Sie sind auf Seite 1von 21

SECTION 400 STRUCTURE REHABILITATION AND REPAIR

401 GENERAL Due to the variation in the types of problems


encountered, the designer must perform an in
depth inspection of the structure to identify
The technology of bridge rehabilitation and the defects that exist, and develop a solution
repair is constantly changing. In addition, which is unique to the problems found. This
many of the defects encountered vary from field inspection should include color
bridge to bridge requiring individual unique photographs and sketches showing pertinent
solutions. Consequently, this section of the details and field verified dimensions.
Manual merely presents an overview of bridge
rehabilitation and some of the more common It is imperative that an in depth, hands on,
types of repairs. The repairs that are discussed inspection of bridges be made, by the Design
are all proven to be reasonably successful and Agency preparing the repair or rehab plans, to
are approved by FHWA for use on Federally determine the extent of structural steel and
funded projects. ODOTs District concrete repairs. This inspection must be
maintenance teams and the Office of made concurrent with plan development.
Structural Engineering are continually Large quantity and cost overruns result when
experimenting with new techniques, many of this inspection is not adequately performed
which appear promising, but have not yet resulting in substantial delays to completion of
reached a point where conclusions can be the project.
drawn with regard to their longevity. Until
these products and procedures are evaluated, All pertinent dimensions which can be
they will not be included in this Manual and physically seen must be field verified or field
they should not be used on Federal aid measured by the designer and incorporated
projects. into the plans. It is not permissible to take
dimensions directly from old plans without
For individual members, it will be necessary checking them in the field because deviations
to determine whether the best option is to from plans are common. Every attempt must
repair or replace. In making this decision, cost be made to prepare plans which reflect the
must be considered along with factors such as actual conditions in the field. However, it is
traffic maintenance, convenience to the public, recognized that uncertainties may exist.
longevity of the structure, whether the rehab is Consequently, the note entitled EXISTING
long term or short term, and the practicality of STRUCTURE VERIFICATION, found in
either option. Section 600 of this Manual, should be
included in the plans with the understanding

4-1
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

that the designer is still responsible for responsible for describing the welding
making a conscientious effort to provide procedures, non destructive testing (NDT)
accurate information based on field requirements, etc. in plan notes.
observations.
Welding is permitted in compression zones
Sketches of various details have been provided the designer ensures that the
provided throughout this chapter. These chemistry of the existing steel is such that it
sketches are not complete nor are they to be can be welded. This will require either review
taken as standard details. They are offered as of old mill certifications or actual sampling of
suggestions or ideas for the designer to use in the material for chemical analysis. This
developing his or her own solutions to the determination must be made by the designer.
unique problems they encounter. Pay close attention to American Welding
Society (AWS) Specifications. Field NDT of
A bibliography has been included at the end of the welds will be required and it will be
this section. While these references contain necessary to specify the type and location of
much information and many innovative ideas, the NDT in the plans.
designers are advised to discuss untested solu-
tions with the Office of Structural Engineering
before completing detail plans. 402.2 FATIGUE ANALYSIS

A fatigue analysis of any existing steel


members to be re-used or rehabilitated is re-
402 STRUCTURAL STEEL quired. It shall be performed in accordance
with the method presented in the latest edition
of the "AASHTO Guide Specifications for
402.1 DAMAGE OR SECTION LOSS Fatigue Evaluation of Existing Steel Bridges"
(which gives a remaining fatigue life) and the
method presented in the current "Standard
It may be necessary to repair a section of a Specifications for Highway Bridges" (which is
steel member that has been damaged by rust or based on allowable stress range). Neither of
other means. Welded repairs are not permitted these methods produces absolute results.
in tension zones. Damaged sections in tension Rather they are useful as indicators of the
zones normally shall be repaired by bolting relative severity of the fatigue detail. So they
new steel to existing steel. The specifics of the should both be evaluated along with any other
details are left to the ingenuity of the designer pertinent information which could help in
due to the vast number of possible solutions. reaching a conclusion.
If it is absolutely necessary to perform welded
repairs in a tension zone, then permission to
do so must be obtained from the Office of
Structural Engineering. The designer will be

4-2
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

A fatigue analysis submittal shall be made to


the Department, at the preliminary design ADTT, "Ta", growth rate "g" and present
stage, for final determination as to whether the age of structure in years.
members require fatigue related upgrading.
impact percentage (10%)
If the submission is made directly to the
Department, any involved review consultant Calculated reliability factor "Rs", basic
shall receive a copy of the transmittal letter. reliability factor "RS0", "FS1", "FS2", "FS3"
The Department's comments shall be directed
through the review consultant, if any. Method B Current Standard AASHTO
specifications for fatigue
Both Method A and Method B, as discussed
below, are to be investigated and the results A table showing:
submitted. The fatigue submittal shall include
the following: Remaining safe and mean fatigue life

Method A AASHTO Guide Specifications Moments and stress ranges at each detail
for Fatigue Evaluation of Existing and location being evaluated.
Steel Bridges
A list of assumptions and input values used
A table showing: for each detail and location being evaluated
including:
Remaining safe and mean fatigue life
Live load distribution factor, axle; (S (in
Moments and stress ranges at each detail feet)/7.0 ft) [(S (in mm)/2134 mm)]
and location being evaluated.
Fatigue vehicle used (HS20-44) [(MS18)]
A list of assumptions and input values used
for each detail and location being evaluated Section properties at the detail and
including: location and a narrative stating whether
those section properties are composite or
Live load distribution factor non-composite.

