STRUCTURAL ENGINEERS
ROCK HILL
TEL: +44(0) 1527 832307 BROMSGROVE
FAX: +44(0) 1527 832711
email:admin @cdpbroms .co.uk WORCS B61 7LH
125062 Proposed Development on land at
Burbages Lane, Exhall, Coventry
Premium Estates Developments Ltd.
Flood Risk Assessment & Drainage
Strategy
Preparedby: HeatherCeney
Checkedby: JohnBlackhall
Approvedby: JohnBlackhall
Date: 16/04/2012
Reference: 125062FRA
Issue1
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
Contents
1. Introduction....................................................................................................................................3
2. Backgroundtothesite....................................................................................................................5
3. ProposedDevelopment..................................................................................................................8
4. DrainageStrategy..........................................................................................................................10
5. FloodRiskAssessment..................................................................................................................17
6. Conclusionsandrecommendations..............................................................................................19
7. References....................................................................................................................................20
AppendixA:Supportingdrawings
AppendixB:FloodMapping
AppendixC:SevernTrentWaterLtd.AssetPlans
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 2 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
1. Introduction
ThisFloodRiskAssessment(FRA)isforaproposedresidentialdevelopmentofaroundfortyfour
houseswithdrives,carparkingandgardensonaplotofapproximately1.2hectares,onlandoff
BurbagesLane,ExhallnearCoventry.Thislandiscurrentlygardens.Thesiteislocatedat
approximateGridReference433822,284156.
Theproposeddevelopmentsiteisaccessedviaanewentranceroadtobeconstructedatthe
locationofNo.30BurbagesLane,andthesiteextendsacrosstherearofexistingpropertiesNos.30
to52.ThesiteliestothewestoftheA444andisneartotheCoventryWelshRugbyClub.
Theproposeddevelopmentsiteisirregularinshapeandisboundedtothewestbythegardensof
existingresidentialpropertiesfrontingBurbagesLane.Landimmediatelytotheeastofthe
developmentsiteboundaryisdesignatedasgreenbelt.
Anexistingstream/ditchcourseislocated60metrestotheeastoftheproposeddevelopment
boundary.
ThisFloodRiskAssessmentiscarriedoutinaccordancewithPlanningPolicyStatement25(PPS25),
BS8533:2011,PlanningPolicyStatement25PracticeGuide(December2009),EnvironmentAgency
GuidanceNote1forDevelopmentgreaterthan1hainFloodZone1,andfollowingtheguidancein
CIRIAC624.
TheproposeddevelopmentisclassifiedasMoreVulnerable(PPS25AnnexD).
Thefollowingdocumentsformpartofthisassessment:
ExistingSewers SevernTrentWater
Atopographicalsurveyhasnotyetbeencarriedoutforthesite.Copiesofdrawingsareincludedin
AppendixA.
ThesiteiswithintheareacoveredbyNorthWarwickshireBoroughCouncilStrategicFloodRisk
AssessmentforLocalDevelopmentFrameworkLevel1Volume1(January2008)preparedby
HalcrowGroupLimited.ThefloodmappingfortheBedworthareaisincludedinAppendixB.
TheEnvironmentAgencywebsiteandStrategicFloodRiskAssessment(SFRA)floodmappingshows
thattheproposeddevelopmentsitelieswithinFloodZone1,atlowriskfromfluvialflooding.
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 3 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
ResearchbytheEnvironmentAgency(EA)showsthatoverthenext80years,theprobabilityof
occurrenceofseverefloodingwillincrease.PPS25setsoutrecommendationsforcontingency
allowancesforclimatechange.Table1summarisestheallowancesforadevelopmentwithadesign
lifehorizonupto2115:
Parameter Allowance
2055to2085 2085to2115
Table1:PPS25contingencyallowancesforclimatechange
ThePPS25PracticeGuiderecommendsthatalifetimeofaresidentialdevelopmentshouldbetaken
asminimum100years.Thereforeaclimatechangeallowanceof30%onrainfallwillbeincludedin
thedesignforthedevelopment.
