Beruflich Dokumente
Kultur Dokumente
PARAMETERS:
MIXTURE: CLASS A
OUTPUT:
TOTAL CONCRETE VOLUME: 0 CU.M.
NO. OF CEMENT BAG: 0 BAGS
VOLUME OF SAND: 0 CU.M.
VOLUME OF GRAVEL: 0 CU.M.
WORK AREA: COLUMN
PARAMETERS:
MIXTURE: CLASS A
OUTPUT:
TOTAL CONCRETE VOLUME: 0 CU.M.
NO. OF CEMENT BAG: 0 BAGS
VOLUME OF SAND: 0 CU.M.
VOLUME OF GRAVEL: 0 CU.M.
WORK AREA: BEAM
PARAMETERS:
MIXTURE: CLASS A
OUTPUT:
TOTAL CONCRETE VOLUME: 0 CU.M.
NO. OF CEMENT BAG: 0 BAGS
VOLUME OF SAND: 0 CU.M.
VOLUME OF GRAVEL: 0 CU.M.
WORK AREA: SLAB
PARAMETERS:
MIXTURE: CLASS A
OUTPUT:
TOTAL CONCRETE VOLUME: 0 CU.M.
NO. OF CEMENT BAG: 0 BAGS
VOLUME OF SAND: 0 CU.M.
VOLUME OF GRAVEL: 0 CU.M.
SUMMARY:
TOTAL OUTPUT:
TOTAL CONCRETE VOLUME: 0 CU.M.
NO. OF CEMENT BAG: 0 BAGS SAY: 0 BAGS
VOLUME OF SAND: 0 CU.M. SAY: 0 CU.M.
VOLUME OF GRAVEL: 0 CU.M. SAY: 0 CU.M.
CHB ESTIMATOR
1
PROJECT: CLUB HOUSE
LOCATION: MENZI VILLAGE
WORK AREA:
PARAMETERS:
SUBTRACTIVE:
WINDOW 1 WINDOW 2 WINDOW 3 WINDOW 4 WINDOW 5 WINDOW 6 WINDOW 7 WINDOW 8
SET: 11 1
WIDTH: 1.5 1.5
HEIGTH: 1.2 1.8
AREA: 19.8 2.7 0 0 0 0 0 0
DOOR 1 DOOR 2 DOOR 3 DOOR 4 DOOR 5 DOOR 6 DOOR 7 DOOR 8
SET: 2 2 3 1
WIDTH: 0.8 0.7 0.6 0.6
HEIGTH: 2.1 2.1 2.1 2.1
AREA: 3.36 2.94 3.78 1.26 0 0 0 0
OUT PUT:
AREA: 199.91
LAYER: 21 TOTAL COST: 19,241.34
COLUMN: 137.5
NO. OF PCS.: 2498.875 say 2748.763
MORTAR ESTIMATOR
MIXTURE: CLASS B
PARAMETER: RATIO : 1:3
COST OF CEMENT: 240 PER BAG
COST OF SAND: 300 PER cubic
OUT PUT:
NO. OF CEMENT: 104.353 BAGS TOTAL COST OF CEMENT: 27549.19728
SAY : 114.7883 BAGS TOTAL COST OF SAND : 2869.70805
VOLUME OF SAND: 8.696085 CU.M.
SAY : 9.565694 CU.M.
OUT PUT:
NO. OF CEMENT: 179.919 BAGS TOTAL COST OF CEMENT: 46509.0615
SAY : 197.9109 BAGS TOTAL COST OF SAND : 3298.515
VOLUME OF SAND: 9.9955 CU.M.
SAY : 10.99505 CU.M.
CHB ESTIMATOR
2
PROJECT: CLUB HOUSE
LOCATION:MENZI VILLAGE
WORK AREA:
PARAMETERS:
SUBTRACTIVE:
WINDOW 1 WINDOW 2 WINDOW 3 WINDOW 4 WINDOW 5 WINDOW 6 WINDOW 7 WINDOW 8
SET:
WIDTH:
HEIGTH:
AREA: 0 0 0 0 0 0 0 0
DOOR 1 DOOR 2 DOOR 3 DOOR 4 DOOR 5 DOOR 6 DOOR 7 DOOR 8
SET:
WIDTH:
HEIGTH:
AREA: 0 0 0 0 0 0 0 0
OUT PUT:
AREA: 49.00
LAYER: 5 TOTAL COST: 4,716.25
COLUMN: 122.5
NO. OF PCS 612.5 say 673.75
MORTAR ESTIMATOR
MIXTURE: CLASS B
PARAMETER: RATIO : 1:3
COST OF CEMENT: 240 PER BAG
COST OF SAND: 300 PER cubic
OUT PUT:
NO. OF CEMENT: 25.578 BAGS TOTAL COST OF CEMENT: 6752.592
SAY : 28.1358 BAGS TOTAL COST OF SAND : 703.395
VOLUME OF SAND: 2.1315 CU.M.
SAY : 2.34465 CU.M.
OUT PUT:
NO. OF CEMENT: 44.1 BAGS TOTAL COST OF CEMENT: 11399.85
SAY : 48.51 BAGS TOTAL COST OF SAND : 808.5
VOLUME OF SAND: 2.45 CU.M.
SAY : 2.695 CU.M.
TILE WORKS ESTIMATE
REFERENCE INPUT OUTPUT
COMMERCIAL SIZE NO. OF TILES AREA NO. OF SET TOTAL NO. OF TILES IDEAL REQUEST REMARKS
(CENTIMETER) (PER SQUARE METER) (SQ.M.) AREA
10X10 100 0.00 0.00 0
100 0.00 0.00 0
100 0.00 0.00 0
10X20 50 0.00 0.00 0
50 0.00 0.00 0
50 0.00 0.00 0
15X15 44.44 0.00 0.00 0
44.44 0.00 0.00 0
44.44 0.00 0.00 0
15X20 33.33 0.00 0.00 0
33.33 0.00 0.00 0
33.33 0.00 0.00 0
15X30 22.22 0.00 0.00 0
22.22 0.00 0.00 0
22.22 0.00 0.00 0
20X20 25 0.96 4 3.84 96.00 105.6 CR FLOOR
25 0.00 0.00 0
25 0.00 0.00 0
20X30 16.66 5.25 3 15.75 262.40 288.6345 CR WALL