Beruflich Dokumente
Kultur Dokumente
4-1
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
that the designer is still responsible for responsible for describing the welding
making a conscientious effort to provide procedures, non destructive testing (NDT)
accurate information based on field requirements, etc. in plan notes.
observations.
Welding is permitted in compression zones
Sketches of various details have been provided the designer ensures that the
provided throughout this chapter. These chemistry of the existing steel is such that it
sketches are not complete nor are they to be can be welded. This will require either review
taken as standard details. They are offered as of old mill certifications or actual sampling of
suggestions or ideas for the designer to use in the material for chemical analysis. This
developing his or her own solutions to the determination must be made by the designer.
unique problems they encounter. Pay close attention to American Welding
Society (AWS) Specifications. Field NDT of
A bibliography has been included at the end of the welds will be required and it will be
this section. While these references contain necessary to specify the type and location of
much information and many innovative ideas, the NDT in the plans.
designers are advised to discuss untested solu-
tions with the Office of Structural Engineering
before completing detail plans. 402.2 FATIGUE ANALYSIS
4-2
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
Method A AASHTO Guide Specifications Moments and stress ranges at each detail
for Fatigue Evaluation of Existing and location being evaluated.
Steel Bridges
A list of assumptions and input values used
A table showing: for each detail and location being evaluated
including:
Remaining safe and mean fatigue life
Live load distribution factor, axle; (S (in
Moments and stress ranges at each detail feet)/7.0 ft) [(S (in mm)/2134 mm)]
and location being evaluated.
Fatigue vehicle used (HS20-44) [(MS18)]
A list of assumptions and input values used
for each detail and location being evaluated Section properties at the detail and
including: location and a narrative stating whether
those section properties are composite or
Live load distribution factor non-composite.
4-3
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
402.3.2 BOX GIRDER PIER CAPS In analyzing the strength of existing members
which are to receive a new deck, a future
wearing surface of 60 psf [2.87 kPa] shall be
Often box girders were constructed using non- included in the dead load.
continuous back-up bars which were stitch
welded in place. The discontinuity in the
back-up bar is of major concern since it acts 402.5 STRENGTHENING OF
like a crack in the member and is the source of STRUCTURAL STEEL
crack propagation into the flange or web. One MEMBERS
possible solution is to drill a horizontal hole
through the web and back-up bar at the points
of discontinuity. See Figure 401 for a sample Welded stud shear connectors shall be
detail. The stitch welds may or may not be a installed full length on all steel beam or girder
problem depending on the stress ranges at bridges in which the deck is being removed
their location. and replaced. The stud spacing shall be
designed in accordance with AASHTO
Section 10.38.5.
402.3.3 MISCELLANEOUS FATIGUE
RETROFITS Bolted cover plates in tension zones or field
welded cover plates in compression zones can
be used to increase strength. Field welding is
Various retrofits have been used for fatigue to be performed in strict compliance with
prone details such as small web gaps which AWS Specifications. Field NDT of the welds
result in stress concentration and subsequent will be required and it will be necessary to
4-4
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
specify the type and location of testing in the "Trimming of Beam Ends" for payment. Pay
plans. Also, practicality of field welding must attention to the clearance to the end cross
be evaluated. Overhead welding is not frames and detail their removal and
practical. replacement if necessary.
Consider jacking the stringers to relieve In lieu of trimming the beam ends, consider
stresses prior to installing cover plates. In this modifying the backwall if backwall removal
manner the cover plates will carry dead load and replacement is being performed as part of
and live load stresses. If the plates are the work. Modifying the backwall would be a
installed without relieving the stresses, they viable option if it were necessary to remove
will carry live load only. This is merely a and replace the end cross frames as a result of
suggestion as to how extra strength might be trimming the beam ends. Another option to
obtained if it is needed. consider is converting the existing abutment
into a semi-integral abutment as discussed in
Other methods of increasing the strength are Section 406.
to attach angles or structural shapes to the web
or flanges. The possibilities are numerous and
must be left to the ingenuity of the designer. 402.7 HEAT STRAIGHTENING
However, the designer must remember to pay
strict attention to practicality as well as
strength and fatigue requirements. Review Beams or girders that have been struck by
unusual details with the Office of Structural trucks or bent by other causes can often be
Engineering before proceeding. repaired by heat straightening only, or in
combination with field welding to install new
When retrofitting or repairing truss members, sections for the damaged steel member
the designer must remember to provide for portions. An assessment by the District Bridge
temporary support where needed. Many truss Engineer or other ODOT representative with
members are non-redundant, and their experience in heat straightening must be made
removal could result in the collapse of the as to the practicality of this type of repair
structure. before proceeding. If heat straightening is
deemed to be practical, a proposal note is
available which describes and controls the
402.6 TRIMMING BEAM ENDS operation. Plan requirements are to provide a
pay quantity and a detail showing the location
of the repair.
