Sie sind auf Seite 1von 52

www.final-yearproject.

com

PLANNING, ANALYSIS, DESIGN AND ESTIMATION OF


NATURAL COOLING TOWER

A PROJECT REPORT
Submitted by
S.RAMANAN (08CER080)
G.SWATHY (08CER103)
J.ARUNACHALAM (08CEL118)

In partial fulfillment for the award of the degree


Of
BACHELOR OF ENGINEERING
IN
CIVIL ENGINEERING

SCHOOL OF BUILDING AND MECHANICAL SCIENCES


KONGU ENGINEERING COLLEGE, PERUNDURAI-638 052
(An Autonomous institution affiliated to Anna University of Technology, Coimbatore)

ANNA UNIVERSITY: COIMBATORE-641 047


OCTOBER-2011

ANNA UNIVERSITY: COIMBATORE-641 047

1
www.final-yearproject.com

BONAFIDE CERTIFICATE
Certified that this project report on PLANNING, ANALYSIS, DESIGN

AND ESTIMATION OF NATURAL COOLING TOWER is a


bonafide work of
S.RAMANAN (08CER080)
G.SWATHY (08CER103)
J.ARUNACHALAM (08CEL118)

Who carried out the project work under my supervision

SIGNATURE SIGNATURE
Prof.S.KRISHNAMOORTHY, M.E., Mrs.S,SUCHITHRA. M.E.,
Head of the Department Assistant Professor
School of Building and Mechanical School of Building and Mechanical
Sciences Sciences
Department of Civil Engineering Department of Civil Engineering
Kongu Engineering College Kongu Engineering College
Perundurai, Erode-638 052 Perundurai, Erode-638 052

Submitted for the University Examination held on ______________

Internal Examiner External Examiner

2
www.final-yearproject.com

ACKNOWLEDGEMENT

3
www.final-yearproject.com

ACKNOWLEDGEMENT
First and foremost we thank the almighty, the greatest architect of the
universe for giving us such a speculate years.

We wish to express our heartfelt thanks to our beloved Correspondent


Thiru.R.K.VISHWANATHAN, B.A., and other philanthropic trust members
for having provided us with the entire necessary infrastructure to undertake this
project.

We are greatly indebted to express our deep sense of gratitude to our


principal, Prof.S.KUPPUSWAMI, B.E., Msc (Engg). Dr.Ing (France) for his
valuable advice and encouragement during the project.

We are grateful to thank our beloved Dean of School of Building and


Mechanical Sciences Dr.K.KRISHNAMOORTHY, M.E., Ph.D., FIE, FIV
for his infallible inspiration and guidance.

We take immense pleasure to express our heartfelt thanks to our beloved


Head of the Department Prof.S.KRISHNAMOORTHI, M.E., for his
encouragement and kind co-operation.

This work would not have been materialized without the great guidance
given to us by our guide Mrs.S.SUCHITHRA, M.E., Ph.D who had been a
constant source of ideas and inspiration with encouragement.

We heartily thank our Project Co-ordinator for their valuable guidance.

Last but not least, we thank our PARENTS and BELOVED FRIENDS
for their moral support.

4
www.final-yearproject.com

ABSTRACT

5
www.final-yearproject.com

ABSTRACT

Our project involves the Planning, Analysis and Design of an Natural


Cooling Tower. The entire design includes slab design, beam design, column
design, and footing design. Calculations are made manually and using software
packages.

The various structural elements are designed using IS 456:2000. The


concrete mix used for slabs, beams and footings are of M25 and the steel used
for all members are high yield strength deformed bars of grade Fe415. Each and
every part is designed by considering the safety point of view and economically.

This project deals with a simple and effective Natural Cooling Tower
design which is designed similar to Pyramid structure with slight modification
to increase its efficiency instead of normal Sand-Clock like structure which
involves tough calculations and tedious rafter column designs. This is a new
concept in Cooling Tower design which strike in our mind when we were gone
to Industrial Visit at Mettur Themal Power Station.

