Beruflich Dokumente
Kultur Dokumente
Inspection
Handbook
This is the fourth edition of the Tank Container
Inspection Handbook. This handbook will be
updated from time to time.
CONTENTS
1
SECTION 5 Identification of Manufacturers'
Defects (73)
Procedure for Reporting
Manufacturers' Defects (78)
Warranty Report - New Defects (81)
July 2009
2
Section 1
SAFETY
3
Section 1 - Safety
Contents of Section
4
DO NOT OPERATE ANY VALVES /FITTINGS
OR ENTER ANY TANK WHICH DOES NOT
POSSESS A VALID SAFETY DOCUMENT.
INTRODUCTION
5
Personnel must not enter any tank
container until a tank entry permit has been
completed. Entry permits are designed to help
ensure compliance with confined space entry
laws and regulations of all governments having
jurisdiction (nation, state/province, locality,
etc.).
6
Sudden release of pressure from discharge
valves or manlid if opened while tank is under
pressure. Avoid standing in front of fittings,
openings or over the manlid if the possibility of
sudden pressure discharge exists. Personnel
should depressurise the tank vessel by
carefully operating the airline valve. Do not
depressurise the tank vessel by attempting to
open the manlid.
7
8
Section 2
DEFINITIONS AND
CLEANING
TERMINOLOGY
9
Section 2 -
Definitions And Cleaning Terminology
Contents of Section
Definitions. (11)
1 Damage (11)
2 Age Related Deterioration (11)
3 Improper Repairs (11)
4 Full Refurbishment (12)
5 Partial Refurbishment (12)
6 Tank (13)
7 Hazardous Tank (13)
8 Statutory Test Date (13)
9 Detachable Parts (13)
10 Consequential Damage (13)
11 Cleaning Terminology (14)
a) Evidence of last cargo (14)
b) Material Safety Data Sheet (MSDS)(14)
c) Certificate of Cleanliness (14)
d) Cleaning Receipt (15)
e) Entry Permit (or Safety Certificate) (15)
f) Safety Document (16)
g) Qualified Person (16)
h) Specialist Cleaning Contractor (16)
i) Transferable Stain (17)
12. GE SeaCo Surveyor (17)
Appendix 2.1 Cleanliness Certificate (18)
Appendix 2.2 Cleaning Receipt (19)
Appendix 2.3 Entry Permit (20)
10
DEFINITIONS
The following definitions are used in this
manual:
1 DAMAGE
3 IMPROPER REPAIRS
11
- The repair is of a quality or condition
which could still be defined as damage
according to GE SeaCo guidelines.
4 FULL REFURBISHMENT
5 PARTIAL REFURBISHMENT
12
6 TANK
7 UN PORTABLE TANK
9 DETACHABLE PARTS
10 CONSEQUENTIAL DAMAGE
13
11 CLEANING TERMINOLOGY
c) Certificate of Cleanliness
14
Cleaning Certificate Validity Date
15
- Tests carried out (as applicable)
- oxygen reading (gas free)
- Purpose of tank entry
- All necessary precautions have been
taken to make the tank safe for
entering and carrying out prescribed
work during the specified time.
f) Cleaning Document
- Cleanliness receipt
- Cleanliness certificate
- Entry permit (safety certificate)
16
i) Transferable Stain
12 GE SeaCo Surveyor
Any GE SeaCo Engineer or any Engineer
authorised by GE SeaCo to carry out Tank
inspections or surveys.
17
APPENDIX 2.1 (GE SeaCo preferred format)
CLEANLINESS CERTIFICATE
ISSUED BY SURVEYOR
TANK NO:
CLEANING PROCESS:
INTERIOR
Entry made into tank by surveyor YES
Free from odour YES
Free from all cargo and contamination YES
Free from corrosion or pitting YES
(if no, report detail below)
Dry YES
VALVES/FITTINGS free from all cargo and contamination
Valves YES
Manlid seal YES
Dip-pipe/ Syphon pipe YES
Gas free Entry Permit issued YES
REMARKS
A thorough visual examination has been carried out and the interior of
the tank, valves and fittings are free of contamination, previous cargo
and odour.
The tank is clean and dry.
18
APPENDIX 2.2
CLEANING RECEIPT (Wash Ticket)
ISSUED BY CLEANING COMPANY
* TANK NO:
* PLACE OF ISSUE:
* CLEANING PROCESS:
* LAST CARGO :
* UN NO. :
REMARKS
19
APPENDIX 2.3
ENTRY PERMIT
ISSUED BY DEPOT / SURVEYOR
ISSUED BY SURVEYOR
- SURVEY COMPANY NAME AND ADDRESS:
TANK NO:
CLEANING PROCESS:
A full examination of the hazard of the tank has been carried out and
the appropriate safety tests completed with acceptable results.
The tank is safe to enter.
20
Section 3
COMPLETION OF TANK
REPAIR ESTIMATE
and
COMPLETION OF
INTERNAL SHELL
CONDITION CHART
21
Section 3 - Completion of Tank
Repair Estimate
and
Completion of Internal
Shell Condition Chart
Contents of Section
22
COMPLETION OF TANKCONTAINER
REPAIR ESTIMATE
INTRODUCTION
23
Additionally, information concerning last cargo
will have already been advised in writing by the
GE SeaCo Ops Centre prior to redelivery.
(4) COMPONENT
24
(5) DAMAGE CODES
If estimating with the ISO/Cedex coding system
use the 2 digit alpha codes to denote the
damage.
25
(iii) Rust, or Damage caused by Rust
(Code 17 (CO))
Code 17 (CO) must be used only in clearly
defined circumstances as follows:
(a) It must be used as a single code in any line
of the Repair Estimate to describe damage
caused by rust which is not a result of a
Manufacturer's Defect or cargo attack or
contamination. The nature of the damage
will be sufficiently implied in the
appropriate Repair Code(s) which are
entered in the adjoining column (see (11)
below).
(b) It must be used in any line of the Repair
Estimate to describe rust, as defined in (a)
above, which requires rectification, by
partial refurbishment.
(c) In the case of full refurbishment of a tank
container Damage code 17 (CO) can only
be used for containers which are more
than 5 years old or which are subject to a
Refurbishment TTB.
For containers less than 5 years old use
Damage Code 62 (MN) - (New
Manufacturing Defect) or 09 (CD) -
(Consequential Damage).
26
(v) Manufacturers' Defects
(Codes 26 (ME) and 62(MN))
27
(6) REPAIR CODES
28
INTERNAL SHELL CONDITION CHART
INTRODUCTION
Whenever there is evidence of interior tank
stains, shell pitting, rust, scoring, scratches,
gouges or any other unsatisfactory internal
condition, this must be documented on the
Tank Container Interior Shell Chart. See
Appendix 3.1 for an example of a form.
When used to document unsatisfactory internal
conditions, the Tank Container Interior Shell
Chart becomes an addendum to the Tank RE
and has the same distribution as the RE. In
addition a copy of the chart must be faxed to
the Engineering and Technical Services Dept.,
GE SeaCo London. (Fax 00 44 (0)207 939 5650 ).
The Inspector enters the following information
when completing the form:
(1) STANDING DATA
Tank Serial Number
Enter tank prefix, serial number and check digit.
Depot/Location
Enter depot name, or preferably, GES depot
code for depot location at which inspection is
performed.
Date
Enter date of inspection.
Report by
Enter Inspector's name.
Inspector Signature
Enter Inspector's signature (at bottom of form)
Tank Unit Type
Enter GE SeaCo tank code
Tank Material
Enter barrel material, i.e. AISI Type 316 steel, or
if lined tank, identify lining material.
29
Last Cargo
Enter the proper name of the last cargo.
UN Number
Enter United Nations reference number.
30
APPENDIX 3.1 - INTERIOR SHELL CHART
REMARKS
FRONT
MANHOLE MANHOLE
AREA AREA
REAR
SIGNATURE
31
APPENDIX 3.2
Location Code 1
R right side
L left side
T roof or top
B bottom (floor)
F front end
D door / ladder & data plate end
U understructure
X whole container
I container interior
E container exterior
32
Location Code 2
33
Location Code 3
34
Location Code 4
35
The diagrams below illustrate the various faces
and components and their appropriate codes:
H1 H4
H2 H3
T1 T2 T3 T4
B1 B2 B3 B4
G1 G2 G3 G4
H5 H4 H3 H2 H1
T3 T2 T1
T5 T4
B5 B4 B3 B2 B1
G5 G4 G3 G2 G1
ladder end
Left Side View
36
APPENDIX 3.3
37
ISO ISO Loc.