Trimming of beam ends is sometimes
necessary due to tilting of the abutment and
closure of the end dam. A detail (plan and
elevation view) showing where the beam is to
be cut is required. Also provide pertinent
notes and include the work with Item 513/863
4-5
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
4-6
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
4-7
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
4-8
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
specified for any bridge overlay project where applicable portions of Section 300 of this
the total square yardage {square meters] of the Manual.
bridge decks to be overlayed is 500 square
yards [400 square meters] or greater. The Superelevated deck sections (existing and
normal depth of uniform removal of the new) may need temporary modifications to the
original deck concrete called for shall be 1 slope of the deck and/or shoulder in order to
inch [25 mm]. Plan removal depths should accommodate the traffic from the phase
not be set up to go below the top mat of deck construction. The designer is to make this
reinforcing. determination during the preliminary design
phase and add additional details and/or notes
as necessary. Structural members may require
404.3 UNDER DECK REPAIR additional structural analysis to insure their
adequacy and that no damage to the member
will occur.
For under deck spalls up to 1 inch [25 mm]
deep use trowelable mortar (a proposal note is On all deck replacement projects, the
available). For more severe underside elevations of the bottom of the beam shall be
deterioration, full depth repairs or Item 519 field determined so that when the deck is built
will be necessary. No spalls over traffic or to the new plan profile grade, it will be
other safety sensitive areas should be patched possible to obtain the required minimum deck
because potential debonding of the patch thickness. Elevations shall be taken at the
creates a hazard to the public. In these areas, beam seats and in the interior portions of the
remove loose concrete and provide a concrete spans. This is a design consideration and is
sealer. not something which should be left for the
contractor to deal with after a contract has
Low pressure epoxy injection has also been been awarded.
tried as a remedy for delaminations detected in
the bottom portion of the deck. However,
there are no indications of how well this 405.1 ELIMINATION OF LONGITU-
method of repair works and its usage should DINAL DECK JOINT
be scrutinized.
4-9
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
If possible, a 2 inch [50 mm] haunch depth When stage construction is used the single
should be provided over the stringers unless longitudinal construction joint shall be sealed
this haunch would cause undue problems with with High Molecular Weight Methacrylate
the profile grade off the bridge. (HMWM) resin.
It is sometimes necessary to raise the profile For additional information and requirements
grade of a structure. One way to accomplish regarding closure pours, regardless of
this change when replacing the deck is by superstructure type, refer to Section 409.1.
using deep haunches. The maximum
recommended haunch depth is 12 inches [300
mm]. Provide reinforcing steel in any haunch
405.4 CONCRETE PLACEMENT
greater than 5 inches [125 mm]. A deep
SEQUENCE
haunch (5 inches [125 mm] or more) shall be
made by providing a haunch similar to the one
illustrated in the Figures portion of Section
405.4.1 STANDARD BRIDGES
300 with the horizontal haunch width limited
to 9 inches [225 mm] on either side of the
flange.
Placement sequences are not generally
detailed for standard steel beam or girder
bridges but are left to the contractor. However,
the designer should recognize the need for a
pour sequence is not limited to long structures
with intermediate expansion devices. Other
4-10
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
possible structure types are bridges with end The most unsatisfactory sequence is to first
spans less than 70 percent of internal spans place concrete in the span contiguous with the
and two span structures where uplift is a short cantilever, especially if concrete is first
concern, structures whose size eliminates one placed in half of the span immediately
continuous pour, etc. adjoining the short cantilever. This sequence
produces the maximum angle change between
the joint elements.
405.4.2 STRUCTURES WITH
INTERMEDIATE HINGES Refer also to Figure 404 for additional
information.
Long multiple span steel beam and girder Where controlled deck placement sequence
bridges have, in the past, been subdivided into alone will not provide adequate protection
units by means of intermediate expansion against damage to the joint, provision should
joints, located at points of contraflexure, in be made for attaching part or all of the joint to
order to keep expansion and contraction the main structural elements after the major
within the capacities of bearing devices and portion of the concrete is placed. Another
expansion joints. The hinged structure is more alternative is to have a separate deck pour of
sensitive to placement of deck slab concrete approximately 36 inches [915 mm], or of a
than a fully continuous structure. This width necessary to accommodate the joint and
sensitivity requires that the sequence of deck its proper placement/installation and
concrete placement be carefully planned alignment, at the joints location to allow for
because (1) the configuration of most installation of the joint after the rest of the
intermediate joints makes them susceptible to deck has been placed.