2
The total area of Cooling tower is 662 m with three compartments which
are used for cooling the hot water supplied to it. The first bottom compartment
consists of filler material above which steel grill is placed to hold the
distribution pipe with sprinklers which carries the hot water and sprinkles it.
The Second compartment which is above the first compartment will have a big
slab with opening at the centre which converges and reduces the area of vapour
reaching the top. Obviously, the vapour starts to condense more and reaches the
collecting chamber at the bottom. And the third, topmost compartment consists
of empty space which has a large opening at the centre than at the Second
compartment which allows the remaining vapour that comes out after
condensing at second compartment to reach the top widely.

6
www.final-yearproject.com

The objectives of this project are

Main objective:

To create a new design in cooling tower construction instead of


conventional structures which are tedious to built

To prepare an economical and effective design using Pyramid like


structure

To make use of atmospheric air for natural cooling instead of electric fan

To prepare simple design instead of complicated design (to avoid


designing of Rafter Column as like in normal cooling tower)

Supplementary Objective:

To draw a plan of Natural Cooling Tower showing the


reinforcement details of slabs, columns, beams and footings
are done AutoCAD 2009.
To analyze the structure elements using STADD. Pro V8i.

7
www.final-yearproject.com

CONTENTS

8
www.final-yearproject.com

CONTENTS

CHAPTER NO TITLE PAGE NO


ABSTRACT

1. INTRODUCTION

2. LITERATURE REVIEW

3. PLAN

4. MANUAL DESIGN

4.1 SLAB DESIGN


4.2 BEAM DESIGN
4.3 COLUMN DESIGN

5. SOFTWARE DESIGN

5.1 COOLING TOWER

6. REINFORCEMENT DETAILS

6.1 SLAB DETAILS

6.2 BEAM DETAILS

6.3 COLUMN DETAILS

7. ESTIMATION OF COOLING
TOWER

8. CONCLUSION

REFERENCE
9.

9
www.final-yearproject.com

LIST OF FIGURES

S.NO TITLE PAGE NO

1. 3D VIEW OF COOLING TOWER

2. REINFORCEMENT DETAIL OF
BEAMS,COLUMNS

3. REINFORCEMENT DETAIL OF
SLAB,FOOTING

10
www.final-yearproject.com

LIST OF SYMBOLS

B Breadth of beam or shorter dimension of a rectangular column

D Overall depth of beam or slab or diameter of column, dimensions


under considerations

W Total Dead load


d

W Total live load


s

D Effective depth of beam or slab or footing

f
ck
Characteristic compressive strength of concrete

f
y
Characteristic strength of steel

l
eff
Effective span of beam or slab or effective length of column

l Shorter dimension of the slab


x

l
y
Longer dimension of the slab

M Bending Moment

A
st
Area of tension reinforcement

M
u
Moment of resistance of a section without compression

reinforcement
X Shorter span co-efficient
x

X
y
Longer span co-efficient

11
www.final-yearproject.com

M Moments in strip per unit width of shorter span


x

M
y
Moments in strip per unit width of longer span

Permissible stress in concrete in bending compression


cbc

S Spacing of the stirrup legs or bent-up bar with in a distance


v

P Axial compressive force


u

M Bending moment at a cross section


u

P
c
Percentage of compression reinforcement

P
t
Percentage of tension reinforcement

Pw Axial compression on wall assumed to act at centre of wall

Av Area of vertical steel

Non dimensional parameters

12
www.final-yearproject.com

INTRODUCTION

13
www.final-yearproject.com

INTRODUCTION

In this present era, the technology in advanced construction has

developed to a very large extent. Some parts of constructions are still in

improving stage which includes Cooling Tower construction. Some researches

are going on to increase the efficiency of Cooling Tower by modifying its

structure and design. Ordinary Sand-Clock shaped Cooling Towers are very

tedious to design and calculate. In this chapter, we are going to deal with

planning, analysis and design of Natural Cooling Tower in brief.

The design is done by two methods. The first one is manual analysis and the

other one is STADD Pro analysis.

In manual design, all the Slabs, Beams and Columns are taken. The design

philosophy and procedures are taken as per the Indian standards. This whole

structure design is done by limit state design.