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 4 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
The1.21hectaresiteisgardensandlandlyingtotherearoftheresidentialpropertiesonBurbages
Lane.Beyondtheeasterndevelopmentboundary,landisdesignatedasGreenBelt.TheRiverSowe
liesaround400metrestotheeastofthesite,beyondtheA444dualcarriageway.
Theexistinglanduseofthedevelopmentsiteisgardens(someovergrown)andtherearealsoa
numberofsheds,bothinuseandderelict,andsomevehicularaccessareaswithhardstandings.
Thereiscurrentlynotopographicalsurveydataavailableforthesite.InspectionofOrdnanceSurvey
Mappingindicatesthattheproposeddevelopmentsitehasanelevationofaround106metres
AboveOrdnanceDatum(AOD)attheproposedroadaccessfromBurbagesLane,fallingtoataround
the100metrecontourlevelneartheeasternboundary.Thegenerallandprofileinthisareashowsa
gradualslopefallingwesttoeastfromBurbagesLaneatthehighpointtowardstheRiverSowe.A
fulltopographicalsurveyforthesitewillbecarriedoutpriortodetaileddesignoftheproposed
developmentanditsdrainagesystem.
Aditchcourse/streamliesapproximately50to60metreseastoftheproposeddevelopment
followingthefieldboundaryline.Thelandbetweenthedevelopmentsiteandditchcourseis
greenbelt,butitisunderstoodthattheDeveloperhasanoptiontopurchaseaplotofland
approximately50x25metresinarea,betweenthedevelopmentsiteandtheditch.
Althoughthereareanumberofshedsandhardsurfacedareasontheexistingsite,forthepurposes
ofthisFloodRiskAssessmentandDrainageStrategy,theexistingsiteisconsideredtobe100%
permeable,asaworstcasescenario.
TheEnvironmentAgencywebsitefloodmappingshowsthatthissiteisclassifiedasZone1andat
lowriskfromfluvialfloodingwithlessthan1in1000annualprobabilityofriverfloodinginanyyear
(<0.1%).AcopyoftheSFRAfloodmapfortheareaisincludedinAppendixB.
2.3 Hydrology
ThenearestmajorsurfacewaterfeatureistheRiverSowewhichliesapproximately400metres
away,totheeastoftheA444.ThefloodplainfortheriverisshownontheSFRAmappingin
AppendixB.Theproposeddevelopmentsiteislocatedonhighground;atitslowestpointthesiteis
elevatedsome8to10metresabovetheriverlevel.
Aditchcourse/streamliesapproximately50to60metreseastofthedevelopmentfollowingthe
fieldboundaryline.Thiswouldappeartoflownorthwardseventuallybecomingatributarytothe
RiverSowe.
AlargegardenpondislocatedtothesouthoftheproposedsiteattherearofNo.54BurbagesLane.
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 5 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
Thereiscurrentlynogroundinvestigationdataavailableforthesite.PublishedBritishGeological
Societydataindicatesthatthesiteislikelytobeunderlainbymudstoneandsandstone.
Groundinvestigationwillbecarriedoutatthesitepriortodetaileddesignofthedevelopmentand
drainage.Percolationtestingwillbecarriedoutasrequired,todeterminewhetherdesignofthe
SuDSfeaturesasinfiltrationdrainageisfeasible.
ForthepurposesofthisFRAanddrainagestrategy,ithasbeenassumedthatnoinfiltrationis
possible.Storagevolumesgiveninthisreportthereforepresenttheworstcasescenario.
AdoptedstormandfoulsewersareshownontheSevernTrentWaterLtd.SewerRecordsin
AppendixC.
InresponsetoaDeveloperEnquiry,SevernTrentWaterLtd.hasstatedthatithasnoconcernswith
thefoulflowfromtheproposeddevelopmentdischargingtotheexistingpubliccombinedsewerat
therearofNos.54to30BurbagesLane.However,STWhasnodataavailableontheinvertlevelsor
conditionofthissewer.CCTVconditionandlevelsurveyswillthereforeberequiredpriortodetailed
designoftheproposedfoulsewerconnection.