ISO COMPONENT DESC
Code Code
Tank Markings (Location = ADNN)
YAA AAR markings
YBM BAM marking
YCT CTC markings
MCA Caution marking
YPM Product marking
YPP Product plate holder LNNN, RNNN,
ADNN
YRI RID/ADR markings
YRT RTMD markings
MST Size marking
YUI UIC markings LNNN, RNNN,
YOM Operator marking ADNN
YFR FRA markings
MHT Height Marking
YDO DOT markings
MMI Weight marking DNNN, ADNN
MCC Country Code LNNN, RNNN, DNNN,
MOL Owners logo FNNN, ADNN
MIS ID set
MSD Markings digit LNNN, RNNN, DNNN,
FNNN, TX1N, TX5N,
MFS Markings set ADNN
MOC Owners code
MPL Cargo plate ADNN
MPD Consolidated data plate ADNN
MPS CSC plate ADNN
MCE ACEP Marking ADNN
MPC Customs plate ADNN
YEA Earth connection marking ADNN
YEW Electrical wiring marking ADNN
YFU FLA plate ADNN
38
ISO ISO Loc.
ISO COMPONENT DESC
Code Code
MPO Owners plate ADNN
YTA Tank plate ADNN
YCC Calibration chart ADNN
MPM Manufacturers plate ADNN
MRU Markings other ADNN
Tank Frame (Location = AFNN)
YWA Walkway AFNN
YWB Walkway / Replace Large AFNN
YWC Walkway / Replace Med AFNN
YWD Walkway / Replace Small AFNN
YWF Walkway fittings AFNN
YWM Walkway mount Bracket AFNN
YTF Tank Frame AFNN
YVP Vertical post AFNN
LH1N to LH5N, LG1N to
RLA Side rail LG5N, RH1N to RH5N, RG1N
to RG5N. LH12 to LH45,
LG12 to LG45, RH12 to
RH45, RG12 to RG45, LH13
to LH35, LG13 to LG35, RH13
RLA Side rail to RH35, RG13 to RG35,
LH14 to LH25, LG14 to LG25,
RH14 to RH25, RG14 to
RG25, LH15, LG15, RH15,
RLC Side Rail RG15, DG2N, DG3N, DG23,
Consani DH2N, DH3N, DH23, FG2N,
YHR Horizontal FG3N, FG23, FH2N, FH3N,
rail FH23.
DB2N, DB3N, DT2N, DT3N,
FB2N, FB3N, FT2N, FT3N,
LB1N, LB5N, LT1N, LT5N,
RLG Rail gusset
RB1N, RB5N, RT1N, RT5N,
TL1N, TL5N, TR1N, TR5N,
UL1N, UL5N, UR1N, UR5N.
39
ISO ISO Loc.
ISO COMPONENT DESC
Code Code
DG1N, DG4N, DH1N,
CFG Corner fitting DH4N, FG1N, FG4N,
FH1N, FH4N
CPA Corner post DB1N, DT1N, DX1N,
CPC Corn post - Consani DB4N, DT4N, DX4N,
FB1N, FT1N, FX1N,
CPV Corner Post - CPV FB4N, FT4N, FX4N.
YDH Document holder AFNN
YDG Doct Holder Cap & Chain AFNN
YDF Doc. Holder Fixing Bolts AFNN
YDR Diagonal Brace
KDG Diagonal Bracing Gussets
YFF Frame Fasteners D*,L* ,R*, F*,
YTG Frame gusset/stiffener T*, U*, AFNN
YMP Frame strap mount pad
YFS Frame Strap
YEC Earth connection AFNN
YLT Load Transfer Area AFNN
KGD Rear Beam Guide (Tank) AFNN
KEI RR Sill Elect Instl-Tank AFNN
YSA Saddle AFNN
YSK Skirt D*, F*, AFNN
Tank Heating (Location = AHNN)
TMT Cargo Thermostat AHNN
CBB Circuit breaker 2 Amp AHNN
CBR Circuit breaker 20 Amp AHNN
SMN Elec.On/Off Switch AHNN
SVS Elec.Volt.Switch AHNN
LIT Electric Lamp AHNN
BEA Electrical Control Box AHNN
YEH Electrical heating element AHNN
40
ISO ISO Loc.
ISO COMPONENT DESC
Code Code
YID Elect Instruction Decal AHNN
WIR Electrical Wiring AHNN
BEG Control Box Door Gasket AHNN
YHC Heating Element Cap AHNN
YET Heating Terminal Block AHNN
ECB Mains Cable 460 volt AHNN
EPL Mains Plug 460 volt AHNN
YSI Steam inlet/outlet AHNN
YDV Steam trap AHNN
YSE Steam tubes AHNN
YSV Tank steam safety valve AHNN
YSL Tank steam line cap AHNN
YTM Tank thermometer AHNN
YTW Thermometer Receptacle AHNN
Tank Insulation (= AINN)
YIG Cladding - GRP
YIZ Cladding -Stainl. Steel
DX2N, DX3N,
YIC Cladding - Aluminum
FX2N, FX3N,
YIN Insulation-foam LX1N to LX5N,
YIR Insulation Rockwool RX1N to RX5N,
PRV Cladding rivets TX1N to TX5N,
UX1N to UX5N,
YCD Cladding support AINN
YCS Tank cladding strap
YCR Clad. Strap Rivets
YSN Sun Shield AINN
YTS Sun shield support AINN
YTM Tank thermometer AINN
41
ISO ISO Loc.
ISO COMPONENT DESC
Code Code
Tank Loading/Unloading (= ALNN)
YAV Air Valve ALNN
YAP Airline Pipe ALNN
YAB Airline Valve - Ball ALNN
YAS Airline Vl - Ball Seating ALNN
YAE Airline Valve (1.5") Flange ALNN
YAT Airline Valve (1.5") Screw ALNN
YAF Airline Valve (2") Flanged ALNN
YAU Airline Valve (2") Screwed ALNN
YAG Airline Vlv / Tank Gsket ALNN
YCA Airline Valve Cap ALNN
YAC Airline Valve Cap (1 in) ALNN
YCG Airline Valve Cap Seal ALNN
YAD Airline Valve Cap(2") ALNN
YAW Weld-in Flange / Airlin Vl ALNN
YXW Weld-in Flange / 3 in Vlv ALNN
YZW Weld-in Flange / 2 in Vlv ALNN
YYW Weld-in Flange / 1in Vlv ALNN
YBF Blind flange ALNN
YGH Bolts ( Bott/Foot valve) ALNN
YBD Bott Outlt Ball Valve - Ball ALNN
YBR Btm Out Vlv - Ball Seat Ring ALNN
YBP Btm Out Btrfly Vl -Clos Plt ALNN
Bott Outlt Buttrfly Valve -
YBK ALNN
Closure Plate Seat Ring
YBO Btm Out Bttrfly Vl - 'O' Rng ALNN
YBS Btm Out Bttrfly Vlv - Spindle ALNN
YFC Bottom Out Cap and chain ALNN
YFG Bottom Outlet Cap Seal ALNN
YFO Btm Out Foot Vlv - 'O' Ring ALNN
YFP Btm Out Foot Vl- Pres Plat ALNN
42
ISO ISO Loc.
ISO COMPONENT DESC
Code Code
YFK Btm Out Foot Vl- Seat Rng ALNN
YFN Bott Outlet Foot Vlv - Spring ALNN
YFD Bott Outlet Vlv / Blank Bolts ALNN
YFE Bott Out Vlv / Blank Gasket ALNN
YBB Bott Outlt Vlv / Foot Bolts ALNN
YBG Bott Outlt Vlv / Foot Gasket ALNN
YBV Bottom Outlet Valve Ass ALNN
YFB Bott Out Valve Blind Flange ALNN
YBL Bottom Outlet Valve Handle ALNN
YFA Bott Out Vlv Spigot Flange ALNN
YBT Bott Outlet Valve TIR Tab ALNN
YBW Weld-in Flang / Bot Outlt Vlv ALNN
YCO Coupling ALNN
YEV External valve assembly ALNN
YFJ Foot Valve / Tank Gasket ALNN
YFV Foot valve assembly ALNN
VVH Foot Valve Handle ALNN
YGD Foot vlv Bolts(Ball- Foot vlv) ALNN
YGV Foot vlv Bolt(Foot vlv - Tnk) ALNN
YGE Foot vlv Bolts(Plat- Ball Vlv ) ALNN
YGA Foot valve gasket ALNN
YFJ Foot Valve / Tank Gasket ALNN
YGB Foot vl Gaskt (Ball-Foot vlv) ALNN
YGP Foot vlv Gasket(Plat -Ball Vl) ALNN
YFH Foot Valve Operating Lever ALNN
YLN Level indicator ALNN
YMA Manometer /Pressure guage ALNN
YMS Manometer step guard ALNN
YEG Remote Trip - Cable Guard ALNN
YTV Sample valve assembly ALNN
43
ISO ISO Loc.