Wheel and axle spacings of the fatigue


truck used as defined in the guide
specification.

Section properties at the detail and


location and a narrative stating whether
those section properties are composite or
non-composite.

4-3
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

402.3 FATIGUE RETROFIT cracking, intersecting welds, lateral


connection plates, longitudinal stiffeners,
cracks and many others. The Office of
402.3.1 END BOLTED COVER Structural Engineering may be contacted for
PLATES assistance in determining the best retrofit for
specific details.

When the fatigue category of welded cover


plate ends or welded flange and web splices 402.4 STRENGTH ANALYSIS
are to be upgraded, bolted splice plates shall
be provided. The bolted plates shall be
designed to carry the total loads (HS20-44 When analyzing existing structural members
[MS18]) at the point of transfer. AASHTO, in for strength, the live load is to be the HS20-44
the 1997 interim and commentary, presents a [MS18] truck (or lane load) and the Alternate
design example for end bolted cover plates. Military Loading as defined in Section 3.7 of
AASHTO.

402.3.2 BOX GIRDER PIER CAPS In analyzing the strength of existing members
which are to receive a new deck, a future
wearing surface of 60 psf [2.87 kPa] shall be
Often box girders were constructed using non- included in the dead load.
continuous back-up bars which were stitch
welded in place. The discontinuity in the
back-up bar is of major concern since it acts 402.5 STRENGTHENING OF
like a crack in the member and is the source of STRUCTURAL STEEL
crack propagation into the flange or web. One MEMBERS
possible solution is to drill a horizontal hole
through the web and back-up bar at the points
of discontinuity. See Figure 401 for a sample Welded stud shear connectors shall be
detail. The stitch welds may or may not be a installed full length on all steel beam or girder
problem depending on the stress ranges at bridges in which the deck is being removed
their location. and replaced. The stud spacing shall be
designed in accordance with AASHTO
Section 10.38.5.
402.3.3 MISCELLANEOUS FATIGUE
RETROFITS Bolted cover plates in tension zones or field
welded cover plates in compression zones can
be used to increase strength. Field welding is
Various retrofits have been used for fatigue to be performed in strict compliance with
prone details such as small web gaps which AWS Specifications. Field NDT of the welds
result in stress concentration and subsequent will be required and it will be necessary to

4-4
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

specify the type and location of testing in the "Trimming of Beam Ends" for payment. Pay
plans. Also, practicality of field welding must attention to the clearance to the end cross
be evaluated. Overhead welding is not frames and detail their removal and
practical. replacement if necessary.

Consider jacking the stringers to relieve In lieu of trimming the beam ends, consider
stresses prior to installing cover plates. In this modifying the backwall if backwall removal
manner the cover plates will carry dead load and replacement is being performed as part of
and live load stresses. If the plates are the work. Modifying the backwall would be a
installed without relieving the stresses, they viable option if it were necessary to remove
will carry live load only. This is merely a and replace the end cross frames as a result of
suggestion as to how extra strength might be trimming the beam ends. Another option to
obtained if it is needed. consider is converting the existing abutment
into a semi-integral abutment as discussed in
Other methods of increasing the strength are Section 406.
to attach angles or structural shapes to the web
or flanges. The possibilities are numerous and
must be left to the ingenuity of the designer. 402.7 HEAT STRAIGHTENING
However, the designer must remember to pay
strict attention to practicality as well as
strength and fatigue requirements. Review Beams or girders that have been struck by
unusual details with the Office of Structural trucks or bent by other causes can often be
Engineering before proceeding. repaired by heat straightening only, or in
combination with field welding to install new
When retrofitting or repairing truss members, sections for the damaged steel member
the designer must remember to provide for portions. An assessment by the District Bridge
temporary support where needed. Many truss Engineer or other ODOT representative with
members are non-redundant, and their experience in heat straightening must be made
removal could result in the collapse of the as to the practicality of this type of repair
structure. before proceeding. If heat straightening is
deemed to be practical, a proposal note is
available which describes and controls the
402.6 TRIMMING BEAM ENDS operation. Plan requirements are to provide a
pay quantity and a detail showing the location
of the repair.
Trimming of beam ends is sometimes
necessary due to tilting of the abutment and
closure of the end dam. A detail (plan and
elevation view) showing where the beam is to
be cut is required. Also provide pertinent
notes and include the work with Item 513/863

4-5
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

402.8 HINGE ASSEMBLIES FHWA requirements. Also, bear in mind that


the installation specifications in the CMS deal
strictly with the installation and testing of
Consideration should be given to removing normal high strength bolts. If Huck or other
hinges and making the members continuous. breakaway fasteners are used, the installation
specifications must be modified by plan note.
If the hinge cannot be removed, consideration
should be given to the need of providing
redundancy in the event of a hinge failure. 403 CONCRETE REPAIR/RESTO-
Figures 402 and 403 show a method for RATION (OTHER THAN
consideration. DECK REPAIR)