However,giventhetopographyofthesite,whileconnectiontothepublicsewershouldremainan
option,thedrainagestrategydescribedinSection4hasbeendevelopedassumingdischargeviaa
SustainableDrainageSystem(SuDS)totheditchcourselyingtotheeast.
ThesiteiswithintheareacoveredbyNorthWarwickshireBoroughCouncilStrategicFloodRisk
AssessmentforLocalDevelopmentFrameworkLevel1Volume1(January2008)preparedby
HalcrowGroupLimited.
ThefloodmappingfortheBedworthareaisincludedinAppendixB.ThisshowsFloodZones2and3
(atmediumandhighriskofflooding)followingtherouteoftheRiverSowe,lyingtotheeastofthe
siteandtheA444.TheproposeddevelopmentsiteislocatedwithinFloodZone1,atlowriskof
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 6 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
fluvialflooding.TheSFRAmappingalsoshowsthattherearenorecordedincidentsofsurfacewater
(pluvial)floodingforthedevelopmentsite.
Locationofproposed
developmentsite
ExtractfromNorthWarwickshireSFRAFloodMapping
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 7 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
3. Proposed Development
TheproposeddevelopmentisclassifiedasMoreVulnerable(PPS25AnnexD)andislocatedwithin
FloodZone1.
3.1 Description
Theproposeddevelopmentcomprisesaroundfortyfourdwellingswithaccessroad,drives,car
parkingandgardensasshownontheArchitectssitelayoutdrawing93670002.Thesiteof
approximately1.21hectaresintotalareawasformerlygardens,withsomeoutbuildingsandvehicle
access.
AnewroadjunctionistobeformedwithBurbagesLane.Atthistimeitisassumedthatthenewroad
intothedevelopmentrunningparalleltothenorthernboundarywouldbeadoptedbytheLocal
Authority.Leadingofftheroadtothesouthisanewaccessroad(assumedunadopted)serving
propertiesNos.16to41.
Theproposeddevelopmentwillhaveanapproximateimpermeableareaof6015m2measuredfrom
thelayoutondrawing93670002,brokendownasgiveninTable2.Theremainderofthesitewillbe
finishedasgardensandsoftlandscaping.
Area
m2
Roofs 2325
AdoptedRoad 1430
AccessRoad 1400
Drives 860
Total 6015
Table2:Proposedimpermeableareas
Assumingthatalldrivesandroadwaysetc.areconstructedwithimpermeablesurfacing,thenthe
proposeddevelopmentwouldbe50%impermeable.
Duetotheincreaseinimpermeablearea,itisproposedtousepermeablepavementforthedrives
andpossiblythenonadoptedaccessroadrefertosection4fordetails.Constructingthedrivesand
accessaspermeablepavementwouldresultinthedevelopmentbeing31%impermeable.
Atopographicalsurveyofthesitehasnotyetbeencarriedout.However,itisanticipatedthatthe
overallsitelevelsandprofilewillbesimilartoexisting.LevelsatthenewroadjunctionatBurbages
Lanearearound106metresAOD,attheeasternboundarylevelsareexpectedtobeataround100
metresAOD.
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 8 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
Duetotheunderlyingmudstoneindicatedbythegeologicalrecords,itisconsideredthatground
conditionsontheproposeddevelopmentsitemaynotbesuitedtodisposalofstormdrainageby
soakaway.Percolationtestingwillbecarriedoutaspartofthegroundinvestigationpriortodetailed
design.Wheredisposalofstormwaterbyinfiltrationispossible,thiswillbeusedtominimisethe
attenuationstoragevolumerequired.
Duetothewesttoeastfallacrossthesite,theinvertlevelatpointofconnectionislikelytobetoo
hightoallowconstructionofagravitysystemforthedevelopment,andasmallpumpingstationwill
probablyberequired.
