Sie sind auf Seite 1von 1

Project Proposal

I. Project Information
Type of Project: Educational and Technological
Proponents: Central Student Council
Number of Beneficiaries: 500 students
Location of Beneficiaries: Pearl Hall Dormitory
Date of Implementation: October 10, 2016
Area of Project Implementation: Mountain View College
Budget Requirement: P300,000.00
Budget Requested: P300,000.00

II. Project Summary


Background: A number of students staying in the dormitory is increasing and they
are all in need of internet. The current internet server cannot cater all students in the
dorm. They need it for their educational need. The dorm have a slow internet
connection so they need a big and new one.

Objectives:
To help students in their assignments and researches through strong internet
connections

III. Project Methodology


Strategy: Replace the current server to a bigger one.
Project Timetable:
Date Activities Output/ Target Person in Charge
June 1, 2016 Planning Detailed Plan on the project Isabel A. Panes
June 15, 2016 Canvassing Prospect Supplier Eden Robantes
August 10, 2016 Purchase Buy the equipment Aizhar Rosales
Sept. 1, 2016 Installation Install the equipment Aizhar Rosales
Oct. 10, 2016 Ribbon Cutting Official Opening to use the server All officers

IV. Project Risk Management


Risk Measures to lessen the risk
- Students will have more time to spend in - Block social media sites on weekdays
Social media and open it on weekends only

V. Project Cost:

Buget Line Item Amount Needed Proposed Sources


Canvassing P 5,000.00 CSC Fund
Purchasing P250,000.00 CSC Fund
Installation P35,000.00 Deonnel Perren ( Alumna)
Cage/Protector P20, 000.00 Deonnel Perren

VI. Conclusion
This project will be a big help to the students. This will enhance their learning
skills in research and will help them discover more.