) 2 Settlement Loose/soft
soils

If H = 1 in. lim 1/2 load corresponding


qult= 9,9 ksf
failure to 10 mm settlement

Note: Plate load test results do not include effects of CONSOLIDATION


15

16

copyright 2006
Derin Ural

17

PLATE LOAD TEST

For Cohesive Soils Cohesionless Soils

qfoundation= qtest qfoundation= qtest(Bfound/Bplate)

(only if Bfound/Bplate 3 )

Sfound= Stest (Bf /Bp) Sfound=St Bf(Bp+0,3) 2

Bp(Bf+0,3)

18

copyright 2006
Derin Ural

PLATE LOAD TEST

Coefficient of Subgrade Reaction , ks :


Used to obtain E: when
modelling soil as elastic
Load springs (Winkler)
q

(use secant) : ks= q / s


[units: kg/cm3,kN/m3]

Settlement
s
EI d4y/dx4= - kBy
19

PLATE LOAD TEST


General relationship:

kS = C1(1+ 2d/b)+C2/b

where; C1, C2 : soil constants


d : depth of test
b : width of plate

Run 2 tests with varying plate size & and depth :


*KNOWN :(k1,d1,b1) & (k2,d2,b2)
*SOLVE : C1,C2

if c = 0 or = 0 ; one test is enough !


20

copyright 2006
Derin Ural

GEOPHYSICAL METHODS

Useful in ground investigation in reconnaissance stage


Supplementary method (not suitable for all soils)
Capable of
estimating depth to bedrock
estimating depth to water table
filling in detail between borehole
Less cost than other in-situ tests

21

GEOPHYSICAL METHODS
1) Seismic Refraction Method:
Seismic waves have different velocities in different types
of soil. Waves are generated either by explosives, or striking
a metal plate with a hammer (geophone & seismograph ).

Two types of stress waves:

P Waves : plane waves


200 m/s in sands to 2500 m/s in clays
S Waves : shear waves

22

copyright 2006
Derin Ural

GEOPHYSICAL METHODS
Seismic Refraction Method - continued:

Principle:
A) Longitudinal waves travel in straight lines in a
medium of constant density.

B) Waves are reflected when they come in contact with


soil strata of different density.

C) Determine seismic velocities & compare with known


values.
23

GEOPHYSICAL METHODS

Seismic Refraction Method - continued:


P-wave velocity:

p= E /(/g) * (1-)/((1-2)(1+ )) : TR<TS

First arrival time to detectors are determined :

Vsoil= L0 / T0
Vrock= (L3-L1) / (T3-T1)
24

copyright 2006
Derin Ural

GEOPHYSICAL METHODS

2) Electrical Resistivity Method:


Differences in electrical resistance of different soil types.

Method

* Place 4 electrodes with equal spacing A.


* Apply a direct current to outer electrodes I.
* Measure potential drop in inner electrode.
25

GEOPHYSICAL METHODS
I
E

Electrodes Current flows & creates


electrical field in soil
A A A

The resistivity of soil is determined by:

= 2AV/I
V:Voltage drop
26

copyright 2006
Derin Ural

GEOPHYSICAL METHODS

3) Cross Hole Seismic Survey:


Two holes are drilled a distance, L, apart. A vertical impulse
is created at the bottom of one of the boreholes by an
impulse. The shear waves generated are recorded by a
transducer at the other borehole.

Method
Shear wave velocity: Vs = L / t
Shear modulus : G=Vs 2 / g
27

SOIL EXPLORATION REPORT

Scope
Description of Structure
Description of Location of Site
Geological Setting
Detailed Field Exploration
Sub-soil Conditions
Water table conditions
Foundation recommendations
Conclusions and limitations 28

copyright 2006

Das könnte Ihnen auch gefallen