PPCD95-A408 (2)

-1-3 (1/1)

REVISION-1 ( Last Version )

DELIVERY SCHEDULE REVISION-0 ( By Pak Sahari ) Annex-3 "Delivery Schedule"


PROJECT: Jawa-2 Project Original Schedule ( Contract ) Revised 2017/3/9
YEAR 2016 2017 2018
Calender 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9
No. STRUCTUAL NAME KEY
SCHEDULE Receipt Tekla : 3 MAR REMARK
WEIGHT 2017
(TON) * Shop Drawing Belum

1-b GT Building 860

1-c ST Building 1,070

Receipt Tekla & Shop


Drawing : 27 Des 2016

1-d 500kV GIS Building 300


CHC Sudah Submit Re-Schedule ke
MC dengan end date Delivery 6
April 2017

1-e 500kV GIS Electrical Building 65 DONE

1-f Chlorination House 100

Pipe Rack 395

Pipe Rack (around HRSG) 6th Jan

Pipe Rack (around GT building) Receipt Tekla & Shop 23rd Oct
Drawing : 31 Jan 2017

Pipe Rack (seal pit area)

Pipe Rack (around seal pit ) 23rd Feb

Pipe Rack (around gas storage area ) 23rd Oct

Pipe Rack (around desalination plant ) 23rd Sep

Pipe Rack (around feed water pumps ) 23rd Mar

Pipe Rack (around ST building ) 23rd Jan

Pipe Rack (around ST south side) 23rd Oct

Pipe Rack (around Workshop) 23rd Feb

Receipt Tekla & Shop


Drawing : 25 Jan 2017
Pipe Rack(Intake Pit Area)

Pipe Rack(GIL Area)

CANCELED
GT Cooling Water Cooler and Pump Shed

GAS STORAGE BUILDING (SUN SHADE) 17

C/W INLET POND and Curtain Wall 115

FUEL GAS COMPRESSOR AREA 10


ELECTRICAL ROOM

SERVICE WATER PUMP SHED 7

CONDENSATE PUMP SHED 3

MAKE-UP WATER PUMP SHED 5

DEMIN. PLANT SHED 11

DEMINERALIZED WATER ELECTRICAL 12


BUILDING

WAREHOUSE 95
SEBELUMNYA SCHEDULE
DIGABUNG ( WAREHOUSE &
WORKSHOP )
WORKSHOP 95

CANCELED
SOUNDPROOF WALL

Other 200

TOTAL FABRICATION WEIGHT 3,360


ACCUMULATIVE TOTAL

Notice to Proceed Material procurement Fabrication by Seller Transportation to Site Delivery Finish to Site. Erection Start
by Seller

Shop Drawing by Buyer (if applicable)


PPCD95-A408 (2)
-1-3 (1/1)
DELIVERY SCHEDULE Annex-3 "Delivery Schedule"
PROJECT: Jawa-2 Project Revised 2017/3/9
YEAR 2016 2017 2018
Calender 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9
No. STRUCTUAL NAME KEY REMARK
SCHEDULE
WEIGHT
(TON)

1-b GT Building 860

1-c ST Building 1,070

1-d 500kV GIS Building 300

1-e 500kV GIS Electrical Building 65

1-f Chlorination House 100

Pipe Rack 395

Pipe Rack (around HRSG) 6th Jan

Pipe Rack (around GT building) 23rd Oct

Pipe Rack (seal pit area)

Pipe Rack (around seal pit ) 23rd Feb

Pipe Rack (around gas storage area ) 23rd Oct

Pipe Rack (around desalination plant ) 23rd Sep

Pipe Rack (around feed water pumps 23rd Mar

Pipe Rack (around ST building ) 23rd Jan

Pipe Rack (around ST south side) 23rd Oct

Pipe Rack (around Workshop) 23rd Feb

Pipe Rack(Intake Pit Area)

Pipe Rack(GIL Area)

GT Cooling Water Cooler and Pump Shed

GAS STORAGE BUILDING (SUN SHADE) 17

C/W INLET POND and Curtain Wall 115

FUEL GAS COMPRESSOR AREA ELECTR 10

SERVICE WATER PUMP SHED 7

CONDENSATE PUMP SHED 3

MAKE-UP WATER PUMP SHED 5

DEMIN. PLANT SHED 11

DEMINERALIZED WATER ELECTRICAL B 12

WAREHOUSE 95

WORKSHOP 95

SOUNDPROOF WALL

Other 200

TOTAL FABRICATION WEIGHT 3,360


ACCUMULATIVE TOTAL

Notice to Proceed Material procurement Fabrication by Seller Transportation to Site Delivery Finish to Site. Erection Start
by Seller

Shop Drawing by Buyer (if applicable)


PPCD95-A408 (2)
-1-3 (1/1)
DELIVERY SCHEDULE Annex-3 "Delivery Schedule"
PROJECT: Jawa-2 Project Revised 2016/11/29
YEAR 2016 2017 2018
Calender 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6
No. STRUCTUAL NAME KEY
SCHEDULE REMARK
WEIGHT
(TON)

1-b GT Building 860

1-c ST Building 1,070

1-d 500kV GIS Building 300

1-e 500kV GIS Electrical Building 65

1-f Chlorination House 100

Pipe Rack 395

GT Cooling Water Cooler and Pump Shed 40

GAS STORAGE BUILDING (SUN SHADE) 17

C/W INLET POND and Curtain Wall 115

FUEL GAS COMPRESSOR AREA ELECTR 10

SERVICE WATER PUMP SHED 7

CONDENSATE PUMP SHED 3

MAKE-UP WATER PUMP SHED 5

DEMIN. PLANT SHED 11

DEMINERALIZED WATER ELECTRICAL B 12

WORKSHOP & WAREHOUSE 190

SOUNDPROOF WALL 17

Other 174

TOTAL FABRICATION WEIGHT 3,391


ACCUMULATIVE TOTAL

Notice to Proceed General Arrangement Drawing Material procurement Fabrication by Seller Transportation to Site Delivery Finish to Site. Erection Start
Issue and Material Order List for by Seller
material procurement
by Buyer
Shop Drawing by Buyer (if applicable)