Inspect the surface of clarifier tank columns and back wash pump
26.Aug 07:30 DS7 CE-C0956 (PBE681161B,PBE681261A/B)foundation after remove formwork in DS7.
HOLD
26.Aug 08:00 DS7 CE-C0957 Inspect the surface of pump shelter (train2) columns after coating in DS7. HOLD
Final inspection for the rebar and formwork of the DS7's Precast pipe support footing
26.Aug 10:00 CPECC camp CE-C0953-R1 in CPECC CAMP. (total=30) HOLD
26.Aug 11:30 DS7 CE-C0960 Sampling backfill soil (zone1,2,3) between two sleeper in DS7. Witness
26.Aug 11:30 DS7 CE-C0961 Sampling backfill soil (zone5,16) in DS7 Witness
26.Aug 11:30 DS7 CE-C0962 Re-sampling of IR-CE-C0954 fail point in DS7 Witness
ISSUED
West Qurna I
RESPONSIBILITY Date: 25-8-2017 Produced Water Treatment M109
Time:
SUBCONTRACT CPECC COMPANY/
OR
Comments
QC DEP. OWNER 8 9 10 11 12 13 14 15 16