ISO COMPONENT DESC
Code Code
YPV Spacer ALNN
YEU Top Ext. Valve Assembly ALNN
YXB Top Outlet Ball Valve - Ball ALNN
YXC Top Out Bal V -Bal Seat Rng ALNN
YGJ Top Outlt B'fly Valve Seal Kit
ALNN
YTD Top Outlt Blind Flange Bolts ALNN
YTC Top Outlt Blind Flang Gasket ALNN
YXP Top Out Butfly Vl - Cls. Plat
ALNN
Top Outlet Butterfly Valve -
YXR ALNN
Closure Plate Seat Ring
YXS Top Outlt Butfly Vl - Spindle ALNN
YXO Top Outl Butrfly Vlv 'O' Ring ALNN
YXD Top Outlt Prss Vlv - 'O' Ring ALNN
YXM Top Outlt Prs. Vl - Pres. Plat ALNN
YXN Top Out Pres Vl - Seat Ring ALNN
YTP Top Outlet Valv / Blank Gskt ALNN
YEJ Top Outlet Valve / Gasket ALNN
YTE Top Outlet Valve / Tnk Bolts ALNN
YTJ Top Outlet Valv / Tnk Gasket ALNN
YTO Top Outlet Valve Assembly ALNN
YTB Top Outlt Vlv Blind Flange ALNN
YTN Top Outlet 10 inch Valve ALNN
YWT Weld-in Flg / Top Outl 10 V ALNN
YTH Top Outlt Vlv Opertg Handle ALNN
YTI Top Outlet Valve TIR Tab ALNN
YCU Custom Seal Tank ALNN
YDI Diptube ALNN
Tank Manhole (Location = AMNN)
YMH Manhole assembly AMNN
YMJ Manlid Handle AMNN
YMF Manhole flange AMNN
44
ISO ISO Loc.
ISO COMPONENT DESC
Code Code
YMC Manhole cover (manlid) AMNN
YMI Manlid cover 6 sw. bolt AMNN
YMQ Manlid cover 8 sw. bolts AMNN
YMK Manway Swingbolt Handnut AMNN
YML Manway Swingbolt Lugs AMNN
YHD Manlid fasteners AMNN
YMO Manlid hinges AMNN
YMB Manlid Hinge Bracket AMNN
YMG Manlid gasket AMNN
YMU Manlid Gasket Seating AMNN
YMT Manlid TIR Tab AMNN
YMD Manhole dipstick AMNN
YMR Manhole dipstick holder AMNN
YME Manway Dipstick Handle AMNN
Tank Pressure Vessel (= APNN)
YSH Shell DX2N, DX3N, FX2N, FX3N,
YXT Shell Ext.r LX1N to LX5N, RX1N to
YNT Shell Int.r RX5N, TX1N to TX5N,
UX1N to UX5N.
YLI Tank lining
Stiffening LX1N to LX5N, RX1N to RX5N,
YST
ring TX1N to TX5N, UX1N to UX5N
YHE Head TX1N to TX5N
YSU Sump UX1N to UX5N
YBA Baffle APNN
YBH Baffle holder APNN
YPA Airline Valve Pad APNN
YPB Bottom Outlet Valve Pad APNN
YPR Pressure Relief Valve Pad APNN
YPT Top outlet valve pad APNN
YUF Vapour flange APNN
YFL Welded flange APNN
45
ISO ISO Loc.
ISO COMPONENT DESC
Code Code
Tank Safety Devices (= ASNN)
YEM Emerg'ncy closr remote cntrl ASNN
YFW Remote Trip - Cable ASNN
YER Remt Trip - Cabl Guard Fixgs ASNN
YEB Remote Trip Bracket ASNN
YEL Remote Trip Operatg Handle ASNN
YED Remote Trip Warning Decal ASNN
YOH Tank overheat fusible link ASNN
YEC Earth connection ASNN
YCF Flame arrestor - cowl type ASNN
YFM Flame arrestor - maxi Hi-flow ASNN
YEX Gas tank /excess flow valve ASNN
YIS Internal safety valve, gas tank ASNN
YTR Tank safety relief valve ASNN
YFT Relief valve flame trap ASNN
YGF Saf. Vl. Hi-Flow PTFE seals ASNN
YGV Saf. Valv.Hiflow Viton seals ASNN
YSR Safety relief flange ASNN
YPI Safety Rlf Vlv - Inr Pres. Sprg ASNN
YPO Safty Rlief Vl - Out Pres Spg ASNN
YVS Safety Relf Vlv - Vac. Sprg ASNN
YTQ Safety Relief Valve Gasket ASNN
YSW Weld-in Flg / Safety Relf Vl ASNN
YRU Tank rupture disc ASNN
YRD Tank rupture disc holders ASNN
YRG Bursting disc gasket ASNN
YRM Tank safty release manomtr ASNN
46
ISO ISO Loc.
ISO COMPONENT DESC
Code Code
Miscellaneous Tank (= AZNN)
YTT 2.5 Year Statutory Test AZNN
YTX 5 Years Statutory Test AZNN
YCI Inspt & Issue Clean Cert. AZNN
YGC Inspt & Issue Gas free Cert. AZNN
YSC Inspect / Issue Safety Cert. AZNN
YTL Leak Test (Barrel/Vlvs etc) AZNN
YTK Spark Test AZNN
HWR Hardware, screws, bolts AZNN
YWN Tank washing nozzles AZNN
BUL Tank Technical Bulletin AZNN
ZZZ No component code AZNN
47
APPENDIX 3.4 Damage Code Description
48
Damage Code Description
GES ISO Costs
ISO Description
Code Code Alloc A/c
14 DH* Dented and Holed L
15 MS* Missing/Lost L
NP Not in Place L
16 LO* Loose L
17 CH Corroded/Holed GES-PR
CO* Corroded/Rusty GES-PR
18 ML* Markings/Labels L
CK* Cracked L
19 CW Cracked Weld L
GO GRP Surface Crack L
GP GRP Surface Crack L
MA Misaligned L
20 Not Within ISO
NI* L
Dimensions
NT* Foreign Fitting L
21 NT Not within TIR regs L
SW Switched L
22 OD Out of Date GES-PR
TR* Test Required GES-PR
DB* Debris/Dunnage L
DY Dirty L
23 Ol Oil Saturated L
OR Odour L
OS Oil Stains L
IO* Old Improper Repair GES- D
24 IR Improper Repair GES- D
NV Not as reqd by user GES- D
IN* New Improper Repair L
25 MM Mismatched L
OU Other Unacceptable L
WM Wrong Material L
26 ME* Existing Manu Defect GES- MD
49
Damage Code Description
GES ISO Costs
ISO Description
Code Code Alloc A/c
27 BK Blocked L
FZ* Frozen L
RO Rotted GES-PR
RT Rotten GES-PR
28 WN Worn GES-PR
WT* Wear and Tear GES-PR
WV Weathered GES-PR
29 PS* Pitted Surface L
50 OI* Over-Inflated L
UI Tyre Over-inflated L
51 IP* Imploded L
52 IC* Improper Cleaniing L
53 OH* Overheating L
54 FD* Forklift Damage L
55 FQ* Food Quality GES-PR
60 SH* Short/Open Circuit L
61 LF* Low Fluid Level L
MN* New Manu Defect GES-
62
PF Paint Failure New MD
63 LK* Leak L
FS* Flat Spots L
64 TU Uneven Tread L
WB Bald Tyre L
66 RD* Rollover Damage L
BL Blowout L
67 FP* Flat/puncture L
RF Run Flat L
DL* Delaminated L
68 SP Separated L
TS Tyre Damage L
69 NL* Nails L
70 RA* Remove For Access L
50
Damage Code Description
GES ISO Costs
ISO Description
Code Code Alloc A/c
ZZ Special Damage L
Refurbishment GES-
94 RP *
Program Cap
Floor Refurbishment GES-
FL*
Program Cap
95
GES-
RR Floor Reburb Program Cap
Preventative GES-
97 PM*
Maintenance PR
GES-
99 RC* Conversion Required Cap
51
APPENDIX 3.5
Repair Code Description
GES ISO
Repair Repair ISO Description
Code Code
GS* Straighten
30 RA Re-align
RS Straighten and Resecure
3X ///// Accumulated. straightening
(code not for use by depots)
IT* Insert
31
OP Overlapping
32 SF Section and Foam
SN* Section
BX Fit by M&R Stock
CH Recharge
EX Fit Part EX Owners Stock
33 IN Install
MK Re mark
RP* Replace
TP Top Up
34 WD* Weld
35 GW* Straighten and weld
DR Drain
GT Remove Glue and Tape
36 MV Remove Markings
RD Remove and Dispose
RM* Remove
37 WP* Sweep
38 WW* Water Wash
39 SC* Steam Clean
40 AB* Abrasive Clean & Paint
52
Repair Code Description
GES ISO
Repair Repair ISO Description
Code Code
PA Paint
41 PR* Partial Refurbishment
PS Wire brush and paint
HN Handling Required
PI Pre-trip Inspection
PV Repairs prior to refurb
42 RU Rebrush
SI Splice
SP* Special Repair Necessary
TR Temporary Repair
ZZ Special Repair
43 SE* Seal
SR Reseal
44 FT Refit
RE* Resecure
45 FR* Free and ease
LC Lubricate
BU Blank Out
46 OX Overlay
PT* Patch
47 RG* Re-Glass / GRP Infill
48 DO* Deodorise
49 PC* Polish Clean