14
www.final-yearproject.com

LITERATURE REVIEW
15
www.final-yearproject.com

LITERATURE REVIEW

COOLING TOWER

Cooling Towers are evaporative coolers used for cooling water or other
working medium to near the ambient wet-bulb air temperature. Cooling towers
use evaporation of water to reject heat from processes such as cooling the
circulating water used in oil refineries and power plants, building cooling, or
chemical reactions, for example.

TYPES OF COOLING TOWERS

I. MECHANICAL DRAFT COOLING TOWERS

16
www.final-yearproject.com

Mechanical Draft Cooling tower has following characteristics,

Large fans to force air through circulated water

Water falls over fill surfaces: maximum heat transfer

Cooling rates depend on many parameters

Large range of capacities

Can be grouped, e.g. 8-cell tower

DISADVANTAGES OF MECHANCIAL DRAFT COOLING TOWER

Towers are very flexible


High vibration values during startup.
Complex gearbox (1800/120 RPM)
Starting cell 2 can shut down cell 1
Reversing fans in cold climates
Water build up in blades
Speeds are slow and based on diameter
Distance to control room
Corrosion from bad pH

17
www.final-yearproject.com

II. NATURAL DRAFT COOLING TOWER

A natural draft cooling tower is a means to remove waste heat from a system
and release it into the atmosphere.Typically used at oil refineries, chemical
plants and power plants to remove heat absorbed from circulating cool water
systems.A common shape is the hyperboloid (See Fig. 1) Cooling towers have
been around for over 100 years. However, in their early for were only about 20
meters high. Today, some can reach over 200 meters.As recently as 20 years
ago, cooling towers were more the exception than the rule in the industry
because of their severely high operating cost and the large amount of capital
required for construction. But with today's need for water conservation and
minimal environmental impact. industry is turning more and more to recycling
water.(GC3) . It has following advantages,

Hot air moves through tower

Fresh cool air is drawn into the tower from bottom

No fan required

Concrete tower <200 m

Used for large heat duties

COMPONENTS

Supply Basin

Tower Pumps

Cooling Towers

Vertical Ribs

Reinforced Concrete Shell

18
www.final-yearproject.com

Internal Void

Diagonal Columns

Hot Water Inlet

Fill

Splash

Film

Hot Water Distribution System

Cold Water Collection

Drift Eliminators - Drift is water lost from cooling towers as liquid


droplets are entrained in the exhaust air. The drift loss is independent of
the water lost by evaporation. The drift loss may be expressed in units of
lb/hr or percentage of circulating water flow. Drift eliminators are used to
control this drift loss from the tower. (Mist)

There are two types of Natural Draft Cooling Towers. They are,

Cross flow type


19
www.final-yearproject.com

Counter flow type

But our new design of Cooling Tower includes different mechanism. It has a
structure with three compartments which are used for cooling the hot water
supplied to it. The first bottom compartment consists of filler material above
which steel grill is placed to hold the distribution pipe with sprinklers which
carries the hot water and sprinkles it. The Second compartment which is above
the first compartment will have a big slab with opening at the centre which
converges and reduces the area of vapour reaching the top. Obviously, the
vapour starts to condense more and reaches the collecting chamber at the
bottom. And the third, topmost compartment consists of empty space which has
a large opening at the centre than at the Second compartment which allows the
remaining vapour that comes out after condensing at second compartment to
reach the top widely.

