Beruflich Dokumente
Kultur Dokumente
com
A PROJECT REPORT
Submitted by
S.RAMANAN (08CER080)
G.SWATHY (08CER103)
J.ARUNACHALAM (08CEL118)
1
www.final-yearproject.com
BONAFIDE CERTIFICATE
Certified that this project report on PLANNING, ANALYSIS, DESIGN
SIGNATURE SIGNATURE
Prof.S.KRISHNAMOORTHY, M.E., Mrs.S,SUCHITHRA. M.E.,
Head of the Department Assistant Professor
School of Building and Mechanical School of Building and Mechanical
Sciences Sciences
Department of Civil Engineering Department of Civil Engineering
Kongu Engineering College Kongu Engineering College
Perundurai, Erode-638 052 Perundurai, Erode-638 052
2
www.final-yearproject.com
ACKNOWLEDGEMENT
3
www.final-yearproject.com
ACKNOWLEDGEMENT
First and foremost we thank the almighty, the greatest architect of the
universe for giving us such a speculate years.
This work would not have been materialized without the great guidance
given to us by our guide Mrs.S.SUCHITHRA, M.E., Ph.D who had been a
constant source of ideas and inspiration with encouragement.
Last but not least, we thank our PARENTS and BELOVED FRIENDS
for their moral support.
4
www.final-yearproject.com
ABSTRACT
5
www.final-yearproject.com
ABSTRACT
This project deals with a simple and effective Natural Cooling Tower
design which is designed similar to Pyramid structure with slight modification
to increase its efficiency instead of normal Sand-Clock like structure which
involves tough calculations and tedious rafter column designs. This is a new
concept in Cooling Tower design which strike in our mind when we were gone
to Industrial Visit at Mettur Themal Power Station.
2
The total area of Cooling tower is 662 m with three compartments which
are used for cooling the hot water supplied to it. The first bottom compartment
consists of filler material above which steel grill is placed to hold the
distribution pipe with sprinklers which carries the hot water and sprinkles it.
The Second compartment which is above the first compartment will have a big
slab with opening at the centre which converges and reduces the area of vapour
reaching the top. Obviously, the vapour starts to condense more and reaches the
collecting chamber at the bottom. And the third, topmost compartment consists
of empty space which has a large opening at the centre than at the Second
compartment which allows the remaining vapour that comes out after
condensing at second compartment to reach the top widely.
6
www.final-yearproject.com
Main objective:
To make use of atmospheric air for natural cooling instead of electric fan
Supplementary Objective:
7
www.final-yearproject.com
CONTENTS
8
www.final-yearproject.com
CONTENTS
1. INTRODUCTION
2. LITERATURE REVIEW
3. PLAN
4. MANUAL DESIGN
5. SOFTWARE DESIGN
6. REINFORCEMENT DETAILS
7. ESTIMATION OF COOLING
TOWER
8. CONCLUSION
REFERENCE
9.
9
www.final-yearproject.com
LIST OF FIGURES
2. REINFORCEMENT DETAIL OF
BEAMS,COLUMNS
3. REINFORCEMENT DETAIL OF
SLAB,FOOTING
10
www.final-yearproject.com
LIST OF SYMBOLS
f
ck
Characteristic compressive strength of concrete
f
y
Characteristic strength of steel
l
eff
Effective span of beam or slab or effective length of column
l
y
Longer dimension of the slab
M Bending Moment
A
st
Area of tension reinforcement
M
u
Moment of resistance of a section without compression
reinforcement
X Shorter span co-efficient
x
X
y
Longer span co-efficient
11
www.final-yearproject.com
M
y
Moments in strip per unit width of longer span
P
c
Percentage of compression reinforcement
P
t
Percentage of tension reinforcement
12
www.final-yearproject.com
INTRODUCTION
13
www.final-yearproject.com
INTRODUCTION
structure and design. Ordinary Sand-Clock shaped Cooling Towers are very
tedious to design and calculate. In this chapter, we are going to deal with
The design is done by two methods. The first one is manual analysis and the
In manual design, all the Slabs, Beams and Columns are taken. The design
philosophy and procedures are taken as per the Indian standards. This whole
14
www.final-yearproject.com
LITERATURE REVIEW
15
www.final-yearproject.com
LITERATURE REVIEW
COOLING TOWER
Cooling Towers are evaporative coolers used for cooling water or other
working medium to near the ambient wet-bulb air temperature. Cooling towers
use evaporation of water to reject heat from processes such as cooling the
circulating water used in oil refineries and power plants, building cooling, or
chemical reactions, for example.