SewersforAdoption6thEditionsetsoutageneralspecificationforapumpingstation.Thetypical
compoundrequiredis8mby10m,accessibletovehicles,andtobelocatednocloserthan15mto
thenearestdwelling.Foradevelopmentof44houses,thereshouldbeadequatestorageprovided
foraround7000litres(7m3)ofsewage.TherearePackagePumpingStationsavailablefromsuppliers
suchasPumpsealandMathewsPumps,forexample,whichcanbecompliantwithSewersfor
Adoption.
EarlydiscussionsshouldbeheldwithSevernTrentWatertoagreethepumpingstationtypeand
location.
A) Dischargeofstormwaterrunofffromthedevelopmenttotheexistingadoptedstormsewer
inBurbagesLane.Thiswillrequireattenuationofstormwaterinpermeablepavementand
attenuationtankpriortorestricteddischargetothesewer.Asforthefouldrainage,a
pumpedsystemmayberequired.
B) Dischargeofstormwaterrunofffromthedevelopmenttotheditchcourselyingtotheeast
ofthesite,viasustainabledrainagefeaturesandanattenuationpondand/orwetlandtobe
constructedontheadditionalplotofgreenbeltlandtotheeast.
Duetothetopographyofthesite,andthepumpingstationrequiredtomakeOptionAfunction,itis
consideredthatOptionBpresentsamoresustainablesolution.Thedrainagestrategyhastherefore
beendevelopedforOptionB.
Attenuation,includingallowanceforclimatechange,willbeprovidedtolimitrunofftothe
equivalentgreenfielddischargerateof5l/s/ha.Stormwaterdrainageisdiscussedfurtherinthe
drainagestrategy(Section4).
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 9 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
ItisproposedthattheSuDSattenuationsystemwilldischargetotheexistingditchcoursewhich
followsthefieldboundarytotheeastofthedevelopmentsite.Itisrecommendedthatthe
Developershoulddeterminetheownershipofthisditchandestablishtherighttoconstructan
outfallatthislocation.
AllsewerconnectionstopublicsewersaresubjecttoagreementwithSevernTrentWaterLimited.
SitedrainageistobedesignedfollowingtheguidanceinSewersforAdoptionandthePPS25Practice
Guide.Sitedrainagewillbedesignedsuchthatthereis:
Noabovegroundfloodingforthe1in30yearevent;and
Nofloodingofbuildingsforthe1in100yearevent,includingallowanceforclimatechange.
4. Drainage Strategy
ThisdrainagestrategyhasbeendevelopedfollowingtherecommendationsinPPS25AnnexFand
theEnvironmentAgencyGuidanceNote1forDevelopmentgreaterthan1hainFloodZone1.Storm
drainagewillbedesignedtomimicexistingsurfacewaterflowsfromthesite,butincorporatean
allowanceforclimatechange.
Sustainabledrainagesystems(SuDS)willbeusedasappropriate.Thedrainagestrategyusesthe
followingprinciples:
Rateofdischargefromsitetomimicgreenfieldrunoffrates,includingallowanceforclimate
change;
Areaofpermeablesurfacingtobemaximised;
SustainableDrainageSystems(SuDS)tobeusedtoattenuatestormwaterrunoff;
Anewpondand/orwetlandareawillbecreatedontheplotofgreenbeltlandtotheeastof
thedevelopment;
Stormwatertodischargetoexistingditchcourseattheeast.
SustainableDrainageSystems(SuDS)aredesignedtomanagetheenvironmentalrisksresultingfrom
urbanrunoffandcontributetoenvironmentalenhancement,whereverpossible.Tomimicnatural
catchmentascloselyaspossibletheaimofSuDSistomanagestormwaterinthefollowinghierarchy
oftechniques:
1. Preventionthroughsitelayoutanddesigntopreventrunoffandpollution,and
incorporaterainwaterreuseandharvesting;
2. Sourcecontrolcontrolofrunoffatornearitssource,e.g.permeablepavementsand
soakaway;
3. Sitecontrolmanagementofrunoffbyroutingtopermeableareasorsoakaway;
4. Regionalcontrolmanagementofrunoffbystoragepriortodischargetoawatercourseor
sewer.