20
www.final-yearproject.com

PLAN

21
www.final-yearproject.com

NATURAL COOLING TOWER PLAN

Natural Cooling Tower Plan

22
www.final-yearproject.com

MANUAL DESIGN

23
www.final-yearproject.com

MANUAL DESIGN
SLAB DESIGN
Triangular Slab =2 x x 5.1x 12x 25

=1530kN/m

=1530X0.6

=918KN

Squareslab =10.6 X 10.6 X 25

= 2809 KN/m

=1685.4 x 0.6 KN

Total Dead Load On Slab = 1530+2809

= 4339 X0.6

=2603.4KN

For 4 slabs = 4 x 4339 = 17356 KN/m

Total live load =4 KN/m2

=4 x 21

= 84 kn /m

Total load = 17440 KN/m for 8 columns

For one column =17440/8 =2180 KN/m

For one metre = 2180 KN

SIDE RATIO OF THE SLAB:

fck = 25 N/mm2

24
www.final-yearproject.com

ly/lx = 21.6/10.6

2.04>2.50

Hence it is considered as oneway slab

DEPTH REQUIRED FOR STIFFNESS:

Span/(depth x modification factor) = 20

Assume pt =1.2%

10600/(depth x 0.95) =20

Depth = 560mm

D =600mm

Effective span = 10.6+0.6

=11.2 m

LOADS:

Load calculation= 1 x 0.6 x 25

= 75KN/m

Self weight of slab = 1 x 4

= 4KN/m

Total= 19KN/m

Ultimate load = 28.5 KN/m

BENDING MOMENT:

Mu = Wul2/8

= [28.5 x(11.2) 2]/8

= 446.88 KN/m

Vu = Wul/2

= (28.5x 11.2)/2

25
www.final-yearproject.com

=159.6N/mm2

LIMITING MOMENT:

Mu lim = 0.138 fck bd2

= 0.138 x 25 x 1000 x (560)2

= 1081KN-m

Mulim >Mu

Hence it is Under reinforced section

MAIN STEEL REINFORCEMENT AND SPACING:

Mu=0.87 fy Ast d[1-(Ast fy/bd fck)]

Astreq=6662.40mm2

Spacing =110mm

Provide 32dia @110mm c/c

(Ast)pro = (1000 x ast)/spacing

= 7307.63 mm2

(pt) req= 100 x Ast req bd

1.1>1.2

Hence it is safe

DISTRIBUTION REINFORCEMENT:

Ast min = 0.12 x bd

= (0.12/100) bd

= 720mm2

Spacing =270mm

Provide 16mm dia @ 270mmc/c

CHECK FOR DEFLECTION:

26
www.final-yearproject.com

fs =0.58 x fy x Ast req/ Ast pro

= (0.58 x 415 x 6717)/7307.6

=221N/mm2

pst (assumed )=1.2%

M.F=0.95

Depth d= span/(20 x M.F)

= 10600/(20 x 1.2)

=555mm< d (assumed)

Hence it is safe

CHECK FOR SHEAR:

Vuc =(Tc x bd ) x k

fck = 25 KN/mm2

p st = 100 x Ast pro/ bd

= 0.53%

Tc = 0.61 N/mm2

Vuc = 0.61 x 1000 x 560 x 0.95

= 324.52 KN

Vuc>Vu

Hence it is safe

BEAM DESIGN

DATA:

fck = 25 N/mm2

fy = 415 N/mm2

27
www.final-yearproject.com

Working load =15 KN/m

Ultimate load = 19 KN/m

Width of support = 0.6m

CROSS SECTIONAL DIMENSION:

Span/depth = 20

10.2/20 = depth

Depth= 510 mm

D= 550mm

Effective span = clear span+ effective depth

= 10+0.55

= 10.55mm

Center to center support = (10 + 0.6) = 10.6m (which ever is lesser)


length = 10.55m

LOAD CALCULATION:
Self weight of beam dead load = 0.6 x 0.6 x 25

= 9 KN /m

Live load = 5KN/m

Total load = 14 KN/m

Ultimate load = 21KN/m

ULTIMATE MOMENT AND SHEAR FORCE:


Mu = (Wu x L) = ( 21x 10.55) = 292.16KN-m

Vu = (Wu x L) = (21x10.55) =110.78KN

28
www.final-yearproject.com

LIMITING MOMENT OF RESISTANCE:


Mu limit = 0.138 x fck x b x d
= 0.138 x 25 x 600 x 550 =745.2KN/m

Mu < Mu (limit) since the sec is under reinforcement

Hence the section as singly reinforcement.