Contact the Office of Structural Engineering if


a pin and hanger assembly is to be 403.1 GENERAL
rehabilitated. Lubrication and nondestructive
testing will be required.
Repairing concrete that is more than
superficially damaged is expensive and
402.9 BOLTS problematic. Since many members can be
completely replaced for less than the cost of
extensive repair, aggressive replacement of
Bolts should conform in general to Section deteriorated members should be pursued.
300 of this Manual. However oversize or Salvaging concrete containing corroding
slotted holes, designed in accordance with reinforcing steel or critically saturated
AASHTO Section 10.24, are permitted in aggregate does not often result in a long
repair or rehabilitation work. Oversize or lasting component since the substrate concrete
slotted holes may be desirable in some repaired is only marginally better than the
remedial applications especially where the fit unsound concrete removed. Any time there
of repair or replacement members or parts are major and extensive repairs being
becomes tedious. These connections shall still proposed to concrete structures, in depth and
be designed as slip critical. thorough investigation of the condition of the
concrete will be required. This investigation
The plans should state the specific must include, but is not limited to, hand
requirements for the holes and necessary investigation with a chipping hammer, drilling
washers since all CMS requirements are for into unsound concrete to determine the depth
standard size holes. of deterioration, and concrete cores. In the
past, the extent of concrete deterioration
The use of breakaway fasteners such as Huck actually encountered in the field has far
bolts are acceptable when clearance problems exceeded the amount anticipated in the design
arise. Remember that two or more bolt manu- stage on certain projects.
facturers must be specified in order to satisfy

4-6
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

403.2 PATCHING For quantities greater than 350 square feet


[35 m2]: A pay item, Item 520,
Pneumatically Placed Mortar, As Per
It is the designer's responsibility to evaluate Plan should be used
the repair areas and determine the most
suitable repair method. The detail plans are required to show and
detail the locations of the areas that require
To serve as a guide to the designer, the patching repairs, consequently Items 519 and
following criteria have been established to 520 are As Per Plan. Additionally, Item 519
help in the patching selection evaluation. needs a plan note requiring the surfaces to be
patched and the exposed reinforcing steel to
Item 519, Patching Concrete Structures, As be abrasively cleaned within 24 hours of
Per Plan, should be used where the repair application of patching material(or erection of
depth is 3 inches [75 mm] or greater and the forms if the forms would render the area
surface can be readily formed and concrete inaccessible to blasting). See the note in
placed. This type of patch is the most durable Section 600 of this Manual.
due to its depth and the utilization of
reinforcing bars to tie it together. Where Trowelable mortar should generally be
extensive curb repair is encountered, the specified when the repair depth is less than 1
patching should be paid for on a lineal foot inches [40 mm] deep, and the repair area is
[lineal meter] basis. This will require an Item less than 150 square feet [15 m2]. Trowelable
Special, Patching Concrete Structure, mortar should also be specified in lieu of
misc.:.......... pay item. A plan note will be pneumatically placed mortar for the case
required describing the work and tying it to where the depth of patch is equal to or less
CMS Item 519. than 3 inches [75 mm] and the quantity is less
than 150 square feet [15 m2]. 3 inches [75
Pneumatically placed mortar should generally mm] is the maximum depth of patch that
be used where the repair surface cannot be should be attempted with this type of mortar.
readily formed and concrete placed, where the
depth of repair is between 1 and 6 inches [25 A pay item, Item Special Patching Concrete
and 150 mm], and where at least 150 square Structures with Trowelable Mortar should be
feet [15 m2] of repair area is involved. used and reference should be made to a
proposal note.
For quantities of 150 to 350 square feet
[15 to 35 m2]: Item 520, Pneumatically The designer shall outline the areas to be
Placed Mortar, As Per Plan should be repaired on the structure and also show where
used. these areas are on details in the plans.

4-7
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

403.3 CRACK REPAIR 2. 1 inches [32 mm] minimum latex


modified concrete (LMC) per
Supplemental Specification 847 or 848.
Cracks can be repaired by epoxy injection for
which a proposal note is available. 3. 1 inches [45 mm] minimum
superplasticized dense concrete (SDC)
Location of the cracks shall be shown in the per Supplemental Specification 847 or
plans and marked in the field. 848.

4. inch [6 mm] Epoxy Waterproofing


404 BRIDGE DECK REPAIR Overlay for Bridge Decks are not
normally recommended except for in the
case where a concrete overlay would
404.1 OVERLAYS ON AN sufficiently lower the bridges load
OVERLAY rating. A proposal note is available.

Be aware that the minimum overlay


In no case should a new asphalt or concrete
thicknesses indicated provide the maximum
overlay be placed over an already present
protection against chloride penetration.
overlay on a bridge deck. Removal of any
Increased thicknesses do not proportionally
existing overlay is required before a new
increase protection. Minimum thicknesses
overlay is placed.
should be used if at all possible. The
maximum thickness should be limited to 2
inches [65 mm].
404.2 OVERLAYS
Overlays are not intended to be used for grade
adjustments.
The following types of overlays may be used
in the repair of an existing reinforced concrete
Overlays shall not be used on new decks.
deck:
A deck condition survey shall be performed in
accordance with Section 412 of this Manual.
1. 1 inches [32 mm] minimum micro-
This survey is required for all overlay projects
silica modified concrete (MSC) per
in order to determine reasonably accurate
either Supplemental Specification 847
variable thickness quantities.
or 848. Micro-silica is state of the art
and is recommended because it provides
greater permeability resistance than the Hydrodemolition is a recommended option for
same thickness of other types of overlay projects where uniform removal depth across
materials. an entire bridge deck is required. It is
recommended that hydrodemolition be