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 10 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
TheuseofSuDSprovidesasignificantcontributiontowardsmoresustainabledevelopmentsince
they:
addressenvironmentalimpactsatsource,ratherthandownstream;
attenuatesurfacerunoffrates,reducingtheimpactofurbanisationonflooding;
protectorenhancewaterquality;
canbeengineeredtobesympathetictotheenvironmentalsettingandtheneedsofthelocal
community;
provideopportunitiesforecologicalhabitatcreation;and
canencouragenaturalgroundwaterrecharge.
Table3summarisesSuDSsystemsandtheirsustainabilitycharacteristics:
Mostsustainable Greenroofs
Basinsandponds
Filterstripsand
swales
Infiltration
devices
Permeable
surfacesand
filterdrains
Leastsustainable Tankedsystems
Table3:SustainabilityofSuDStechniques
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 11 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
Table4showsasummaryofthefeasibilityofdifferentSuDStechniquesfortheproposed
developmentsite:
Unfeasible
Feasible
Greenroofs Requiresflatorminimalslopetoroofs. Notconsideredfeasibleonthistype
Limitedvalueforrunoffattenuationin
ofresidentialdevelopment.
comparisontoothertechniques.
Table4SuDSfeasibilitymatrix
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 12 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
Principlesofsustainabledrainagewillbeappliedtotheproposeddevelopmentsitebyusing
permeablepavingwherepossibletominimiseimpermeablearea.Attenuationforstormrunoffis
providedinacoarseaggregatesubbasebeneaththepavementwhichdelaystimeofentrytothe
sewersystem.Itisproposedthatdrivewaysandparkingareasshouldbeconstructedinpermeable
pavement.Permeablesurfacingproductsarealsoavailableforplayareas.
Forthepurposesofthisdrainagestrategy,itisassumedthatthesoilsonthesitearenotsuitablefor
designofinfiltrationdrainage.Whilesomenaturalinfiltrationwilloccurbeneathpermeableareas,
(asoccursnowfortheexistinggreenfieldsite),percolationratessuitablefordesignofsoakaway
systemsmaynotberealisedduetotheunderlyingstrata.(Rateofpercolationintothesubsoilwill
bedeterminedbytestingduringthegroundinvestigation,priortodetaileddesign).
Downpipesfromtheroofswillbeallowedtodischargeontothepermeablepavement.Thestorm
waterwillpercolatethroughthepavementandcoarseaggregatereservoirlayer,delayingtimeof
entryinthesewer.Itisrecommendedthatwaterbuttsareinstalledonthepropertiestoallow
rainwatertobeharvestedforexternalreuse.
Duetotheassumedlowpermeabilityoftheunderlyingsoils,thepermeablepavedareaswillbe
providedwithoverflowpipes.Outletsfromthereservoirbeneathpermeableareaswilldischargeto
astormwatersewersystem,whichwilloutfalldownstreamtoanattenuationpond.Thecoarse
aggregateactsasafilterforthesurfacewaterrunoff,bothslowingtherateofdischargeand
improvingwaterquality.
Areasoflandscapingshouldbedesignedwherepossibletoacceptrunofffromimpermeableareas.
Theattenuationpondwillbedesignedwithapermanentlywetareaandincludewetlandandsemi
dryareastoallowadiversehabitattoestablish.Aroundthepond,thestormwaterstorageareawill
beconstructedtoallowsomenaturalinfiltrationofstormwatertooccur.Theattenuationpond
outflowwouldbeviaaswaleoutfallingtotheditch/stream.Theswalewillalsobeconstructedto
allowsomeinfiltrationthroughastonebed.Aflowcontrolchamberorweirwillbeprovidedto
restrictdischargeintotheditchtotheequivalentgreenfieldrate.
Thefinalvolumeofstoragerequiredwillbedeterminedfollowinggroundinvestigationand
percolationtesting.
Stormwaterrunoffforthegreenfieldsitehasbeenestimatedusingthemethodstatedinthe
guidancetodevelopersissuedbySevernTrentWaterLtd.Thisstatesthatpeakstormflowsforthe
proposeddevelopmenttoasewer(30yeardesignstorm)shouldbelimitedtoagreenfieldrunoffof
5litres/sec/hasubjecttoaminimumof5litres/sec.