16
www.final-yearproject.com
17
www.final-yearproject.com
A natural draft cooling tower is a means to remove waste heat from a system
and release it into the atmosphere.Typically used at oil refineries, chemical
plants and power plants to remove heat absorbed from circulating cool water
systems.A common shape is the hyperboloid (See Fig. 1) Cooling towers have
been around for over 100 years. However, in their early for were only about 20
meters high. Today, some can reach over 200 meters.As recently as 20 years
ago, cooling towers were more the exception than the rule in the industry
because of their severely high operating cost and the large amount of capital
required for construction. But with today's need for water conservation and
minimal environmental impact. industry is turning more and more to recycling
water.(GC3) . It has following advantages,
No fan required
COMPONENTS
Supply Basin
Tower Pumps
Cooling Towers
Vertical Ribs
18
www.final-yearproject.com
Internal Void
Diagonal Columns
Fill
Splash
Film
There are two types of Natural Draft Cooling Towers. They are,
But our new design of Cooling Tower includes different mechanism. It has a
structure with three compartments which are used for cooling the hot water
supplied to it. The first bottom compartment consists of filler material above
which steel grill is placed to hold the distribution pipe with sprinklers which
carries the hot water and sprinkles it. The Second compartment which is above
the first compartment will have a big slab with opening at the centre which
converges and reduces the area of vapour reaching the top. Obviously, the
vapour starts to condense more and reaches the collecting chamber at the
bottom. And the third, topmost compartment consists of empty space which has
a large opening at the centre than at the Second compartment which allows the
remaining vapour that comes out after condensing at second compartment to
reach the top widely.
20
www.final-yearproject.com
PLAN
21
www.final-yearproject.com
22
www.final-yearproject.com
MANUAL DESIGN
23
www.final-yearproject.com
MANUAL DESIGN
SLAB DESIGN
Triangular Slab =2 x x 5.1x 12x 25
=1530kN/m
=1530X0.6
=918KN
= 2809 KN/m
=1685.4 x 0.6 KN
= 4339 X0.6
=2603.4KN
=4 x 21
= 84 kn /m
fck = 25 N/mm2
24
www.final-yearproject.com
ly/lx = 21.6/10.6
2.04>2.50
Assume pt =1.2%
Depth = 560mm
D =600mm
=11.2 m
LOADS:
= 75KN/m
= 4KN/m
Total= 19KN/m
BENDING MOMENT:
Mu = Wul2/8
= 446.88 KN/m
Vu = Wul/2
= (28.5x 11.2)/2
25
www.final-yearproject.com
=159.6N/mm2
LIMITING MOMENT:
= 1081KN-m
Mulim >Mu
Astreq=6662.40mm2
Spacing =110mm
= 7307.63 mm2
1.1>1.2
Hence it is safe
DISTRIBUTION REINFORCEMENT:
= (0.12/100) bd
= 720mm2
Spacing =270mm
26
www.final-yearproject.com
=221N/mm2
M.F=0.95
= 10600/(20 x 1.2)
=555mm< d (assumed)
Hence it is safe
Vuc =(Tc x bd ) x k
fck = 25 KN/mm2
= 0.53%
Tc = 0.61 N/mm2
= 324.52 KN
Vuc>Vu
Hence it is safe
BEAM DESIGN
DATA:
fck = 25 N/mm2
fy = 415 N/mm2
27
www.final-yearproject.com
Span/depth = 20
10.2/20 = depth
Depth= 510 mm
D= 550mm
= 10+0.55
= 10.55mm
LOAD CALCULATION:
Self weight of beam dead load = 0.6 x 0.6 x 25
= 9 KN /m
28
www.final-yearproject.com
Ast=1403.12mm
SPACING:
Sv = (0.87*Fy*Asv*d/Vus) = (0.87*415*157*350/110.8x10^3)
= 223.27mm
29
www.final-yearproject.com
fck = 25 N/mm2
fy = 415 N/mm2
Span/depth = 20
14.2/20 = depth
Depth= 412 mm
D= 450mm
= 14.2+0.55
= 14.75mm
LOAD CALCULATION:
Self weight of beam dead load = 0.4 x 0.4 x 25
= 4KN /m
30
www.final-yearproject.com
Ast=1085mm
31
www.final-yearproject.com
Tc =0.36 N/mm^2
Tv<Tc, Hence safe
SPACING:
Sv = (0.87*Fy*Asv*d/Vus) = (0.87*415*157*350/110.8x10^3)
= 223.27mm
Sv = 0.75*d =0.75*350 =262.5mm
Sv = 300mm
DESIGN OF FOOTING:
GIVEN:
Pu = 2500KN
b = 600 KN
d= 600 KN
SIZE OF FOOTING:
Footing area = 10 mm
Pu= 244.14N/mm2
Hence, the footing is adequate in the soil pressure developed at the base is
less than the factored bearing capacity of soil.