4-8
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

specified for any bridge overlay project where applicable portions of Section 300 of this
the total square yardage {square meters] of the Manual.
bridge decks to be overlayed is 500 square
yards [400 square meters] or greater. The Superelevated deck sections (existing and
normal depth of uniform removal of the new) may need temporary modifications to the
original deck concrete called for shall be 1 slope of the deck and/or shoulder in order to
inch [25 mm]. Plan removal depths should accommodate the traffic from the phase
not be set up to go below the top mat of deck construction. The designer is to make this
reinforcing. determination during the preliminary design
phase and add additional details and/or notes
as necessary. Structural members may require
404.3 UNDER DECK REPAIR additional structural analysis to insure their
adequacy and that no damage to the member
will occur.
For under deck spalls up to 1 inch [25 mm]
deep use trowelable mortar (a proposal note is On all deck replacement projects, the
available). For more severe underside elevations of the bottom of the beam shall be
deterioration, full depth repairs or Item 519 field determined so that when the deck is built
will be necessary. No spalls over traffic or to the new plan profile grade, it will be
other safety sensitive areas should be patched possible to obtain the required minimum deck
because potential debonding of the patch thickness. Elevations shall be taken at the
creates a hazard to the public. In these areas, beam seats and in the interior portions of the
remove loose concrete and provide a concrete spans. This is a design consideration and is
sealer. not something which should be left for the
contractor to deal with after a contract has
Low pressure epoxy injection has also been been awarded.
tried as a remedy for delaminations detected in
the bottom portion of the deck. However,
there are no indications of how well this 405.1 ELIMINATION OF LONGITU-
method of repair works and its usage should DINAL DECK JOINT
be scrutinized.

For bridges up to 90 feet [27 meters] in width,


405 BRIDGE DECK consideration should be given to eliminating
REPLACEMENT the longitudinal deck joint if one exists.
However if the existing bearings are rockers
and bolsters, they may need to be replaced
Notes similar to those found in Section 600 of with elastomeric bearings since the transverse
this Manual should be provided for deck movement due to temperature changes will be
removal in order to prevent damage to increased. Rockers and bolsters were designed
existing steel stringers. Refer also to the to move in a longitudinal direction only.

4-9
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

An alternate to the cost of replacing all 405.3 CLOSURE POUR


bearings in a structure is to increase the fit-up
clearance or lateral play between the head of
the rocker and its cap. One method (option) to A closure pour may not be necessary for
consider is to provide a new rocker cap which replacement of a deck on existing stringers
has an increased transverse width which is even when using stage construction since
able to accommodate the new, increased differential deflections will be resisted by the
anticipated transverse movements. This existing cross frames.
revision of the standard rocker bearing allows
some additional lateral movement before the If a deck replacement project also includes an
rocker head contacts the cap's welded side integral or semi-integral retro-fit at the
plate. abutments a closure pour may be required.
New concrete abutment diaphragms without a
closure pour at the stage line, will not allow
405.2 DECK HAUNCH the unloaded existing beams to freely deflect
during the deck replacement pour.

If possible, a 2 inch [50 mm] haunch depth When stage construction is used the single
should be provided over the stringers unless longitudinal construction joint shall be sealed
this haunch would cause undue problems with with High Molecular Weight Methacrylate
the profile grade off the bridge. (HMWM) resin.

It is sometimes necessary to raise the profile For additional information and requirements
grade of a structure. One way to accomplish regarding closure pours, regardless of
this change when replacing the deck is by superstructure type, refer to Section 409.1.
using deep haunches. The maximum
recommended haunch depth is 12 inches [300
mm]. Provide reinforcing steel in any haunch
405.4 CONCRETE PLACEMENT
greater than 5 inches [125 mm]. A deep
SEQUENCE
haunch (5 inches [125 mm] or more) shall be
made by providing a haunch similar to the one
illustrated in the Figures portion of Section
405.4.1 STANDARD BRIDGES
300 with the horizontal haunch width limited
to 9 inches [225 mm] on either side of the
flange.
Placement sequences are not generally
detailed for standard steel beam or girder
bridges but are left to the contractor. However,
the designer should recognize the need for a
pour sequence is not limited to long structures
with intermediate expansion devices. Other

4-10
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

possible structure types are bridges with end The most unsatisfactory sequence is to first
spans less than 70 percent of internal spans place concrete in the span contiguous with the
and two span structures where uplift is a short cantilever, especially if concrete is first
concern, structures whose size eliminates one placed in half of the span immediately
continuous pour, etc. adjoining the short cantilever. This sequence
produces the maximum angle change between
the joint elements.
405.4.2 STRUCTURES WITH
INTERMEDIATE HINGES Refer also to Figure 404 for additional
information.

Long multiple span steel beam and girder Where controlled deck placement sequence
bridges have, in the past, been subdivided into alone will not provide adequate protection
units by means of intermediate expansion against damage to the joint, provision should
joints, located at points of contraflexure, in be made for attaching part or all of the joint to
order to keep expansion and contraction the main structural elements after the major
within the capacities of bearing devices and portion of the concrete is placed. Another
expansion joints. The hinged structure is more alternative is to have a separate deck pour of
sensitive to placement of deck slab concrete approximately 36 inches [915 mm], or of a
than a fully continuous structure. This width necessary to accommodate the joint and
sensitivity requires that the sequence of deck its proper placement/installation and
concrete placement be carefully planned alignment, at the joints location to allow for
because (1) the configuration of most installation of the joint after the rest of the
intermediate joints makes them susceptible to deck has been placed.
damage if the deck placement sequence results
in large angle changes between the articulated
elements of the joints, and (2) the develop- 406 EXPANSION JOINT
ment of composite action in previously placed RETROFIT
spans may cause deflections to vary from
design deflections and result in a rough
profile. While it is desirable to seal the expansion
joint of bridges, it is not desirable to demolish
Plans should show the placement sequence, a functional expansion joint and possibly a
but should allow the contractor the option of backwall simply for the purpose of installing
a different sequence, subject to the approval of a seal. As long as a severe corrosion problem
the Director. Generally, concrete should be does not exist, additional coating will preserve
placed on the long cantilever before concrete the components exposed to the expansion
is placed on the short cantilever, particularly joint discharge until the deck is replaced.
before placement in the span contiguous with However, it must in fact be established that a
the short cantilever. severe problem does not exist if coating is the
chosen course of action.