Sitearea=1.21ha.Thereforetheproposedpeakstormdischargefromthedevelopmentsitetoa
sewerislimitedto6.05l/s.
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 13 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
RunoffhasbeenestimatedusingtheModifiedRationalMethod(timeofentry5minutes)witha
30%allowanceforclimatechange.Assumingalldrivesetc.areimpermeable,runoffratesforreturn
periodsofupto100yearsareshowninTable5foraproposedimpermeableareaof0.601ha.
ReturnPeriod Runoff
1Year 108.7l/s
10Years 205.9l/s
30Years 252.2l/s
100Years 313.1l/s
Table5:Estimatedrunofffromproposeddevelopment(includingclimatechangeallowance)
Flowcontrolwithattenuationstorageisrequiredtoachieveatotalallowabledischargetothe
ditch/streamequivalenttothe6.05l/sgreenfieldrunoffrate.
Itisproposedtouseapermeablepavingsystem,attenuationpondandwetlandtoprovide
attenuationstorage.Useofpermeablepavingwilldelaytimeofentryandsoreducepeakflowsinto
theattenuationpond.
Forthissite,itisproposedtoprovideattenuationstorageforalleventsuptothe1in100year
storm.TheWinDesQuickStorageEstimatehasbeenusedtoestimatetheattenuationstoragewhich
wouldberequiredforthesite,forthe1in100yearevent,includinga30%allowanceforclimate
change.
EstimatedstoragevolumesinTable6havebeencalculatedfortwoscenarios:
A) Allroads,accessanddrivewaysconstructedinimpermeablesurfacing;
B) Drivewaysandaccessconstructedaspermeablepavement,allowingsomenatural
infiltrationintothesubgradefortheseareas,equivalenttotheexistinggreenfieldsite.
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 14 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
Table6:Estimatedattenuationstoragevolumes
Attenuationstorageforthe1in100yearsevent(includingallowanceforclimatechange)willbe
providedforthesitebyacombinationofattenuationpondandwetland,andpermeablepavement.
Forthepurposesofthisdrainagestrategyitisassumedthatstoragecouldbeapportionedas
follows:
SuDSFeature StorageProvision
Attenuationpondandwetlandarea Approximately200to250m3
Permeablepavementtodrivesandaccess Approximately150to180m3
Totalprovision Uptoapproximately400m3
Table7:SuDSStoragevolumes
Thepermeablepavementwillallowsomenaturalinfiltrationintothesubsoil.Thisdrainagestrategy
assumesthatthepermeablepavementwillnotbedesignedasaninfiltrationdrainagesystem;
althoughnaturalinfiltrationwouldoccur,aswiththeexistingsoils,permeabilityofthegroundmay
notachievetheratesofpercolationnecessaryforaninfiltrationsystem.Thereforeitisassumedthat
dischargepipeswillberequiredfeedingintothestormsewernetworkoutfallingtotheattenuation
pond.
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 15 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
Evenwithareducedstoragevolume,thepermeablepavementprovidesbenefitsinslowingtherate
ofrunoffandincreasingtimeofentryintothepipenetwork,aswellasimprovedwaterquality.If
theareaofpermeablepavementisreduced,thenthepondwillneedtobeincreasedinsizeto
compensate.
ThestoragevolumesinTable6arecalculatedassumingthatnoinfiltrationintothegroundwilloccur
atthepermeablepavement,andsopresentaworstcasescenario.Percolationtestingwillbecarried
outatdetaileddesign,theresultsofwhichmayallowtherequiredstoragevolumetobereduced.
Anattenuationpondisproposedontheplotofgreenbeltlandlyingtotheeastofthedevelopment
site.Thepondwillbedesignedtohaveapermanentlywetarea,butalsoallowforwetlandand/or
semidrystormwaterstorageareastoallowadiversehabitattoestablish.
Thedesignandcapacityofthestoragepondandwetlandareaswilldependonthetopographyof
thesite.(Asurveyisnotcurrentlyavailable).However,apreliminaryassessmentoftheplotofland
indicatesthatapondwithstormwaterstoragevolumeofuptoaround250m3shouldbeachievable.