32
www.final-yearproject.com
DEPTH OF FOOTING :
Moment consideration,
d= 273 mm
Pt=0.25
Tc= Vul/bd
=0.36
REINFORCEMENT IN FOOTING:
Ast = 1083.15mm2
Astpro =1257mm2
33
www.final-yearproject.com
Vu =550 x[1250-550]
= 175 mm
KsTc
= 0.33 N/mm2
=0.32 N/mm2
Hence it is safe.
34
www.final-yearproject.com
STADD.Pro RESULTS
35
www.final-yearproject.com
STADD.PRO RESULT
SLAB DESIGN
BEAM DESIGN
FOR BOTTOM BEAM
B E A M N O. 1 DESIGN RESULTS
36
www.final-yearproject.com
----------------------------------------------------------------------------
----------------------------------------------------------------------------
REINF. (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm)
REINF. (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm)
----------------------------------------------------------------------------
----------------------------------------------------------------------------
----------------------------------------------------------------------------
37
www.final-yearproject.com
----------------------------------------------------------------------------
B E A M N O. 53 D E S I G N R E S U L T S
---------------------------------------------------------------------------
----------------------------------------------------------------------------
REINF. (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm)
38
www.final-yearproject.com
REINF. (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm)
----------------------------------------------------------------------------
----------------------------------------------------------------------------
----------------------------------------------------------------------------
B E A M N O. 56 D E S I G N R E S U L T S
----------------------------------------------------------------------------
39
www.final-yearproject.com
----------------------------------------------------------------------------
REINF. (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm)
REINF. (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm) (Sq. mm)
----------------------------------------------------------------------------
----------------------------------------------------------------------------
----------------------------------------------------------------------------
COLUMN DESIGN
C O L U M N N O. 13 D E S I G N R E S U L T S
(Equally distributed)
----------------------------------------------------------
----------------------------------------------------------
END JOINT: 10 Puz : 5621.05 Muz : 0.00 Muy : 0.00 IR: 0.95
41
www.final-yearproject.com
REINFORCEMENT DETAILS
42
www.final-yearproject.com
REINFORCEMENT DETAILS
43
www.final-yearproject.com
44
www.final-yearproject.com
45
www.final-yearproject.com
ESTIMATION
46
www.final-yearproject.com
DETAILED ESTIMATION
S.N DESCRIPTI N L B D in QTY REMARKS
o ON O in in m
m m
1. EARTH
WORK
EXCAVATIO
N
Total 1208.682
Sand m3
Fillin
g
3. PCC
WORK
In Footing A 3 2.5 2.5 0.2 3.75m3
In Footing B 2 1.8 1.8 .2 1.296m3
4. RCC WORK
In Footing A 3 2.5 2.5 1.6 30m3
In Footing B 2 1.8 1.8 1.1 7.128m3
47
www.final-yearproject.com
IN SLAB
Rectangular 4 11. 9.4 0.6 254.88m3
8
Triangular 8 11. 5.2 0.6 147.264m
8 3
RCC BEAM 8 10. 0.6 0.6 30.528m3
6
INCLINED 4 14. 0.6 0.6 20.488m3
BEAM 2
48
www.final-yearproject.com
49
www.final-yearproject.com
CONCLUSION
CONCLUSION:
This project gives us a good practice for designing of our future
Building ,
50
www.final-yearproject.com
51
www.final-yearproject.com
REFERENCE
REFERENCES
52