4-11
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

On overlay projects, when practical, a retrofit sure that all items of work are described and
similar to that shown on Figures 405 and 406 included somewhere for payment.
can be used. The purpose of the steel bars in
Figures 405 and 406 is to eliminate thin layers Many designers consider the detailing of these
of concrete over the existing steel. These thin joints to be of secondary importance and
concrete layers would not adhere well to the merely a nuisance. However improper
steel and would break off in a short period of detailing of these joints has frequently caused
time. There have been some reports of project delays and caused numerous problems.
problems with the field installation of the strip The joints are important to the longevity of the
seals and with the physical operation of the structure or they would not be included in the
seal. The designer will need to ensure that work. Designers must take care to ensure that
there are sufficient clearances for the they are designed and detailed in a
installation and the proper operation of the professional manner.
seal. In lieu of using all field assembly and
field welding, the designer has the option of On projects involving stage construction,
using a combination of partial shop fabrication joints in the seal armor must be located and
with the remainder of the expansion joint shown in the plans. A complete penetration
being assembled and welded in the field. An butt weld should be provided at the armor
alternative is the use of the Polymer Modified joints and a partial penetration butt weld
Asphalt Expansion Joint System as discussed should be provided around the outer periphery
in Section 300 of this Manual. This joint is of the abutting surfaces of the retainer (not in
limited in movement to 1 inches [40 mm]. the area in contact with the gland). The gland
should be continuous and installed in one
Note that the designer will have to investigate piece. Consideration should be given to the
the existing joint on the particular structure(s) means of performing this one piece
and develop details for carrying the retrofit installation.
past the gutter line and into the sidewalk or
parapet. Details must show any existing On more extensive projects, where the deck is
concrete to be removed, how to attach new being replaced, consider using the semi-
steel armor to existing steel, how to attach integral design shown on Figures 407 and 408.
new steel to concrete, how to attach retainers, There are many variations to this solution and
dimensions, any new concrete, reinforcing Figures 407 and 408 are presented only as a
steel requirements, material requirements and general guide. This type of design can be used
coating requirements. In general views from for bridges whose foundations are stable and
the centerline of the joint looking toward the fixed (for example on two rows of piles). It is
deck and the backwall, a plan view and not to be used when the foundation consists of
section views are required. If the roadway a single row of piles. The semi-integral design
width is being increased due to removal of a is appropriate for bridge expansion lengths up
safety curb and upgrading to the deflector to 250 feet [80 meters] (400 feet [125 meters]
shape, a detail of the horizontal extension of total length assuming 2/3 movement in one
the end dam steel must be provided. Make direction). Additional considerations are that

4-12
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

the geometry and layout of the approach slab, [100 mm] or less. If the structure is raised
wingwalls, curbs, sidewalks, utilities and more than 4 inches [100 mm], the bridge seat
transition parapets must be compatible with should be raised for its entire length by adding
(not restrain) the anticipated longitudinal a reinforced concrete cap.
movement. For example approach slabs would
have to move independently of turned back
wings since the superstructure and approach 408 BRIDGE DRAINAGE
slab move together. If the approach slab were
connected to turned back wings in any
manner, then movement of the entire Much damage has occurred on bridges as a
superstructure would be restricted. Also refer result of poorly designed drainage. The
to Section 200 of this Manual for further principles stated in Section 200 and 300,
discussion. which cover drainage design for new
structures, apply to rehab work also. Proper
Type A pressure relief joints shall be specified drainage is extremely important to the
when the approach roadway pavement is rigid longevity of the structure. All dysfunctional
concrete and shall be placed at the end of the drainage systems should be retrofitted.
approach slab. See Section 200 of this Consequently, the designer must give
Manual for further discussion. adequate attention to the development and
presentation of correct details for this
important function.
407 RAISING AND JACKING
BRIDGES If it is found that existing scuppers are not
necessary, and the deck is not being replaced,
they should be plugged. If the scuppers are
Thought must be given to any required jacking plugged, the additional drainage directed off
procedure and constraints. The bridge must be the bridge must be collected.
raised uniformly in a transverse direction in
order to avoid inducing stresses into the super- If the deck is being replaced, the scuppers
structure. Differential movement between should be removed and the welds ground
stringers shall be limited to inch [6 mm]. smooth.
Similarly, consideration must be given to the
stresses induced into the structure by raising Existing functional scuppers may need to be
the bridge at one substructure unit with extended so that they are 8 inches [200 mm]
respect to another. Limitations on the below the bottom flange. Check to see if the
differential raising between units may be bottoms are rusted through before preparing
necessary if stresses are found to be excessive. the scupper extension detail.