DESIGN OF TENSION REINFORCEMENT:

Mu=0.87 x 415 x Ast x 550 x (1-((Ast x fy)/ (b x d x fck)))

745.2x 10^6=0.87 x 415 x Ast x 550 x (1-((Ast x 415)/(600x 550 x 25))

Ast=1403.12mm

(Ast) pro= (1000 x ast)/(spacing) , Assume 12mm dia bars,

Provide 12mm dia bars @240mm c/c

Also provide 2no.s of hanger bar of 12mm dia bars

CHECK FOR SHEAR REINFORCEMENT:


Tv =Vu/bd = 110.78x10^3/600*550 = 0.184 N/mm^2
Pt =(100*Ast)/bd =100*1404/600*550 =0.25%
Refer table 19 IS 456:2000 ,Pg no;73
Tc =0.36 N/mm^2
Tv<Tc, Hence safe

Assumed 10mm dia 2 legged stirrups

Ast shear = 157mm2

SPACING:
Sv = (0.87*Fy*Asv*d/Vus) = (0.87*415*157*350/110.8x10^3)
= 223.27mm
29
www.final-yearproject.com

Sv = 0.75*d =0.75*350 =262.5mm


Sv = 300mm

DESIGN OF INCLINED BEAM


DATA:

fck = 25 N/mm2

fy = 415 N/mm2

Working load =8 KN/m

Ultimate load = 12KN/m

Width of support = 0.6m

CROSS SECTIONAL DIMENSION:

Span/depth = 20

14.2/20 = depth

Depth= 412 mm

D= 450mm

Effective span = clear span+ effective depth

= 14.2+0.55

= 14.75mm

Center to center support = (14.2+ 0.6) = 14.8m (which ever is lesser)


length = 14.75m

LOAD CALCULATION:
Self weight of beam dead load = 0.4 x 0.4 x 25

= 4KN /m

Live load = 2KN/m

Total load = 6KN/m

30
www.final-yearproject.com

Ultimate load = 9KN/m

ULTIMATE MOMENT AND SHEAR FORCE:


Mu = (Wu x L)/8 = ( 9x 14.75) /8 = 244.75KN-m

Vu = (Wu x L)/2 = (9x14.75) /2 =66.38KN

LIMITING MOMENT OF RESISTANCE:


Mu limit = 0.138 x fck x b x d
= 0.138 x 25 x 400 x 400 =220.8KN/m

Mu < Mu (limit) since the section is under reinforcement

Hence the section as singly reinforcement.

DESIGN OF TENSION REINFORCEMENT:

Mu=0.87 x 415 x Ast x 410 x (1-((Ast x fy)/ (b x d x fck)))

220.8 10^6=0.87 x 415 x Ast x 410 x (1-((Ast x 415)/(400x 410 x 25))

Ast=1085mm

(Ast) pro= (1000 x ast)/(spacing) , Assume 12mm dia bars,

Provide 12mm dia bars @ 280mm c/c

Also provide 2no.s of hanger bar of 12mm dia bars

CHECK FOR SHEAR REINFORCEMENT:


Tv =Vu/bd = 66.38x10^3/400*410 = 0.405N/mm^2
Pt =(100*Ast)/bd =100*1404/400*410 =0.66%
Refer table 19 IS 456:2000 ,Pg no;73

31
www.final-yearproject.com

Tc =0.36 N/mm^2
Tv<Tc, Hence safe

Assumed 10mm dia 2 legged stirrups

Ast shear = 157mm2

SPACING:
Sv = (0.87*Fy*Asv*d/Vus) = (0.87*415*157*350/110.8x10^3)
= 223.27mm
Sv = 0.75*d =0.75*350 =262.5mm
Sv = 300mm

DESIGN OF FOOTING:
GIVEN:

Pu = 2500KN

b = 600 KN

d= 600 KN

Assume, S.B.C of Soil =185 KN/m2

SIZE OF FOOTING:

Load on column = 2500 KN

Self weight of footing = 250 KN

Total factored load = 2750 KN

Footing area = 10 mm

Adopt square footing of size 3.2 m x 3.2 m

Factored soil pressure at bars is,

Pu= 244.14N/mm2

Hence, the footing is adequate in the soil pressure developed at the base is
less than the factored bearing capacity of soil.