4X NA* No Action Necessary
50 SD* Sanding / Grind smooth
51 DU* Dry Out
52 AJ Adjust
TC* Test Calibrate
53
Repair Code Description
GES ISO
Repair Repair ISO Description
Code Code
AC Air Clean
53
DC* Dismantle and Clean
54 PP* Pickle/Passivate
55 CC* Chemical Clean
57 PX* Patch and Foam
58 IF* Full length insert
59 DF* Drain and Fill
5X TB* Tech Bulletin completed
61 XW* Grind and Weld
BD Brand
66 MD* Modify
RT Re Rate
67 IP* Photograph
77 RR* Remove and Refit
80 RW* Rewire
81 AR* Air
88 RX* Renew with Recon Part
89 RB* Rebuild
95 RC* Recondition/Refurbish
97 VM* Preventative Maintenance
99 CO* Conversion
54
APPENDIX 3.6 COST ALLOCATION
ANY ITEM
Repair of impact damage. Various L
Replacement of missing 15 L
components. (MS)
Replacement of life expired 28 GESPR
components, damage resulting (WT)
from inevitable exposure to
normal operating conditions.
e.g. hardening / deterioration
of seals, discoloration of
decals, electrical component
not functioning and no signs of
damage etc.
Unacceptable improper repairs 25 L
done during the most recent (IN)
lease or unacceptable non
standard components fitted
during the most recent lease.
Unacceptable improper repairs 24 GESD
done prior to the most recent (IO)
lease or unacceptable non-
standard components fitted
prior to the most recent lease.
Consequential damage 09 L
resulting from the Lessee's (CD)
failure to carry out a necessary
repair. i.e. saturation of the
insulation resulting from a
failure to repair the cladding.
55
Description / Remarks Damg Cost
Code Alloc.
CLEANLINESS
Cleanliness Certificate missing 15 L
(MS)
Normal cleaning of the tank - 23 L
interior and cargo spillage on (DB)
exterior
Normal cleaning of the tank - 28 GESPR
exterior (road dirt, not cargo (WT)
spillage)
Additional cleaning of the tank 52 L
due to improper cleaning (IP)
before redelivery when the
tank is returned with a valid
cleaning document.
This is when the tank is not
sufficiently clean. i.e. re-
cleaning of seals , valves or
blemishes / traces of previous
cargo
Removal of non standard 18 L
decals or marks. (ML)
Residue of previous cargo that 08 L
can only be removed by (CT)
special procedures. These
procedures can include
structural repair, partial or full
refurbishment, component
replacement, or a special
cleaning method.
This code should not be used
for seals and gaskets
56
Description / Remarks Damg Cost
Code Alloc.
POLISHING
Polishing of the tank - interior. 23 L
e.g. .removal of cargo residues (DB)
TESTING
Periodic testing of the tank, e.g. 22 GESPR
21/2 and 5 year tests (TR)
Leak test due to repairs on the Various L
shell etc.(code leak test same
as the damage)
57
Description / Remarks Damg Cost
Code Alloc.
MANUFACTURING DEFECTS
New manufacturing defects 62 New
(i.e. a manufacturing defect (MN) Man.
not detailed by a current Defect
technical bulletin). this also
includes post refurbishment
repair work.
Existing manufturing defect 26 Existing
(detailed by a current TTB). (ME) Man.
Defect
SEALANT
Replacement of sealant which 28 GESPR
has failed as a result of ARD. (WT)
Sealant required as a result of 16 L
an impact damage or improper (LO)
operation.
58
Section 4
INSPECTION
PROCEDURES
59
Section 4 - Inspection Procedures
Contents of Section
60
INSPECTION PROCEDURES
INTRODUCTION
There are seven standard inspections that
might be carried out while tank containers are in
depot off-hire. GE SeaCo will confirm the
inspections required.
All inspections must be carried out by a
GE SeaCo Surveyor except for pre-delivery
Onhire Surveys which should be carried out by the
depot's own quality control personnel.
Inspection Types and their Objectives
a) Post-Estimate (Estimate Verification) :
Ensures the Repair Estimate conforms to
GE SeaCo requirements.
b) Joint-survey:
Confirms with the customer's surveyor the
allocation of repair costs.
c) Post-Repair:
Ensures the tank has been repaired
correctly and is now a status A tank.
d) Combined - Post-Repair and On-Hire:
Ensures the tank has been repaired
correctly and is now a status A tank.
Additionally, provide for inspection as in f).
e) Supplementary Estimate Verification:
Ensure the additional work is necessary.
f) Lessee On-Hire Survey
Performed prior to lease, ensuring the tank
complies with requirements. Include a
written report and photos together with an
updated cleaning certificate.
g) Pre-delivery Inspection
Depot check prior to lease ensuring the
tank complies with requirements.
61
A. POST-ESTIMATE INSPECTION
Authenticating the Repair Estimate
Must be performed promptly after depot has
completed the Repair Estimate.
Must be performed on ALL tanks:
- returned from lease
- freemoved in a damaged condition
- freemoved units that sustain transit damage
Is not required on tanks:
- freemoved in a Status A condition.
- freemoved from manufacturer
Note: These tanks will require a visual exterior
inspection for transit damage
Action to be taken by the GES Surveyor:
The GE SeaCo Surveyor must inspect the tank
and ensure that the repair estimate is correct.
the Repair Estimate must be completed in
accordance with the instructions in Section 3.
When the GE SeaCo Surveyor is satisfied that
the Repair Estimate for the Tank is correct he
must sign and date the estimate.
Repair estimate checks must include:
- A current, valid Certificate of Cleanliness.
- The last cargo data is correctly entered.
- Damage Codes noted correctly, ensuring
the Cost Allocation is correct.
- Only damage requiring repair is noted.
- Correct method of repair is to be adopted.
- Tank Technical Bulletin requirements met.
- Repair costs (labour / materials) are correct.
Using combination damages and low cost re-
conditioned components as opposed to new.
- Function Testing of the electrical heating or
other components has been carried out.
- Statutory Test requirements complied with.
- An internal mapping chart completed if a
problem exists on the shell interior.
62
B. JOINT-SURVEYS (with customers surveyor)
The joint survey is carried out after the post-
estimate inspection and must be performed
using the GE SeaCo - Printed Estimate.
The customer's surveyor must provide his own
copy of the Repair Estimate. All customers
surveyors must attend at same time.
The two surveyors must agree the material
costs and labour hours as allocated or an
amended allocation. The estimate must clearly
show all amendments.
