Beruflich Dokumente
Kultur Dokumente
Risk assessment on any facility is most efficiently done by first dividing the facility into components with
unchanging risk characteristics. For a cross-country pipeline, this involves collecting data on all portions of the
pipeline and its surroundings and then using this data to dynamically segment the pipeline into segments of
varying length. Risk algorithms are applied to each of the segments, producing risk estimates that truly reflect
changing risks along the pipeline.
The risk estimating algorithms are conceptually very straightforward. However, as with any assessment of a
complex mechanical system installed in a varying, natural environment, there are many details to consider. This is
illustrated by an example risk assessment on a hypothetical pipeline. .
Varying levels of analyses rigor are available to risk assessors. For example, a resistance estimate might be
modeled as simply being related to stress level and pipe characteristics or, for more robust analyses, could include
sophisticated finite element analyses. In this example, a certain amount of detail is omitted in order to better
demonstrate the higher level principles.
To illustrate key concepts, one time-independent failure mechanism (third party damage) and one time-dependent
failure mechanism (external corrosion) are assessed. All other failure mechanisms will follow one of these two
forms. Estimates from all failure mechanisms can be combined in various ways to meet the needs of the
subsequent risk management processes.
Example:
MEASUREMENT UNITS
Risk $/year
Probability of Failure (PoF) failures/mile-year
Consequence of Failure (CoF) $/failure
Time to Failure (TTF) years
Exposure events/mile-year
Mitigation %
Resistance %
PoF_third-party damage
= (3 damage events per mile-year) x (1 - 98% mitigated) x (1
- 75% resistive)
This same approach is used for other time-independent failure mechanisms and for all portions of the
pipeline.
Risk assessors similarly calculate all risk elements for each of the
6,530 segments. To estimate PoF for any portion of the 120 mile
pipeline, a probabilistic summation is used to ensure that length
effects and the probabilistic nature of estimates are appropriately
considered. To estimate total risk, an expected loss calculation for
the full 120 miles yields $25,200 of risk exposure from this pipeline
per year of operation. The average is $210/mile-year.
Risk Management
The risk estimates generated in this way are extremely useful to decision
makers. Such estimates can become part of the budget setting and valuation
processes. In this example, the company first uses these values to compare
to, among other benchmarks, a US national average for similar pipelines of
$350/mile-year. The comparison needs to consider the P90 level of
conservatism employed. Often, a P90 or higher level of conservatism is
appropriate for determining risk management on specific pipeline segments,
but will not compare favorably to historical incident data since those generally
reflect P50 estimates.
Understanding how each pipeline segment contributes to the overall risk sets
the stage for efficient risk management.