Thepondshouldbefencedofffromthedevelopment,forsafetyreasons.Gatedmaintenanceaccess
willberequired.Pondsandwetlandareascanalsobedesignedtoprovidepublicamenityandopen
space.Forexample,theareacouldbedesignedasanaturereserve,includingwalkwaysandseating
areas.
ThevolumesinTable6arecalculatedassumingthatnoinfiltrationintothegroundwilloccuratthe
permeablepavementorpond,andsopresentaworstcasescenario.Percolationtestingwillbe
carriedoutatdetaileddesign,theresultsofwhichmayallowtherequiredstoragevolumetobe
reduced.
Theoutflowfromthepond/wetlandwilldischargetotheditchcoursewhichfollowsthefield
boundaryattheeasternedgeoftheplot.Flowcontrolwillbeintroducedintheformofaflow
controlchambere.g.hydrobraketoensurethattotaldischargefromthesystemislimitedtothe
equivalentgreenfieldrunoffrateof6.05l/s.
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 16 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
Fluvialflooding
Pluvial/surfacewaterflooding
TheproposeddevelopmentisclassedasMoreVulnerabletoPPS25AnnexD.Thesiteisshownas
FloodZone1ontheEAfloodriskmapping,andisthereforeatlowriskfromfluvialfloodingwithan
annualprobabilityoflessthan1in1000.
SinceallbuildingsarelocatedinFloodZone1,theproposeddevelopmentlayoutsatisfiesthePPS25
FloodRiskVulnerabilityandFloodZonecompatibilityrequirements.Accesstoandfromthesiteis
locatedinFloodZone1,atlowriskfromflooding.
Theproposeddevelopmentsiteisnotindicatedinanareaofhistoricpluvial(surfacewater)flooding
ontheSFRAmappingincludedinAppendixB.
However,thedevelopmentproposalsdoincreasetheimpermeablearea,comparedtoexisting.Itis
proposedtoprovidepermeablepavingtothedrivesandparkingareastominimisetheimpermeable
areaofthesite.
Theslopeofthesite,lyingdownhillfromBurbagesLane,alsoindicatesapotentialforsurfacewater
flooding.Drainagedesignatthenewentranceroadshouldensurethatgulliesordrainagekerbare
positionedtointerceptanyoverlandflowfromBurbagesLane.
Itisproposedtoprovideattenuationforstormwaterrunoff,intheformofapondand/orwetland,
andpermeablepavementtothedrivewaysandaccess,inordertomitigatetheimpactofincreasing
theimpermeableareaofthesiteandallowforfutureclimatechangeinaccordancewithPPS25.This
isdescribedinSection4.
SitedrainageistobedesignedfollowingtheguidanceinSewersforAdoptionandthePPS25Practice
Guide.Sitedrainagewillbedesignedsuchthatthereis:
Noabovegroundfloodingforthe1in30yearevent;and
Nofloodingofbuildingsforthe1in100yearevent,includingallowanceforclimate
change.
Duetotheprovisionofpermeablepavingandattenuationforthesite,itisconsideredthatthe
proposeddevelopmentisatlowriskofpluvialflooding.
Surfacewaterrunofffromthesiteistobemanagedbypermeablepavementandattenuationwith
controlleddischargetotheditchcourserunningalongthefieldboundarytotheeastofthesite.The
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 17 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
attenuationandflowcontrolwillbedesignedtomimictheexistinggreenfieldconditions,including
allowanceforclimatechange.
Itisthereforeconsideredthattheproposeddevelopmentwillnotincreasetheriskoffluvialor
surfacewaterfloodinginthewidercatchment.Theadditionofrainwaterharvestingintheformof
waterbuttsfortheproperties,wouldalsocontributetothesustainabilityofwatermanagementfor
thesite.
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 18 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
ThisFloodRiskAssessment(FRA)andDrainageStrategyisfortheproposeddevelopmentofaround
fortyfourhouseswithdrives,carparkingandgardensonaplotofapproximately1.21hectares,on
landatBurbagesLane,Exhall,Coventry.