The estimate must be signed and dated by
both the GE SeaCo and customer's surveyors.
The GE SeaCo Surveyor may alter an item on
the estimate by amending the damage and
repair codes, description and the costs.
After amendment the repair must still conform
to Tank Inspection criteria or requirements.
Cost amendments must be agreed with depot.
If the customer's surveyor agrees costs, but
refuses to sign the estimate, he should be
warned that the survey is invalidated. The
GE SeaCo Surveyor must write on the estimate
Costs agreed but customer's surveyor
unwilling to sign, and sign / date it himself.
The depot must report the joint survey result
and amended costs immediately to the local
GE SeaCo Ops Centre.
If agreement is not reached between the
surveyors then the GE SeaCo Surveyor must
immediately report to the GE SeaCo Ops Centre.
Lessee Refused Costs Report
- Details of refused costs
- Colour photographs of the refused items
- Reasons why costs refused..
- Send report to GE SeaCo Ops Centre.
- A copy of this form is shown at Appendix 4.2.
63
C. POST-REPAIR INSPECTION
Post-Repair Inspection
The following procedures must be followed
when performing a Post-Repair Inspection.
At any time new or amended requirements or
criteria may be introduced for specific tanks or
tank containers in general, these must be
applied in addition to the procedures below
during the Post-Repair Inspection.
64
C.3 Photographs and On-Hire Report
Every tank container will require a number of
photographs to be taken during the On-Hire
Inspection. The photographs must clearly
show - interior, sides, ends, top, underside and
the top and bottom valve/ manlid compartment.
An On-Hire report must be completed in an
approved format together with an internal
mapping chart. The Cleaning Certificate shall
be renewed. The report and photographs must
be made available on the Inspection
Companys web site.
C.5 GQ decal
When the On-Hire inspector is satisfied that the
tank container meets all the necessary criteria
he must issue a GQ sticker for that tank
container. This should be placed into the
document holder. Any previous GQ Sticker
must be removed.
Only when all the above steps have been
satisfactorily completed, can the tank be noted a
status A tank, the depot may then transmit the
unit status to the Ops Centre.
65
NOTES Post-Repair
Note 1
If the GE SeaCo Surveyor considers that the
depot has omitted to repair items included on
the estimate or has not repaired items
correctly, then he must clearly mark these
items for rework on the estimate.
The cost of rework is for the depots account.
Rework repairs must commence immediately
and be completed in a timescale agreed with
the GE SeaCo Surveyor.
Following completion of rework, the unit must
be re-inspected by the GE SeaCo Surveyor.
Inspections will continue until the GE SeaCo
Surveyor is satisfied that it meets the
GE SeaCo requirements and quality standards.
Note 2
If the GE SeaCo Surveyor considers that
additional repairs are required, the depot must
produce an Additional Estimate which must be
approved by the GE SeaCo Surveyor.
If the additional repairs are required as a result
of damage caused to the unit whilst in the
depot or repairs that should have been
identified by the depot estimator at the time of
offhire, the costs of rectification must be for the
depot account. In this case no Additional
Estimate is required.
66
D COMBINED POST-REPAIR & ON-HIRE
This inspection combines the inspection
requirements of
C Post-Repair and
F Lessee On-Hire Survey
E. SUPPLEMENTARY ESTIMATE
VERIFICATION
The original estimate should indicate all
damages requiring repair in addition to all
TTBs and maintenance work required at the
time of redelivery.
67
F. LESSEE ON-HIRE SURVEY
If the customer requests an On-hire Survey
then he should be encouraged to attend the
Pre-delivery Inspection. In this case the
procedures below must be followed in addition
to the Pre-delivery Inspection procedures.
If the customer does not require an On-hire
Survey then the Pre-delivery Inspection
carried out by the GE SeaCo Surveyor will
serve to ensure that the tank container is in
good working order prior to delivery to lease.
Procedure
This survey must be carried out with reference to
the criteria detailed in Section 8, Inspection
Guidelines for Tank Containers.
If an item is beyond the acceptable limits as
specified in Section 8 the survey must cease
until the required repairs have been carried out.
If the customer's surveyor accepts the unit as
being in satisfactory operating condition but
nevertheless refuses to sign the On-Hire
Survey form, the GE SeaCo Representative
must note in the REMARKS box the words
acceptable to customer but customer's
surveyor unwilling to sign. The GE SeaCo
Representative must also add brief comments
as to the reason for the refusal. The GE SeaCo
Representative must immediately advise the
local GE SeaCo OPs Centre. In this situation
the unit can be delivered to the customer.
The GE SeaCo Surveyor must immediately
inform the local GE SeaCo Ops Centre:
- Customers surveyor rejects a unit as non-
satisfactory and in the opinion of the
GE SeaCo Surveyor the unit is in
satisfactory condition.
68
- If the customer's surveyor requests further
checks of the unit in addition to those
detailed in this handbook.
If the customer's surveyor has his own On-Hire
Survey report and requests the GE SeaCo
Surveyor to sign it; the GE SeaCo Surveyor
must not sign it unless all the following
conditions are fulfilled:
- All codes used are clearly defined on form.
- All comments relating to the condition and
operating serviceability of the unit are in
accordance with those entered on the
GE SeaCo form.
- The customer's surveyor also signs the
GE SeaCo form.
- The customer's surveyor provides the
GE SeaCo Representative with a copy of
his own On-Hire Survey Report.
The GE SeaCo form is always the official
report confirming the agreement between
GE SeaCo and the customer regarding the
operating condition and serviceability of the
unit. The customer's own On-Hire Survey
Report does NOT take precedence over
GE SeaCo's.
69
G. PRE-DELIVERY INSPECTION
This inspection must be carried out
immediately prior to release of the container.
The depot prior to delivery to the customer
must survey every tank being delivered for
which GE SeaCo has given release
authorisation. In the case of special tanks their
individual requirements must be checked.
The depot must ensure the tank:
- Conforms to GE SeaCo booking requirements
- Any special requirements detailed in the
booking advice have been completed
- The tank container is of the correct type as
detailed in the booking advice.
- If it is more than 6 months since the On-Hire
Inspection then the pre-delivery inspection
must include a leak check.
- Is fit for service according to GE SeaCo repair
requirements and quality standards, including
specific requirements for Special Tanks.
- Must be fully operational according to the
inspection criteria.
If the tank is not repaired correctly, then it must
reworked.
- The cost of rework is for the depot's a/c.
- Rework repairs must commence
immediately and be completed in a
timescale agreed with the GE SeaCo
Operations Centre.
- The unit must be re-inspected
Electrical Or Reefer Tanks - depot must
produce and retain the run test results.
Once the Pre-Delivery Inspection has been
satisfactorily completed then the lower section of
the GQ sticker must be completed.
70
APPENDIX 4.1 GQ Stickers
71
APPENDIX 4.2 Lessee Refused Costs Report
The form shown below must be used to report the
items refused at joint survey by the lessee
surveyor.
LESSEE REFUSED
COSTS REPORT
Unit serial No.: Date:
LESSEE REPRESENTATIVE
Co. Name: Surveyors Name:
GE SeaCo REPRESENTATIVE
Co. Name: Surveyors Name:
72
Section 5
IDENTIFICATION OF
MANUFACTURERS'
DEFECTS
and
PROCEDURE FOR
REPORTING
MANUFACTURERS'
DEFECTS
73
Section 5 -
Identification of Manufacturers' Defects
and
Procedure for Reporting Manufacturers'
Defects
Contents of Section
74
IDENTIFICATION OF MANUFACTURERS'
DEFECTS
75
Expansion of the insulation causing the
insulation and cladding to exceed ISO
tolerances is often the result of moisture
ingress. It may be that defects to the security
or water tightness of the cladding joints at
manufacture are the root cause of the defect.
76
(iii) Corrosion Blisters
This is the most serious type of corrosion and
can cause much damage to the steel unless
promptly treated. Corrosion blisters form below
the paint film and result in deep seated areas of
rust and rapid decomposition of the steel.
In the early stages the blisters appear as small
bumps beneath the paint film which at this
stage is still undamaged. As the steel starts to
break down the size of the blisters increase
until they break through the paint film. By this
stage the corrosion process is well advanced
and will have already significantly reduced the
steel thickness.
