Risk Assessment Matrix

Matrix below provides leaders a process to assess risk based on severity and probability of each hazard.
The point where the severity row and probability column intersect defines the level of risk of a hazard.
See reverse for “Risk Acceptance Authority Levels”. Taking unnecessary risk is unacceptable.

Composite Risk Management


Probability Frequent Likely Occasional Seldom Unlikely
Severity
A B C D E

Catastrophic I E E H H M

Critical II E H H M L

Moderate III H M M L L

Negligible IV M L L L L
Definitions of Severity USAG Benelux
• Catastrophic: Death or permanent total disability, system loss, major property damage
• Critical: Permanent partial disability, temporary total disability in excess of 3 months,
Leader's Guide
major system damage, significant property damage To Composite Risk
• Moderate: Minor injury lost workday accident, compensable injury or illness,
minor system damage, minor property damage Management
• Negligible: First Aid or minor supportive medical treatment, minor system impairment
Definitions of Probability
• Frequent: Occurs often, continuously experienced
• Likely: Occurs several times
• Occasional: Occurs sporadically
• Seldom: Unlikely, but could occur at some time
• Unlikely: Can assume it will not occur
Definition of Risk Levels (combining severity and probability)
• E = Extremely High: Loss of ability to accomplish mission if hazards occur during mission
• H = High: Significant degradation of mission capabilities if hazards occur during mission
• M = Moderate: Minor injury, lost workday accident, compensable injury or illness,
minor system damage, minor property damage
• L = Low: Little or no impact on mission accomplishment
WHAT IS COMPOSITE RISK MANAGEMENT? • Require planners/action officers to be HELPFUL COMPOSITE RISK MANAGEMENT
familiar with the composite risk management WEBSITES
• Composite Risk management is a decision process. • FM 5-19:
making process used to mitigate risks • Ensure composite risk assessments are an https://crc.army.mil/riskmanagement/FM5-19.pdf
associated with all hazards that have the integral part of decision briefings, decision
potential to injure or kill personnel, damage or papers, and event IPR’s. • Combat Readiness Center:
https://crc.army.mil/home/default.asp?#
destroy equipment, or otherwise impact • Require proponents of high risk programs to POV Risk Assessment Tool (ASMIS-2)
mission effectiveness. The Focus is now on assess program documents and ensure the Driving/POV training resources
what can kill people today, enemy or composite risk management process is Composite Risk Management training ….
accident? embedded. Soldier Training Support Package:

¾ Focal point of USAG Benelux LEADERS SHOULD ASK… • USAG Benelux Installation Safety Office:
Commander’s Safety philosophy and http://www.usagbenelux.eur.army.mil/sites/installation/safetyinf
Strategic Safety Plan. o.asp
• What are the Man, Machine, and
¾ Fundamentals captured in FM 5-19. Environment hazard factors of an operation?
¾ Risks can be quantified and managed by • Can the hazards be eliminated? Risk Acceptance Authority Levels:
determining the probability and severity of • What are the risks if the hazards cannot be
a potential loss due to a hazardous eliminated? Low & Moderate Risk: can be accepted by
condition.
• How can the risks be minimized? Are there the Commander/Leader responsible for the
¾ Leaders are responsible and accountable
other safer options? operation/activity.
for assessing their operation as a total
• Do the benefits outweigh the risks?
system and ensuring that planning, risk
management decisions, and execution • Is the decision-making required at a higher High Residual Risk: must be elevated to at
proactively identifies hazards, assesses level? least the Garrison Commander level
the associated risks, and identifies control depending on availability.
measures necessary to reduce the risks 5-STEP PROCESS
to the level commensurate with their
Extremely High Residual Risk: must be
commander's intent. • Identify hazards to the force. Consider all elevated to the first General Officer in the
aspects of current and future situations, chain of command.
COMPOSITE RISK MANAGEMENT WILL… environment, and known historical problem
areas.
• Allow leaders to make informed decisions • Assess hazards to determine risks.
• Provide Soldiers a mental process in making Assess the impact of each hazard in terms
decisions that affect their day-to-day lives. of potential loss and cost based on
probability and severity.
WHAT LEADERS CAN DO • Develop controls and make risk
decisions. Develop control measures that
• Ensure all leaders complete the Composite eliminate the hazard or reduce its risk. As
Risk Management Basic Course on-line control measures are developed, risk is re-
(available on the Combat Readiness evaluated until the residual risk is at a level
University,https://safetylms.army.mil/librix/logi where the benefits outweigh the costs.
nhtml2.asp?v=usasc). • Implement controls that eliminate the
hazard or reduce its risk.
• Require senior leaders to mentor junior • Supervise and evaluate. Enforce
leaders in planning using their experiences in standards and controls. Evaluate the
dealing with risks. effectiveness of controls and adjust/update
as necessary.