When raising a structure, the adjustment in


beam seat elevations shall be accomplished by
steel shims if the amount raised is 4 inches

4-13
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

409 WIDENING For widenings (2 beams or more) where the


decks phase line is not between the new and
existing superstructure members, Figure 409-
409.1 CLOSURE POUR C, a closure pour will still be required.
Existing cross frames (designated C1in Figure
409-C) under the closure pour location need
No single rule is applicable for closure pours to be released before the phase 1 deck removal
on a widening project. The flexibility of each begins. Cross frames between new and
member, the overall theoretical deflection and existing members should be installed before
use of integral or semi-integral abutments will the phase 2 pour. Re-install the released
cause each project to be unique. The purpose crossframes after the phase 2 pour but before
of the closure pour is to accommodate the the phase 3 pour. Rebar splices should occur
differences in deflection which can occur within the closure section. The width of the
between the new and the old during closure section should be at least 30 inches
construction. [800 mm].

For widenings where the existing deck is For widenings (2 beams or more) where a new
removed and a new or wider, deck is being deck is being constructed but the phase line is
placed, with no superstructure members between existing superstructure members and
added, no closure pour is necessary. See at least 3 bays away from new member
Figure 409-A. locations, Figure 409-D, a closure pour is still
required. The procedure for crossframe
For widenings (2 beams or more) where either release should be the same as defined in the
the existing deck is to remain or the phase line paragraph above. The closure pour may be
of a new deck will be between the existing eliminated for this condition if the designer
and new superstructure, a closure pour should can show that the outside existing member,
be provided. Cross frames (designated B1 in now being attached to the new member, is not
Figure 409-B) in the bay between the new and restrained from returning to its original
existing superstructure should not be welded unloaded position by the new cross frames
until after the phase 1 and 2 new deck portions (designated D1in Figure 409-D).
have been placed. After the cross frames have
been welded, the closure section, phase 3, can Closure pours may be eliminated if the
be completed. Rebar splices should occur differential deflection is expected to be less
within the closure section. The width of the than inch [6 mm], regardless of
closure section should be at least 30 inches superstructure type.
[800 mm]. See Figure 409-B.

4-14
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

In special cases, the minimum closure section 409.3 FOUNDATIONS


width may be reduced by the use of
mechanical connectors as discussed in
Sections 200 and 300 of this Manual. The Differential foundation settlements must be
designer should not blindly apply this considered. For example, if it is required to
exception since the use of lap splices is widen a bridge adjacent to an existing spread
preferred and recommended. footing, it is possible that the existing foun-
dation has settled as much as it is going to.
Longitudinal construction joints should be However, if the widened portion is placed on
treated with a high molecular weight a new spread footing, then that portion will
methacrylate (HMWM) sealer. See the settle with respect to the original and distress
discussion in Section 300 for additional to the structure will result. Consequently, the
information. new portion should be placed on piling or
drilled shafts in an attempt to limit differential
settlement.
Falsework for the new slab should be
independent and not be tied to the original
superstructure. This would not apply to Substructure foundations need to be
falsework for the closure section. See Section investigated for scour. The investigation
405.3 for closure pour requirements for deck consists of determining what the substructures
replacements. The release of falsework for are founded on; how deep the foundation is;
reinforced concrete slab superstructures may and a decision on whether potential scour will
need to be coordinated (i.e. specified in the endanger the substructures integrity. Local
plans) between phases in certain situations. scour and stream meander need to be
considered.
Closure pours on bridge structures with
integral or semi-integral abutments shall
include the abutments diaphragm concrete. 409.4 CONCRETE SLAB BRIDGES
Any concrete pier diaphragm shall also be
included in the closure pour.
For single span slab bridges where stage
construction is provided, all bridges should be
screened to determine whether the main
409.2 SUPERSTRUCTURE
reinforcement is parallel to the centerline of
DEFLECTIONS
the roadway or is perpendicular to the
abutment.
The widened section should be designed so
that superstructure deflections for the new and
old portions are similar.

4-15
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

Early standard drawings called for the main the pier type is cap and column. Individual
reinforcement to be placed perpendicular to free standing columns are not permitted.
the abutments when the skew angle became
larger than a certain value. This angle was re- When the existing piers are either T-type or
vised over the years as new standard drawings wall-type piers, the designer should evaluate
were introduced. whether the new individual column should be
tied back into the existing substructure unit or
Concrete slab bridges should be screened remain free standing. Two or more adjacent
according to the following criteria: free standing individual columns without a
cap are not permitted.
Prior to 1931 the slab bridge standard drawing
required the main reinforcement to be placed
perpendicular to the abutments when the skew 410 RAILING
angle was equal to or greater than 20 degrees.
This angle was revised to 25 degrees in 1931,
30 degrees in 1933 and finally 35 degrees in Railing not meeting current standards will
1946. The standard drawing in 1973 required require upgrading when that structure is
the main reinforcement to be parallel with the included in a construction project as defined
centerline of roadway regardless of the skew in Section 300 of this Manual.
angle.
There are several methods for upgrading
If the skew angle of the bridge is equal to or existing parapets to the deflector shape.
greater than the angles listed above for the
year built, a temporary longitudinal bent will
have to be designed to support the slab where 410.1 FACING
it is cut. For example a bridge built in 1938
with a 25 degree skew does not require a bent,
however a bridge built in 1928 with a 25 This method works when the existing parapet
degree skew does require a bent to be is in relatively good condition. The existing
designed. parapet and safety curb can be partially
removed and a facing section placed on top as
The deck should be inspected in the field to shown in Figure 410. Dowels should be at
make a visual verification of the reinforcing least 6 inches [150 mm] deep and should be
steel direction. spaced at no more than 15 inches [400 mm]
c/c. Grout should be epoxy grout per CMS
705.20. It will be necessary to call for epoxy
409.5 PIER COLUMNS grout as other materials are also covered in
these specifications. Details showing removal
of existing concrete, dimensions for placement
New pier columns added for the purpose of of new concrete, treatment of the parapet at
widening shall be tied into the existing pier if the expansion joint (coordinate with details