damage if the deck placement sequence results
in large angle changes between the articulated
elements of the joints, and (2) the develop- 406 EXPANSION JOINT
ment of composite action in previously placed RETROFIT
spans may cause deflections to vary from
design deflections and result in a rough
profile. While it is desirable to seal the expansion
joint of bridges, it is not desirable to demolish
Plans should show the placement sequence, a functional expansion joint and possibly a
but should allow the contractor the option of backwall simply for the purpose of installing
a different sequence, subject to the approval of a seal. As long as a severe corrosion problem
the Director. Generally, concrete should be does not exist, additional coating will preserve
placed on the long cantilever before concrete the components exposed to the expansion
is placed on the short cantilever, particularly joint discharge until the deck is replaced.
before placement in the span contiguous with However, it must in fact be established that a
the short cantilever. severe problem does not exist if coating is the
chosen course of action.
4-11
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
On overlay projects, when practical, a retrofit sure that all items of work are described and
similar to that shown on Figures 405 and 406 included somewhere for payment.
can be used. The purpose of the steel bars in
Figures 405 and 406 is to eliminate thin layers Many designers consider the detailing of these
of concrete over the existing steel. These thin joints to be of secondary importance and
concrete layers would not adhere well to the merely a nuisance. However improper
steel and would break off in a short period of detailing of these joints has frequently caused
time. There have been some reports of project delays and caused numerous problems.
problems with the field installation of the strip The joints are important to the longevity of the
seals and with the physical operation of the structure or they would not be included in the
seal. The designer will need to ensure that work. Designers must take care to ensure that
there are sufficient clearances for the they are designed and detailed in a
installation and the proper operation of the professional manner.
seal. In lieu of using all field assembly and
field welding, the designer has the option of On projects involving stage construction,
using a combination of partial shop fabrication joints in the seal armor must be located and
with the remainder of the expansion joint shown in the plans. A complete penetration
being assembled and welded in the field. An butt weld should be provided at the armor
alternative is the use of the Polymer Modified joints and a partial penetration butt weld
Asphalt Expansion Joint System as discussed should be provided around the outer periphery
in Section 300 of this Manual. This joint is of the abutting surfaces of the retainer (not in
limited in movement to 1 inches [40 mm]. the area in contact with the gland). The gland
should be continuous and installed in one
Note that the designer will have to investigate piece. Consideration should be given to the
the existing joint on the particular structure(s) means of performing this one piece
and develop details for carrying the retrofit installation.
past the gutter line and into the sidewalk or
parapet. Details must show any existing On more extensive projects, where the deck is
concrete to be removed, how to attach new being replaced, consider using the semi-
steel armor to existing steel, how to attach integral design shown on Figures 407 and 408.
new steel to concrete, how to attach retainers, There are many variations to this solution and
dimensions, any new concrete, reinforcing Figures 407 and 408 are presented only as a
steel requirements, material requirements and general guide. This type of design can be used
coating requirements. In general views from for bridges whose foundations are stable and
the centerline of the joint looking toward the fixed (for example on two rows of piles). It is
deck and the backwall, a plan view and not to be used when the foundation consists of
section views are required. If the roadway a single row of piles. The semi-integral design
width is being increased due to removal of a is appropriate for bridge expansion lengths up
safety curb and upgrading to the deflector to 250 feet [80 meters] (400 feet [125 meters]
shape, a detail of the horizontal extension of total length assuming 2/3 movement in one
the end dam steel must be provided. Make direction). Additional considerations are that
4-12
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
the geometry and layout of the approach slab, [100 mm] or less. If the structure is raised
wingwalls, curbs, sidewalks, utilities and more than 4 inches [100 mm], the bridge seat
transition parapets must be compatible with should be raised for its entire length by adding
(not restrain) the anticipated longitudinal a reinforced concrete cap.
movement. For example approach slabs would
have to move independently of turned back
wings since the superstructure and approach 408 BRIDGE DRAINAGE
slab move together. If the approach slab were
connected to turned back wings in any
manner, then movement of the entire Much damage has occurred on bridges as a
superstructure would be restricted. Also refer result of poorly designed drainage. The
to Section 200 of this Manual for further principles stated in Section 200 and 300,
discussion. which cover drainage design for new
structures, apply to rehab work also. Proper
Type A pressure relief joints shall be specified drainage is extremely important to the
when the approach roadway pavement is rigid longevity of the structure. All dysfunctional
concrete and shall be placed at the end of the drainage systems should be retrofitted.
approach slab. See Section 200 of this Consequently, the designer must give
Manual for further discussion. adequate attention to the development and
presentation of correct details for this
important function.
