2017-08-23 La Guardia Gate Project - Update #05 GRADED LAYOUT-2 Sep/11/2017 03:30

EPS: HSE HSE PROJECTS


EPS: HSE-CURRENT CURRENT PROJECTS
EPS: HSE-C-NFR INFRASTRUCTURE
Project: LGA BL02-1 2017-08-23 La Guardia Gate Project - Update #05
WBS: LGA BL02-1.2 Construction
WBS: LGA BL02-1.2.3 Mobilization/General

CON0010 1d CON0020 5d
Pre construction video Mobilization to the si te
inspection and yoddock fence

M0010 CON0020 CON0010 PCO#3

WBS: LGA BL02-1.2.4 Site Works

CON0030 2d CON0050 5d
Cut site and degrub Exc avate for vaults and
set

PCO#3 CON0040, CON0030 M0030,


CON0050, CON0230,
PCO#2 CON0100,
CON0110,

CON0040 13d
Retaining wall

CON0030, M0080
PCO#2

65d

WBS: LGA BL02-1.2.6 Piping Works

CON0070 15d CON0090 5d CON0110 5d CON0120 5d CON0140 11d


Control line piping Buried piping offsite Prefab valves and hy dro Valve i nst allation Pressure testing and
installation site hydro and drying

PCO#10, CON0080, CON0070 CON0140 CON0050 CON0120, CON0110 CON0140 CON0120, CON0150,
PCO#9 CON0090 CON0200 CON0080, M0040
CON0090

0d 0d -1d 19d 0d

CON0130 5d CON0080 5d CON0100 7d


Control house and heater Backfill large piping on Concrete pads and
set site supports

PCO#8 CON0150 CON0070 CON0140 CON0050 PCO#8

27d 0d

CON0060 37d
Buried large piping
installation site

PCO#6 PCO#9,
PCO#10

0d

WBS: LGA BL02-1.2.7 Heater, Generator, I&C Works

CON0160 4d CON0150 4d CON0170 5d CON0180 1d CON0190 0d


Site final grading and Heater connections and Tie-ins (by others) Gas-in (by others) Gate Station Complete
drainage riser s et to fi nal meter li ne-up set
grade

CON0200, CON0300, CON0140, CON0170 CON0150 CON0180 CON0170 CON0210, CON0180 M0080
MD M0060 CON0130 CON0190

53d 0d 0d 0d 37d

WBS: LGA BL02-1.2.8 Electrical Works

CON0200 20d
Electrical ins tallations

CON0110 CON0160,
M0050, MD

-1d

WBS: LGA BL02-1.2.5 Restoration Works

CON0210 20d
Site restoration, apron
and road restoration

CON0180 PCO#4

0d

CON0220 2d
Guardrail

PCO#4 CON0300,
M0070

0d

WBS: LGA BL02-1.2.9 LGA Retire


WBS: LGA BL02-1.2.9.LGA Gate retire LGA Gate retire

CON0230 10d CON0240 5d


Cut and cap pipes Remove vault covers,
outside vaults inside piping and core
holes in floor

CON0050 CON0240 CON0230 CON0250

45d 45d

WBS: LGA BL02-1.2.9.LGA Governor retire LGA Governor retire

CON0250 5d CON0260 8d CON0270 5d CON0280 1d


Cut and cap pipes Demo pipe and fitting Remove vault covers, Post cons truction video
outside vaults from inside building inside piping and core inspection
holes in floor

CON0240 CON0260 CON0250 CON0270 CON0260 CON0280, CON0270 M0080


M0080

45d 45d 45d 45d

CON0290 5d
Post cons truction video
inspection

CON0310 M0080

0d

Acti vi ty ID Ori g i n a l
Acti vi ty Na me

Page 1 of 1 Oracle Corporation


Pre d e ce sso rsSu cce sso rs

To ta l Fl o a t

Das könnte Ihnen auch gefallen