32
www.final-yearproject.com

FACTORED BENDING MOMENT :

Cantilever projection from side face of column =1.3m

Bending moment at side face of column =206.30 KN/m

DEPTH OF FOOTING :

Moment consideration,

Mu =0.138 fck bd2

d= 273 mm

Shear force for metre width is,

Vud = 250(1250 - d)N

Assume Tc = 0.36 N/mm2

For M20 grade of concrete with nominal % of reinforcement,

Pt=0.25

Tc= Vul/bd

=0.36

Adopt effective depth = 550mm

Overall depth =600mm

REINFORCEMENT IN FOOTING:

Mu=0.87 fy Ast d[1-(Ast fy/bd fck)]

Ast = 1083.15mm2

Adopt 16mm dia. Bars @ 160mm c/c

Astpro =1257mm2

CHECK FOR SHEAR STRESS:

33
www.final-yearproject.com

Vu =550 x[1250-550]

= 175 mm

The permissible shear stress is,

KsTc

= 0.33 N/mm2

Nominal shear stress = Tv = Vu/bd

=0.32 N/mm2

Hence it is safe.

34
www.final-yearproject.com

STADD.Pro RESULTS

35
www.final-yearproject.com

STADD.PRO RESULT
SLAB DESIGN

ELEMENT LONG. REINF MOM-X /LOAD TRANS. REINF


MOM-Y /LOAD

(SQ.MM/ME) (KN-M/M) (SQ.MM/ME) (KN-M/M)

60 TOP : 696. 14.08 / 3 696. 4.98 / 3

BOTT: 696. -1.26 / 2 696. -0.24 / 2

61 TOP : 696. 3.02 / 3 696. 15.85 / 3

BOTT: 696. -0.08 / 2 696. -1.48 / 2

62 TOP : 696. 3.20 / 3 696. 17.02 / 3

BOTT: 696. -0.10 / 2 696. -1.60 / 2

63 TOP : 696. 3.04 / 3 696. 15.53 / 3

BOTT: 696. -0.08 / 2 696. -1.47 / 2

BEAM DESIGN
FOR BOTTOM BEAM

B E A M N O. 1 DESIGN RESULTS

M25 Fe415 (Main) Fe415 (Sec.)

36
www.final-yearproject.com

LENGTH: 10500.0 mm SIZE: 550.0 mm X 550.0 mm COVER: 25.0


mm

SUMMARY OF REINF. AREA (Sq.mm)

----------------------------------------------------------------------------

SECTION 0.0 mm 2625.0 mm 5250.0 mm 7875.0 mm 10500.0 mm

----------------------------------------------------------------------------

TOP 619.58 585.78 585.78 585.78 723.91

REINF. (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm)

BOTTOM 0.00 582.40 582.40 582.40 0.00

REINF. (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm)

----------------------------------------------------------------------------

SUMMARY OF PROVIDED REINF. AREA

----------------------------------------------------------------------------

SECTION 0.0 mm 2625.0 mm 5250.0 mm 7875.0 mm 10500.0 mm

----------------------------------------------------------------------------

TOP 8-10 8-10 8-10 8-10 10-10

REINF. 1 layer(s) 1 layer(s) 1 layer(s) 1 layer(s) 1 layer(s)

BOTTOM 2-16 4-16 4-16 4-16 2-16

REINF. 1 layer(s) 1 layer(s) 1 layer(s) 1 layer(s) 1 layer(s)

SHEAR 2 legged 8 2 legged 8 2 legged 8 2 legged 8 2 legged 8

REINF. @ 160 mm c/c @ 160 mm c/c @ 160 mm c/c @ 160 mm c/c @


160 mm c/c

37
www.final-yearproject.com

----------------------------------------------------------------------------

SHEAR DESIGN RESULTS AT DISTANCE d (EFFECTIVE DEPTH)


FROM FACE OF THE SUPPORT

SHEAR DESIGN RESULTS AT 815.0 mm AWAY FROM START


SUPPORT

VY = 40.97 MX = 2.91 LD= 3

Provide 2 Legged 8 @ 160 mm c/c

SHEAR DESIGN RESULTS AT 815.0 mm AWAY FROM END


SUPPORT

VY = -53.86 MX = 2.91 LD= 3

Provide 2 Legged 8 @ 160 mm c/c

Similar results for 8 bottom beams.