407 RAISING AND JACKING
BRIDGES If it is found that existing scuppers are not
necessary, and the deck is not being replaced,
they should be plugged. If the scuppers are
Thought must be given to any required jacking plugged, the additional drainage directed off
procedure and constraints. The bridge must be the bridge must be collected.
raised uniformly in a transverse direction in
order to avoid inducing stresses into the super- If the deck is being replaced, the scuppers
structure. Differential movement between should be removed and the welds ground
stringers shall be limited to inch [6 mm]. smooth.
Similarly, consideration must be given to the
stresses induced into the structure by raising Existing functional scuppers may need to be
the bridge at one substructure unit with extended so that they are 8 inches [200 mm]
respect to another. Limitations on the below the bottom flange. Check to see if the
differential raising between units may be bottoms are rusted through before preparing
necessary if stresses are found to be excessive. the scupper extension detail.
4-13
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
For widenings where the existing deck is For widenings (2 beams or more) where a new
removed and a new or wider, deck is being deck is being constructed but the phase line is
placed, with no superstructure members between existing superstructure members and
added, no closure pour is necessary. See at least 3 bays away from new member
Figure 409-A. locations, Figure 409-D, a closure pour is still
required. The procedure for crossframe
For widenings (2 beams or more) where either release should be the same as defined in the
the existing deck is to remain or the phase line paragraph above. The closure pour may be
of a new deck will be between the existing eliminated for this condition if the designer
and new superstructure, a closure pour should can show that the outside existing member,
be provided. Cross frames (designated B1 in now being attached to the new member, is not
Figure 409-B) in the bay between the new and restrained from returning to its original
existing superstructure should not be welded unloaded position by the new cross frames
until after the phase 1 and 2 new deck portions (designated D1in Figure 409-D).
have been placed. After the cross frames have
been welded, the closure section, phase 3, can Closure pours may be eliminated if the
be completed. Rebar splices should occur differential deflection is expected to be less
within the closure section. The width of the than inch [6 mm], regardless of
closure section should be at least 30 inches superstructure type.
[800 mm]. See Figure 409-B.
4-14
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
4-15
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
Early standard drawings called for the main the pier type is cap and column. Individual
reinforcement to be placed perpendicular to free standing columns are not permitted.
the abutments when the skew angle became
larger than a certain value. This angle was re- When the existing piers are either T-type or
vised over the years as new standard drawings wall-type piers, the designer should evaluate
were introduced. whether the new individual column should be
tied back into the existing substructure unit or
Concrete slab bridges should be screened remain free standing. Two or more adjacent
according to the following criteria: free standing individual columns without a
cap are not permitted.
Prior to 1931 the slab bridge standard drawing
required the main reinforcement to be placed
perpendicular to the abutments when the skew 410 RAILING
angle was equal to or greater than 20 degrees.
This angle was revised to 25 degrees in 1931,
30 degrees in 1933 and finally 35 degrees in Railing not meeting current standards will
1946. The standard drawing in 1973 required require upgrading when that structure is
the main reinforcement to be parallel with the included in a construction project as defined
centerline of roadway regardless of the skew in Section 300 of this Manual.
angle.
There are several methods for upgrading
If the skew angle of the bridge is equal to or existing parapets to the deflector shape.
greater than the angles listed above for the
year built, a temporary longitudinal bent will
have to be designed to support the slab where 410.1 FACING
it is cut. For example a bridge built in 1938
with a 25 degree skew does not require a bent,
however a bridge built in 1928 with a 25 This method works when the existing parapet
degree skew does require a bent to be is in relatively good condition. The existing
designed. parapet and safety curb can be partially
removed and a facing section placed on top as
The deck should be inspected in the field to shown in Figure 410. Dowels should be at
make a visual verification of the reinforcing least 6 inches [150 mm] deep and should be
steel direction. spaced at no more than 15 inches [400 mm]
c/c. Grout should be epoxy grout per CMS
705.20. It will be necessary to call for epoxy
409.5 PIER COLUMNS grout as other materials are also covered in
these specifications. Details showing removal
of existing concrete, dimensions for placement
New pier columns added for the purpose of of new concrete, treatment of the parapet at
widening shall be tied into the existing pier if the expansion joint (coordinate with details
4-16
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
4-17
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
300 of this Manual for additional guidance. those areas. A description of the core results
The cost comparison is to be submitted shall accompany the deck condition survey
(included) as part of the Preliminary Design report.
Submission package.