TheproposeddevelopmentisclassifiedasMoreVulnerabletoPPS25AnnexD.Allproposed
buildingsarelocatedinFloodZone1atlowriskfromfluvialflooding.
SuDSfeatureswillbeincorporatedintothedevelopmentintheformof:
Waterbutts;
Permeablepavingtodrivewaysandaccess;
Pondand/orwetlandwithcontrolleddischarge.
Itisproposedtoprovideattenuationforstormwaterrunoff,intheformofpermeablepavementto
drivesandanattenuationpond.Theattenuationwillmitigatetheimpactofincreasingthe
impermeableareaofthesite,andallowforfutureclimatechangeinaccordancewithPPS25.Atthe
newentranceroad,gulliesordrainagekerbwillbepositionedtointerceptanyoverlandflowfrom
BurbagesLane.Itisthereforeconsideredthatthedevelopmentisatlowriskfrompluvialflooding.
Surfacewaterdischargefromthesitewillberestrictedto6.05l/stomimicthegreenfieldconditions.
Attenuationanddrainagewillbedesignedincludingallowanceforclimatechange.Itistherefore
consideredthattheproposeddevelopmentwillnotincreasetheriskoffluvialorsurfacewater
floodinginthewidercatchment.
ItisproposedthattheSuDSattenuationsystemwilldischargetotheexistingditchcoursewhich
followsthefieldboundarytotheeastofthedevelopmentsite.Itisrecommendedthatthe
Developershoulddeterminetheownershipofthisditchandestablishtherightorobtainconsentto
constructanoutfallatthislocation.
Thefoulsewersystemislikelytorequireasewagepumpingstationinordertoconnecttothe
SevernTrentWaterpublicsewerinBurbagesLane.Itisrecommendedthattherequirementsand
proposedlocationforthepumpingstationarediscussedwithSevernTrentWaterLtd.atanearly
opportunity.
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 19 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
7. References
1. BS8533:2001.Assessingandmanagingfloodriskindevelopmentcodeofpractice,BSI,
October2011.
2. BS753313:2009:Pavementsconstructedwithclay,naturalstoneorconcretepaversPart13:
Guideforthedesignofpermeablepavementsconstructedwithconcretepavingblocksandflags,
naturalstoneslabsandsettsandclaypavers.BSI,March2009.
3. PlanningPolicyStatement25:developmentandFloodRisk,CommunitiesandLocalGovernment,
TSO,March2010.
4. PlanningPolicyStatement25:DevelopmentandFloodRiskPracticeGuide,Communitiesand
LocalGovernment,TSO,December2009.
5. NorthWarwickshireCountyCouncilStrategicFloodRiskAssessmentforLocalDevelopment
FrameworkLevel1Volume1,HalcrowGroupLimited,January2008.
6. SewersforAdoption6thEdition,Wrc,2006.
7. CIRIA697TheSuDSManual.London2007.
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 20 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 16/04/2012
SCALED MEASUREMENTS ARE NOT TO BE TAKEN
FROM THIS DRAWING.
ALL MEASUREMENTS AND DIMENSIONS TO BE
8
7
6
5 11
4 12
3 15
2
14
13 11
16
17
41 18 23
22
40 21
20
39 19 24
38
25
37 26
REVISIONS date
36 PROJECT TITLE
27 PROPSED DEVELOPMENT AT
35
BURBAGES LANE, EXHALL,
29 CLIENT
PREMIUM ESTATES
DEVELOPMENTS LTD
30
31 DRAWING TITLE
Site Plan/Layout Plan
Location Plan
32
33
PROJECT No.
34 9367
DRAWING No.
9367-00-02
date DECEMBER 2011
scale 1:250, 1:1250
cad-ref 9367-05
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 16/04/2012
125062BurbagesLane,Exhall,Coventry
FloodRiskAssessment&DrainageStrategy
CompleteDesignPartnershipLtd. RegistrationNo.3866200
Issue1 16/04/2012