FOR INCLINED BEAM

B E A M N O. 53 D E S I G N R E S U L T S

M25 Fe415 (Main) Fe415 (Sec.)

LENGTH: 14637.6 mm SIZE: 550.0 mm X 550.0 mm COVER: 25.0


mm

SUMMARY OF REINF. AREA (Sq.mm)

---------------------------------------------------------------------------

SECTION 0.0 mm 3659.4 mm 7318.8 mm 10978.2 mm 14637.6 mm

----------------------------------------------------------------------------

TOP 582.40 582.40 582.40 582.40 582.40

REINF. (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm)

38
www.final-yearproject.com

BOTTOM 0.00 582.40 582.40 582.40 0.00

REINF. (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm)

----------------------------------------------------------------------------

SUMMARY OF PROVIDED REINF. AREA

----------------------------------------------------------------------------

SECTION 0.0 mm 3659.4 mm 7318.8 mm 10978.2 mm 14637.6 mm

----------------------------------------------------------------------------

TOP 4-16 4-16 4-16 4-16 4-16

REINF. 1 layer(s) 1 layer(s) 1 layer(s) 1 layer(s) 1 layer(s)

BOTTOM 2-16 4-16 4-16 4-16 2-16

REINF. 1 layer(s) 1 layer(s) 1 layer(s) 1 layer(s) 1 layer(s)

SHEAR 2 legged 8 2 legged 8 2 legged 8 2 legged 8 2 legged 8

REINF. @ 160 mm c/c @ 160 mm c/c @ 160 mm c/c @ 160 mm c/c @


160 mm c/c

FOR TOP BEAM

B E A M N O. 56 D E S I G N R E S U L T S

M25 Fe415 (Main) Fe415 (Sec.)

LENGTH: 10000.0 mm SIZE: 400.0 mm X 400.0 mm COVER: 25.0


mm

STAAD SPACE -- PAGE NO. 17

SUMMARY OF REINF. AREA (Sq.mm)

----------------------------------------------------------------------------

SECTION 0.0 mm 2500.0 mm 5000.0 mm 7500.0 mm 10000.0 mm

39
www.final-yearproject.com

----------------------------------------------------------------------------

TOP 395.68 0.00 0.00 0.00 391.28

REINF. (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm)

BOTTOM 303.13 303.13 303.13 303.13 303.13

REINF. (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm)

----------------------------------------------------------------------------

SUMMARY OF PROVIDED REINF. AREA

----------------------------------------------------------------------------

SECTION 0.0 mm 2500.0 mm 5000.0 mm 7500.0 mm 10000.0


mm

----------------------------------------------------------------------------

TOP 3-16 2-16 2-16 2-16 3-16

REINF. 1 layer(s) 1 layer(s) 1 layer(s) 1 layer(s) 1 layer(s)

BOTTOM 4-10 4-10 4-10 4-10 4-10

REINF. 1 layer(s) 1 layer(s) 1 layer(s) 1 layer(s) 1 layer(s)

SHEAR 2 legged 8 2 legged 8 2 legged 8 2 legged 8 2 legged 8

REINF. @ 170 mm c/c @ 170 mm c/c @ 170 mm c/c @ 170 mm c/c @


170 mm c/c

COLUMN DESIGN

C O L U M N N O. 13 D E S I G N R E S U L T S

M25 Fe415 (Main) Fe415 (Sec.)


40
www.final-yearproject.com

LENGTH: 3000.0 mm CROSS SECTION: 600.0 mm X 600.0 mm


COVER: 40.0 mm

** GUIDING LOAD CASE: 3 END JOINT: 1 SHORT COLUMN

REQD. STEEL AREA : 7395.32 Sq.mm.