See Figure 411 for an example of the survey
report form.
412 CONCRETE BRIDGE DECK
REPAIR QUANTITY A sketched plan of the deck area, both top
ESTIMATING surface and underside, shall be included with
the bridge deck condition survey. The
unsound areas should be plotted on the sketch
A deck condition survey shall be conducted indicating the approximate dimensions which
and a report prepared for each existing were used to estimate the percentage of total
concrete deck. The survey shall be performed unsound deck area.
as near as practicable to the plan preparation
stage and shall be completed before beginning The minimum number of cores to be taken for
detail design work for the deck rehabilitation a bare concrete deck shall be determined by
since it is to be used as a design tool toward the following criteria:
that end. If the survey will be two winters or
more old at the scheduled time of sale, a new ! A minimum of two (2) per bridge for
survey shall be performed. The new survey bridges with a deck area less than 2500
will include recoring of the deck as deemed square feet [225 square meters].
necessary.
! A minimum of three (3) per bridge for
The top surface of bare concrete decks shall bridges with a deck area between 2500 to
be both visually inspected and sounded for 5000 square feet [225 to 450 square
obvious signs of deterioration. The top meters].
surface of decks with an asphalt overlay shall
be visually inspected for signs of obvious and ! A minimum of four (4) per bridge for
suspected deterioration. bridges with a deck area between 5000 to
10,000 square feet [450 to 900 square
The underside of all decks shall be inspected. meters] with one additional core for each
Where there are indications of delamination, additional 10,000 square feet [900 square
water intrusion, discoloration, spalls, meters] or part thereof.
efflorescence or other signs of distress, the
underside shall be sounded. The decks shall For bridge decks with an asphalt overlay the
then be cored in suspicious areas to verify and minimum number of cores listed above is
further define areas of unsoundness. If it is required but it is further recommended that
suspected that full depth repair may be additional cores be taken due to the variability
required, cores shall be taken full depth or at of unknowns hidden under the overlay.
least to the bottom mat of reinforcing steel in
4-18
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
An estimate of the unsound deck area as a Deck cores shall be analyzed for chloride
percentage of total deck area shall be made content.
from all of the information gathered from the
survey and testing. It should be noted that active corrosion is
assumed to be taking place if a chloride ion
content greater than 2.0 lbs. per cubic yard
[1.2 kg/m3] is present and/or if there is an
observed rebar electrical potential reading of
greater than -0.35 volts compared to a copper-
copper sulfate reference half cell.
4-19
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
412.2 ACTUAL QUANTITIES, concrete area is 50% to 60% of the total deck
ESTIMATING FACTORS area. Therefore, unless there are overriding
circumstances, the decks shall be replaced
rather than rehabilitated when this area equals
The following table gives estimating factors. or exceeds 60% of the total deck area.
The estimating factors are related on a sliding
scale in order to project the quantities based Do not include a pay item for full depth repair
upon measured areas to plan quantities 6 to 9 when such work is not indicated. The unit
months beyond the actual date of the deck price established by this practice is worthless.
condition survey, including one winter.
For any overlay project establishing accurate
quantities are difficult. The difficulty is only
Measured % Estimating Project %
Unsound Area Factor Plan Area increased if the bridge has an existing
asphaltic or rigid concrete overlay. As
0-10 0-3 30 asphaltic concrete overlays do not allow
15 2.33 35 conventional sounding methods, additional
20 2 40 coring and/or evaluation methods listed in
Section 412.1 are recommended.
25 1.9 47.5
30 1.87 55 Required removal thicknesses of existing
35 1.79 62.5 overlays should be established by coring of
40 1.69 67.5 the deck to establish the true thickness of the
existing overlay. Do not use the original
45 1.56 70 design plans specified overlay thickness.
50 1.50 75
60 1.33 80 Variable thickness quantities should be
70 1.21 85 established based on unsound areas of deck
and assuming a depth to the bottom of the top
80 1.09 87.5 layer of reinforcing steel + inch [19 mm].
90 1.00 90 Coring should be used to verify delamination
depth.
The plan quantity must be increased by a Hand chipping bid items for overlay projects
factor of 15% when the survey is one winter requiring hydrodemolition removal are
old. associated with variable thickness quantities.
Using 10% of the variable thickness surface
Life cycle cost comparisons indicate that the area for quantities is one alternative, but other
benefits derived from replacement versus methods may be acceptable. Take note that
rehabilitation are approximately equal when this percentage is based on the variable
the amount of unsound and delaminated
thickness surface area and not the entire deck
4-20
SECTION 400 STRUCTURE REHABILITATION AND REPAIR APRIL 2000
4-21