4-16
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

required and described under Expansion Joint 411 BEARINGS


Retrofit), parapet transition details, typical
sections, joint spacing, reinforcing steel, limits
for purpose of measurement and payment, and Notes may be provided to rehabilitate the
what pay item the work is to be included with bearings if that is the chosen course of action.
are also required. It is customary to split the jacking of the
superstructure into one pay item (see Section
A typical note can be found in Section 600 of 407 of this Manual) and the actual bearing
this Manual. Be aware that this note is general restoration work into another. The contractor
and must be modified as needed for specific should be given the option of totally replacing
applications. the bearings with like bearings in lieu of
rehabilitating the existing.

410.2 REMOVAL FLUSH WITH If elastomeric bearings are used at abutments


THE TOP OF THE DECK where the existing expansion joint is built
according to Standard Bridge Drawing SD-1-
69, the joint must be modified. The retired
If the outside of the existing parapet is in bad Standard Bridge Drawing SD-1-69 end dam
enough condition, the parapet and curb can be consists of an angle, attached to the
sawn off and a new parapet installed. Dowels superstructure, which angle overlaps the
should be at least 6 inches [150 mm] deep and abutment backwall. If compressible type
should be spaced at no more than 15 inches bearings are used with this arrangement, the
[400 mm] c/c. The basis for this depth and reaction will be transferred to the end dam
spacing is research report FHWA-CA-TL-79- angle causing distress to the end of the deck.
16 prepared by CalTrans in June of 1979
where they performed crash testing of various All bearings at an individual substructure unit
railing sections with shallow rebar anchorage. shall be the same type. The bearings at any
Grout should be epoxy per CMS 705.20. It one substructure unit shall be compatible with
will be necessary to call for epoxy grout as all the bearings at the other substructure units.
other materials are also covered in these
specifications.
When rehabilitation of existing bearings is
being considered, the designer should make a
410.3 THRIE BEAM RETROFIT cost comparison between rehabilitating the
existing bearings and replacing them with all
new bearings and any additional costs
If it is determined that upgrading of the associated with modifying the existing
parapet to the deflector shape is not prudent, structure to accommodate the new bearings.
there is a standard bridge drawing available For new bearings, preference should be given
that can be applied. to using elastomeric bearings. See Section

4-17
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

300 of this Manual for additional guidance. those areas. A description of the core results
The cost comparison is to be submitted shall accompany the deck condition survey
(included) as part of the Preliminary Design report.
Submission package.
See Figure 411 for an example of the survey
report form.
412 CONCRETE BRIDGE DECK
REPAIR QUANTITY A sketched plan of the deck area, both top
ESTIMATING surface and underside, shall be included with
the bridge deck condition survey. The
unsound areas should be plotted on the sketch
A deck condition survey shall be conducted indicating the approximate dimensions which
and a report prepared for each existing were used to estimate the percentage of total
concrete deck. The survey shall be performed unsound deck area.
as near as practicable to the plan preparation
stage and shall be completed before beginning The minimum number of cores to be taken for
detail design work for the deck rehabilitation a bare concrete deck shall be determined by
since it is to be used as a design tool toward the following criteria:
that end. If the survey will be two winters or
more old at the scheduled time of sale, a new ! A minimum of two (2) per bridge for
survey shall be performed. The new survey bridges with a deck area less than 2500
will include recoring of the deck as deemed square feet [225 square meters].
necessary.
! A minimum of three (3) per bridge for
The top surface of bare concrete decks shall bridges with a deck area between 2500 to
be both visually inspected and sounded for 5000 square feet [225 to 450 square
obvious signs of deterioration. The top meters].
surface of decks with an asphalt overlay shall
be visually inspected for signs of obvious and ! A minimum of four (4) per bridge for
suspected deterioration. bridges with a deck area between 5000 to
10,000 square feet [450 to 900 square
The underside of all decks shall be inspected. meters] with one additional core for each
Where there are indications of delamination, additional 10,000 square feet [900 square
water intrusion, discoloration, spalls, meters] or part thereof.
efflorescence or other signs of distress, the
underside shall be sounded. The decks shall For bridge decks with an asphalt overlay the
then be cored in suspicious areas to verify and minimum number of cores listed above is
further define areas of unsoundness. If it is required but it is further recommended that
suspected that full depth repair may be additional cores be taken due to the variability
required, cores shall be taken full depth or at of unknowns hidden under the overlay.
least to the bottom mat of reinforcing steel in

4-18
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

Core locations shall be determined from 412.1 SPECIAL REQUIREMENTS


conditions detected primarily from the bottom FOR QUANTITY
side of the deck, however, the top surface may ESTIMATING FOR BRIDGES
also indicate areas to be cored. At least one 500 FEET [150 m] OR
core shall be taken from an apparently sound GREATER IN LENGTH
area and the others from questionable areas for
comparison.
In addition to the requirements of Section 412
The cores shall be submitted to the District above, additional requirements are added for
Bridge Engineer with proper identification. structures with a length of greater than 500
They shall be retained for a minimum period feet [150 meters].
of six months following the award of the
actual construction contract. An electrical potential survey shall be
performed. The area of active corrosion shall
Cores shall be inspected for: be compared with the delaminated area to
determine a more accurate repair area.
! Obvious crumbling
! Stratification or delamination zones Consideration should be given to engaging a
! Soundness of aggregate company or agency specializing in bridge
! Depth and condition of reinforcing steel deck condition surveys which include
thermographic acoustic and radar techniques,
A description of the core results shall electromagnetic sounding and nuclear
accompany the deck condition survey report. magnetic resonance.