77
PROCEDURE FOR REPORTING
MANUFACTURERS' DEFECTS
78
Existing Manufacturers' Defect
PROCEDURE
79
An example of the Warranty Report is shown
as Appendix 1.
80
APPENDIX 5.1
Manufacturer : Inspected By :
Cause of defect :
Comments : Copy to :
81
82
Section 6
IDENTIFICATION OF
FREQUENT MISUSE OF
TANK CONTAINERS
83
Section 6 - Identification of Frequent
Misuse Of Tank Containers
Contents of Section
84
IDENTIFICATION OF FREQUENT MISUSE
OF TANK CONTAINERS
A container may be deemed to have been
misused if it has been subjected to any of the
following conditions which have
resulted in damage:
- Used in excess of the designed
working pressure, or without
ventilation (implosion).
- Handled by any means other than
those specified in ISO document DIS
3874. Top side lift equipment
(unladen tanks only) must be of the
full frame type. Handling by forklift
equipment is not permitted for tank
containers.
- Transported a cargo that has caused
damage by reaction between the
cargo and the container.
- Transported by any vehicle or vessel
which is not suitable for the carriage of
containers.
- Used when the operating or assembly
instructions have not been followed or
when necessary components are not
present or correctly fitted.
Complete the Repair Estimate as normal
be immediately report misuse to Ops
Centre.
85
Containers subjected to misuse may be
identified if they display characteristics
such as:
Used in excess of designed working
pressure.
- splits or distortion to steam tubes or
shell. Implosion will result in the tank
shell or other components bowing
inwards. It is caused by failure to vent
the tank after cleaning or whilst
discharging.
Handled by any means other than specified in
ISO document DIS 3874. Top side lift
equipment (unladen tanks only) must be of
the full frame type.
- Distortion of the top third of tank shell
(chains too short)
- Distortion of the manway area due to
lifting by use of a yoke in the manway
opening
- End frames leaning in towards the
interior of the unit (chains too short)
- Permanent twist in the container
about a diagonal horizontal axis.
(Lifted by chains from two diagonally
opposite corner castings)
- Distortion to the underside shell,
steam tubes or cladding (lifting by
forks)
- Distortion to the side shell or cladding
due to top side lifting without
adequate support to the bottom side
- Distortion of the tank support bearers
or movement of the tank within the
frame due to the unit having been
dropped.
86
Transported a cargo that has caused
damage to the tank by reaction between the
cargo and the container.
- General corrosion and staining
- Corrosion pitting
- Stress corrosion cracking
- Damage to paint coating or cladding
caused by spillage or storage in a
chemical environment
87
88
Section 7
IMPROPER REPAIRS
89
Section 7 - Improper Repairs
Contents of Section
90
IMPROPER REPAIRS
91
performed in an GE SeaCo depot which does not
meet the GE SeaCo repair criteria should be
rejected and the tank container considered still
damaged and unavailable for lease until the repair
has been made good in accordance with GE
SeaCo repair procedures.
92
Section 8
INSPECTION
GUIDELINES FOR TANK
CONTAINERS
ACCEPTABLE
CONTAINER
CONDITION
(ACC)
93
Section 8 - Inspection Guidelines for
Tank Containers Safety
Contents of Section
Introduction (95)
1 Cleanliness (96)
2 Frame (98)
3 Walkway Assembly (105)
4 Paintwork (105)
5 Insulation and Cladding (106)
6 Manway Assembly (109)
7 Safety Valves (112)
8 Top Valves (115)
9 Shell (121)
10 Bottom Valves (123)
11 Heating (128)
12 Miscellaneous
a) Decals and Data Plates (130)
b) Document Holder (132)
c) Spill Box & Compartments (133)
13 Test (134)
94
INTRODUCTION
NO REPAIR IS REQUIRED.
95
1 CLEANLINESS
1.a) INTERIOR
Not Acceptable Damage/Condition
Acceptable Damage/Condition
- Discoloration or dull appearance.
- Abrasions or scratches more than 120 grit
polish equivalent.
An Internal Shell Condition Chart must be
completed for all interior shell defects. See
Section 3 for details.
NOTE: Tanks without a cleaning document
must be considered unsafe and should not be
inspected.
A cleanliness document is required for all tanks
prior to redelivery to depot for lease termination
(off-hire).
If the cleanliness document is not a Cleanliness
Certificate the tank may be off-hired but a
Cleanliness Certificate is required and should be
added to the off-hire estimate and issued by a
qualified person.
Note: where stains are present, clean a test area at
the time of estimate preparation to both
determine the cost and ensure stains do not
conceal corrosion pitting.
If heavily stained tanks are redelivered, contact the
Ops Centre immediately, to arrange re-cleaning prior
to off-hire.
96
1.b) EXTERIOR
Acceptable Damage/Condition
- Minor dust and dirt (NOT visible from 10
metres).
NOTE: The valve and spill boxes must be
clean. Check areas of overspill for damage to
paint and cladding. Inspect drain tubes to
ensure they are clear.
97
2 FRAME
Acceptable Damage
- Dents or distortions not exceeding 15 mm
in depth except as qualified above.
NOTE: The GE SeaCo preferred corner post
insert shape has angled ends. However
existing inserts with square ends are
acceptable if all other criteria are satisfied.
A maximum of two structurally sound inserts
are allowed to each post.
An insert may include a maximum of two
formed edges.
98
Not Acceptable
99
Acceptable Damage
2.2iii a full-leng
.0th insert is allowed.
100
2.b TOP /BOTTOM /SIDE /END /CRASH
END RAILS
(Incl. stacking supports and centre
mounted crash rails)
Not Acceptable Damage
- Cuts, holes gouges or splits.
- Cracks in welds or parent metal.
- Improper repairs.
- Dents or distortions greater than 25 mm.
- Out of straight greater than 25 mm per 2m.
- Distortion reducing clearance between end
bottom rail and valve to less than 5mm.
- Severe corrosion.
- Loose or missing fasteners.
- Out of ISO.
- Acceptable Damage
- Dents or distortions not exceeding 25mm.
- Dents in bottom face of bottom rails which
do not affect any formed edge.
NOTE: If the damage cannot be straightened
and it is necessary to repair either by an
overplate, insert or a section then the following
criteria will apply when assessing the type and
extent of repair required.
The minimum permissible length of an
overplate, insert or section repair is 50mm; no
maximum limit.
No insert or section may finish within 50mm of
the corner fitting weld or within 50mm of an
existing vertical weld.
If the planned insert or section will end within
these areas then the repairs should be extended to
the corner fitting or the existing weld.
Over-plating is restricted to the top, bottom and
inside faces of the rail where the formed edge is
free of damage.
101
2.c) ANCILLARY BRACING AND LOAD
TRANSFER AREAS (LTA)
Acceptable Damage
- Dents and distortions less than 25mm.
102
2.d) TANK BEARER SUPPORTS
Acceptable Damage
103
e) ISO DIMENSIONS (FRAME)
i) Diagonals
v) Cladding
- Any dent, bend or bow beyond the limits of
the ISO corner fittings.
104
3 WALKWAY AND LADDER ASSEMBLY
Insecure.
Cuts, holes, dents affecting safety.
Distortions greater than 50mm.
Dents greater than 25mm.
Out of ISO.
Missing or loose fasteners.
Acceptable Damage
4 PAINTWORK
- Severe Corrosion.
- Severely damaged by cargo contamination.
- Excessive scrapes and abrasions or
delamination
Acceptable Damage
- Superficial Corrosion.
- Discoloration or faded paint colour.
- Minor scrapes and abrasions.
105
5 INSULATION AND CLADDING
5.a) INSULATION
5.b) CLADDING
Acceptable Damage/Condition
106
NOTE: In all cases of damage to the cladding,
the tank shell, heating tubes and electrical
components must also be checked.
107
Cladding Patch Repair
108
6 MANWAY ASSEMBLY
6.a) MANLID AND SWINGBOLT ASSEMBLIES
Not Acceptable Damage/Condition
- Leaks.
- Missing customs sealing ring.
- Dents or distortion greater than 6mm or
affecting proper sealing of the manlid.
- Missing, insecure, seized or non-
operational parts.
- Cracks.
- Pitting, corrosion or contamination.
- Improper repairs.
Acceptable Damage/Condition
- Non-standard hand nuts and pivot pins that
are of similar design and material e.g.
bronze or stainless steel.
