Development Project Proforma/Proposal (DPP)

Part-A
Project Summary

1 Project Title : -
(e-Stamping Implementation Pilot Project)

2 (a) Sponsoring Ministry : Information and Communication Technology


/Division Division, Ministry of Posts, Telecommunications
& Information Technology.

2 (b) Executing Agency : Office of the Controller of Certifying Authorities.


(CCA)

3 Objectives of the Project : To convert present paper based non-judicial


revenue stamp to electronic stamping.
To increase Govt. revenue from stamp duty.
To enhance transparency in stamp duty
management and remove forgery of stamp duties.
To build a central database to make an ease of
the verification process.

4 Location of the Project : Office of the Controller of Certifying Authorities,


BCC Bhaban, Agargaon, Sher-e-Bangla Nagar,
Dhaka.

Division District Upazila

1 2 3

Dhaka Dhaka Agargaon, Sher-e-Bangla Nagar,


Dhaka

5 Project Estimation :

a) Estimated Cost of the i) Total : 14318.27


Project (In Lakh Taka)

ii) GoB : 14318.27

iii) PA : 0

b) Exchange rate with date : N/A


6 Location wise cost break- : (Annexure-I)
down to be attached as per
Annexure-I

7 (b) Source of Financing GOB Fund against DPPs Year wise Allocation
(In Lakh Taka)
Whether the priority list of Year wise GoB Fund Source of Required In case of re-
the project has been made Requirement GoB Fund appropriation
according to available Financial Amount from other
resource in the FY 2015-2016 Year project (s)
If yes, give the sl. no. what will be
the impact of
the project
(s)
1 2 3 4 5
The project is included in Green Through year-wise
Page of ADP 2015-16, Serial 2016-2017 1532.85 allocation in the
no: 830 (page 724). "E- 2017-2018 11133.94 Annual
N/A
Stamping Implementation Development
2018-2019 1651.48
Project" is proposed. Programme

TOTAL : -- 14318.27 -- --

8 Project
Implementation
Period:
i) Date of : 1st July,
Commencement 2016
ii) Date of Completion : 30-Jun-19