REQD. CONCRETE AREA: 352604.69 Sq.mm.

MAIN REINFORCEMENT : Provide 24 - 20 dia. (2.09%, 7539.82 Sq.mm.)

(Equally distributed)

TIE REINFORCEMENT : Provide 8 mm dia. rectangular ties @ 300 mm c/c

SECTION CAPACITY BASED ON REINFORCEMENT REQUIRED


(KNS-MET)

----------------------------------------------------------

Puz : 6268.60 Muz1 : 265.71 Muy1 : 265.71

INTERACTION RATIO: 0.99 (as per Cl. 39.6, IS456:2000)

SECTION CAPACITY BASED ON REINFORCEMENT PROVIDED


(KNS-MET)

----------------------------------------------------------

WORST LOAD CASE: 3

END JOINT: 10 Puz : 5621.05 Muz : 0.00 Muy : 0.00 IR: 0.95

41
www.final-yearproject.com

REINFORCEMENT DETAILS

42
www.final-yearproject.com

REINFORCEMENT DETAILS

BOTTOM BEAM REINFORCEMENT DETAILS

INCLINED BEAM REINFORCEMENT DETAILS

43
www.final-yearproject.com

TOP BEAM REINFORCEMENT DETAILS

COLUMN REINFORCEMENT DETAILS

44
www.final-yearproject.com

FOOTING REINFORCEMENT DETAILS

45
www.final-yearproject.com

ESTIMATION

46
www.final-yearproject.com

DETAILED ESTIMATION
S.N DESCRIPTI N L B D in QTY REMARKS
o ON O in in m
m m
1. EARTH
WORK
EXCAVATIO
N

For footing A 3 2.5 2.5 3.6 67.5m3


For Footing B 2 1.8 1.8 3.2 20.74m3
Total 88.24m3
2. SAND
FILLING
In Ground 2 21. 5.4 2.9 676.512m
Level 6 3
2 21. 4.4 2.9 551.232m
6 3
Total 1227.744
m3
Deduction 4 7.5 0.9 0.9 12.15m3 ()x7.5x0.9x0
.9
4 5.4 0.8 0.8 6.912m3 (1/2)x5.4x0.8x
0.8
Total 19.062m3

Total 1208.682
Sand m3
Fillin
g
3. PCC
WORK
In Footing A 3 2.5 2.5 0.2 3.75m3
In Footing B 2 1.8 1.8 .2 1.296m3
4. RCC WORK
In Footing A 3 2.5 2.5 1.6 30m3
In Footing B 2 1.8 1.8 1.1 7.128m3

47
www.final-yearproject.com

IN SLAB
Rectangular 4 11. 9.4 0.6 254.88m3
8
Triangular 8 11. 5.2 0.6 147.264m
8 3
RCC BEAM 8 10. 0.6 0.6 30.528m3
6
INCLINED 4 14. 0.6 0.6 20.488m3
BEAM 2

TOP BEAM 4 10. 0.4 0.45 8.586m3


6 5
Total 461
746m3

48
www.final-yearproject.com

49
www.final-yearproject.com

CONCLUSION

CONCLUSION:
This project gives us a good practice for designing of our future

projects.This helps us to gain a lot of training and experience in planning,

designing and estimation of different components in a Multi Storey Residential

Building ,

50
www.final-yearproject.com

51
www.final-yearproject.com

REFERENCE

REFERENCES

Reinforced Concrete (Limit State Design) by, A.K.JAIN. Published by


Khanna Publishers.
IS: 456 2000, Indian Standard Plain and Reinforced Concrete code of
practice (Fourth Revision) Published by Bureau of Indian Standard.
IS: 875 (Part I) 1987, Indian Standard code of practice for design loads
(other than earthquake) for buildings and structures. (Second Revision),
Published by Bureau of Indian Standard.
SP-16: 1978, published by Bureau of Indian Standard (12th edition).
Advanced reinforced concrete design (second edition) by P.C.Varghese.

52

Das könnte Ihnen auch gefallen