An estimate of the unsound deck area as a Deck cores shall be analyzed for chloride
percentage of total deck area shall be made content.
from all of the information gathered from the
survey and testing. It should be noted that active corrosion is
assumed to be taking place if a chloride ion
content greater than 2.0 lbs. per cubic yard
[1.2 kg/m3] is present and/or if there is an
observed rebar electrical potential reading of
greater than -0.35 volts compared to a copper-
copper sulfate reference half cell.

It is not the intent to remove chloride


contaminated or electrically active concrete
but rather the results of the chloride ion
content tests are to be used as a support tool
for determining the type and extent of
rehabilitation to be recommended.

4-19
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

412.2 ACTUAL QUANTITIES, concrete area is 50% to 60% of the total deck
ESTIMATING FACTORS area. Therefore, unless there are overriding
circumstances, the decks shall be replaced
rather than rehabilitated when this area equals
The following table gives estimating factors. or exceeds 60% of the total deck area.
The estimating factors are related on a sliding
scale in order to project the quantities based Do not include a pay item for full depth repair
upon measured areas to plan quantities 6 to 9 when such work is not indicated. The unit
months beyond the actual date of the deck price established by this practice is worthless.
condition survey, including one winter.
For any overlay project establishing accurate
quantities are difficult. The difficulty is only
Measured % Estimating Project %
Unsound Area Factor Plan Area increased if the bridge has an existing
asphaltic or rigid concrete overlay. As
0-10 0-3 30 asphaltic concrete overlays do not allow
15 2.33 35 conventional sounding methods, additional
20 2 40 coring and/or evaluation methods listed in
Section 412.1 are recommended.
25 1.9 47.5
30 1.87 55 Required removal thicknesses of existing
35 1.79 62.5 overlays should be established by coring of
40 1.69 67.5 the deck to establish the true thickness of the
existing overlay. Do not use the original
45 1.56 70 design plans specified overlay thickness.
50 1.50 75
60 1.33 80 Variable thickness quantities should be
70 1.21 85 established based on unsound areas of deck
and assuming a depth to the bottom of the top
80 1.09 87.5 layer of reinforcing steel + inch [19 mm].
90 1.00 90 Coring should be used to verify delamination
depth.

The plan quantity must be increased by a Hand chipping bid items for overlay projects
factor of 15% when the survey is one winter requiring hydrodemolition removal are
old. associated with variable thickness quantities.
Using 10% of the variable thickness surface
Life cycle cost comparisons indicate that the area for quantities is one alternative, but other
benefits derived from replacement versus methods may be acceptable. Take note that
rehabilitation are approximately equal when this percentage is based on the variable
the amount of unsound and delaminated
thickness surface area and not the entire deck

4-20
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000

surface area. Another method would be to get 413 REFERENCES


local experience from the District
Maintenance and Construction personnel as to
what percentage would be best to use. A 1. FHWA-RD-78-133, "Extending the
separate hand chipping bid item is not Service Life of Existing Bridges by
required if the method of removal is Increasing Their Load Carrying
mechanical scarification as this is included in Capacity," 1978
the overlay variable thickness quantity.
2. NCHRP Report 206, "Detection and
Accurate records of actual quantities shall be Repair of Fatigue Damage in Welded
maintained for each bridge. Highway Bridges," 1978

3. NCHRP Report 222, "Bridges on


It is recommended that the Districts review
Secondary Highways and Local Roads --
any criteria for selecting rehabilitation and
Rehabilitation and Replacement," 1980
replacement projects with the Offices of
Maintenance Administration and Structural
4. NCHRP Project 12-17 Final Report,
Engineering to help assure state wide
"Evaluation of Repair Techniques for
consistency on rehabilitation or replacement
Damaged Steel Bridge Members: Phase
deck projects.
l," 1981
It should be noted that in all cases,
5. NCHRP Report 243, Rehabilitation and
maintaining the structural integrity of the
Replacement of Bridges on Secondary
structure is of prime importance. The effects
Highways and Local Roads," 1981
of exposing large areas of the top mat of
reinforcing in areas such as cantilevered
6. NCHRP Report 271, "Guidelines for
parapets, negative moment reinforcing over
Evaluation and Repair of Damaged Steel
beams on stringer bridges and over piers on
Bridge Members," 1984
continuous slab bridges and in other areas of
a critical nature must be clearly understood
7. NCHRP Report 293, "Methods of
from a design standpoint.
Strengthening Existing Highway
Bridges," 1987

8. NCHRP Report 333, "Guidelines for


Evaluating Corrosion Effects in Existing
Steel Bridges,"1990

9. Park, Sung H., "Bridge Rehabilitation


and Replacement (Bridge Repair Prac-
tice)," S. H. Park, P.O. Box 7474,
Trenton, N.J., 08628- 0474, 1984

4-21

Das könnte Ihnen auch gefallen