109
NOTE: Seals may be cleaned and re-used or
be "turned" to use both sides.
See paragraph 8 below for details of standard
seals and gaskets.
MANLID
7 3
5 2
ITEM DESCRIPTION
1 Cover
2 Seal ring
3 Swingbolt assembly
4 Neckring
5 Hinge pin
6 Self locking nut
7 Washer
8 Main hinge pin
110
6.c) DIPSTICK AND CALIBRATION CHART
NOTE:
111
7 SAFETY VALVES
- Contamination or corrosion
- Missing parts.
- Distortions affecting correct operation.
- Leaks or incorrect pressure setting.
- Missing or non-operational Customs
sealing ring.
- Improper repairs, seals or gaskets.
- Missing or illegible statutory markings.
Acceptable Damage/Condition
Missing TIR wires where customs ring is fitted.
Missing dust plug.
112
RELIEF VALVE
Item Description
1 Plastic plug
2 Cap
3 Setting locking grub screw
4 Pressure spring pair
5 Pressure Plate
6 Vacuum spring pad
7 Body
113
7.b) FLAME ARRESTOR GAUZE (where fitted)
Not Acceptable Damage/Condition
- Missing parts (only if originally fitted).
- Damage or distortion affecting proper
operation.
- Contamination.
NOTE: Flame arrestors are not fitted to
pressure only valves or to non-hazardous
tanks.
c) RUPTURE DISC ASSEMBLIES
Bursting Disc (where fitted)
Not Acceptable Damage
- Leaks or incorrect pressure rating.
- Contamination or corrosion.
- Damage (broken) or distortion affecting
correct operation or sealing.
- Improper parts, repairs, seals or gaskets.
- Damaged pressure gauge (tell-tale gauge)
affecting correct operation.
NOTE: Rupture discs are not normally fitted as
standard. Many tanks have rupture disc flange
assemblies fitted. Where rupture discs and
flange assemblies are in good condition they
should remain on the tank. A damaged disc
must be removed.
Rupture discs and tell-tale gauge are fitted as
standard to top outlet only tanks and special
tanks e.g.
TY0, TY1, TY2
TD0, TD1, TD2
TA0, TA1, TA2, TA4
TH1, TH2, TH4
TZ1T, TZ2T, TZ3T, TZ4T, TZ5T, TZ6T,
TZ7T, TZ9T.
TU2T, (and applicable TS2).
NOTE: check with ETS Dept. regarding rupture
disc requirements.
114
8 TOP VALVES
8.a) AIRLINE VALVE (VENT / VAPOUR
RETURN VALVE)
Not Acceptable Damage
- Leaks.
- Contamination or corrosion.
- Damage or distortion affecting correct
operation or sealing.
- Non-stainless steel (300 series) parts.
- Defective or non-stainless steel pressure
gauge.
- Missing /broken cap, seal or chain.
- Improper repairs, seals or gaskets.
- Non-stainless steel cap,
- Missing or non-operational Customs
sealing ring.
- Missing or non-operational parts.
NOTE:
Gauges (manometer) are not fitted as
standard but should not be removed (and
aperture plugged) unless defective.
Outlet screw fitting BSP standard for 6 bar
tanks, 10 bar tanks are fitted with a bolted
flange.
Standard seals and gaskets, see below
8.b) TOP OUTLET VALVE (where fitted)
Not Acceptable Damage
- Leaks.
- Contamination.
- Damage or distortion affecting correct
operation or sealing.
- Missing or non-operational parts.
- Damaged seals affecting proper sealing.
- Improper repairs, seals or gaskets.
- Non-stainless steel (300 series) parts.
- Non standard parts Missing Customs
Sealing ring.
115
NOTE: Provision is made for top outlet valves
but the top valve is not fitted, as standard, to
tanks with bottom outlets.
- Leaks.
- Contamination.
- Damage or distortion affecting correct
operation or sealing.
- Missing or non-operational parts.
- Non-stainless steel
- Gap (at bottom less than 8mm, greater
than 14mm)
116
TOP DISCHARGE
ITEM DESCRIPTION
1 Pull ring
2 Handle lever
3 Handle (LH)
4 Spring
5 Handle location pin
6 M6 x 16 screw
7 Retaining washer
8 M8 x 20 capscrew (2)
9 M8 spring washer (2)
10 Stuffing clamp flange c\w TIR
11 PTFE bush
12 PTFE 'O' ring (2)
13 Viton 'O' ring
14 Spindle
15 Spindle seat
16 Body
M8 nut (2)
17
M8 spring washer (2)
18 Closure plate
19 PTFE lower spindle bush
20 PTFE 'O' ring
21 PTFE 'O' ring
22 Lower spindle
23 PTFE seal
24 Seal clamp & Nitrile 'O' ring
117
TOP DISCHARGE
118
STANDARD SEALS AND GASKETS
119
8.c) TOP OUTLET BLANK
- Leaks.
- Contamination or corrosion.
- Damage or distortion affecting correct
operation or sealing.
- Missing or defective parts.
- Non stainless steel.
- Contamination.
Acceptable Damage/Condition
120
9 SHELL
Acceptable Damage/Condition
Gradual distortions /slow dents measured
over the length between exterior stiffeners
less than 10mm in the bottom two thirds or
less than 6mm in the top third of tank shell.
Light abrasions or scratches to 120 grit
polish equivalent or finer.
Superficial etching with no resulting
contamination traps. (Type A and where the
thickness is not below the minimum.)
Original manufacture rolling marks.
121
NOTE: Statutory re-testing is required after all
welded repairs to the tank shell.
Where pitting is recorded a thorough
investigation must be carried out.
An Internal Shell Condition Chart must be
completed whenever defects requiring
repair are detected.
NOTE: All pitting must be reported by type,
surface area affected and location on the
chart detailed in Section 3. An inspection
must be carried out to determine the depth
of pitting and that visible pitting does not
mask cavity pitting or stress corrosion.
The investigation will involve localised polishing
of the surface followed by visual examination
with the aid of a magnifying glass and dye
penetrant.
122
10 BOTTOM VALVES
a) FOOT VALVE
Leaks.
Contamination or corrosion
Damage or distortion affecting correct
operation or sealing.
Improper repairs, seals or gaskets.
Non-stainless steel parts.
Missing or broken Customs sealing ring.
123
FOOT VALVE
ITEM DESCRIPTION
1 Stuffing seal
2 Viton seal
3 Spindle
4 PTFE seal
5 Spindle bearing
6 Seal energiser
7 Bush seal
8 PTFE seal
9 Viton 'O' ring
10 Spring boss gasket
11 Spring assembly
12 Clamp bolt (2)
13 PTFE 'O' ring
14 M10 x 15 bolt
15 Spring washer (2)
16 Handle assembly
17 Poppet
18 Fortyt 'O' ring
19 Retaining pin
20 Lift fork
21 Countersunk screw (2)
22 Retaining washer
23 Clamp bolt (2)
24 Spring washer (2)
25 Stuffing clamp
26 Retaining washer
124
b) BOTTOM OUTLET VALVE
Not Acceptable Damage
Leaks.
Contamination or corrosion.
Damage or distortion affecting correct
operation or sealing.
Improper repairs, seals or gaskets.
Non-stainless steel parts.
Missing or broken Customs sealing ring.
125
BOTTOM OUTLET
ITEM DESCRIPTION
1 Split ring
2 Operating lever
3 Handle (LH)
4 Handle location spring
5 Handle location pin
6 M6 countersunk screw
7 Retaining washer
8 M8 x 25 socket capscrew (2)
9 M8 washer (2)
10 Stuffing clamp
11 PTFE bush
12 PTFE 'O' ring
13 Viton 'O' ring
14 Spindle
15 PTFE seal
16 Body
17 M8 spring washer (2)
M8 nut (2)
18 Closure plate
19 PTFE lower spindle bush
20 PTFE 'O' ring
21 PTFE 'O' ring
22 Lower spindle
23 PTFE main seal
24 Nitrile 'O' ring
Clamp plate
126
c) OUTLET BLANK (BLIND) FLANGE
Non Acceptable Damage
Leaks.
Contamination or corrosion.
Non - stainless steel.
Damage or corrosion affecting operation
Missing Customs sealing ring.
e) REMOTE TRIP
Not Acceptable Damage
Damage rendering remote trip inoperable.
Seized.
Insecure.
NOTE: Remote trips are fitted as standard to
bottom outlet I>2.65 bar tanks.
e) FUSIBLE LINK
Not Acceptable Damage
- Damage rendering fusible link inoperable.
- Insecure.
- NOTE: Fusible links are not fitted as
standard to pre-2003 manufactured tanks.
Where fitted, the link must remain in place.
127
11 HEATING
a) STEAM TUBE AND CAP
Not Acceptable Damage
Leaks.
Damaged screwed fittings.
Missing dust caps.
Missing or broken chain.
Distortion to the tank shell,
(due to overpressure or ice expansion).
Acceptable Damage/Condition
Tight dust caps which require to be
removed by use of a normal wrench.
NOTE: In all cases of damage the steam tubes
must be pressure tested.
Defective steam traps should be removed;
replacement is not required.
Steam tube dust caps may be made from
aluminium casting, stainless steel, gun metal or
bronze. Replacement caps must be of the
most economical material.
b) THERMOMETER
Not Acceptable Damage
Not operationing correctly.
Broken face or dial.
Missing or insecure.
Improperly fitted.
Acceptable Damage/Condition
Condensation which does not prevent legibility.
Non standard type.
NOTE: Thermometers are fitted as standard to
ALL insulated tanks.
128
c) ELECTRIC HEATING
Non operational.
Damage or deterioration that may allow
moisture ingress to control boxes or
elements.
Insecure components, cables or terminals.
Corroded terminals or components.
Improper repairs.
Earth leakage less than 1 megohm.
Missing parts.
129
12 MISCELLANEOUS
a) DECALS AND DATA PLATES
Not Acceptable Damage
Insecure.
Missing or illegible plates.
Missing or illegible.
Obscured or partly missing decals.
Twisted or bent beyond limits of ISO.
Acceptable Damage/Condition
Scuffs and scratches.
Dents or distortion except as qualified above.
NOTE All Statutory markings (decals and
plates) must be present,.
130
TANK MARKINGS
131
TANK MARKINGS CONTINUED
b) DOCUMENT HOLDER
Acceptable Damage/Condition
132
c) SPILL BOX AND COMPARTMENTS
Non operational.
Cargo residue or waste material.
Twisted or bent beyond the ISO limits.
Blocked drain tubes.
Damaged.
Insecure doors /lids where fasteners do
not tightly secure the lid for transport.
Missing Customs sealing ring and door
fasteners.
Acceptable Damage/Condition
133
13 TEST
a) Leak Test
134
The bottom outlet valve should be tested using
an apparatus similar to that shown below.
Leaks.
Acceptable Damage/Condition
Water level
135
Location /Component Air Tolerance Liquid Tolerance
Shell Zero Zero
Manlid, manlid seal Zero Zero
Flanges, gaskets Zero Zero
Exterior of all valves Zero Zero
Relief valve O ring Zero Zero
Airline butterfly valve ball seal Manufacturers tolerance Zero
Airline valve closure plate seal Manufacturers tolerance Zero
Butterfly valve closure plate seal Manufacturers tolerance Zero
Foot valve closure plate O ring Manufacturers tolerance Zero
Bottom valve assembly Zero Zero
(both valves closed)
Outlet cap or plate Zero Zero
c) Statutory Test
137
Test Intervals
The table below gives the maximum interval
between tests or examinations that is
acceptable to the Competent Authorities.
138
Section 9
CONVENTION FOR
SAFE CONTAINERS
(CSC)
139
Section 9 - Convention for Safe Containers
Contents of Section
Convention for Safe Containers. (141)
Fitting the CSC Plate (141)
Marking the container to indicate that it is
operated under ACEP (142)
Appendix 9.1 - Data Plate (143)
Personal NOTES (144)
140
CONVENTION FOR SAFE CONTAINERS
(CSC)
1 INTRODUCTION
Every container must be checked on return to
depot to ensure that it carries a valid data plate.
This consolidated data plate should incorporate
a CSC plate. If the data plate does not include
a CSC plate then this must be fitted separately.
In addition every container must be checked to
ensure that it is marked to indicate that it is
operated under GE SeaCo's Approved
Continuous Examination Programme
(ACEP). See paragraph 3 below for detailed
instructions.
2 FITTING A CSC PLATE
A new data plate must be fitted when:
- The original data plate has been lost.
- The container has never been fitted with a
data plate.
Contact the GE SeaCo Operations Centre for
the technical data, which must be stamped on
the plate.
All letters and numbers stamped on the plate
must be a minimum of 5mm in height. An
example of a typical data plate and the data
required is illustrated below.
141
3. MARKING THE CONTAINER TO INDICATE
THAT IT IS OPERATED UNDER ACEP
Every tank must be marked with the standard
GE SeaCo ACEP approval number or a decal
bearing the approval number ACEP-BDA-01 on
or next to the CSC plate. This approval number
is unique to GE SeaCo and if a decal bearing any
other approval number is found on the container
it must be removed.
If the ACEP decal is missing, a decal bearing the
above approval number must be fixed to the CSC
plate in the section entitled Next Examination
Due. Alternatively, if there is insufficient space,
fit the decal immediately next to the CSC plate.
The standard ACEP decal is illustrated below:
142
Appendix 9.1 - DATA PLATE
GE SEACO srl
BRIDGETOWN BARBADOS
TANK SERIAL No. SCZU 870030-8
MANUFACTURE BY YORKSHIRE MARINE CONTAINERS
ADDRESS BEVERLEY ENGLAND
Date OF MANUFACTURE:
MANUFACTURERS SERIAL NO:
TANK DESIGN CODE: ASME. SECT. VIII DIV.1
TANK TYPE UN
PORTABLE TANK T11:
CAPACITIES/WEIGHTS/DIMENSIONS
NOMINAL LIQUID CAPACITY 24,000 LITRES
TOTAL MEASURE WATER CAPACITY AT 200C
24010 6343 US
TitARE WEIGHT: 3650 kg 8046 lb
MAXIMUM PAYLOAD: 26830 kg 59150 lb
MAXIMUM GROSS WEIGHT: 30480 kg 67200 lb
PRESSURES
TANK WORKING PRESSURE: 4-0 bar 58 lb/in
TANK TEST PRESSURE: 6-0 bar 87 lb/in
STEAM TUBE WORKING PRESSURE: 4 bar 58 lb/in
STEAM TUBE TEST PRESSURE 6 bar 87 lb/in
TEMPERATURES
AMBIENT TEMPERATURE RANGE:
METALLURIGAL DESIGN TEMPERATURE:
MAXIMUM PRODUCT TEMPERATURE
TOTAL HEAT LEAKAGE FACTOR:
FOR TEMPERATURE DIFFERENCE RANGE:
MATERIALS
TANK SHELL & ENDS BS1501:PART3: 316S33.
TANK WELDS BS316S92. STEAM DUCTS 316S33
SHELL THICKNESS 4.8mm, ENDS 5.7mm
EQUIVALENT MIN.THICKNESS MILD STEEL 6.35mm
INSULATION POLYURETHANE
FRAME BS 50C HIGH TENSILE STEEL
CONNECTIONS
BOTTOM OULET 3 inch AIRLINE 2 inch BSP
TOP OUTLET 3 inch BSTD STEAM TUBES .75 inch BSP
INSPECTING AUTHORITY
LLOYDS REGISTER INDUSTRIAL SERVICES
REGULATING AUTHORITIES AND APPROVAL/PERMIT Nos.
Approval No. DOT (UK) IMO Type 1
DOT (US) IMOO1
ADR/RID CERT No 032567 CTC
UIC APPROVAL RAILWAYS CODE
COUNTRY OF APPROVAL UNITED KINGDOM
TESTS
FIRST AND SUBSEQUENT TEST DATES 4/92
5 YEAR TEST DATE
WITNESS MARK
CSC SAFETY APPROVAL
APPROVAL REFERENCE GB-LR 7708-3/92
DATE MANUFACTURED APRIL 92
IDENTIFICATION NO. SCZU 870030-8
MAXIMUM GROSS WEIGHT 30,480 kg 67,200 lb
ALLOWABLE STACKING WEIGHT FOR 162,560 kg 358,380
1.8G 15240 kg lb
RACKING TEST LOAD VALUE 33,600 lb
2R LONGITUDINAL INERTIA &IR LATERAL INERTIA TESTED
ACEP BDA-01
143
NOTES
144
NOTES
145
NOTES
146